Created byFuzzy Cloud

Supreme Court of India

GREAT OFFSHORE LTD.versusIRANIAN OFFSHORE ENGINEERING & CONSTRUCTION COMPANY

Citation
2008 INSC 975
Decided
25 August 2008
Disposal
Appeal(s) allowed

Holding

A faxed charter party agreement that is signed by both parties satisfies the "in writing" requirement of Section 7 of the Arbitration and Conciliation Act, 1996, making it a valid arbitration agreement and justifying the appointment of an arbitrator.

Summary

Great Offshore Ltd. filed an arbitration petition asserting that a charter party agreement (CPA) faxed on 22 August 2005 contained a valid arbitration clause. Iranian Offshore Engineering & Construction Co. contested the existence of a binding contract, alleging the faxed CPA was a forged copy, lacked the respondent's seal, and was not an original. The Court held that the petitioner bore the initial burden to prove a valid arbitration agreement, which was satisfied by the faxed CPA’s apparent legitimacy and supporting correspondence; the burden then shifted to the respondent to prove forgery, which it failed to do. The Court interpreted Section 7 of the Arbitration and Conciliation Act, 1996 to accept faxed documents as "in writing" and required only signatures, not original copies, seals, or signatures on every page. Consequently, the faxed CPA was deemed a valid arbitration agreement, and the petition for appointment of a sole arbitrator was allowed.

Issues considered

  • The existence of a valid arbitration agreement under Section 7 of the Arbitration and Conciliation Act, 1996.
  • Whether a faxed document satisfies the statutory requirement of being "in writing" and signed by the parties.
  • Whether the alleged lack of original, seal, or signatures on each page defeats the validity of the agreement.
  • Whether the respondent proved that the faxed CPA was forged.

Legislation cited

Subjects

Arbitration agreementSection 7Faxed contractWritten formSignatureForgeryContract formationUNCITRAL Model LawAutonomy of willArbitration petitionCharter party agreement

Judgment

                                      [2008] 12 S.C.R. 515

  ../
                                 GREAT OFFSHORE LTD.                              A
                                               II.
                          IRANIAN OFFSHORE ENGINEERING &
                               CONSTRUCTION COMPANY
                            (Arbitration Petition No.1 O of 2006)
                                     AUGUST 25, 2008                              8

                     Arbitration and Conciliation Act, 1996:
                      s. 7 - Petition for appointment of arbitrator - On the
                basis of arbitration agreement faxed by petitioner - Claim of c
                respondent that there was no conclu(led agreement between
                parties and signatures on FAX agreement were forged -
                Held: Initial burden to prove that valid arbitration agreement
                existed was on petitioner - Fax header prima facie suggested
                that agreement was genuine - Burden shifted to respondent
                                                                                D
                to prove that the signatures on agreement were forged w~ich
                it failed to discharge - Thus valid arbitration agreement
     _,..       existed - Petition for appointment of arbitrator allowed -
                UNCITRAL Model Law on International Commercial
                Arbitration (1985).
                                                                                E
                       s. 7(4)(a) - Arbitration agreement - Essential elements
                of - Held: Arbitration agreement has to be in writing and
                signed by both the parties, though no need for parties to
                sign every page of the arbitration agreement - Also no
                requirement that it has to be original - The Act defines the F
  ,....,_
                term 'in writing' - Court is precluded from adding another
                term to the definition - Adding technicalities disturbs parties
                autonomie de la volonte - Interpretation of statutes - Adding
                or reading words into the statute.
                      s. 7(4)(a) - FAX agreement - AcceptabHity of, under s. 7.,... G
r-___.          Held: FAX falls under 'other means of telecommunication' -
                Hence acceptable under s. 7 - Court to view the legislative
                intention especially in the light of Act's main objectives of
                minimizing the supervisory role of Courts in the arbitral process.
                                              515                                   H
            (
    516       SUPREME COURT REPORTS            [2008] 12 S.C.R.


A         Words and phrases: 'Fax' - Meaning of
          The parties had done business with each other in
    2004. They expressed mutual interest for doing business
    for the second time. On June 23rd, 2005, the applicant-
    petitioner faxed an offer to the respondent. In turn, the
8   respondent faxed a letter of intent on the same day.
    Applicant acknowledged the award of contract in favour
    of respondent.
         On August 13th, the respondent faxed a letter to
c   the respondent, suggesting that additional provisions
    be incorporated in a new draft of the contract and further
    asked the applicant to pay the outstanding amount from
    the preceding contract.
       On August 22nd, the applicant allegedly sent the
D faxed Charter Party Agreement (CPA) to the respondent.
  Both parties signed the faxed CPA, and it bore the
  applicant's seal. However, it did not bear the
  respondent's seal. On October 26, the respondent
  originally asserted that it never signed the faxed CPA
E and that the document was forged.
       The applicant filed the present petition seeking
  appointment of sole arbitrator. The respondent
  contended that the two parties had not progressed
  beyond the stage of negotiation and that there was no
F concluded contract between them and hence there was
  no question of referring the dispute to arbitration; and
  the "faxed CPA" of August 22nd was (1) a copy, not the
  original; (2) was stamped by one, not by both parties;
  (3) one of the parties did not sign every page; and (4) it
G was first sent vide fax.
          Allowing the petition, the Court
       HELD: 1.1. The burden to prove that a valid contract
  containing an arbitration clause existed first rested on
H the applicant, as it was the applicant who moved this
             GREAT OFFSHORE LTD. v. IRANIAN OFFSHORE          517
                     ENG. & CONST. COMPANY

   v    Court. The faxed CPA, on its face, appears legitimate,       A
        thus the onus shifted to the respondent to prove that it
        was forged. It appears, prima facie, to be legitimate
        because it bears the heading "08-SEP-2005 13:52 FROM
        IOEC HEAD OFFICE TO ALLAHVER[)I" (the "fax
        header"). This is an important piece of evidence that        s
        makes its genuineness more probable. Hypothetically,
        the applicant could have fabricated the fax header. But
        that is highly unlikely and presumes much more than
        what is expected in normal human conduct especially
        when that conduct concerns the forgery of an executive       c
        officer's signature. It should not be forgotten that this
        case is between sophisticated companies, not warring
        family members that dispute the authenticity of a Will.
        [Para 55] [536-F-H, 537-A]
            Dresser Rand S.A. v. Mis. Bindal Agro Chemical Ltd.      D
        & Another, AIR 2006 SC 871 - relied on.

              May & Butcher Limited v. The King (1934) 2 KB 17; Ml
        s. Rickmers Verwaltung Gimb .H v. Indian Oil Corporation
        Ltd., AIR 1999 SC 504 - referred to.
                                                                     E
            Chitty on Contracts [29th Edn. Vol.1] - referred to.
              1.2. There is no evidence· to suggest that the faxed
        CPA was forged. To the contrary, the evidence is the
        faxed CPA bearing the parties' signatures coupled with
        correspondence         between      the    parties.    The F
        correspondence, as it is more than just a pleading, adds
        additional weight to the applicant's story. The applicant's
        letter of 21st October corroborates the allegation that
        respondent's official delivered the faxed CPA to the
        applicant on 12th September. The date of delivery of G
        12th September fits the timeline provided on the fax
t- "·   header, as the respondent could only have delivered
        the faxed CPA after 8th September. Moreover, it appears
        that having received the faxed CPA on 12th September,
        the applicant was prompted to ask for the original vide H
    ....



           518       SUPREME COURT REPORTS             [2008] 12 S.C.R.


A          email on 14th September. Once again, the dates match           ·"*
           up. [Para 57] [537-C-E]
       2.1. In terms of Section 7(3) and 7(A)(a) of Arbitration
  and Conciliation Act, 1996, the arbitration agreement has
  to be in writing and signed by the parties. There is no
B requirement that the arbitration agreement has to be an
  original. Where the statute has gone to great lengths to
  define exactly what is meant by the term "in writing,"
  the Court is precluded from adding another term to
  definition. Indeed, "it is contrary to all rules of
c construction to read words into an Act unless it is
  absolutely necessary to do so." An exception to this                          I
  rule can be made. But before adding words to a statute,                       ~
  the Court must be abundantly clear of three matters: (1)
  the intended purpose of the statute or provision in
  question, (2) that by inadvertence the draftsman and
D Parliament failed to give effect to that purpose in the
  provision in question; and (3) the substance of the
  provision Parliament would have used, had the error in
  the Bill been noticed. One of the main objectives of the
  Arbitration and Conciliation Act, 1996 is to minimise the
E role of the Court; adding additional requirements to the
  Act is antithetical to such a goal. [Paras 61- 64] [539-
  E,G-H, 540-A,B]
                 Bihar State Mineral Development Corporation & Another
           v. Encon Builders (1) (P) Ltd., (2003) 7 SCC 418; K.K. Modi
F          v. K.N. Modi & Others, (1998) 3 SCC 573; Renula Bose
           (Smt.) v. Rai Manmathnath Bose, AIR 1945 PC 108;
           Assessing Authority-Cum-Excise and Taxation Officer,
           Gurgaon & Another v. East India Cotton Mfg. Co. Ltd.,
           Faridabad (1981) 3 SCC 531 - relied on.
G              Stock v. Frank Jones (Tiptan) Ltd., (1978) 1 All ER 948,
           p.951;
                 Justice G.P. Singh's Principles of Statutory
           Interpretation, 11th Edition, 2008 - referred to.
H                2.2. Section 7 does not require that the parties stamp
     GREAT OFFSHORE LTD. v. IRANIAN OFFSHORE           519
             ENG. & CONST. COMPANY

the agreement. It would be incorrect to disturb the          A
Parliament's intention when it is so clearly stated and
when it in no way conflicts with the Constitution. [Para
65] [540-C]
     2.3. Nothing in Section 7 suggests that the parties
must sign every page. Even if the faxed CPA is construed 8
as a "document," it need only be "signed by the parties"
pursuant to Section 7(4)(a). Every page does not need
to be signed. If it is considered a "document," then this
requirement would be met. Both parties signed the faxed
CPA in the signature box at the bottom of Part I. That C
said, the faxed CPA more closely fits within Section
7(4)(b)'s requirements. [Para 66] (540-D-F]
     2.4. Section 7(4)(b) states that an agreement is in
writing if it is contained in "an exchange of letters, telex,
                                                              0
telegrams or other means of telecommunication which
        a
provide record of the agreement." This section covers
agreements that are sent via facsimile ("fax") as they are
"other means of telecommunication". "Fax" is defined as
"a machine that scans documents electronically and
transmits a photographic image of the contents to a E
receiving machine by telephone line'' or "a document
received by such a machine." This definition clearly provides
that a fax falls under "other means of telecommunication."
Thus, faxed agreements are acceptable under Section 7 of
the Act. [Para 67] [540-F-H, 541-A]                           F
     Chambers 21st Century Dictionary - referred to.
      2.5. With no evidence to indicate that the
respondent's signature was forged, the faxed CPA
stands on its own as the record of agreement. Likewise, G
Section 7(4)(b) stands satisfied. The court has to
translate the legislative intention especially when viewed
in light of one of the Act's "main objectives": "to minimise
the supervisory role of Courts in the arbitral process.
Adding technicalities disturbs the parties' "autonomy of H
    520      SUPREME COURT REPORTS                [2008] 12 S.C.R.


A the will" (I' autonomie de la volonte}, i.e., their wishes. If
  this Court adds a number of extra requirements such as
  stamps, seals and originals, then ·the parties' intention
  to arbitrate would be foiled by formality. Such a stance
  would run counter to the very idea of arbitration, wherein
B tribunals all' over the world generally bend over
  backwards to ensure that the parties' intention to
  arbitrate is upheld. [Paras 68- 71] [541-8,C,E,F]
       2.6. Technicalities like stamps, seals and even
  signatures are red tape that have to be removed before
C the parties can· get what they really want - an efficient,
  effective and potentially cheap resolution of their dispute.
  The autonomie de la volonte doctrine is enshrined in the
  policy objectives of the United Nations Commission on
                                                                     "
                                                                     i



  International Trade Law ("UNCITRAL") Model Law on
D International Commercial Arbitration, 1985, on which
  Indian Arbitration Act is based. The courts must
  implement legislative intention. It would be improper and
  undesirable for the courts to add a. number of extra
  formalities- not envisaged by the legislation. The courts
E directions should be to achieve the legislative intention.
  [Para 71, 72] (541-H, 542-A-C]'
          Law and Practice of International Commercial
    Arbitration, Alan Redfern and Martin Hunter, Street & Maxwell,
    London, 1986; · Model Law on International Commercial
F   Arbitration, 1985 - referred to.
        3.1. Once it is established that the faxed CPA is
  valid, it follows that a valid contract and a valid arbitration
  clause exist. This contract, the faxed CPA, does not suffer
G from a conditional clause, as did the Letter of Intent.
  Thus, the respondent's argument that the parties were
  not ad idem must fail. [Para 74] (542-G]
       3.2. The charter party agreement that had been
  signed by the applicant and the respondent clearly
H indicated that the parties have entered into a valid and
           GREAT OFFSHORE LTD. v. IRANIAN OFFSHORE             521
                   ENG. & CONST. COMPANY

~f concluded contract. The other correspondence between · A
     the parties also leads to a definite conclusion: the parties
     have entered into a valid contract containing an
     arbitration clause. Since a dispute has arisen between
     the applicant and the respondent, it needs to be referred
     to the arbitrator. On consideration of the totality of the      B
y
·,   facts and circumstances, the applicant is entitled in law
     to an order for appointment of a sole arbitrator.
     Consequently, Hon'ble Justice S.N. Variava, the retired
     Judge of the Supreme Court is requested to accept this
     arbitration. [Para 75, 76] [542-H, 543-A,C]                     c
                          Case Law Reference
          AIR 2006 SC 871              relied on     Para 51
          AIR 1999 SC 504              referred to   Para 51
          {2003) 1 sec 418             relied on     Para 61         D
          (1998) 3 sec 573             relied on     Para 61
          AIR 1945 PC 108              relied on     Para ?3
          (1981) 3 sec 531             relied on     Para 63
          ORIGINAL CIVIL JURISDICTION : Arbitration Petition No.     E
     10 of 2006
         S.K. Mukherjee, Vivek Kishore, Sangeeta Bharti, Ruchi
     Gaur Narula and S.R. Setia for the Appellant.
         Shrish Kumar Misra, Garbesh Kabra, Ajay Kr. Singh and       F
~    Uma Bhattacharya for the Respondents.
          The Judgment of the Court was delivered by
           DALVEER BHANDARI, J. 1. Great Offshore Limited
     has filed a petition under section 11 (5)(6)(9) and (12) of the G
     Arbitration and Conciliation Act, 1996 whereby the applicant
     seeks the appointment of a sole arbitrator. The applicant, Great
     Offshore Ltd., submits that it has entered into a charter party
     agreement with the respondent, Iranian Offshore Engineering
     & Construction Company. The charter party agreement ("CPA") H
     522        SUPREME COURT REPORTS                   [2008] 12 S.C.R.


 A contains an arbitration clause. Relying on this'.. Clause, the
   applicant has asked this Court to appoint an· arbitrafor to
   resolve the dispute. The respondent, however, contends that
   the two parties had not progressed beyond the stage of
   negotiation and that there is no concluded contract between
 B them. Therefore, it is argued that th·ere is no question of
   referring the dispute to arbitration.
           2. BriefJ facts which are relevant to dispose of this
     arbitration petition are recapitulated below.
         3. The charter party agreement in dispute marks the
 C second time the parties have done business with each other.
   The first time was in 2004. In March of that year, the respondent
   entered into a contract with the Oil and Natural Gas
   Corporation Limited ("ONGC") to carry out construction work
   on ONGC's installations at Bombay High. On 26th October,
 D 2004, the applicant and the respondent entered into a charter
   party agreement. Under this prior agreement, the respondent
   hired a vessel combination from the applicant. The respondent
   required a specialized offshore construction barge known as
   a "Gal Constructor." It also required an anchor handling tug,
 E named "AHT Malaviya Five." The AHT Malaviya is used in
   combination with the Gal Constructor. I shall refer to the Gal
   Constructor and the AHT Malaviya as the "vessel combination."
         4. The respondent needed this combination to. execute
    offshore work for ONGC. This work was part of ONGC's
 F RSPPM project, Phase I. The first phase was completed in
  : November 2004.
          5. In this case, the controversy is confined to the alleged
     agreement relating to the second phase of ONGC's project.
 G           6. In this arbitration petition, I need to decide whether the
      pa'rties have entered into a valid contract containing an
       arbitration clause. To this end, it has become imperative to
       review the relevant correspondence between them. Only then
      will I be able to arrive at a conclusion as to whether there was
       a concluded contract or whether the parties had never
. H , ·progressed beyond the stag~ of negotiation.             ..... ·
             GREAT OFFSHORE LTD. v. IRANIAN OFFSHORE 523
            ENG. & CONST. COMPANY [DALVEER BHANDARI, J.]
..,.r        7. After the parties expressed mutual interest in resuming          A
        business for Phase 11, the respondent faxed a letter to the
        applicant. The letter is dated June 20th, 2005. In this letter, the
        respondent expressed its intention to use the applicant's
        vessel combination for 170 days pursuant to the same terms
        as the preceding agreement. A few amendments, however,                   B
        were to be made to that agreement.
'
'f

              8. The applicant responded vide email the next day and
        stated that it would like to "come to an agreement." After
        meeting the respondent on 22nd June, the applicant faxed an
        offer to the respondent on June 23rd, 2005.                              c
              9. In turn, the respondent faxed a letter of intent on June
        23rd, 2005. The letter stated that it was " ... a firm and
        unconditional letter of intent (for short LOI) for award of contract
        for charter hire of your barge Gal Constructor and Malviya 5".
                                                                                 D
        Nevertheless, the very same letter contained a contingency clause:
             "This Agreement is subject to IOEC [respondent]
             providing a suitable barge and AHT acceptable to GE
             Shipping [applicant] for a period of 45-55 days on
             mutually agreed rates for commencement between 25th                 E
             October and 10th November 05 for BHN MOL project
             works."
               10. On July 15 \ 2005, the respondent's minutes of


.       meeting indicate that the barge (vessel) was to be available
        for visual examination .i ••• until 25th of July after which the barge
        will leave AJMAN port in UAE for the project in PG".
                                                                                 F


              11. On August 4th, 2005, the applicant explained that it
        no longer wanted the respondent to provide a barge for 45-
        55 days, as mentioned in the respondent's June 23rd letter of
                                                                         G
        intent. Because the parties could not agree on the rate for this
        service1 the applicant said that it would make alternate
        arrangements.
             12. On August 11th, the respondent sent a letter in regard
        to modifying the Barge Gal Constructor so that it could function         H
      524          SUPREME COURT REPORTS                [2008] 12 S.C.R.


      as a riser installation barge. Based on its engineering analysis,
                                                                            '-r
A
      it sought to install " ....5 davits in the port or STBD side at the
      barge" as well as a " ... working platform as an extension to
      main deck in the aft quarter over one of the anchor rests".
             13. In response to a meeting on August 8th and the above
B     letters, the respondent faxed a letter to the applicant on August
                                                                                f
      13th, 2005. The letter suggested that additional provisions be         :.>f..

      incorporated in a new draft of the contract. The respondent
      requested the right to modify the Gal Constructor, thereby
      enabling it to perform a riser installation. The respondent further
c     asked the applicant to pay the outstanding amount (USO
      188,500) from the preceding contract. In conclusion, the
      respondent stated that it would be willing to finalize the contract
      before the 30th of August.
        14. On 16th August, the parties met to discuss the
D proposed changes. The applicant formally responded to the
                                                                                      "'
  respondent's suggestions in a letter dated August 22nd, noting             .._
  that the parties had come to the following agreement regarding
  a number of outstanding issues:                                            '.)-



      S. No.         Clause                  Agreement
E
         1   Modifications for Riser Clause on the basis of
             Installation            Addendum 3 to Charter
                      '              Party dated 26th Oct 04 to
                                     be incorporated ·
f •      2       Early Termination Clause It was mutually agreed not to
                                          include the clause suggested
         3       Employment of vessel      Clause as per Charter
                                           Party dated 26th Oct 04 to
                                           be incorporated
G       4        Sublet Clause             Clause 17 of the charter
                                           party to be referred in
                   d
                                           additional clause pertaining
            ,.                             to sublet
         5       . Cred.it note issue      Addressed hereunder
H
           GREAT OFFSHORE LTD. v. IRANIAN OFFSHORE 525
          ENG. & CONST. COMPANY [DALVEER BHANDARI, J.]
~·
           ... we confirm our acceptance of the credit note amounting         A
           to US$186,618 ... for subject vessel combination for
           charter party dated 25th Oct 2004 .... "

            15. Before proceeding with the correspondence, it is
      pertinent to note that the faxed charter party agreement ("faxed
      CPA") is dated August 22nd. After having settled a number of            B
'¥
;y.   outstanding issues vide the above letter, the applicant allegedly
      sent the faxed CPA to the respondent on the same day.

           16. The faxed CPA officially entitled the "Charter Party
      for Offshore Service Vessels Code Name 'Supplytime 89"'
      dated August 22nd, 2005 is reproduced, in relevant part. The            c
      "charterer" is the respondent, and the applicant is the "owner":

           1. Place & Date. Mumbai, India. 22nd August 2005.        . ..

           9. Period of Hire.           204 days firm I minimum ...
                                                                              D
           14. Early termination of charter (state amount of hire payable)
           (Cl. 26(a))                 Not Applicable.

           18. Employment of Vessel restricted to (state nature of
           service(s))

           (Cl Sa)) Hook up, commissioning, accommodation and                 E
           offshore Installation work such as I-Tube installation and Riser
           Installation and all other activities of RSPPM Project, within
           Vessel's natural Capabilities and safe practices/ operations.

           19. Charter Hire (state rate & currency) (Cl 10(a) & (d))
                                                                              F

-·         22. Payments ...
                                              USO 31,000 ... PDPR ...



                 Payments shall be made against acceptable,
                 unconditional, revolving and irrevocable Letter of Credit
                                                                              G
                 issued at sight by the Charterer's bank for USO
~                6,500,000 ...
                 These L/C(s) to be opened, latest by 15th September
                 2005. However draft of L/C(s) should be provided to the
                 Owners by 1st September 2005.                                H
    526        SUPREME COURT REPORTS                    [2008] 12 S.C.R.


A         33. Law and arbitration (state Cl 31 (a) or 31 (b) or 31 (c), as
          agreed, If 31c agreed also state place of arbitration) (Cl.31)
          Clause 31 (c)-lndianArbitration and Conciliation Act, 1996 at
          Mumbai                                       •

B
                                                                               '(
          17. I must provide some background before dealing with             ·¥
     other documents, as the faxed CPA sits at the center of this
    .dispute.
C       18. It appears that both parties signed the faxed CPA,
  and it bears the applicant's seal. However, it does not bear
  the respondent's seal. The applicant contends that it had sent
  the original to the respondent on August 22nd. The respondent
  did not return the original. Instead, on September 8th, the
D respondent's head office faxed a copy of the CPA to its local
  office. [The top of the said fax shows the date and time as                .;-·
  well as the place from and to which it was sent; it reads "08-
  S E P-2005 13:52 FROM IOEC HEAD OFFICE TO
  ALLAHVERDI"]. This faxed copy is signed by the. respondent'~
  Project Director, Mr. M. Sabbaghi.
E
        19. The respondent's Mr. Ali Rahmati provided the
  applicant the faxed CPA on October 12th, according to the
  applicant's letter dated October 21st. In a letter dated October
  26, the respondent originally asserted that it never signed the
F faxed CPA and that the document was forged.
        20. Between the date on which the applicant sent the
  faxed CPA - 22nd August - and the date on which the
  respondent reportedly returned it to the applicant - 12th
  September, ONGC had advised the respondent to get the
G vessel combination certified before proceeding with a Riser
  installation. ONGC's letter dated 30th August stated that the
  vessel did not have any past track record with riser installations.
         21 . The applicant later expressed concern that the
    respondent's failure to return the original contract, i.e., charter
H
               GREAT OFFSHORE LTD. v. IRANIAN OFFSHORE 527
              ENG. & CONST. COMPANY [DALVEER BHANDARI, J.]
  o/      party agreement, could result in undue delay. In an email sent        A
          at 9:03 a.m. on 14th September, the applicant stated, in
          relevant part, that:-
               "... You would appreciate that it is imperative for us to have
               the charter party with us in order to initiate actions from
               various departments such as operations, fleet personnel,         B
  ';
  ,'.¥         accounts etc to prepare for the said contract and in
               absence of this document we are not in a position to push
               for same. This will result in last minute hassles and delays.
                   "
                                                                                c
               22. The respondent's email rejoinder came at 4:31 p.m.
          on the same day. The relevant part reads as under:-
               "

               The CPA of Gal Constructor and Malavya 5 is ready in our
                                                                        D
               office and will be hand over to you.
   '"!'

                   "
                23. On September 15th, 2005, the applicant sent the
          following email to the respondent. It reads in relevant part as
          under:-                                                               E

               "1. Understand that charter party is ready in your office.
               However, we are yet to receive the same and urgently
               require it to be circulated among the concerned
               departments so that they are prepared for the next contract.     F
 ~'\-          Will get in touch with your office again today for the same_
                   "

               24. The respondent faxed a letter dated September 23rct,
          2005 to the applicant. The letter asks the applicant to issue
          a cheque for the outstanding amount due from the parties' G
          Phase I work. It further demands that the applicant grant the
;~
          respondent the sole and absolute right to sublet the vessel to
          its subcontractor(s) at the agreed charter party rate. It
          concludes by saying that the respondent " ... can not conclude
          the charter party agreement until the above issue are settled." H
      528        SUPREME COURT REPORTS                  [2008] 12 S.C.R.

                                     h                                       ~~
. A          25. On September 24t , the respondent met with Likpin              1


      . Engineers to discuss whether the applicant's vessel could be
        converted to perform a riser installation. Likpin surveyed the
        vessel on_ 23rd September 2005 and, in the following minutes,
        concluded that:- .
 B·
            "Taking into account the number of problems associated
                                                                                '(
            with the vessel, it is the conclusion of Likpin and IOEC that     :¥..
                                                                               I


            the Gal Constructor is not suitable as a riser installation .
            . . . the vessel size combined with the limited crane reach ,
            cannot be corrected or overcome and hence the vessel
 c          should not be chart~red for riser installation operations."
            26. fn a letter dated September 27th, 2005, the
      respondent again asked the applicant to issue a cheque or
      remit $186,618. It once again demanded that it be granted
      the right to sublet the vessel and that until those issues were
 0
      settled, it could not conclude the CPA.
           27. In a letter dated September 29th, 2005, the
      respondent reiterated its demands, namely, that the applicant          ::..
      remit $186,618 and that it provide the respondent with the
 E    sole and absolute right to sublet the vessel combination. It
      admitted that this payment had nothing to do with Phase 11 of
      the project and thus " ... has no connection with the current
      negotiations and should be closed out immediately, so that
      Phase II can begin on a clean slate." It further stated that:
 F          " ... the sole and absolute right to sublet the vessel to IOEC
                                                                              -1·
            subcontractors ... is an essential element in IOEC work            ·'
            plan for Phase II. ... Lack of, or delay in, the ability to
            exercise the sublet option will impact on IOEC work plan
            and also affect the cost schedule of RSPPM project and
 G          is not acceptable to IOEC. Please note that time is running
            short and in absence of GESCO's immediate compliance               ;>---<
            with above two requirements IOEC may be compelled to
            tal<e recourse to other options .... "
            28. The applicant responded to ti1e above with the
 H
                 GREAT OFFSHORE LTD. v. IRANIAN OFFSHOR~ 529
                ENG. & CONST. COMPANY [DALVEER BHANDARI, J.]
     o/     following letter dated 30th September 2005. The relevant part       A
            reads as under:-
                 "... We are in the process of arranging funds to be remitted
                 to you against the said amount and will confirm remittance
                 as soon as possible. 2) Your request for sole and absolute
                 right to sublet the vessel is not acceptable to us. The LOI    8
      '
     .~
                 for the contract has been issued by you on 23rd June 2005
                 after we mutually agreed on the terms and conditions of
                 charter party. Thereafter, on your request, we have provided
                 with you with signed originals of the charter party on 22nd
                 August 2005 for your signatures. You have accepted the         c
                 same and conformed to us vide your letter communique
                 dated 14 September that he charter party has been signed
                 and is ready in your office and will be handed over to us.
                 Previous to that, you have also sent us letter saying that
                 you confirm that the charter party will be finalized by 30     D
    - ...        August 2005. While we have been provided a photocopy
                 of the signed charter party by your office, it is now 30
                 September and rather than keeping your commitment and
                 returning the original and issuing the UC as promised,
                 you are deliberately delaying the same.                        E
                 29. The letter goes on to demand that the respondent
            immediately issue the signed, stamped original charter party
            agreement as well as the irrevocable line of credit. The
            applicant further demanded that both tasks be completed by
            1st October at 1200 hours.                                          F
   ~ '\

                  30. Vide letter dated 1oth October, the applicant informed
            the respondent that the applicant's vessel combination arrived
            at P & V Channel, Mumbai on October 6th. Because it had yet
            to receive the line of credit, it informed the respondent that it
                                                                              G
            could not proceed further with the mobilization of the vessel
~ "'-       combination. The applicant provided the respondent with an
            invoice for mobilizing its vessel combination. It gave the
            respondent another chance to comply with the purported
            contract: "please note that contractual hire will begin as and
                                                                              H
    530       SUPREME COURT REPORTS                [2008] 12 S.C.R.

                                                                       ~'+-
A from 0000 hours of the 11th October 2005. We on our party
  stand ready and willing to comply with all our obligations."
        31. In its October 101h letter, the respondent reiterated
  that the terms of the agreem.ent were still under negotiation
  and that no contracted had been concluded. It objected to the
B absence of a provision that provided the respondent with the
                                                                          ~
  absolute right to sublet the vessel.                                  ¥
         32. It also argued that the applicant's vessel combination
  was not fit for the agreed purpose. This issue is beyond the
c scope of this decision, which limits itself to deciding whether
  or not a contract containing an arbitration clause was formed.
  While I have made mention of some of the other issues, such
  as whether the vessel was fit for the agreed purpose, I need
  riot rehash each and every one. All matters, save for whether
  the alleged contract/arbitration clause was formed, would be
D
  more appropriately addressed by an Arbitral Tribunal.
                                                                         -r
        33. The letter goes on to state that it would still consider
  hiring the applicant's vessel combination if it received the
  right to sublet and also if the crane were made fit for the
E purpose   for which the respondent intended. On 1ath October,
  the respondent sent a letter in which it stated that it would
  have to look for a vessel from an alternative provider. The
  respondent said that it would treat the matter with the applicant
  as "closed." It concluded by asking the applicant to pay the
F amount due for Phase I. It sent a letter on 20th October
  reiterating the same.                                                   ·/·,

         34. On 21st October, the applicant sent a letter detailing
    the sequence of events that had occurred between the parties.
    Para 5 of the said letter is reproduced as under:-
G
          "The Charter Party Agreements, two originals duly signed
          and stamped by us, were submitted to your office on 22nd            :r-.
          August 2005 requesting you to forward us one original
          after execution of the same from your side. You never
          returned one original for our records. However, your Mr
H
                GREAT OFFSHORE LTD. v. IRANIAN OFFSHORE 531
               ENG. & CONST. COMPANY [DALVEER BHANDARI, J.]
    ¥
                Ali Rahmati had handed over to us a fax copy of the               A
                formal Charter Party document signed by your Mr.M.
                Sabbaghi when we had a meeting with him on 12th
                September 2005. A copy of the same is enclosed herewith
                for your perusal."
                  35. In its 25th October letter, the respondent once again       B
     ~
    ·~·
           claimed that the charter party remained unconcluded. It alleged
           that the faxed copy of the charter party agreement was "forged
           and the story of delivery false and concocted." Moreover, it
           stated that "sipce we have found the vessel completely unfit
           for riser installation as the said vessel with the present condition   c
           of the crane is not suitable at all, therefore we thought fit to
           withdraw from the negotiation .... " It claimed that the applicant
           had misrepresented its vessel's ability to perform a riser
           installation. Thus, it thought this misrepresentation had vitiated
           the negotiations. At this point, it appeared that their relationship   D
    --+    had officially soured.

     .4,
                 35. In its letter dated 15th November, the respondent
           reiterated much of what is already provided above. Of interest,
           it stated that:-
                                                                                  E
                "You are aware that initially, we intended to hire the vessel
                combination for only 170 days. However, since you agreed
                to take barge and AHT from us for 45-55 days, we agreed
                to extend the intended hire period from 170 days to 200
                days and accordingly in this background the said LOI was F
   -"\          issued. However, since thereafter you unilaterally declined
                to take our barge and AHT on the ground of difference in
                rate levels offered by us, we, in view of the said condition
                and in the light of your refusal to accept our barge and
                AHT, asked you for absolute subletting right of the said
                                                                              G
                vessels to compensate us/minimize our expenses for risk
:- -;\          of additional days than the originally intended 170 days.
                The correspondences which were exchanged between
                us make it aptly clear that negotiations and change in
                terms and conditions from your side continued even after
                                                                                  H
    532       SUPREME COURT REPORTS                 [2008] 12 S.C.R.


A         issuance of LOI and therefore the question of concluding "'-+·
          the CPA in respect of RSPPM project phase-II does .not ~~
          arise at all."
         37. In its December 2nd, 2005 letter, the respondent called _
    upon the applicant to arrange for a third party inspection of
8   the applicant's vessel, in order to determine whether or not it
    was suitable for riser installation.
         38. In response, on 23rd January 2006, the applicant
    served the respondent with a notice of arbitration. On 2nd
c   February 2006, the respondent replied to the same.
        39. With the relevant correspondence 9utlined above, I
  turn to the parties' main submissions. The applicant contends,
  inter alia, that the faxed copy of the charter party agreement
  ("faxed CPA") dated 22nd August is a binding, concluded
D contract. The applicant gives four reasons for this assertion.
       40. First, the faxed CPA is signed by both parties.
  Second, the applicant's statement to this effect was not denied _,.
  in the pleadings [See the last page of the respondent's
  supplementary written submission of May 13th, 2005: (" ... it
E was not s_igned properly and but for the last page, the said fax
  communication, did not bear signature on other page.")
          41. Third, the respondent admitted in its letter dated 14th
    September that the original CPA" ... is ready in our office and
F   will be hand to you." The applicant argues that because the
    applicant had already signed the original CPA, there was
    nothing left for the respondent to do but sign. Hence, by saying
    it was "ready", I may infer that it was signed.
       42. Fourth, the respondent's letter of 101h October did
G not deny the fact that the original CPA was signed by the
  respondent and was waiting in the respondent's office, even
  though the applicant had asserted as much in its letter dated
  30th August. It was not until 261h October that the respondent
  deemed it necessary to deny this fact.
H
                GREAT OFFSHORE LTD. v. IRANIAN OFFSHORE 533
               ENG. & CONST. COMPANY [DALVEER BHANDARI, J.]
  ¥        43. The respondent contends that because the original                 A
     signed copy was never given to the applicant, the parties
     were in negotiations at all times. With respect to the faxed
     CPA, it points to the fact that the respondent did not sign
     every page. It gives further weight to the fact that the faxed
     copy was not sent vide fax from the respondent to the applicant;            B
   I rather, it was first sent vide fax from the respondent's main
  )(
     office to its local branch.
                  44. Learned counsel for the respondent states in its written
           submission that " ... the respondent failed to even sign the
           formal contract document that the applicant had sent to it for        c
           its signature." It argues that because the original CPA was not
           signed by the respondent, the Court will have to find a contract,
           if any, in the correspondence. According to Mulla:-
                "In construing whether or not a particular agreement does
                                                                                 D
  ......        or does not amount to a contract, the court would look for
                the intention of the parties, the nature of the transaction,
                the language employed in the informal agreement and
                other relevant circumstances. None of these is conclusive
                in itself.... The fact that the parties contemplate that the
                letters or an informal agreement would be superceded by E
                a more formal one, does not prevent it from taking effect
                ~s a contract. If the letter of intent is acted upon, especially
                for a length of time, the court is likely to hold the parties
                bound by the contract." [See Mulla, Indian Contract and
                Specific Relief Acts, 13th Edition at pages 317-318].            F
 ~-\
                 45. In Dresser Rand S.A. v. Mis. Bindal Agro Chemical
           Ltd. & Another, AIR 2006 SC 871 at page 884 at para 34, a
           two-Judge Bench of this Court emphasized that whether letters
           of intent rise to the level of being a contract hinges on the
                                                                         G
           terms of the letter itself. It observed as under:-
~-
                "It is no double true that a Letter of Intent may be construed
                as a letter of acceptance if such intention is evident from
                its terms. It is not uncommon in contracts involving detailed
                procedure, in order to save time, to issue a letter of intent    H
    534       SUPREME COURT REPORTS                  (2008] 12 S.C.R.


          communicating the acceptance of the offer and asking
                                                                         ~
A
                                                                                 ~
          the contractor to start the work with a stipulation that the
          detailed contract would be drawn up later. If such a letter
          is issued to the contractor, though it may be termed as a
          Letter of Intent, it may amount to acceptance of the offer
B         resulting in a concluded contract . . . . But the question
          whether the letter of intent is merely an expression of            I
                                                                         ¥-
          intentic?n to place an order in future or whether is a final
          acceptance of the offer thereby leading to a contract, is
          a matter that has to be decided by reference to the terms
c         of the letter. "
                                                 [Emphasis added].
        46. The respondent's main submission is that it never
  actually concluded a contract and that, if anything, the applicant
  mistakenly thought that the respondent's LOI of 23rd June was
D
  an offer. Why else would the applicant have sent its acceptance        ~·
  on 4th? Its attack against the LOI as a contract is two-fold.
  First, it argues that the parties cannot leave a major piece of
                                                                         ~
  the contract open for future negotiation. Second, it contends
  that the parties were not eye-to-eye, or ad idem on the points.
E
        47. According to the respondent, the applicant's
  assumption that the respondent's 23rd June LOI read with the
  applicant's 4th August letter is misplaced. The LOI of 23rd
  June read with the applicant's letter of 4th August does not
F form a contract because a contract cannot leave a major part
  of its terms open to future negotiation. The respondent relies         +.
  on May & Butcher Limited v. The King (1934) 2 KB 17, for
  the proposition that an agreement in which some critical part
  of the contract matter is left undetermined is no contract at all.
G      48. In its assertion that the applicant's LOI of 23rd June
  was conditional, it points to the following language from the
                                                                         ~
  same LOI: "this agreement is subject to IOEC providing a
  suitable barge and AHT acceptable to GE Shipping for a
  period of 45-55 days on mutually agreed rates for
H commencement between 25tn October and 1oth November 05
           GREAT OFFSHORE LTD. v. IRANIAN OFFSHORE 535
          ENG. & CONST. COMPANY [DALVEER BHANDARI, J.]

      for BHN MOL project works." The respondent's supplying the        A
      barge to the applicant for 45-55 days went unmet when the
      applicant said it would not need this barge.
           49. In addition, the respondent argues that this condition
      was material to the contract, as evidenced by the fact that the
      respondent only agreed to increase the duration of the work       B
~     from 170 to 200 days if it got paid for supplying the barge. By
      doing so, the respondent was attempting to offset the costs it
      would incur by having the applicant's vessel combination for
      an extra 30 days.
                                                                        c
            50. Furthermore, the respondent claims that no contract
      could arise from its LOI of 23rd June because the parties were
      not ad idem, i.e., in agreement on each point. Along these
      lines, Chitty on Contracts [29th Edn. Vol.1 at page 134] has
      observed:-
                                                                        D
~          "When parties carry on lengthy negotiations, it may be
           difficult to say when and whether a contract has been
.,.        concluded. The court must then look at the whole
           correspondence and decide, whether on its true
                                                                   11
           construction, the parties had agreed to the same terms.      E
            51. In Mis. Rickmers Verwaltung Gimb H v. Indian Oil
      Corporation Ltd., AIR 1999 SC 504 at page 509 para 12, this
      Court reiterated this stand: "Unless from the correspondence
      it can unequivocally and clearly emerge that the parties were
      ad idem to the terms, it cannot be said that an agreement had     F
      come into existence between them through correspondence."
      [See also: Dresser Rand S.A. v. Mis. Bindal Agro Chemical
      Ltd. & Another, AIR 2006 SC 871 at page 879 para 21
      (affirming the same)]
                                                                        G
           52. The respondent argues that they were still negotiating
      the terms and conditions. It cites to its letter of 13th August
      and the applicant's letter of .22nd August as evidence of
      continued negotiations. In the respondent's letter dated 13th
      August, it suggests that a number of changes be made to the
                                                                        H
     536       SUPREME COURT REPORTS                (200~] 12 S.C.R.



A    "new draft contract." [emphasis added]. "Draft" suggests that      ...
     nothing had been finalized. Moreover, the letter lists a number
     of issues that were still open to negotiation. The applicant's
     letter of 22nd August, however, addressed the proposed
     changes.
B~
           53. The respondent concedes that while it.said it would
     sign and finalize the contract by 30th August, it changed its
     mind on 27th August and conveyed the message that it would
     not enter the agreement until all outstanding issues were
     resolved.
c
           54. Like the applicant's counsel, the respondent also
     makes use of the fact that the applicant did not object to the
     respondent's letter dated 13th August. The applicant should
     have said that there was no question of finalizing the contract
     when it had already been finalized. I note that this argument
0
     seems unfair because the applicant could not have gotten the
     faxed CPA from the respondent until ath September at the
     earliest, as that is the date that appears on the fax. According
     to the applicant, it received the faxed copy on 12th September.
E          55. Of course, all of the respondent's arguments become
     moot if the faxed CPA dated 22nd is valid. In the instant case,
     the burden to prove that a valid contract containing an
     arbit~ation clause existed first rested on the applicant, as it
     was the applicant that was moving this Court. However, upon
F    producing the faxed CPA that, on its face, appears legitimate,
     the onus shifted to the respondent to prove that it was forged.
        It appears, prima facie, to be legitimate because it bears
  the heading "08-SEP-2005 13:52 FROM IOEC HEAD OFFICE
  TO ALLAHVERDI" (hereinafter the "fax header"). This is an
G important piece of evidence that mal<es its genuineness more
  probable than not. Hypothetically, the applicant could have
  fabricated the fax header. But that is highly unlikely and
  presumes much more than what is expected in normal human
  conduct especially when that conduct concerns the forgery of
H an executive officer's signature. It should not be forgotten that
                     GREAT OFFSHORE LTD. v. IRANIAN OFFSHORE 537
                    ENG. & CONST. COMPANY [DALVEER BHANDARI, J.]
           +I
                this case is between sophisticated companies, not warring          A
                family members that dispute the authenticity of a will.
                               -
                       56. The respondent could argue that it handed over an
                unsigned copy of the faxed CPA and that the applicant forged
                it after the fact. Such an assumption is equally dubious. Why
                would the respondent go through the trouble of returning the       B
           ~    applicant's August 22nd CPA unsigned, when it had been
                routed vide fax through its Head Office?
                      57. There is no evidence to suggest that the faxed CPA
                was forged. To the contrary, the evidence we do have is the c
                faxed CPA bearing the parties' signatures coupled with
                correspondence between the parties. The correspondence,
                as it is more than just a pleading, adds additional weight to
                the applicant's story. The applicant's letter of 21st October
                corroborates the allegation that Ali Rahmati delivered the faxed
                                                                                 D
        ~
                CPA to the applicant on 12th September. The date of delivery
                of 12th September fits the timeline provided on the fax header,
                as the respondent could only have delivered the faxed CPA
           ~
                after ath September. Moreover, it appears that having received
                the faxed CPA on 12th September, the applicant was prompted
                to ask for the original vide email on 14th September. Once E
                again, the dates match up.
                      58. The fax header, on its face, suggests that the
                document is genuine. This conclusion is bolstered by the
                above-mentioned correspondence. Thus, I find that the F
      -·-\      applicant had discharged its initial burden of sufficiently proving
                that the faxed CPA was not forged. The onus shifted to the
                respondent to prove that its signature was forged. With no
                evidence to support its assertion, the resp.ondent cannot
                discharge its onus. Therefore, I find that the faxed CPA is
                                                                                    G
                legitimate and is not a product of forgery. As such, I need not
~..   f.
                look for the existence of a contract on the basis of the LOI of
                23rd June.

                      59. The question then becomes whether the faxed CPA
                is valid under the r€=!1evant law. Here, the purported contract    H
    538         SUPREME COURT REPORTS                 [2008] 12 S.C.R.


A   provides that the Arbitration and Conciliation Act, 1996 (26 of
    1996) is to be used. (page 3 of faxed CPA dated 22 August
    2005]. In the preceding contract the same Act was used.
    Therefore, it comes as no surprise that the parties have not
    objected to the same in the instant case.
B        60. Section _7 of the Arbitration and Conciliation Act, 1996
    (26 of 1996) provides:
          (1)   In this part, "arbitration agreement" means an
                agreement by the parties to submit to arbitration all
c               or certain disputes which have arisen or which may
                arise between them in respect of a defined legal
                relationship, whether contractual or not.
          (2)   An arbitration agreement may be in the form of an
                arbitration clause or in the form of a separate
D               agreement.
          (3)   An arbitration agreement shall be in writing.
          (4)   An arbitration agreement is in writing if it is
                contained in-             ·
E               (a)   a document signed by the parties;
                (b)   an exchange of letters, telex, telegrams or
                      other means of telecommunication which
                      provide a record of the agreement; or
F               (c)   an exchange of statements of claim and defence
                      in which the existence of the agreement is
                      alleged by one party and not denied by the other.
          (5)   The reference in a contract to a document containing
                an arbitration clause constitutes an arbitration
G
                agreement if the contract is in writing and the
                reference is such as to make that arbitration clause
                part of the contract.
         61. Section 7 squarely deals with the present controversy.
H   This Court has taken note of Section 7(3) & 7(A)(a)'s
                  GREAT OFFSHORE LTD. v. IRANIAN OFFSHORE 539
                 ENG. & CONST. COMPANY [DALVEER BHANDARI, J.]
  -;.-'
             requirement that the arbitration agreement be in writing and A
             signed by the parties. According to the learned counsel for
             the applicant, affixing a seal under section 7 of the Act is not
             a requirement. [See: Bihar Stale Mineral Development
             Corporation & Another v. Encon Builders (1) (P) Ltd., (2003)
             7 sec 418 at page 423 para 13 (one of the essential B
      I      elements of an arbitration agreement is that "the parties must
      'ii;
             agree in writing to be bound by the decision of such tribunal.")
             and K.K. Modi v. K.N. Modi & Others, (1998) 3 SCC 573 at
             page 585 para 21 ("there are, of course, the statutory
             requirements of a written agreement . . . . Vide Section 2 c
             Arbitration Act, 1940 and Section 7 Arbitration and Conciliation
             Act, 1996.")
                  62. The respondent makes much of the fact that the "faxed
             CPA" of August 22nd is (1) a copy, not the original; (2) is
             stamped by one, not by both parties; (3) one of the parties did     D
      -~
             not sign every page; and (4) it was first sent vide fax.
                   63. Section 7 defeats all four assertions. First, there is
             no requirement that the arbitration agreement be an original.
             Where the statute has gone to great lengths to define exactly
             what is meant by the term "in writing," we are precluded from       E
             adding another term to definition. Indeed, "it is contrary to all
             rules of construction to read words into an Act unless it is
             absolutely necessary to do so." [See: Justice G.P. Singh's
             Principles of Statutory Interpretation, 11th Edition, 2008, at
             page 62.63, citing to Renula Bose (Smt.) v. Rai Manmathnath         F
   ---\-
             Bose, AIR 1945 PC 108, p. 110; Stock v. Frank Jones (Tiptan)
             Ltd., (1978) 1 All ER 948, p.951; Assessing Authority-Cum-
             Excise and Taxation Officer, Gurgaon &Another v. East India
             Cotton Mfg. Co. Ltd.,. Faridabad (1981) 3 SCC 531].
                                                                                 G
                   64. An exception to this rule can be made. But before
_. -l.       adding words to a statute, " ... the Court must be abundantly
             clear of three matters: (1) the intended purpose of the statute
             or provision in question, (2) that by inadvertence the draftsman
             and Parliament failed to give effect to that purpose in the
                                                                                 H


 ff
    540       SUPREME COURT REPORTS               [2008] 12 S.C.R.


A   provision in question; and (3) the substance of the provision
                                                                      '-+·
    Parliament would have used, had the error in the Bill been
    noticed." [See: Justice G.P. Singh's Principles of Statutory
    Interpretation, 11th Edition, 2008 at page 75 citing to Inca
    Europe Ltd. v. First Choice Distribution (a firm) (2000) 2 All
B   ER 109, at page 115 (HL)]. As I mention below, one of the
    main objectives of the Arbitration and Conciliation Act, 1996      jj


    is to minimise the role of the Court; adding additional
    requirements to the Act is antithetical to such a goal.
          65. Second, the plain language of Section 7 once again
c governs my conclusion. Section 7 does not require that the
    parties stamp the agreement. It would be incorrect to disturb
    the Parliament's intention when it is so clearly stated and
    when it in no way conflicts with the Constitution.
        66. Third, nothing in Section 7 suggests that the parties
D
  must sign every page. Once again, if I take the respondent's
  argument to its logical conclusion, I would have no choice but
  to read language into the Act that is not there. Even if the         ~·
  faxed CPA is construed as a "document," it need only be
  "signed by the parties" pursuant to Section 7(4)(a). Every page
E does not need to be signed. If it is considered a "document,"
  then this requirement would be met. As established above,·
  both parties signed the faxed CPA in the signature box at the
  bottom of Part I. That said, the faxed CPA more closely fits
  within Section 7(4)(b)'s requirements.
F                                                                      -j-,_   I
        67. Fourth, Section 7(4)(b) states that an agreement is
  in writing if it is contained in "an exchange of letters,. telex,
  telegrams or other means of telecommunication which
  provide a record of the agreement." .This section covers
  agreements that are sent via facsimile ("fax") as they are "other
G
  means of telecommunication". "Fax" is defined as "a machine
                                                                       )r-·
  that scans documents electronically and transmits a
  photographic image of the contents to a receiving machine by
  telephone line" or "a document received by such a machine."
  [See: Chambers 21st Century Dictionary, Allied Publisher's
H
                     GREAT OFFSHORE LTD. v. IRANIAN OFFSHORE 541
                    ENG'. & CONST. COMPANY [DALVEER BHANDARI, J.]

       +'      Limited (1996)]. This definition clearly provides that a fax falls     A
               under "other means of telecommunication." Thus, faxed
               agreements are acceptable under Section 7 of the Act.
                     68. Section 7(4)(b) further requires us to ask whether a
               record of the agreement is found in the telecommunication, in
               this case a fax. What could be a better record of the agreement        B
       !
       )f:     than the signatures of the parties themselves? As noted above,
               with no evidence to indicate that the respondent's signature
               was forged, the faxed CPA stands on its own as the record
               of agreement. Likewise, Section 7(4)(b) stands satisfied.
                                                                                      c
                     69. The court has to translate the legislative intention
               especially when viewed in light of one of the Act's "main
               objectives": "to minimise the supervisory role of Courts in the
               arbitral process. [See: Statements of Objects and Reasons of
               Section 4(v] of the Act].
                                                                                      D
       .'-1          70. If this Court adds a number of extra requirements
               such as stamps, seals and originals, we would be enhancing
               our role, not minimising it. Moreover, the cost of doing business
        1      would increase. It takes time to implement such formalities.
               What is even more worrisome is that the parties' intention to          E
               arbitrate would be foiled by formality.
                     71. Such a stance would run counter to the very idea of
               arbitration, wherein tribunals all over the world generally bend
               over backwards to ensure that the parties' intention to arbitrate
               is upheld. Adding technicalities disturbs the parties' "autonomy F
       ~-      of the will" (I' autonomie de la volonte), i.e., their wishes. [For
               a general discussion on this doctrine see Law and Practice
               of International Commercial Arbitration, Alan Redfern and
               Martin Hunter, Street & Maxwell, London, 1986 at pages 4
               and 53].                                                            G

._..   A             72. Technicalities like stamps, seals and even signatures
                are red tape that have to be removed before the parties can
                get what they really want - an efficient, effective and potentially
              · cheap resolution of their dispute. The autonomie de la volonte
                                                                                      H
                                                                .•   ..   ·~




    542       SUPREME COURT REPORTS                  [2008] 12 S.C.R.


A   doctrine is enshrined in the policy objectives of the United
    Nations Commission on International Trade Law ("UNCITRAL")
    Model Law on International Commercial Arbitration, 1985, on
    which our Arbitration Act is based. [See Preamble to the Act].
    The courts must implement legislative intention. It would be
B   improper and undesirable for the courts to add a number of
    extra formalities not envisaged by the legislation. The courts
    directions should be to achieve the legislative intention. The
    courts must implement legislative intention. It would be
    improper and undesirable for the courts to add a number of
c   extra formalities not envisaged by the legislation. The courts
    directions should be to achieve the legislative in!ention.
         73. One of the objectives of the UNCITRAL Model Law
    reads as under:-
          "the liberalization of international commercial arbitration
D
          by limiting the role of national courts, and by giving effect
          to the doctrine "autonomy of will," allowing the parties the
          freedom to choose how their disputes should be
          determined." [See Policy Objectives adopted by
          UNCITRAL in the preparation of the Model Law, as cited
E         in Law and Practice of International Commercial
          Arbitration, Alan Redfern and Martin Hunter, Street &
          Maxwell, London (1986) at page 388 (citing U~ doc.A/
          CN.9/07, paras 16-27].

F       74. It goes without saying, but in the interest of providing
  the parties a comprehensive review of their arguments, I note
  that once it is established that the faxed CPA is valid, it follows
  that a valid contract and a valid arbitration clause exist. This
  contract, the faxed CPA, does not suffer from a conditional
G clause, as did the Letter of Intent. Thus, the respondent's
  argument that the parties were not ad idem must fail.
        75. I have heard the learned counsel appearing for the
  applicant and the respondent at length. I have carefully reviewed
  the entire correspondence between the parties. The charter
H party agreement that had been signed by the applicant and
'\
                           GREAT OFFSHORE LTD. v. IRANIAN OFFSHORE 543
                          ENG. & CONST. COMPANY [DALVEER BHANDARI, J.]
            ~-
                   the respondent clearly indicated that the parties have entered      A
                   into a valid and concluded contract. The other correspondence
                   between the parties also leads to a definite conclusion: the
                   parties have entered into a valid contract containing an
                   arbitration clause. Since a dispute has arisen between the
                   applicant and the respondent, it needs to be referred to the        B
             I
                   arbitrator.
             Jt
                         76. On consideration of the totality of the facts and
                   circumstances, I am clearly of the opinion that the applicant is
                   entitled in law to an order for appointment of a sole arbitrator.
                   Consequently, I request Hon'ble Justice S.N. Variava, the           c
                   retired Judge of the Supreme Court, to accept this arbitration.
                   The learned arbitrator would be at liberty to fix his own fee. I
                   direct the parties to appear before the learned arbitrator on
                   81h September, 2008 or any date convenient to the learned
                   arbitrator.                                                         D
            ·-<          77. Before parting with this arbitration petition, I would
                   like to make it abundantly clear that the learned arbitrator
                   shall not be bound by any observations which have been made
                   in this judgment. The observations have been made only to
                   decide this arbitration petition.                                   E

                        78. The Registry is directed to communicate this order
                   to the learned arbitrator to enable him to enter upon the
                   reference and decide the matter as expeditiously as
                   practicable.
            ....          79. Consequently, this arbitration petition is allowed and
                                                                                       F

                   disposed of. In the peculiar facts and circumstances of this
                   case, I direct the parties to bear their own costs.
                   D.G.                                           Petition allowed.
                                                                                       G
     ....
             4.


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Arbitration agreement"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.