Created byFuzzy Cloud

Supreme Court of India

H. LATHAKUMARIversusVAMANAPURAM BLOCK PANCHAYAT ANP ORS.

Citation
2009 INSC 868
Decided
7 July 2009
Disposal
Appeal(s) allowed

Holding

The arbitration clause in the contract remains enforceable because the 1988 Government Order applies only to Public Works Department contracts and the Panchayat did not delete clause 73.

Summary

The appellant, H. Lathakumari, entered into a contract with Vamanapuram Block Panchayat on 15 March 1999 that incorporated clause 73 of the Madras Detailed Standard Specifications, mandating arbitration of disputes. When a dispute arose, the appellant invoked Section 11 of the Arbitration and Conciliation Act, 1996 to seek appointment of an arbitrator, but the respondent denied the existence of an arbitration agreement, relying on a Government Order dated 19 November 1988 that purportedly deleted arbitration clauses in public works contracts. The High Court dismissed the application, holding that the order rendered the arbitration clause ineffective. On appeal, the Supreme Court examined whether the 1988 order applied to the Panchayat contract and concluded that it was limited to Public Works Department contracts and did not automatically delete the arbitration clause in this agreement. Since the Panchayat had not expressly removed clause 73, the arbitration agreement remained valid. Consequently, the Court allowed the appeal and directed the respondent to refer the dispute to the Superintending Engineer for arbitration.

Issues considered

  • Whether the Government Order dated 19 November 1988 deleting arbitration clauses in PWD contracts applies to the contract between the appellant and Vamanapuram Block Panchayat.
  • Whether an arbitration agreement exists under clause 73 of the Madras Detailed Standard Specifications in the said contract.
  • Whether the appellant is entitled to appoint an arbitrator under Section 11 of the Arbitration and Conciliation Act, 1996.

Legislation cited

Subjects

ArbitrationArbitration clauseSection 11Arbitration and Conciliation ActGovernment Order 19-11-1988Public Works DepartmentContractual disputeSupreme Court appeal

Judgment

                                                                                     "
                          [2009] 9 S.C.R. 10


A                         H. LATHAt<UMAR!
                                                                         "
                                   v.                                             -·
        VAMANAPURAM BkOCK PANCHAYAT ANP ORS,
              (Civil Appeal No, 4152 of 2009)
                             JU~Y 7, 2009
B                                                                          cl,
         [R.V. RAVEENDRAN AND J.M. PANCHAL, JJ.]

          Arbitration and Conciliation Act, 1996: s. 11 - Pan9,h~y§ti
    Raj Departmentdid not decide to delete the arbitrntiqn c.l~use
c   in its contracts in terms of Gov~mm~nt Qr(l~r dat~d 19.11, 1988
    which was applicable to PWD contracts - The agreement
    between appellant and Respondent- Panchayat contained
                                                                                 ..,,
    arbitration clau$e - Hence, dispute referable to arbitration -      ,...
    Madras Detailed Standard Specifications - Clause 73.
D
      The parties entered into a contract agreement d~t~~
  15.3.1999 containing arbitration clause. Di~p~t~ ar9se in
  respect of said contract. The appellant filed an applici!tion
  under Section 11 of the Arbitration and Conciliation Act,
  1996 seeking appointment of an Arbitrator. The first
E respondent denied the claims and also contended that
  there was no arbitration agreement. The contention of the              ~
  respondents was that the government had decided to
  scrap arbitration by Government Order dated 19.11.19~8~
  High Court dismissed the application. Hence ttle appeal,
                                                                                  -·
F
      Allowing the appeal, the Court

       HELD: A reading of the order dated 19.11,1988 clearly
  shows that the deletion of the ~rbitration clause wa&
  direeted only in re9~rd tQ the Publio Work Department
G                                                                         ~
  contracts. In fact, it specifieally pr9vided that the question
  of adopting such delet!Qn by other departments of the
  Government or by s~tutory bodies would be examined                      ~-
  by the concerned department/statutory body. Admittedly,                        .....
H                                  10
                 H. LATHAKUMARI v. VAMANAPURAM BLOCK                     11
                             PANCHAYAT AND ORS.
         ~

             n~j~her the first respondent nor the         Panchayat Raj A
             Oepartment, de.cided. to delete the ~rbitration clause. On
             the other hand, the first r~sP.011dent entered into an
             agreement with the appellant long after the said
             Government Order dated 19.11.1988, that Is, on 15.3.1999
             and did not choose to delete clause 73 from the MOSS B
    ~
             made part of the agreement. If the first respondent
             wanted to delete the arbitration agreement, it ought to
             Ju~ye scored out clause 73 from the MOSS which
             \nGh~ded ~ !Jr~!~ration clause in the agreement. That was
             not done. lo fact, in PWO contra~ts, to which the bar on c
             arbitration was applied, the printed form of Articles of

-    '(
             Agreement'was amended to includQ a clause which
             confirmed that the "contractor has also signed the copy
             of the Madras petailed Standard Specifications excluding
             &l!JY§@ 7~ and other clauses relating to arbitration ...... "
                                                                           D
             6ignifi~irnUy §Y~'1 an exclusion was not made in the
             article& of Agr@@m~nt enter~E! hy tfle first respondent
             Panchayat. Thu& the @rbitrnti911 cla~§ft \Vi§ intended to
             form a part of the contract between the parties. Therefore,
             the disputes between the parties were referable to
             arbitration in terms of the said arbitration agreement. The E
             first respondent is directed to refer the disputes to the
    -~
             §yp@rintending Engineer in terms of the arbitration
             agreement ~gntained in clause 73 of MOSS. [Paras 5 and
             7] [15-A-H; 16-A-B]
                                                                              F
                 CIVIL. APPHl,,lATf; JURlf).PICTION : Civil Appeal No.
             4152 pf 2009.
                  From the Judgment qnd Order dated 13.01.2003 in
             Arbitration Request -No. 9 of 2.001 ~nd order dated 14.12.2005   G
             in O.P. No. 12477 of 2003 of the High Court of Kerala at
             Ernakulam.

_,->,            P. Sureshan and Shakil Ahmed Syed for the Appellants.

                 R. Sathish for the Respondent.                               H
    12      SUPREME COURT REPORTS                    [2009) 9 S.C.R.
                                                                           ,..
A        The Judgment of the Court was delivered by

         R.V. RAVEENDRAN, J. 1. Leave granted. Heard both
    parties.

         2. The Vamanapuram Block Panchayat, first respondent
B   herein, entered into a "contract agreement" dated 15.3.1999
                                                                             '),.__
    with the appellant under which the work of "RIDF-111, Pangode
    Sivakshetram - Thannichal Road improvements" was entrusted
    to her .......
            as per the articles of agreement, plans, specifications
    and conditions of contract approved by the Superintending
c   Engineer, Commissionerate of Rural Development, State of
    Kerala. The Articles of agreement confirmed that the contractor
    had also signed the copy of the Madras Detailed -standard                          --+
    Specifications (for short 'MOSS') and addenda volume thereto
    in acknowledgement of being bound by all the conditions of the         )'

D clauses. The MOSS which thus became a part of the contract
  · between the parties, provided for settlement of disputes by
    arbitration vide clause 73 which is extracted below :

      , "73. Arbitration.-ln case of any dispute or difference
         between the parties to the contract either during the
E
       · progress or after the completion of the works or after the
         determination, abandonment, or breach of the contract as
         to the interpretation of the contract, or as to .any matter or      f-
         thing arising thereunder except as to the matters left to the
         sole discretion of the Executive Engineer under clauses
F        20, 22, 27(c), 29, 36, 37 and 40 of the Preliminary
         Specification, or as to the withholding by the Executive
         Engineer of payment of any bill to which the contractor may
         claim to be entitled, then either party shall forthwith give to
         the other notice of such dispute or difference, and such
G       dispute or difference shall be and is, hereby referred to the            ......
         arbitration of the Superintending Engineer of the nominated
         cir~le mentioned in the 'Articles of Agreement" (hereinafter
         called the "arbitrator") and the award of such arbitrator shall         ......___
         be final and binding on the parties."                                               .....
H
•d                      H. LATHAKUMARI v. VAMANAPURAM BLOCK                             13
                       PANCHAYAT AND ORS. [R.V. RAVEENDRAN, J.]
                         3. Certain disputes having arisen in respect of the said            A
                1
                    contract, the appellant, by letter dated 28.12.2000, sought
                    reference to arbitration of its claims aggregating to
                    Rs.13,06,936/- in terms of the aforesaid arbitration clause
                    contained in the MOSS forming part of the agreement. The
                    Block Development Officer, Vamanapuram Panchayat, sent a                 B
                    reply dated 4.1.2001 denying the claims and informing the
            ,..,.   contractor that if she did not resume the work, the contract
                    would be terminated at her risk and cost. The respondents,
                    however, did not deny the existence of the arbitration
                    agreement in the said reply.                                             c
                          4. Thereafter, the appellant filed an application under
                    section 11 of the Arbitration & Conciliation Act, 1996 ('Act' for
                    short) seeking appointment of an Arbitrator. The first
                    respondent filed a counter denying the clair'!JS and also ,
                    contending that there was no arb.itration agreement. The said D
                    application was dismissed by the designate of the Chief _,
                    Justice of the High Court by order dated 13.1.2003. He·
                    considered the contention of the appellant that there was an
                    arbitration agreement in terms of clause 73 of MOSS for·
                    resolving the disputes. He also referred to the contention of the E
      '             respondents that the government had decided to scrap
                    arbitration by Government Order dated 19.11.1988, relevant
                    portions of which read as under :
                +
 ....                   "On a detailed examination of the matter, Government finds
                                                                                   'F
                        that the system of arbitration has generally gone against
                        the interests of the government and therefore, government
                        has decided to stop altogether the system of referring the
                        disputes for arbitration under any circumstances.

     ---r               Accordingly, Government orders the following :                       G

     ...       )         (1)   xxxxxxxx                                     t
                                                                                I
                                                                                    I




                         (2)   Disputes and differences arising between the
                               department and the contractors in the PWD
                                                                                             H
                                                                                          ,..
    14                                                  [2009] 9 S.C.R.
                SUPREME COURT REPORTS
                                                                                      ''h
                                                                                          -~
                                                                                          I

                                                                                          '
A                 contracts shall not oe referred to arbitration
                   hereafter and all -provisions relating td atbitration in
                   the tender ddcuments shall be deleted or scored off
                "' under the signature of the executing parties.
                  HawevfJr, If any wgrk is financed by an agency and
                  that agency insists to have provision for
                  atbitrationi provision f()t arbitrstion may be
                  provided in the agreement in respect at such work.

          (3)     xxxxx
c         (4)     The question of adopting the abbVe ptocedtJte in            -
                  other departments and organlzatiGflS like Kerala
                  State Electricity Board will b~ examined by th@             -
                  concerned department.;'

D                                                  {emphasis suoplied]

         The learned Designate pf the Chief Justice accepted the
    said contention of the respondents and held as follows :

         "In view of the above notification (Government Order?) the
E        arbitration clause in the tender documents and in the
         agreement shall stand deleted or scored off. When the
         above arbitration clause from the tender documents had
         been specifically deleted by the above notification; the
         applicant cannot again rely on the above arbitration clause              +
F        and seek an order for appointing an arbitrator. As the                       ~
         (:lbove arbitration clause has been deleted by the above
         notification, the prayer for appointing an arbitrator for
         resolving the disputes and differences between the parties
         cannot be allowed."
G      5. The said order is challenged in this appeal by special
  leave. The question therefore is whether there is an arbitration
  agreement between the parties? The first respondent did not
  deny the existence of an arbitration clause in terms of clause
  73 of MOSS, which was admittedly a part of the agreement.
H The contention was that the said arbitration clause stood
                 H. LATHAKUMARI ~ VAMANAPURAM BLOCK                            15
                PANdHAVAt AND ORS. [RV RAVE:ENORAN, J.j
             deleted from contracts in view of the G.O. dated 19.11.1988.            A
       -'\
             The question is whether the arbitration clause has, in fact, stood
             deleted. A reading of the said order dated 19.11.1988 clearly
             shows that the deletion of the arbitration clause was directed
             only in r~gard to the Public Work Department contracts. In fact,
             it specifically provided that the question of adopting such             B
             deletion by other departments of the Government or by statutory
      _.     bodies would be examined by the concerned department/
             statutory body. It is thus clear that the deletion of clause 73 of
             MOSS from the contract was made applicable only in regard
             to the contracts entered into by the Public Works DepartmEl!nt          c
             of the State of Kerala and th~ question whether other
             governmental or quasi-governmental agencies should delete
             such a provision, was left to the individual decision/discretion
             of the respective authorities.

                   6. Admittedly, neitl:ler the first respondent nor the             D
             Panchayat Raj Department, decided to delete the arbitrati?n
             clause. On the other hand, the first respondent entered into an
             agreement with the appellant long after the said Government
             Order dated 19.11.1988, that is, on 15.3.1999 and did not
             choose to delete clause 73 from the MOSS made part of the               E
             agreement. If the first respondent wanted to delete the
             arbitration agreement, it ought to have scored out clause 73
             from the MOSS which was signed and made a part of the
       +     agreement or included a clause in the agreement that clause
,./
             73 of MOSS would not apply or that there shall be n'o                   F
             arbitration. That was not done. In fact, in PWD contracts, to
             which the bar on arbitration was applied, the printed form of
~            Articles of Agreement was amended to include a clause which
             confirmed that the "contractor has also signed the copy of the
 (
             Madras Detailed Standard Specifications excluding clause 73             G
             and other clauses relating to arbitration. ..... " Significantly such
.,,,. .J     an exclusion is not made in the articles of Agreement entered
             by the first respondent Panchayat. It is thus clear that the
             arbitration clause was intended to form a part of the contract
             between the parties. Therefore, the disputes between the
                                                                                     H
    16      SUPREME COURT REPORTS                   [2009] 9 S.C.R.


A   parties are referable to arbitration in terms of the said
    arbitration agreement No other objection to the arbitration Is
    raised.

         7. In view of the above, the appeal is allowed and the first,,.
    respondent is directed to refer the disputes to the
8
    Superintending Engineer in terms of the arbitration agreement
                                                                               '
                                                                               ,-
    contained in clause 73 of MDSS within six weeks fro~ today.
    Nothing stated above shall be construed as an expression of
    any opinion on the merits of the claim.
                                                                               ?-·
C D.G.                                              Appeal allowed.




                                                                               l-

                                                                           +


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Arbitration"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.