G H QUIPPO CONSTRUCTION EQUIPMENT LIMITEDversusJANARDAN NIRMAN PVT. LIMITED
- Citation
- 2020 INSC 380
- Decided
- 29 April 2020
- Disposal
- Appeal(s) allowed
- Bench
- UDAY UMESH LALIT
Holding
The respondent’s failure to object to the arbitrator’s jurisdiction and the venue of arbitration constitutes a waiver, precluding any later challenge under Section 34.
Summary
Quippo Construction Equipment Ltd entered into four rental agreements with Janardan Nirman Pvt Ltd, each containing an arbitration clause under the Construction Industry Arbitration Association (CIAA). One agreement stipulated Kolkata as the place of arbitration, but the sole arbitrator conducted proceedings in Delhi and issued a common ex‑parte award on 24‑03‑2015. The respondent did not participate in the arbitration and later challenged the award under Section 34, arguing that the venue clause was breached. The Supreme Court held that the arbitration was a domestic institutional one, the venue clause was not a jurisdictional bar, and the respondent’s failure to raise any objection amounted to a waiver under Section 4 of the Arbitration Act. Consequently, the Court restored the Alipore District Court’s dismissal of the Section 34 petition and set aside the High Court’s order overturning it. The appeal was allowed, reinstating the Alipore Court’s jurisdiction.
Issues considered
- The applicability of the venue clause (place of arbitration) when the arbitration was conducted at a different location.
- Whether the respondent’s non‑participation and failure to object amounts to a waiver of objections under Section 4 of the Arbitration and Conciliation Act, 1996.
- The jurisdiction of the court under Section 34 to entertain the petition for setting aside the award.
- The effect of having a common award for multiple agreements with differing arbitration clauses.
Legislation cited
- Arbitration and Conciliation Act, 1996s. 16, s. 20, s. 34, s. 37, s. 4, s. 5, s. 8, s. 9
Subjects
Judgment
272 [2020]REPORTS
SUPREME COURT 6 S.C.R. 272 [2020] 6 S.C.R.
A QUIPPO CONSTRUCTION EQUIPMENT LIMITED
v.
JANARDAN NIRMAN PVT. LIMITED
(Civil Appeal No. 2378 of 2020)
B APRIL 29, 2020
[UDAY UMESH LALIT AND VINEET SARAN, JJ.]
Arbitration and Conciliation Act, 1996 – ss.4, 16, 20 and 34
– Four agreements entered into between the parties – Dispute –
C Sole arbitrator appointed – In one of the agreements the venue was
Kolkata but proceedings were conducted at Delhi – Litigation ensued
both before the Courts at Kolkata and Delhi – Common ex-parte
award passed – Respondent filed petition u/s.34 in the Court of
District Judge, Alipore – Dismissed – Order set aside by High Court
– Held: Arbitration in question is a domestic and an institutional
D arbitration where Construction Industry Arbitration Association
(CIAA) was empowered to and did nominate the Arbitrator – It is
not as if there were completely different mechanisms for appointment
of Arbitrator in each of the agreements – Only distinction is that as
per one of the agreements, the venue was to be at Kolkata –
E Specification of “place of arbitration” may have special significance
in an International Commercial Arbitration, where the “place of
arbitration” may determine which curial law would apply –
However, in the present case, the applicable substantive as well as
curial law would be the same – Further, respondent neither
participated in arbitration proceedings nor objected to jurisdiction
F of the Arbitrator, thus deemed to have waived all such objections –
Now precluded from raising any objection as to the venue of
arbitration – Conclusion drawn by the Court at Alipore was correct
– Order of High Court set aside while that of the Court at Alipore is
restored.
G Allowing the appeal, the Court
HELD: 1.1 In the present case the arbitration in question
is a domestic and an institutional arbitration where CIAA was
empowered to and did nominate the Arbitrator. It is not as if there
were completely different mechanisms for appointment of
H
272
QUIPPO CONSTRUCTION EQUIPMENT LIMITED v. JANARDAN 273
NIRMAN PVT. LIMITED
Arbitrator in each of the agreements. The only distinction is that A
according to one of the agreements the venue was to be at
Kolkata. The specification of “place of arbitration” may have
special significance in an International Commercial Arbitration,
where the “place of arbitration” may determine which curial law
would apply. However, in the present case, the applicable B
substantive as well as curial law would be the same. It was possible
for the respondent to raise submissions that arbitration pertaining
to each of the agreements be considered and dealt with separately.
It was also possible for him to contend that in respect of the
agreement where the venue was agreed to be at Kolkata, the
arbitration proceedings be conducted accordingly. Considering C
the facts that the respondent failed to participate in the
proceedings before the Arbitrator and did not raise any
submission that the Arbitrator did not have jurisdiction or that
he was exceeding the scope of his authority, the respondent must
be deemed to have waived all such objections. [Paras 22-23]
D
[288-A-D]
1.2 The respondent is now precluded from raising any
submission or objection as to the venue of arbitration, the
conclusion drawn by the Court at Alipore while dismissing
Miscellaneous Case No.298 of 2015 was quite correct and did
E
not call for any interference. The High Court was in error in setting
aside said Order. In any case, the fact that the cause title showed
that the present appellant was otherwise amenable to the
jurisdiction of the Alipore Court, could not be the decisive or
determining criteria. [Para 24][288-E]
F
Narayan Prasad Lohia v. Nikunj Kumar Lohia and
Others (2002) 3 SCC 572 : [2002] 1 SCR 1136 - relied
on.
Duro Felguera, S.A. v. Gangavaram Port Limited (2017)
9 SCC 729 : [2017] 10 SCR 285 – referred to.
G
Case Law Reference
[2017] 10 SCR 285 referred to Para 18
[2002] 1 SCR 1136 relied on Para 20
H
274 SUPREME COURT REPORTS [2020] 6 S.C.R.
A CIVIL APPELLATE JURISDICTION: Civil Appeal No. 2378
of 2020.
From the Judgment and Order dated 14.02.2019 of the High Court
at Calcutta in appeal bearing No. CAN 10094 of 2018.
Ritin Rai, Sr. Adv., Shashank Manish, Ms. Manasi Chatpalliwar,
B Ms. Prerita Aggarwal, Ms. Twinkle Kataria, Yash Kumar, Abhipsit
Mishra, Arjun S.B., Mridul Godha, Advs. for the Appellant.
Kuriakose Varghese, V. Shyamohan, Surya Prakash, Ms. Isha
Ghai (for KMNP Law), Advs. for the Respondent.
C The Judgment of the Court was delivered by
UDAY UMESH LALIT, J.
1. Leave granted.
2. In this appeal the Original Claimant challenges the final judgment
and order dated 14.02.2019 passed by the High Court at Calcutta in
D
CAN No.10094 of 2018.
3. The basic facts culled out from the award dated 24.03.2015
passed by the Arbitrator in the present case are:-
“That the respondent company who is engaged in the business of
E infrastructure development activities approached the claimant
company who is also dealing in the business of providing
equipments for infrastructure activities to provide on rent two Piing
Rig HR-180 and (1) 300 CPM compressor (equipments) for
carrying out the work as per the respondent’s instructions. After
deliberations and negotiations, an agreement dated 1.8.2010 was
F entered into between the parties in respect of the abovesaid
construction equipments for its work site C/o Janardhan Nirman
Pvt. Ltd. L & TECC site, NTPC BARH site, BARH, Distt. Patna,
Bihar. Being satisfied with the equipment services provided by
the claimant company, the respondent further approached the
G claimant company for taking on rent another one (1) Pilling Rig-
MAIT HR 180 (equipment) for its same abovesaid work site,
along with double set of crew/operator for each equipment for
carrying out the works as per the respondent’s instructions. After
deliberations and negotiations, an agreement 2.10.2010 was entered
into between the parties herein in respect of the abovesaid
H
QUIPPO CONSTRUCTION EQUIPMENT LIMITED v. JANARDAN 275
NIRMAN PVT. LIMITED [UDAY UMESH LALIT, J.]
equipments. Thereafter, the respondent further entered into A
agreements dated 19.3.2011 and 14.4.2011 for taking on rent one
(1) Pilling Rig HR 180 vide each of the said agreements for
carrying out the work as per the respondent’s instructions for its
work site at C/o Janardhan Nirman Pvt. Ltd., SAIL, DSP,
Durgapur, West Bengal and C/o Janardhan Nirman Pvt. Ltd., NH-
B
34, Farakka-Dafkhola Road Project, Near Kaliachak, Distt. Malda,
West Bengal, respectively.”
4. In General Terms and Conditions appended to the aforesaid
Agreements, resolution of disputes between the parties was provided
for as under:-
C
4.1 The relevant clauses in respect of the agreement dated
01.08.2010 were to the following effect:-
“24. Governing Law Jurisdiction & Arbitration: The parties
hereto agree that the courts and tribunals at New Delhi shall have
the exclusive jurisdiction and shall be governed in accordance D
with the law in India.
24.1 Arbitration: In the event of any claim, dispute or difference
arising out of or in connection with the interpretation or
implementation of the agreement or out of or in connection with
any breach, or alleged breach of the Agreement (hereinafter E
referred to as “the dispute”) between the parties, the parties hereby
agreed to refer such dispute to Arbitration under Construction
Industry Arbitration Association (CIAA) Rules and Regulations
save and except that on behalf of both the parties to the Agreement.
The owners shall be entitled to select the sole Arbitrator out of
the panel of CIAA. The proceedings shall be governed by the F
Arbitration and Conciliation Act, 1996 with any statutory
modification thereto or re-enactment thereof. The venue for
holding such arbitration proceedings would be New Delhi.”
4.2 On the other hand, the relevant arbitration clause in the
agreement dated 14.04.2011 was to the following effect:- G
“24. Governing Law Jurisdiction & Arbitration: All and any
dispute arising out of or in connection with this contract, including
any question regarding its existence, validity or termination, shall
be referred to and finally resolved by arbitration in Kolkata in
accordance with the arbitration Rules of the Construction Industry H
276 SUPREME COURT REPORTS [2020] 6 S.C.R.
A Arbitration Council (“CIAC Arbitration Rules”) for the time being
in force at the commencement of the arbitration, which rules are
deemed to be incorporated by reference in this Clause. The owner
shall be entitled to select the sole Arbitrator out of the panel of
CIAC. This agreement is governed by the laws of India and the
parties hereto agree that only that courts and tribunals at Kolkata
B
shall have the exclusive jurisdiction the dispute arise out of the
terms of the Agreement or its interpretation.
The language of the arbitration shall be in English language. The
provision shall survive the termination/expiry of this agreement.”
C 5. In pursuance of the aforementioned agreements, construction
equipments were provided by the appellant to the respondent at the
respective sites as per instructions of the respondent. According to the
terms and conditions of the agreements the respondent was to make
payment within seven days from the date of submission of monthly bills
failing which the respondent would be liable to pay interest for delayed
D period. Since the payments were not forthcoming, the appellant by its
letter dated 21.01.2012 asked the respondent to pay the outstanding dues.
In its response dated 01.02.2012 the respondent accepted that every
Rig hired by it was as per the agreement. Since the payments were not
forthcoming, by communication dated 02.03.2012 the appellant gave
E notice invoking arbitration. Relying on clauses 24 and 24.1 as stated
above, it was stated that Shri L.C. Jain, President Consumer Forum
(Retd.) was appointed as the Sole Arbitrator who would be conducting
proceedings at New Delhi to adjudicate upon the dispute between the
parties. It was also stated:-
F “You are requested to reply and join the arbitration proceedings
within 14 days from the receipt of this notice and/or make payment
of the entire outstanding, amount of Rs.78,78,533/- (Rupees
Seventy Eight Lakhs Seventy Eight Thousand Five Hundred Thirty
Three Only) with interest @ 18%p.a. to the outstanding amount.”
G A copy of this communication was marked to Construction Industry
Arbitration Council (‘CIAC’, for short).
6. In its reply dated 15.03.2012 the respondent denied existence
of any agreement between the parties. It, however, did not take any
steps to participate in the arbitration. On the other hand, the respondent
filed Title Suit No.189 of 2012 in the Court of Civil Judge, Junior Division,
H
QUIPPO CONSTRUCTION EQUIPMENT LIMITED v. JANARDAN 277
NIRMAN PVT. LIMITED [UDAY UMESH LALIT, J.]
Second Court at Sealdah, praying that the agreements be declared null A
and void and for permanent injunction restraining the appellant from
relying on the arbitration clauses contained in the agreements. At the
interim stage, a restraint order was passed by the Trial Court as a result
of which the proceedings before the Arbitrator were stayed. An
application under Sections 5 and 8 of the Arbitration and Conciliation
B
Act, 1996 (for short “the Act”) was filed by the appellant submitting that
the dispute between the parties be referred to arbitration.
7. While accepting the application moved on behalf of the appellant
the Trial Court in its Order dated 26.5.2014 observed:-
“The defendant has already stated that there are agreements C
between the parties containing arbitration clause. They referred
the matter to arbitration in terms of the said arbitration clause to
resolve payment related dispute. In support of their contention,
the defendant produced a series of original agreements, signed by
both parties. I fail to understand why the plaintiff signed in a series
of documents, which they claim to be non-existing. As stated earlier, D
the plaintiff failed to give any explanation regarding falsity and
forgery committed by the defendant in executing the said
agreements. On perusal of the agreements, it transpires that all
the agreements contain payment and usage terms in detail. The
agreements also contain arbitration clause i.e. with regard to any E
claim and any dispute regarding implementation, execution and
interpretation or breach of the agreements between the parties.
Therefore, the dispute between the parties regarding
payments is within the scope of arbitration clause. The defendants
are justified in referring the matter to arbitration. Rather the plaintiff F
filed this suit even after having knowledge of arbitration proceeding.
……
All the disputes between the parties being the matters
covered by arbitration clause are to be adjudicated by the arbitrator.
Therefore, this court has no jurisdiction to hear and try this suit.” G
The application preferred by the appellant was thus allowed and
the plaint was directed to be returned.
8. The respondent filed Miscellaneous Appeal No.57 of 2014 in
the Court of Additional District Judge, Second Court, Sealdah, challenging
said order dated 26.05.2014. Pending appeal, interim relief was prayed H
278 SUPREME COURT REPORTS [2020] 6 S.C.R.
A for by the respondent and repeated adjournments on that count were
sought by the respondent before the Arbitrator. The Arbitrator granted
accommodation to the respondent on some occasions but as no interim
order was passed by the appellate court, the proceedings before the
Arbitrator continued. By ex-parte award dated 24.03.2015, the Arbitrator
accepted the claim preferred by the appellant. The award was a common
B
award covering claims in respect of all the four agreements. The award
observed:-
“The claimant company approached the Construction Industry
Arbitration Council (CIAC), the institutional body set up for this
purpose, for appointment of an arbitrator as per provisions of the
C agreement entered between the claimant company and
respondents to resolve the dispute that arose in between the
claimant company and the respondents. To resolve the dispute in
between the parties, the CIAC assigned this matter to me (L.C.
Jain) as sole arbitrator. Notice of reference sent by the claimant
D company is dated 02.03.2012 and thereafter the arbitrator was
appointed and file was put up before the sole arbitrator who fixed
the date for appearance of parties.
… … …
The respondent was provided ample opportunities and time to
E settle the account but the respondent failed to settle the account
and ultimately the claimant issued notice dated 02.03.2012 invoking
the arbitration clause of the abovesaid agreements in order to
settle the dispute with the respondent in accordance to the
provisions of CIAC manual and requested to CIAC for referring
F the matter to arbitration and accordingly the matter has been
referred to arbitration. CIAC issued notice dated 30.05.2012 to
the respondents and asked for appearance and filing of reply/
written statement on 04.07.2012.
… … …
G On receipt of the notice by the respondent, the respondent wrote
to CIAC that an appeal has been filed before the Ld. Additional
District Judge, at Sealdah, Kolkata against the order of the Ld.
Civil Judge and the matter may be adjourned and accordingly the
matter was adjourned and intimation was sent to the respondents.
The respondent was also informed that without obtaining a stay
H
QUIPPO CONSTRUCTION EQUIPMENT LIMITED v. JANARDAN 279
NIRMAN PVT. LIMITED [UDAY UMESH LALIT, J.]
order from the court of Ld. Additional District Judge, at Sealdah, A
Kolkata, the proceedings will not be adjourned but the respondents
have not filed any stay order with CIAC in the arbitration
proceedings in this matter. For not putting appearance or by not
filing the reply/written statement, the respondent was proceeded
ex-parte and intimation of the same was sent to respondent by
B
CIAC. In fact, CIAC sent copy of all proceedings (orders) of
each date to the respondent but the respondent every time on
receipt of intimation from CIAC continued to send the request for
adjournment of the proceedings before the Sole Arbitrator through
CIAC and has never filed any copy of the stay order, if any passed
by the Ld. Additional District Judge, at Sealdah, Kolkata, nor filed C
any reply/written statement or objections for consideration of the
Sole Arbitrator.
… … …
The respondent has taken the plea before the Ld. Civil Judge that
the agreements as mentioned above have not been entered by D
him and all the documents are forged and fabricated and the Ld.
Civil Judge in his order in the Civil Suit No.189 of 2012 has
considered these pleas of the respondent and after due
consideration of these pleas, directed the respondent to join the
arbitration proceedings. … … E
Thus the claimant is entitled to receive from the respondent an
amount of :-
i) Rs.78,78,533/- (Rupees Seventy Eight Lacs Seventy
Eight Thousand Five Hundred Thirty Three only) i.e.
claim amount. F
ii) Interest @ 11% per annum on the amount of
Rs.78,78,533/- (Rupees Seventy Eight Lacs Seventy
Eight Thousand Five Hundred Thirty Three only) as
pendente lite interest from 2.3.2012 i.e. from date of
reference invoking arbitration till the date of award i.e. G
24.03.2015;
iii) Interest @ 11% per annum from the date of award i.e.
from 25.03.2015 till realisation;
iv) The claimant has deposited with CIAC the cost of
arbitration i.e. arbitration fee and allied charges pertaining H
280 SUPREME COURT REPORTS [2020] 6 S.C.R.
A to the portion of respondent amounting to Rs.1,47,072/-
(Rupees One Lac Forty Seven Thousand Seventy Two
only) and the claimant is entitled to receive the same
from the respondent.
Claimant has been directed to deposit stamp paper worth
B Rs.12,000/- with CIAC for pronouncing the award and the
claimant accordingly filed the stamp paper worth Rs.12,000/- with
CIAC and the award has been pronounced. The award has been
filed with CIAC.”
Soon after the award, OMP No. 449 of 2015 was filed by the
C appellant in the High Court of Delhi seeking relief under Section 9 of the
Act post the passing of the award.
9. The respondent being aggrieved filed a petition under Section
34 of the Act before the High Court at Calcutta being AP No.1141 of
2015, which was dismissed by the High court on 17.07.2015 after
D observing that it was not clear from the cause title how the petition could
have been filed in the High Court.
10. Thereafter a petition under Section 34 of the Act was filed by
the respondent being Miscellaneous Case No.298 of 2015 in the Court
of District Judge, Alipore. The respondent reiterated its case about non-
E existence of any agreement. It also stated, inter alia, that the venue of
arbitration in terms of the agreement dated 14.04.2011 was at Kolkata.
11. On 20.02.2016 the Appellate Court dismissed Miscellaneous
Appeal No.57 of 2014 as not being maintainable.
12. On 06.01.2007, OMP No. 449 of 2015 was rejected by the
F High Court of Delhi, inter alia, on the ground that no prime facie case
was made out by the appellant. It was, however observed that the dismissal
would not have any bearing on the decision that may be rendered in the
pending petition under Section 34 of the Act before the Court at Alipore.
13. Being aggrieved by the order dated 20.02.2016, the respondent
G filed Revision Petitions being CO Nos.1320 and 1322 of 2016 in the
High Court at Calcutta, which by its order dated 28.03.2017 dismissed
said Revision Petitions as not being maintainable but reserved rights of
the respondent to agitate all the issues within the ambit of Section 34 of
the Act, in the proceedings pending before the Court at Alipore. Special
Leave Petition (Civil) Nos.25279-25280 of 2017 arising therefrom were
H dismissed by this Court on 06.10.2017.
QUIPPO CONSTRUCTION EQUIPMENT LIMITED v. JANARDAN 281
NIRMAN PVT. LIMITED [UDAY UMESH LALIT, J.]
14. The petition filed by the respondent under Section 34 of the A
Act, viz. Miscellaneous Case No.298 of 2015 was, thereafter, dismissed
by the Court at Alipore on 13.08.2018 with following observations:-
“After perusal of the case record I find that there was an arbitration
clause in the agreement and the Arbitrator was appointed at New
Delhi and the Ld. Arbitrator has passed the award in favour of B
the opposite parties. The question of jurisdiction of Section 34 has
been raised. There are several case laws as cited by the Ld.
Lawyer for the opposite parties. From the said case laws it is
found that the jurisdiction of Section 34 is where the arbitration
award was passed or in the place where the seat of arbitration
was agreed by the parties. In the recent case laws reported in C
2017 SCC Online SC 4421, I find that the jurisdiction is exclusively
in that place where the arbitration was done. Ld. Lawyer, for the
petitioner referred the agreement in between the parties stating
that there is a Clause of arbitration at Kolkata but in reply the Ld.
Lawyer for the opposite parties stated that there are several D
agreements and the place of arbitration is mentioned in other
agreements is at Delhi and accordingly the arbitration has made
at New Delhi and this Court has no jurisdiction to entertain of this
Misc. Case U/s 34 of the Act and only Courts at Delhi have the
jurisdiction to entertain the same.
E
Accordingly, after careful scrutiny of the case record as well as
the observation of the Hon’ble Apex Court I find that the arbitration
award was passed at New Delhi and accordingly the Court of
New Delhi has the jurisdiction to entertain the application u/s 34
of the Arbitration and Conciliation Act. This Court has no
jurisdiction. So, the present case is bad for want of jurisdiction.” F
15. The respondent initially challenged the Order dated 13.08.2018
by filing Revision Petition (C.O. No.3400 of 2018) which was dismissed
as not being maintainable by the High Court at Calcutta on the ground
that a remedy of filing a petition under Section 37 of the Act was available.
The respondent thereafter filed appropriate petition being CAN No.10094 G
of 2018 which was allowed by the High Court at Calcutta vide judgement
dated 14.02.2019 with the following observations:-
1
Indus Mobile Distribution Pvt. Ltd. vs. Datavind Innovations Pvt. Ltd.: (2017) 7 SCC
678.
H
282 SUPREME COURT REPORTS [2020] 6 S.C.R.
A “Accordingly, since it is evident from the cause title itself that
the respondent herein was otherwise amenable to the
jurisdiction of the Alipore court, the order impugned dated
August 13, 2018 is set aside and Misc. Case No.298 of 2015
(R.No.385 of 2015) is restored to the board of the Additional
District Judge, 16th Court at Alipore.”
B
Said Judgment of the High Court is presently under challenge.
16. In the circumstances, it is clear that:-
(i) Though each of the four agreements provided for arbitration,
the award rendered by the Arbitrator was a common award;
C and
(ii) In one of the agreements the venue was stated to be Kolkata
and yet the proceedings were conducted at Delhi;
However, at no stage, the aforesaid objections were raised by the
D respondent before the Arbitrator and the respondent let the arbitral
proceedings conclude and culminate in an ex-parte award. Therefore,
the question that arises is whether the respondent could be said to have
waived the right to raise any of the aforesaid objections.
17. We heard Mr. Ritin Rai, learned Senior Advocate for the
appellant and Mr. Kuriakose Varghese, learned Advocate for the
E
respondent.
18. Mr. Ritin Rai, learned Senior Advocate submitted that all the
while the respondent was denying the existence of the agreements
between the parties; that after seeing the agreements in original the
Civil Court had accepted the application preferred by the appellant under
F
Sections 5 and 8 of the Act; that the decision rendered by the Civil Court
attained finality with the dismissal of Special Leave Petition by this Court;
that the respondent chose not to participate in the arbitration proceedings;
and that it was only at the stage of preferring petition under Section 34
of the Act that a submission was raised about the venue of arbitration. It
G was submitted that having chosen not to raise any objection on the issue
of jurisdiction or competence of the Arbitrator to go ahead with the
matter pertaining to issue covered by arbitration, the respondent must be
taken to have waived any such objection. It was submitted that, in any
case, the Arbitrator was appointed through Construction Industry
Arbitration Association (‘CIAA’, for short) which was also the modality
H under the agreement dated 14.04.2011.
QUIPPO CONSTRUCTION EQUIPMENT LIMITED v. JANARDAN 283
NIRMAN PVT. LIMITED [UDAY UMESH LALIT, J.]
In response, it was submitted by Mr. Varghese, learned Advocate A
that every arbitration agreement had to be considered independently
and if an agreement specified the venue to be at Kolkata, the party
autonomy in that behalf ought to be respected. Reliance was placed on
the decision of this Court in Duro Felguera, S.A. vs. Gangavaram
Port Limited2, where there were six arbitral agreements and each one
B
of them was subject matter of independent reference to arbitration.
19. Before we deal with the nature of controversy, we may extract
relevant provisions namely Sections 4, 16 and 20 of the Act.:-
“4. Waiver of right to object.- A party who knows that-
a) Any provision of this Part from which the parties may C
derogate, or
b) Any requirement under the arbitration agreement,
Has not been complied with and yet proceeds with the
arbitration without stating his objection to such non- D
compliance without undue delay or, if a time limit is provided
for stating that objection, within that period of time, shall be
deemed to have waived his right to so object.
………
16. Competence of arbitral tribunal to rule on its E
jurisdiction.-
(1) The arbitral tribunal may rule on its own jurisdiction, including
ruling on any objections with respect to the existence or validity
of the arbitration agreement, and for that purpose, -
a) An arbitration clause which forms part of a contract shall F
be treated as an agreement independent of the other terms
of the contract; and
b) A decision by the arbitral tribunal that the contract is null
and void shall not entail ipso jure the invalidity of the
arbitration clause. G
(2) A plea that the arbitral tribunal does not have jurisdiction shall
be raised not later than the submission of the statement of defence;
however, a party shall not be precluded from raising such a plea
2
(2017) 9 SCC 729 H
284 SUPREME COURT REPORTS [2020] 6 S.C.R.
A merely because that he has appointed, or participated in the
appointment of, an arbitrator.
(3) A plea that the arbitral tribunal is exceeding the scope of its
authority shall be raised as soon as the matter alleged to be beyond
the scope of its authority is raised during the arbitral proceedings.
B (4) The arbitral tribunal may, in either of the cases referred to in
sub-section (2) or sub-section (3), admit a later plea if it considers
the delay justified.
(5) The arbitral tribunal shall decide on a plea referred to in sub-
section (2) or sub-section (3) and, where the arbitral tribunal takes
C a decision rejecting the plea, continue with the arbitral proceedings
and make an arbitral award.
(6) A party aggrieved by such an arbitral award may make an
application for setting aside such an arbitral award in accordance
with section 34.
D
………
20. Place of arbitration. - (1) The parties are free to agree on
the place of arbitration.
(2) Failing any agreement referred to in sub-section (1), the place
E of arbitration shall be determined by the arbitral tribunal having
regard to the circumstances of the case, including the convenience
of the parties.
(3) Notwithstanding sub-section (1) or sub-section (2), the arbitral
tribunal may, unless otherwise agreed by the parties, meet at any
F place it considers appropriate for consultation among its members,
for hearing witnesses, experts or the parties, or for inspection of
documents, goods or other property.”
20. While dealing with a case where instead of an odd number of
Arbitrators, as is contemplated under Section 10 of the Act, the parties
G had agreed to arbitration of two Arbitrators and where objection in that
behalf was not taken before the Arbitrators, a three Judge Bench of this
Court in Narayan Prasad Lohia vs. Nikunj Kumar Lohia and others3
considered the amplitude and applicability of Section 4 of the Act. The
relevant paragraphs of the decision are:-
3
H (2002) 3 SCC 572
QUIPPO CONSTRUCTION EQUIPMENT LIMITED v. JANARDAN 285
NIRMAN PVT. LIMITED [UDAY UMESH LALIT, J.]
“5. On 22-12-1997 the 1st respondent filed an application in the A
Calcutta High Court for setting aside the award dated 6-10-1996.
On 17-1-1998 the 2nd respondent filed an application for setting
aside this award. One of the grounds, in both these applications,
was that the arbitration was by two arbitrators whereas under the
Arbitration and Conciliation Act, 1996 (hereinafter called “the said
B
Act”) there cannot be an even number of arbitrators. It was
contended that an arbitration by two arbitrators was against the
statutory provision of the said Act and therefore void and invalid.
It was contended that consequently the award was unenforceable
and not binding on the parties. These contentions found favour
with a Single Judge of the Calcutta High Court who set aside the C
award on 17-11-1998. On 18-5-2000 the appeal was also dismissed.
Hence this appeal to this Court.
………
8. Mr Venugopal submits that Section 10 of the said Act is a
mandatory provision which cannot be derogated. He points out D
that even though the parties are free to determine the number of
arbitrators such number cannot be an even number. He submits
that any agreement which permits the parties to appoint an even
number of arbitrators would be contrary to this mandatory
provision of the said Act. He submits that such an agreement E
would be invalid and void as the Arbitral Tribunal would not have
been validly constituted. He submits that composition of the Arbitral
Tribunal itself being invalid, the proceedings and the award, even
if one be passed, would be invalid and unenforceable.
9. Mr Venugopal submits that Section 4 of the said Act would F
only apply provided:
(a) a party knew that he could derogate from any provision of this
part, or
(b) a party knew that any requirement under the arbitration
agreement had not been complied with G
and the party still proceeded with the arbitration. He submits that,
this case does not fall under category (b) above. He submits that
even category ( a) would not apply because waiver can only be in
respect of a matter from which a party could derogate. He submits
that in respect of provisions which are non-derogable there can H
286 SUPREME COURT REPORTS [2020] 6 S.C.R.
A be no waiver. He submits that Section 10 is a provision from which
a party cannot derogate. He submits that matters from which a
party cannot derogate are those provided in Sections 4, 8, 9, 10,
11(4) and (6), 12, 13(4), 16(2), (3) and (5), 22(4), 27, 31, 32, 33,
34(2) and (4), 35, 36, 37, 38(1) and 43(3). He submits that, as
against this, matters from which a party can derogate are those
B
provided under Sections 11(2), 19(1) and (2), 20(1) and (2), 22(1),
24, 25, 26 and 31(3).
………
14. We have heard the parties at length. We have considered the
C submissions. Undoubtedly, Section 10 provides that the number
of arbitrators shall not be an even number. The question still
remains whether Section 10 is a non-derogable provision. In our
view the answer to this question would depend on the question as
to whether, under the said Act, a party has a right to object to the
composition of the Arbitral Tribunal, if such composition is not in
D accordance with the said Act, and if so, at what stage. It must be
remembered that arbitration is a creature of an agreement. There
can be no arbitration unless there is an arbitration agreement in
writing between the parties.
………
E
16. It has been held by a Constitution Bench of this Court, in the
case of Konkan Rly. Corpn. Ltd. v. Rani Construction (P) Ltd.4
that Section 16 enables the Arbitral Tribunal to rule on its own
jurisdiction. It has been held that under Section 16 the Arbitral
Tribunal can rule on any objection with respect to existence or
F validity of the arbitration agreement. It is held that the Arbitral
Tribunal’s authority under Section 16, is not confined to the width
of its jurisdiction but goes also to the root of its jurisdiction. Not
only this decision is binding on this Court, but we are in respectful
agreement with the same. Thus it is no longer open to contend
G that, under Section 16, a party cannot challenge the composition
of the Arbitral Tribunal before the Arbitral Tribunal itself. Such a
challenge must be taken, under Section 16(2), not later than the
submission of the statement of defence. Section 16(2) makes it
clear that such a challenge can be taken even though the party
4
H (2002) 2 SCC 388
QUIPPO CONSTRUCTION EQUIPMENT LIMITED v. JANARDAN 287
NIRMAN PVT. LIMITED [UDAY UMESH LALIT, J.]
may have participated in the appointment of the arbitrator and/or A
may have himself appointed the arbitrator. Needless to state a
party would be free, if it so chooses, not to raise such a challenge.
Thus a conjoint reading of Sections 10 and 16 shows that an
objection to the composition of the Arbitral Tribunal is a matter
which is derogable. It is derogable because a party is free not to
B
object within the time prescribed in Section 16(2). If a party
chooses not to so object there will be a deemed waiver under
Section 4. Thus, we are unable to accept the submission that
Section 10 is a non-derogable provision. In our view Section 10
has to be read along with Section 16 and is, therefore, a derogable
provision. C
………
20. Respondents 1 and 2 not having raised any objection to the
composition of the Arbitral Tribunal, as provided in Section 16,
they must be deemed to have waived their right to object.”
D
Thus, even stipulation in Section 10 that number of Arbitrators
“shall not be an even number” was found to be a derogable provision
and since no objections were raised to the composition of the Arbitral
Tribunal, as provided in Section 16, the concerned respondents were
deemed to have waived their right to object.
E
21. In Duro Felguera2 the submission that for convenience of
either side the original contract was split into five different contracts and
as such there ought to be a composite reference to arbitration covering
all the contracts was not accepted by this Court. It was found by this
Court:-
F
“42. … … The case in hand stands entirely on different footing.
As discussed earlier, all five different packages as well as the
Corporate Guarantee have separate arbitration clauses and they
do not depend on the terms and conditions of the Original Package
No. 4 TR nor on the MoU, which is intended to have clarity in
execution of the work.” G
Incidentally, it was a case of International Commercial Arbitration
and in each of those agreements the seat of Arbitration was at Hyderabad.
Moreover, the matter had arisen from an arbitration petition preferred
under Section 11(6) of the Act.
H
288 SUPREME COURT REPORTS [2020] 6 S.C.R.
A 22. In the present case the arbitration in question is a domestic
and an institutional arbitration where CIAA was empowered to and did
nominate the Arbitrator. It is not as if there were completely different
mechanisms for appointment of Arbitrator in each of the agreements.
The only distinction is that according to one of the agreements the venue
was to be at Kolkata. The specification of “place of arbitration” may
B
have special significance in an International Commercial Arbitration,
where the “place of arbitration” may determine which curial law would
apply. However, in the present case, the applicable substantive as well
as curial law would be the same.
23. It was possible for the respondent to raise submissions that
C arbitration pertaining to each of the agreements be considered and dealt
with separately. It was also possible for him to contend that in respect of
the agreement where the venue was agreed to be at Kolkata, the arbitration
proceedings be conducted accordingly. Considering the facts that the
respondent failed to participate in the proceedings before the Arbitrator
D and did not raise any submission that the Arbitrator did not have
jurisdiction or that he was exceeding the scope of his authority, the
respondent must be deemed to have waived all such objections.
24. In the circumstances, the respondent is now precluded from
raising any submission or objection as to the venue of arbitration, the
E conclusion drawn by the Court at Alipore while dismissing Miscellaneous
Case No.298 of 2015 was quite correct and did not call for any
interference. The High Court, in our view, was in error in setting aside
said Order. In any case, the fact that the cause title showed that the
present appellant was otherwise amenable to the jurisdiction of the Alipore
Court, could not be the decisive or determining criteria.
F
25. We, therefore, allow this appeal, set aside the Judgment and
Order under appeal and restore the Order dated 13.08.2018 passed by
the Court at Alipore in Miscellaneous Case No. 298 of 2015. No costs.
G Divya Pandey Appeal allowed.
H
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.