DEVAKI ANTHARJANAMversusSREEDHARAN NAMBOODIRI & ANR.
- Citation
- 2009 INSC 887
- Decided
- 7 July 2009
- Disposal
- Appeal(s) allowed
- Bench
- MUKUNDAKAM SHARMA
Holding
The executing court’s assessment of compensation for ground‑floor improvements was valid, the respondents were bound by their undertaking not to claim compensation for the first‑floor works, and the High Court erred in interfering, exceeding its jurisdiction under CPC 115.
Summary
The appellant-landlady filed a suit for recovery of possession of a property and the respondents claimed compensation for improvements they had made. The trial court, based on a commissioner’s report, awarded Rs 1,35,500 as compensation and decreed possession in favour of the appellant. After the decree, the respondents sought additional compensation under Section 5(3) of the Kerala Compensation for Tenants Improvements Act, 1959 for improvements made after the decree. The executing court re‑valued the ground‑floor improvements and ordered the appellant to pay an extra Rs 3,12,000, which the appellant complied with. The respondents then filed a revision; the High Court set aside the executing court’s order and remanded the matter to fix further compensation. The Supreme Court held that the respondents were bound by their undertaking not to claim compensation for the first‑floor works, that the executing court’s assessment of ground‑floor improvements was lawful, and that the High Court exceeded its jurisdiction under CPC 115 by interfering. Consequently, the appeal was allowed, the High Court order set aside, and the trial court’s decree restored.
Issues considered
- The respondents' entitlement to additional compensation for improvements made after the decree under Section 5(3) of the Kerala Compensation for Tenants Improvements Act, 1959.
- Whether the respondents' undertaking not to claim compensation for first‑floor constructions bars them from claiming any further compensation.
- The scope of the executing court’s power under Section 5(3) and whether the High Court could interfere with its assessment under CPC 115.
Legislation cited
Subjects
Judgment
[2009] 10 S.C.R. 779
DEVAKI ANTHARJANAM A
V.
SREEDHARAN NAMBOODIRI & ANR.
(Civil Appeal No. 3206 of 2006)
JULY 7, 2009
B
[DR. MUKUNDAKAM SHARMA AND
DR. B.S. CHAUHAN, JJ.]
Kera/a Compensation for Tenants Improvements Act,
1959 - ss. 5(3) and 2(b) - Suit for recovery of possession of C
immovable property - Defendants claimed compensation for
improvements made by them in the property - Suit decreed
- Compensation for improvements also adjudged in the
decree - Execution petition - Additional compensation
awarded by Executing Court ·in terms of s.5(3) for o
improvements made in property after the date of decree -
Revision petition against - High Court remitted the matter to
Executing Court to assess claim for further compensation -
Justification of - Held :On facts, not justified - The Executing
Court assessed compensation with regard to improvements E
after proper assessment thereof with aid and assistance of the
Court Commissioner - Findings recorded by Executing Court
were legal and valid - High Court committed manifest error
of law and also exceeded its jurisdiction by interfering with the
said findings - Code of Civil Procedure, 1908 - s. 115.
F
The appellant-landlady filed suit for recovery of
possession of immovable property. In the written
statement, the respondents-defendants claimed
compensation for the improvements made by them in the
suit property. The trial court decreed the suit and, on G
basis of the report given by Court Commissioner aided
by an expert, directed that the respondents would be
entitled to receive compensation of Rs.1,35,0001-. The
779 H
780 SUPREME COURT REPORTS [2009] 10 S.C.R.
A decree, though challenged by the respondents, was
upheld by the first appellate court as well as the High
Court. Since despite the decree, and payment of
compensation by appellant, the respondents did not
vacate the suit property, the appellant filed execution
B petition seeking their eviction. Respondents prayed for
additional compensation in terms of Section 5(3) of the
Kerala Compensation for Tenants Improvements Act,
1959 for improvements made to suit property after the
date of decree. The Executing Court after coming to a
C finding that the entire ground floor of the property was
completed before the date of decree and that such factor
escaped the notice of the earlier Commissioner and
Expert appointP.d by Court for that purpose at the trial
stage, made revaluation of the entire ground floor portion
and directed the appellant to deposit an amount of
D Rs.3, 12,000/- over and above the amount of Rs. 1,35,000/
- adjudged in the decree. Appellants deposited the
additional amount of Rs.3, 12,000/- as well, but the
respondents filed revision petition claiming further
compensation for the improvements made. The High
E Court remitted the matter to the Executing Court to
assess the claim of respondents. Hence the present
appeal.
Allowing the appeal, the Court
F
HELD : 1.1. It was p~inted out that the respondents
were seeking payment of compensation for the
improvements made despite an undertaking given by
them before the Court that they would not claim any
G value for the improvements made in the first floor of the
property. Any construction made after the aforesaid
undertaking cannot be said to be improvements made in
the bonafide belief that they are entitled to make some
improvements. [Para 23] [792-G-H; 793-A]
H
DEVAKI ANTHARJANAM ~ SREEDHARAN 781
NAMBOODIRI & ANR.
'(
1.2. Even assuming for the purpose of argument that A
- the respondents could make some improvements even
after passing of the decree by the trial court, but they
could not have made any improvement in the suit
property by way of constructing the first floor and claim
compensation for it when they had given a clear B
undertaking that they would not claim any compensation
towards value of the said construction made on the first
floor. They also undertook that they would not claim
anything on account of the construction of the room and
the toilet in the first floor. They are bound by the aforesaid c
undertaking given to the Court and they are not entitled
to resile from the same subsequently and claim any
compensation. When they filed an undertaking they
definitely had the knowledge that they are not entitled to
make any improvement thereon in view of the currency
D
of the order of injunction and therefore they proceeded
to give such an undertaking which disentitles them to
claim any compensation towards any such improvement
made. [Para 24] [793-A-E]
1.3. The Executing Court took notice of the said fact E
and therefore assessed compensation with regard to
improvements made in respect of the ground floor only
after proper assessment thereof with the aid and
assistance of the Court Commissioner aided by an expert
at Rs. 3,12,000/- over and above Rs. 1,35,500/-. The High F
Court acted without jurisdiction in interfering with the
aforesaid order in the exercise of the jurisdiction under
Section 115 CPC. [Paras 25 and 26] [793-E-G]
1.4. There is no reason to linger on the matter any
G
~
further by remanding the matter back to the High Court
+ as it is found that the findings recorded by the executing
court are legal and valid. The said findings do not call for
any interference and the High Court committed a manifest
error of law and also exceeded its jurisdiction by
H
,.
782 SUPREME COURT REPORTS [2009] 10 S.C.R.
A interfering with the said findings. The order passed by the
High Court is set aside and the order of the trial court is
restored. The trial court is directed to take steps for
execution of the decree in accordance with law. [Para 27]
[793-G-H; 794-A-B]
-
B
Kunjan Nair Sivaraman Nair v. Narayanan Nair and Ors.
(2004) 3 sec 277, referred to.
Case Law Reference:
(2004) 3 sec 211 referred to Para 19
c
CIVIL APPELLATE JURISDICTION : Civil Appeal No.
3206 of 2006.
From the Judgment & Order dated 25.5.2005 of the High
o Court of Kerala at Ernakulam in Civil Revision Petition No. 803 •
of 2004. (G).
T. Anamika, B.V. Deepak and (for T.T.K. Deepak & Co.)
for the Appellants.
E Subramonium Prasad for the Respondent.
The Judgment of the Court was delivered by
DR. MUKUNDAKAM SHARMA, J. 1. This appeal is '
directed against the judgment and order dated 25.5.2005
F passed by the High Court of Kerala whereby the High Court
while allowing the Civil Revision filed by the respondent herein
and setting aside the order passed by the Execution Court
directed that the Execution Court should proceed to fix the value
of improvements due to the respondent in accordance Section
G 5(3) of the Kerala Compensation for Tenants Improvements Act,
1959 (for short "the Act").
2. The appellant herein filed a suit seeking for a decree
for recovery of possession of immovable property including the
H building on the strength of a title with a further prayer for grant
DEVAKI ANTHARJANAM v:SREEDHARAN NAMBOODIRI 783
& ANR. [DR. MUKUNDAKAM SHARMA, J.]
1
of a decree for mesne profit. The suit was instituted by the A
-"'·
appellant in her capacity as the landlady of the said property
in the year 1987. The respondents/judgment debtors contested
the said suit by filing a written statement. In the written statement
filed by the respondents, they claimed value of improvements
made by them which they themselves assessed at Rs. 7 lakhs B
and for recovery of the same.
3. By judgment and decree passed on 31.5.1991, the suit
filed by the appellant was decreed granting a decree for
recovery of possession of the plaint schedule property from the
respondents and also decreeing the suit for recovery of mesne
c
profit at the rate of Rs. 1000 per year from the defendant No.1
/respondent No. 1 from the date of institution of the suit tin
delivery of possession. It was also directed in the said suit that
respondent No. 1 would be entitled to get value of
·improvements of Rs. 1,35,000/- from the plaintiff/appellant D
herein and that the amount would be first charged on the plaint
schedule property and that the defendant No. 1 would also pay
the cost of the suit to the plaintiff/appellant.
4. The aforesaid decree was challenged by the E
respondents herein before the first appellate court which
dismissed the said appeal.
5. Feeling aggrieved, the respondent filed an appeal
before the High Court wherein also the value of improvements
as fixed by the trial court and upheld by the first appellate court F
was challenged.
6. The High Court, however, dismissed the said appeal
and thereby upheld and confirmed the decree passed by the
trial court as also confirmed by the first appellate court. G
, _,
' Consequent result is that the claim of the independent title and
also the claim of title by way of adverse possession set up by
the respondents were rejected whereas all the courts including
the High Court confinned only to the extent that the respondents
were entitled to value of improvements being Rs. 1,30,000/- for H
784 SUPREME COURT REPORTS [2009] 10 S.C.R.
A the building and Rs. 5,500/- for the motor pump set and pump
house, aggregating to a total of Rs. 1,35,500/- only.
.r-·
7. The aforesaid valuation was made by the trial court by
its judgment and decree dated 31.5.1991 on the basis of Exts.
C2 and C3, Final Report and Valuation Statement of August
B
and September, 1990 submitted by the Commissioner
appointed by the Court aided by an expert. The said amount
also came to be paid by the appellants herein.
8. After the decree was granted by the trial court under
c judgment and order dated 31.5.1991 and since despite the
decree and also payment of the compensation as determined
and assessed by the courts including the High Court, the
respondents did not vacate the suit premises, the appellants
were compelled to file an execution case bearing Execution
D Petition No. 331 of 1999 seeking for eviction of the
respondents from the suit premises. In the said execution
petition, the respondents took up a plea that in terms of the
provisions of Section 5(3) of the Act, the execution court is
required to conduct a supplementary enquiry to determine (i)
E additional compensation for improvement made to the building
after the date of the decree on the ground that the Act permits
to include amount of compensation for the improvements made
,even subsequent to the passing of the decree and (ii) on
revaluation of this building for which compensation had already
F been adjusted in the decree, the value of the said building with
reference to its conditions.
9. The Executing Court took up the aforesaid plea raised
by the respondents and after consideration of the same and
after hearing the counsel appearing for the parties held that the
G judgment debtors/ respondents could not be said to be persons
in bonafide occupation of the premises so as to come within . ~
the ambit of "tenant" under Section 2(d) of the Act from the date
of the decree and therefore they would not be entitled to the
value of improvements put up subsequent to the date of decree.
H The Executing Court also found as a matter of fact that as on
DEVAKI ANTHARJANAM v. SREEDHARAN NAMBOODIRl785
& ANR. [DR. MUKUNDAKAM SHARMA, J.]
-.. the date of the decree, the building in the property did not have A
any first floor and that the first floor had come 'nto existence
..,_
after passing of the decree. Consequent to the recording of the
aforesaid finding, the Executing Court held that the respondents/
judgment debtors were not entitled to additional compensation
for the improvements effected after the date of the decree. B
However, the Executing Court took into account the condition
of the entire ground floor of the building on the basis of the
i- Commissioner's Report filed in execution proceedings and its
own finding that the entire portion of the ground floor had been
completed before the date of the decree in the suit a factor c
which had escaped the notice of the earlier Commissioner and
Expert appointed by the Court for that purpose at the trial stage.
10. The Executing Court thereafter made a revaluation of
the entire ground floor portion of the building and directed that
an amount of Rs. 3, 12,000/- was to be deposited by the D
appellants-decree holder over and above the amount of Rs.
1,35,500/- adjudged in the decree which was already deposited
by the appellant.
11. Needless to point out that the aforesaid assessment E
of Rs. 3, 12,000/- was made without giving any depreciation of
the building. Be that as it may, it transpires from the records
that the appellants paid the said amount also in terms of the
order passed by the Executing Court that is to say the
appellants deposited the amount of Rs. 3, 12,000/- over and F
above the amount of Rs. 1,35,500/-.
12. The respondent still not being satisfied, filed a revision
petition before the High Court of Kerala. In the final order
passed in the revision petition, the High Court held that unless
the appellants could establish that there was an order passed G
~
by the High Court restraining the respondent from claiming
further value of improvements, the respondent would be entitled
to get such improvements also and that the same could not be
denied. Having held thus in paragraph 14, the High Court
observed as follows:- H
786 SUPREME COURT REPORTS [2009] 10 S.C.R.
A "14. It is also the settled position of law that section 5(3)
of the Compensation for Tenants lmrovements Act only
empowers the executing court to assess the amount of
compensation for improvements made subsequent to the
date up to which compensation for improvements had
B been adjudged in the decree and section 5(3) does not
enable the executing court to re-open the adjudication
made by the trial court as held in Kamalamma vs.
Madhavan pillai (1959 K.L.T. 578). In this case there are
no materials available on record to find whether there was
c a final order of injunction prohibiting the petitioner from
claiming further value of improvements. The executing court
proceeded on the wrong assumption that since the trial
court passed the decree for recovery of the suit property,
the petitioner is not entitled to claim any value of
improvements effected after the said date. That finding is
D
illegal. So the matter requires reconsideration. I have no
other option but to set aside the impugned order and
remand the case back to the executing court to fix the value
of improvements due to the petitioner in accordance with
the provisions contained in section 5(3) of the
E Compensation for Tenants Improvements Act."
13. In terms of the aforesaid findings, the civil revision filed
. by the respondent was allowed by the High Court. The order
passed by the Executing Court was set aside and matter was
F rem.anded back to the Executing Court to fix the value of
improvements in accordance with the provisions of Section
5(3) of the Act.
14. The appellan~ being aggrieved by the aforesaid order
G of remand passed by the High Court, has filed this appeal in
which notice was issued by this Court and after notice was
served this Court granted the leave. The original records of the
case have been received. On the prayer of the parties, there
was a direction by this Court that this appeal be listed for
hearing during summer vacation and consequently it was
H
DEVAKI ANTHARJANAM v. SREEDHARAN NAMBOODIRI 787
& ANR. [DR. MUKUNDAKAM SHARMA, J.]
placed before us for final hearing during the summer vacation A
when we heard the learned counsel appearing fer the parties.
15. Before we proceed to discuss the rival contentions
raised on behalf of the respective parties, we would like to
make a reference to the relevant provision of the aforesaid
B
Kerala Compensation for Tenants Improvements Act, 1959.
Section 2(b) of the Act reads as follows: -
"2(b) "improvement" means any work or product of a work
which adds to the value of the holding, is suitable to it and
consistent with the purpose for which the holding is let, c
mortgaged or occupied, but does not include such
clearances, embankments, levellings, enclosures,
temporary wells and water-channels as are made by the
tenant in the ordinary course of cultivation and without any
special expenditure or any other benefit accruing to land D
from the ordinary operations of husbandry;"
16. The expression "tenant" is also.defined under Section
2(d) of the Act as follows :
"2. (d) 'Tenant'.-'tenant' with its grammatical variations E
and cognate expressions includes-
(i) a person who, as lessee, sub-lessee, mortgagee or
i
sub-mortgagee or in good faith believing himself to be
lessee, sub-lessee, mortgagee, or sub-mortgagee of land, F
is in possession thereof;
(ii) a person who with the bona fide intention of attorning
and paying a reasonable rent to the person entitled to
cultivate or let wasteland, but without the permission of
such person, brings such land, under cultivation and is in G
occupation thereof as cultivator; and
"'
(iii) a person who comes into possession of land belonging
to another person and makes improvements thereon in the
bona fide belief that he is entitled to make such H
788 SUPREME COURT REPORTS (2009] 10 S.C.R.
A improvements."
17. Further, Section 4 of the Act lays down that every tenant
shall on eviction be entitled to compensation for improvements
which were made by him or his predecessor-in-interest or by
any person not in occupation at the time of the eviction who
8
derived title from either of them and for which compensation
had not already been paid; and every tenant to whom
compensation is so due shall, notwithstanding the
determination of the tenancy or the payment or tender of the
mortgage money or premium , if any, be entitled to remain in
C possession until eviction in execution of a decree or order of
court.
18. Section 5 thereof provides that the decree passed in,
eviction suit would be conditional on payment of compensation.
D Sub-Section (3) of Section 5 thereof which is relevant for our
purpose is also extracted below:-
"5(3) The amount of compensation for improvements
made subsequent to the date up to which compensation
for improvements has been adjudged in the decree and
E
the re-valuation of an improvement, for which
compensation has been so adjudged, when and in so far
as such re-valuation may be necessary with reference to
the condition of such improvement at the time of eviction
as well as any sum of money accruing due to the plaintiff
F subsequent to the said date for rent, or otherwise in
respect of the tenancy, shall be determined by order of the
court executing the decree and the decree shall be varied
in accordance with such order."
G 19. The aforesaid provisions particularly Section 2(d) and
Section 5 came to be considered by this Court in the case of /
•
Kunjan Nair Sivaraman Nair vs. Narayanan Nair and Others
((2004) 3 sec 277]. We have carefully considered the said
decision. In paragraph 23 of the aforesaid judgment this Court
H has considered the definition of Section 2(d) and analysed the
DEVAKI ANTHARJANAM v. SREEDHARAN NAMBOODIRl789
& ANR. [DR. MUKUNDAKAM SHARMA, J.]
said definition of tenant by stating thus:- A
"23. It is to be noted that the three clauses of Section 2(d)
use different expressions to meet different situations and
class of persons. While clause (i) refers to a person who
is a lessee or sub-lessee, or mortgagee or sub-mortgagee
8
or in "good faith" believing himself to be any one of the
above such persons, clause (ii) deals with a person with
"bona fide intention" by doing any one of the things
enumerated is in occupation as cultivator, and clause (iii)
deals with a person who comes into possession of land
belonging to another and makes improvement thereon in C
the "bona fide belief' that he is entitled to make such
improvements. According to the appellant, both clauses (i)
and (iii) are applicable to him. Clause (i) deals with the
person who bona fide believes himself to be a lessee in
.. respect of the land in question. The fact that he asserted D
a claim for purchase of jenmam rights. irrespective of the
rejection of the claim would go to show that at any rate he
was believing in good faith to be one such person viz.
lessee. Clause (iii) encompasses a person who comes
into possession of land belonging to another person and E
makes improvements thereon with the bona fide belief that
he is entitled to make such improvements. The appellant
was claiming himself to have been put in possession as
the nephew of late Narayanan Nair, and as a person in sur.h
possession - claims to have made certain F
improvements. Indisputably he was in possession. Though,
in view of the judgments of the courts below his claim to
assert a title in him has been rejected and his possession
cannot be a lawful possession to deny the right of the real
owner to recover possession or assert any adverse claim G
against the lawful owner to any longer squat on the property
- his initial induction or entering into possession cannot
be said to be by way of encroachment. Whether such a
person could not claim to have entertained a bona fide
belief that he is entitled to make such improvements has H
790 SUPREME COURT REPORTS [2009] 10 S.C.R.
,'
A to be factually determined with reference to the point of ~
time as to when he really made such improvements. If the
alleged improvements are found to have been made after
the disputes between parties commenced then only it may
not be in bona fide belief. Improvements made, if any, even
B thereafter only cannot fall under clause (iii). The court
dealing with the matter is required to examine the claim
and find out whether the prescriptions in the different
clauses individually or cumulatively have any application to
the claim of the appellant for improvements alleged to have
c been made, if so really made. The courts below have noted
that the appellant made a claim that he was a lessee and
thereafter made the improvements. The courts below do
not appear to have considered the issues arising at any
rate in respect of the claim for the alleged improvements
said to have been made, from the aforesaid angle. As
D
factual adjudication is necessary as to whether the
appellant acted in good faith or with bona fide belief as
envisaged; this has to be decided taking into consideration
the materials placed before the court in that regard. It is,
therefore, appropriate that the trial court should consider
E this aspect afresh uninfluenced by any observation made
by it earlier or by the appellate courts. We also do not
express any 'conclusive opinion on the merit of the claim
except indicating the parameters relevant for such
consideration. For that limited purpose, the matter is
F remitted to the trial court which shall make an endeavour
to adjudicate the matter within six months from the date of
judgment, after allowing the parties to place material in
support of their respective stands."
G 20. In view of the aforesaid settled legal position, we are
req.uired to consider whether the respondent could make a
claim for enhanced compensation for improvements allegedly •.
made by him.
21. Initially, when the suit was filed, even at that stage the
H
DEVAKI ANTHARJANAM v. SREEDHARAN NAMBOODIRI 791
& ANR. [DR. MUKUNDAKAM SHARMA1 J.]
-.. relief sought for in the suit was for a decree of recovery of A
possession as also for payment of mesne profit. In the said suit
itself, the respondent pleaded in the written statement that he
has made improvements in the suit premises and therefore, he
is entitled to claim value of improvements made by him which
they themselves assessed and determined at Rs. 7 lakhs and B
prayed for recovery of the same. The suit was decreed both
for decree of recovery of possession and also for payment of
mesne profit. The trial court held that the respondent would be
entitled to Rs. 1,35,500 as value of improvements which was
based on the report of the Court Commissioner aided by an c
expert. All the aforesaid findings recorded by the trial court were
under challenge both before the first appellate court as also-
before the High Court. Both the courts not only upheld and
confirmed the decree but also held that the appellants are
; entitled to a decree of eviction whereas the respondents would
D
be entitled to compensation for improvements made at Rs.
1,35,500/-.
22. We are also conscious of the fact that an affidavit was
filed by the respondents herein before the Kerala High Court
on 12th July, 1999 wherein they had given an outline of the E
eviction proceedings initiated against them by the appellant
herein. They had stated that the second appeal arises from a
decree and judgment in OS No. 294of1987 of the Sub Court,
lrinjalakuda. It was also mentioned therein that the suit was for
declaration, title and recovery of possession. In the Second F
Appeal the appellant filed CMP 1133 of 1999 seeking order
of injunction to restrain the respondents herein from undertaking
any construction activity in the plaint schedule property and
committing any waste therein and that the said CMP was filed
on the allegation that the respondents herein were attempting G
to construct a first floor to the existing residential building situate
>
in the plaint schedule property. In the said application, it was
also alleged that the said construction work was done in order
to delay the benefit of decree that might be passed in the
appeal and that the existing residential building was constructed H
792 SUPREME COURT REPORTS [2009] 10 S.C.R.
A by the ancestors of the appellant (respondents herein). It was ~ ,...
stated that the said allegations are incorrect. Despite the said
statement, the High Court passed an interim order of injunction
restraining the respondents particularly respondent No. 1 from
making any further construction in the property. After stating thus,
B the respondents through respondent No. 1 gave an undertaking
in the said affidavit particularly in paragraph Nos. 3 and 4 in
the following manner:-
"3. We are not constructing first floor to the existing
residential building. A small room with an attached toilet
c was constructed more than two to three weeks prior to the
date of passing of the order of injunction. As regards the
said room, the flooring painting and plastering of the
ceiling is yet to be completed. Once we are informed of
the passing of the order of the injunction we had stopped
D further works including the one stated above. I think it
proper to seek the permission of this Hon'ble Court to
complete the said work. Accordingly, the accompanying
CMP is filed seeking permission to complete the flooring,
painting and plastering works of the said small room and
E toilet already constructed on the first floor of the existing
residential building.
4. We undertake that we will not claim the value of the said
room and toilet constructed on the first floor of the building
F Neither we will claim any special equities on account of
the construction of the said room and toilet. We may be
permitted to complete the said works at our risk and
costs."
23. It is also pointed out that now the respondents are
G seeking for payment of compensation for the aforesaid
improvements also made despite an undertaking given by them
before the High Court that they would not claim any value of the
said room and the improvements made in the first floor of the
building. Since the aforesaid undertaking was placed on record
H by the respondents, any constructions made after the aforesaid
DEVAKI ANTHARJANAM v. SREEDHARAN NAMBOODIRI 793
& ANR. [DR. MUKUNDAKAM SHARMA, J.]
undertaking given by the respondents cannot be said to be A
improvements made in the bonafide belief that they are entitled
to make some improvements.
24. Even assuming for the purpose of argument that the
respondents could make some improvements even after
8
passing of the decree by the trial court, but they could not have
made any improvement in the suit property by way of
constructing the first floor and also claimed compensation for
" it when they had given a clear undertaking that they would not
claim any compensation towards value of the said constructions
made on the first floor of the building. They also undertook that
c
they would not claim anything on account of the construction of
- the room and the toilet in the first floor. They are bound by the
aforesaid undertaking given to this Court and they are not
entitled to resile from the same subsequently and claim any
compensation. When they filed an undertaking they definitely D
had the knowledge that they are not entitled to make any
improvement thereon in view of the currency of the order of
injunction and therefore they proceeded to give sucrr an
undertaking which disentitles them to claim any compensation
towards any such improvement made . E
25. The trial court or the executing court took notice of the
said fact and therefore had assessed compensation with
regard to improvements made in respect of the ground floor
only after proper assessment thereof with the aid and F
assistance of the Court Commissioner aided by an expert at
Rs. 3, 12,000/- over and above Rs. 1,35,500/-.
26. The said findings and conclusions arrived at by the trial
court are found to be valid and justified. The High Court acted
without jurisdiction in interfering with the aforesaid order in the G
> exercise of the jurisdiction under Section 115 of the Code of
Civil Procedure.
27. We do not find any reason to linger on the matter any
further by remanding tne matter back to the High Court as we H
794 SUPREME COURT REPORTS [2009) 10 S.C.R.
A find that the findings recorded by the executing court are legal
and valid. In our considered opinion, the said findings do not
call for any interference and the High Court committed a
manifest error of law and also exceeded its jurisdiction by
interfering with the said findings. We, therefore, allow this
B appeal and set aside the order passed by the High Court and
restore the order of the trial court. The trial court would now take
steps for execution of the decree in accordance with law.
28. The appeal is allowed with costs.
C B.B.B. Appeal allowed.
-
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.