Created byFuzzy Cloud

Supreme Court of India

JAYANTILAL INVESTMENTSversusMADHUVIHAR CO-OPERATIVE HOUSING SOCIETY AND ORS.

Citation
2007 INSC 26
Decided
10 January 2007
Disposal
Appeal(s) allowed

Holding

Section 7A of MOFA removes the consent requirement only for additional buildings that are part of a scheme, but does not exempt the promoter from the conveyance obligations under Sections 10 and 11, and the High Court erred in not determining whether the project involved a single building with wings or multiple buildings.

Summary

Jayantilal Investments, a promoter, was sued by MadhuVihar Co‑operative Housing Society for conveyance of title and an injunction restraining further construction on a plot in Kandivali. The Society argued that under the Maharashtra Ownership Flats Act (MOFA) the promoter must obtain flat‑takers' consent for any additional structures and convey title within a prescribed period, while the promoter relied on the amendment inserting Section 7A, claiming consent was no longer required for additional buildings. The Supreme Court examined the legislative intent behind the amendment, the distinction between "additional structures" and "additional buildings" within a scheme, and the interplay of Sections 7, 7A, 10 and 11 of MOFA. It held that Section 7A removed the consent requirement only for additional buildings that are part of a scheme, provided the plan is approved, but the promoter’s obligation to disclose the development potential and to convey title under Sections 10 and 11 remains unchanged. The Court found that the High Court had not properly determined whether the project involved a single building with multiple wings or multiple independent buildings, a factual issue critical to applying Section 7A. Consequently, the appeal was allowed and the High Court judgment set aside, with the matter remitted for reconsideration. The appeal was allowed with no order as to costs.

Issues considered

  • The applicability of the amended Section 7A of MOFA to the promoter's construction of additional wings versus additional buildings.
  • Whether the promoter must obtain prior consent of flat‑takers for constructing additional wings under the original Section 7.
  • The promoter's obligation to convey title to the cooperative society under Sections 10 and 11 of MOFA despite the amendment.
  • The interpretation of "developeability" versus "conveyance" under MOFA and the effect of the Maharashtra Amending Act No. 36/86.

Legislation cited

Subjects

MOFASection 7Section 7Aconveyanceco‑operative housing societydeveloper obligationsflat‑takers consentdevelopeabilityFloor Space Indexlay out planamendment

Judgment

 -                              JAYANTILAL INVESTMENTS
                                               v.
              MADHUVIHAR CO-OPERATIVE HOUSING SOCIETY AND ORS.

                                      JANUARY 10,2007
                                                                                          A




                      [DR. ARIJIT PASAYAT AND S.H. KAPADIA, JJ.]                          B

               Maharashtra Ownership Flats (Regulation of the Promotion
          of Construction, Sale, Management and Transfer) Act, 1963 with
          Amending Act 36186; ss. 3, 4, 7(1), 7(A), JO and 1J/Maharashtra Ownership
          Flats (Regulation of the Promotion of Construction) Rules, 1964; Clauses        C
          3 and 4:
  'I
  I              Rights and obligation ofa promoter-Sale offlats-Agreement between
          promoter and buyers of flats-Construction of additional structure-
          Consent of flat owners-Requirement of-Held: Amendment in Section 7
          made ands. 7-A introduced by amending the Act to make position explicit         D
           which according to Legislature existed implicitly before amendment-
      I
           Obtaining ofprior consent by flat owners not required for constructing any
 1        additional structure-However, approval of the plan by competent authority
          necessary-Jn terms of clauses 3 and 4 of Rules, it is statutory and
          mandatory on the part of promoter to give details of land amenities,            E
          facilities and also to make full and true disclosure of development
          potentiality of the plot-High Court has failed to examine the question as
           to whether the promoter had undertaken the project in question for
          construction of additional building or for construction of one building
          with 7 wings-Answer to the question would decide about applicability of
          amended provisions of the Act, as amended and also as to whether time           F
           to execute the conveyance arrived at or not-Hence, matter remitted to
          High Court for reconsideration-Urban Land Ceiling Act, 1976-s. 2(1).

                Respondent no.1, a Co-operative Society and its members instituted a
          suit against the appellant-promoter for conveyance, injunction restraining      .G
__,       the promoter from putting up further constructions and questioning the
          validity of the sanction given by the competent authority to the amended plan
          under which the competent authority sanctioned additional 2 wings applying
          the newly available norms. Trial Court partly decreed the suit, permitting
          the appellant-promoter to complete construction as per the amended plan.
                                                                                          H
                                              677
    678                  SUPREME COURT REPORTS                   [2007] 1 S.C.R

A   The trial court gave a period of three years to him for executing conveyance
    in favour of the Co-operative Society under the provisions of Maharashtra
    Ownership Flats (Regulation of the Promotion of Construction, Sale,
    Management and Transfer) Act, 1963 (MOFA). Aggrieved, the Co-operative
    Society preferred an appeal before the High Court. A cross appeal was
    preferred by the appellant-promoter. High Court allowed the appeal filed
B   by the Co-operative Society and dismissed the appeal filed by the appellant
    directing him to convey right, title and interest and execute all relevant
    documents in respect ofMadhu Vihar Scheme in favour of the Co-operative
    Society and appellant was restrained permanently from making any
    construction over the suit plot situated at Kandivali (West), Mumbai inter
c   alia holding that under section 7 of MOFA the appellant was prohibited
    from putting up additional constructions after the plan stood disclosed to
    the flat takers; that the promoter was not entitled to make any alteration
                                                                                    !
                                                                                    (
                                                                                    t,
    in the structure without prior consent of the flat takers; that the promoter
    could not make any additions in the structure of the building without the       )
    prior consent of the society and that under Section 7 A of the amended Act,
D   the prohibition was not to apply in respect of the construction of any other
    additional building or structure constructed or to be constructed under a
    scheme or a project of development in the lay out plan; and that the
    appellant-promoter was not entitled to derive any benefit from Section 7A
    ofMOFA and, he was not entitled to construct additional building in the             ,•
                                                                                        ·'
    suit plot. Hence the present appeal.
E
          Appellant contended that Section 7 ofMOFA enjoined the promoter,
    inter alia, not to construct any additional structure without the consent of
    the flat takers; that the State Legislature imposed such a restriction on the
    promoter contrary to the object of the Act and, consequently, the legislature
F   stepped in to change it by· enacting the Amending Act No. 36/86 and
                                                                                        I
    making it effective retrospectively; that the Amending Act deleted the
    restriction and left the promoter free to construct any additional structure
    without oi>taining the consent of the flat takers in the building; that the
    underlying purpose of the amendment is that maximum possible housing
    as per the prevailing by-laws should be available to enable the maximum
G   number of members of the public to be accommodated therein and that the
    individual rights of flat takers should not be allowed to come in the way of
    achievement of this public purpose; that the object behind amending Section
    7 and Section 7 A is to enable the promoter to construct an additional
    structure; that the object behind the amendment is to ease the problem of
H   shortage of housing; that any other interpretation would defeat the very
                ,it.,

                        JAY ANTILAL INVESTMENTS v. MADHUVIHAR CO-OP. HOUSING SOCIETY                679

      .. .,             purpose of the amendment to Section 7 and Section 7A of the Act; that on            A
                        facts, relying on the lay out plans, that even under the initial lay out plan
                        of 1985, 7 wings were to be constructed; that the sanction obtained by the
                        appellant for construction of 5 + 2 wings on the suit plot was in terms of
                        the original Plan sanctioned when 7 wings stood sanctioned; and that in
                        the facts and circumstances of this case, the amended provisions of
                        Sections 7 and 7A of MOFA were applicable and, consequently, the
                                                                                                            B
                        appellant was not obliged to execute a conveyance in favour of the society
           1
                        till the appellant is in a position to fully exploit the development potentiality
                        of the suit plot.

                             Respondent no.1-Society submitted that under MOFA there are two                c
                        concepts, namely, developeability and conveyance; that the two concepts
                        operate in different fields and, therefore, Section 7 and 7A cannot override
                        Sections 10 and 11 read with the relevant rules; that under Section
                        3(m)(iii) and (iv) a promoter is required to disclose the nature, extent and
                        description of the common areas and facilities in its advertisement/ brochure;
                                                                                                            D
                        that section 4(1) requires a promoter to enter into a written agreement in
                        the prescribed form; that the residual FSI in the plot or the lay out not
                        consumed will be available to the promoter till the registration of the
                        society. However, after registration of the society the remaining FSI shall
                        be available to the society; that Section 7A stood inserted in MOFA vide
                        Maharashtra Amending Act 36/86 and by the same Amending Act Section                 E
                        4(1A) was also inserted and, therefore, Section 7A has to be read with
                        Section 4(1A); that Section 7A does not give to the promoter the right of
                        developeability in eternity; that the lay out plan as well as the NOC obtained
                        by the promoter from the authorities was to construct a building with 7
                        wings; that Section 7A was not applicable to the present case since in the          F
        .....
                        present case the scheme consisted of one building with 6 to 7 wings; that




..
                        Section 7A applies when there is a project or scheme which indicates phase
                        wise development of a large plot made known to the intending flat takers;
                        that Section 7A in such cases does not empower the intending flat takers
                        to prevent construction of additional building according to such scheme;
mi.                                                                                                         G
                        that Section 7A does not confer any additional benefits or rights to a
                        promoter to construct additional building which did not form part of the
                        scheme/project in the lay out disclosecl to the ~at takers; that the NOC
                        obtained by the promoter from the Urban Land Ceiling Authorities (ULC)
                        read with the lay out plan/ block plan' of 1985 as well as the agreements
                        with the flat takers showed that the scheme/ project/ lay out was in respect        H
                                                                                     ,,J,
    680                  SUPREME COURT REPORTS                    [2007] I S.C.R.

A   of only one building with different wings; that the lay out plan does not               .,. ' ,._
    indicate phase wise development; and that the agreement with the flat
    takers indicated the scheme for only one building and in the circumstances,
    Section 7A is not attracted.

          Amicus Curiae submitted that it is not open to th.~ builders to insert
B   clauses in the agreement with the flat takers stating that conveyances will
    be executed only after the entire property is developed; that the contention
    of the promoter in the present case is that its obligation to form society and
                                                                                            ...
    execute a conveyance only after completion of the scheme is misconceived
    because under Sections 10 and 11 when the builder enters into an
c   agreement with the flat takers he is required to form a co-operative society
    as soon as the minimum number of flat takers is reached and, thereafter,
    the conveyance has to be executed in favour of the society within four
    months after the formation thereof in terms of Section 11; that MOFA has
    been enacted to regulate the activities of the builders and not to confer
    benefits on them; and that the builder could construct any additional
D
    structure without the consent of the flat purchasers. However it is pointed
    out that Section 7A does not have the effect of conferring any rights on
                                                                                             -~
    builders to claim an exemption from their obligations under Sections 10
    and 11 ofMOFA.

E         Allowing the appeal, the Court

          HELD: 1.1. Judgment of the Bombay High Court in Ka/pita Enclave
    case was based on the interpretation of unamended Section 7 of the
    Maharashtra Ownership Flats (Regulation of the Promotion of Construction,
    Sale, Management and Transfer) Act(MOFA). It was held that a promoter
F   was not entitled to put up add!tional structures not shown in the original               !'"
    lay out plan without the consent of the flat takers. Thus, consent wa.s
    attached to the concept of additional structure. Section 7 was accordingly
    amended and Section 7A was accordingly inserted by Maharashtra Amending
                                                                                                      ,;
    ~ct No. 36/86 in order to make the position explicit, which according to                          tfll
G   the legislature existed prior to amendment in the 1986 Act, implicitly.                           >-
    Section 7 ofMOFA came to be amended and for the purpose ofremoval of
    doubt, additional Section 7A came to be added. Section 7A was declared as
    having been retrospectively substituted and it was deemed to be effective as
    if the amended clause had been in force at all material times.                                t
H                                                         [Para 17] [692-B-D].
           JAY ANTILAL INVESTMENTS v. MADHUVIHAR CO-OP. HOUSING SOCIETY                681

                Ka/pita Enclave Co-operative Housing Society Ltd. v. Kiran Builders           A
           Private Ltd., (1986) MhLJ 110, referred to.

                1.2. Reading Section 7 and Section 7 A of MOFA, it is clear that the
           question of taking prior consent of the flat takers does not arise after
           the amendment in respect of any construction of additional
           structures.However, the right to make any construction of additional               B

-   -;
           structures/ buildings would come into existence only on the approval of
           the plan by the competent authority. That, unless and until, such a plan
           stood approved, the promoter does not get any right to make additional
           construction. [Para 17) [692-F-G]

                  1.3. By insertion of Section 7A, the legislature had made it clear that
                                                                                              c
             the consent of flat takers was never the criteria applicable to construction
         ... of additional buildings by the promoters. The object behind the said
             amendment was to give maximum weightage to the exploitation of
             development rights which existed in the land. Thus, the intention behind the
             amendment was to remove the impediment in construction of the additional         D
             buildings, if the total lay out allows construction of more buildings, subject
             to compliance of the building rules or building by-laws or Development
             Control Regulations. At the same time, the legislature had retained Section
             3 which imposes statutory obligations on the promoter to make full and
             true disclosure of particulars mentioned in Section 3(2) including the
             nature, extent and description of common areas and facilities. Sub-section
                                                                                              E
             (lA) to Section 4 of the Act was also introduced by the same amending Act
             under which the promoter is bound to enter into agreements with the flat
             takers in the prescribed form. [Para 17) [693-A-D]

                 1.4. Obligation of the promoter under MOFA to make true and full             F
           disclosure of the flat takers remains unfettered even after the inclusion of
           Section 7 A in MOF A. That obligation remains unfettered even after the
           amendment made in Section 7(1)(ii) of MOFA. That obligation is
           strengthened by insertion of sub-section (lA) in Section 4 of MOFA by the
           Amendment Act Therefore, every agreement between the promoter and the
           flat taker shall comply with the prescribed Form V. It may be noted that,          G
           in that prescribed form, there is an explanatory note which inter alia states
           that clauses 3 and 4 of Maharashtra Ownership Flats (Regulation of the
           Promotion of Construction etc.) Rules, 1964 (MOFA) shall be statutory and
           shall be retained. It shows the intention of the legislature. Clauses 3 and
           4 of the Rules are declared to be statutory and mandatory by the legislature       H
                                                                                        ).

    682                   SUPREME COURT REPORTS                     [2007] l S.C.R

A   because the promoter is not only obliged statutorily to give the particulars
    of the land, amenities, facilities etc., he is also obliged to make full and true
    disclosure of the development potentiality of the plot which is the subject
    matter of the agreement. [Paras 20] [694-D-F, 695-F]

          1.5. Condition of true and full disclosure flows from the obligation of
B   the promoter under MOFA vide Sections 3 and 4 and Form V which
    prescribes the form of agreement. This obligation remains unfettered
    because the concept of developeability has to be harmoniously read with the              ;.          ,_
    concept of registration of society and conveyance of title. Once the
    entire project is placed before the flat takers at the time of the
c   agreement, then the promoter is not required to obtain prior consent of the
    flat takers as long as the builder put up additional construction in
    accordance with the lay out plan, building rules and Development Control
    Regulations etc. [Para 21] [695-H, 696-A-B]

         2.1. In the impugned judgment, the High Court has failed to examine
D
    the question as to whether the project undertaken in 1985 by the appellant-
    promoter was in respect of construction of additional buildings or whether
    the project in the lay out plan consisted of one building with 7 wings. The
    question which the High Court should have examined is as to whether the
    project in question consists of 7 independent buildings or whether it is one
E   building with 7 wings. The answer to the above question will decide the
    applicability or non-applicability of Section 7(1)(ii) ofMOFA, as amended.
    The answer to the above question will decide whether the time to execute
    the conveyance has arrived or not. This will also require explanation from
    the competent authority/respondent no. 8. [Para 22] [696-D-F]
F                                                                                             ,,
          2.2. In the dates and events submitted by the appellant-promoter, there
    is a reference to the permission granted by Urban Land Ceiling authorities
    which states that the owner/developer shall construct a building with 7
    wings. One neetls to examine the application made by the promoter when                               .
    he submitted the lay out plan in 1985. If it is the building with 7 wings
G   intended to be constructed in terms of the lay out plan then the High Court
    is also required to consider the effect of the judgment in the case of
    Ravindra Mutneja and Ors. v. Bhavan Corporation and Ors. in which the
    single Judge has held that if a building is put up as a wing of an existing                    I'-
    building, it cannot be constructed without the prior permission of the flat
H   takers. In that connection, the High Court shall also consider permission
       JAYANTILAL INVESTMENTS v. MADHUVIHAR CO-OP. HOUSING SOCIETY [KAPADIA, J.]   683

       dated 16.11.1984 under section 21(1) ofULC Act, application made to the           A
       competent authority when initial lay out plan was sanctioned, applications
       for amendments to lay out plans made from time to time and also agreements
       between promoter and flat takers. For the aforesaid reasons and in
       view of the law enunciated in this judgment, the impugned judgment is
       set aside and the matter is remitted to the High Court for reconsideration.
                                                 [Paras 22-23) (696-F-H, 697-A-C]
                                                                                         B

            Ravindra Mutneja and Ors. v. Bhavan Corporation and Ors., (2003)
       5 Born. CR 695, referred to.

            CIVIL APPELLATE JURISDICTION: Civil Appeal No. 3233 of2006.                  C

            From the Final Judgment and Order dated 16.3.2006 of the High Court
       of Judicature at Bombay in F.A. Nos. 786 and 989/2004.

            G.E. Vahanvati, S.G. Sunil Gupta, Kavin Gulati, Nakul Diwan, Avinash         D
       Pandey, Ms. Rashmi and T. Mahipal, with them for the Appellant.

            M.K. Gilani, Harshad V.H., Pratap Venugopal, E. Venukumar (for
       M/s. K.J. John & Co.), Pallav Shishodia, Atul Y. Chitale, Suchitra
       Atul Chitale, Sujeeta Srivastava and Madhup Singhal for the Respondents.          E

             The Judgment of the Court was delivered by

            KAPADIA, J. : l. What are the rights and obligations of a promoter
...,   under the provisions of the Maharashtra Ownership Flats (Regulation of the
.

       Promotion of Construction, Sale, Management and Transfer) Act, 1963               F
       ("MOFA") is the question which·has arisen for determination in this civil
       appeal.

            2. On 26.8.1980 an agreement was arrived at between the vendors and
       the appellant herein (Mis Jayantilal Investments-Promoter) in respect of          G
       8559.57 sqm. ofland in CTS No. 1068 village Kandivili, Tehsil Borivili, Greater
       Mumbai. Subsequently, under a Revised Draft Development Plan, a 44 ft.
       wide road was indicated and; consequently, the area admeasuring 8559.57
       sqm. stood divided. On account of this division, a plot admeasuring 6071
       sqm. emerged as the suit land. On 16.11.1984 the appellant-promoter obtained
                                                                                         H
    684                   SUPREME COURT REPORTS                   (2007) I S.C.R

A   NOC under Section 21(1) of the Urban Land Ceiling Act, 1976 ("ULC Act")
    permitting it to construct a building with 7 wings and 13 7 tenements for
    weaker section. The construction was to be made in accordance with the
    prevailing Municipal Regulations, Town Planning requirements and Statutory
    Regulations. On 21.l 0.1985 the lay out plan was sanctioned. It indicated I
    building with 7 wings. At that time, due to existence of a narrow road as
B   access, the promoter was entitled only to FSI of0.75. This plan was amended
    in 1986, 1987, 1989, 1992 and 1994 with'out any objection from the flattakers.
    At this stage, it may be mentioned that on 6.5.1986 the lay out plan was
    revised and approved with 5 wings having additional floors as well as FSI
    of 1.00 due to construction of 44 ft. wide DP road on the original plot
c   admeasuring 8559.57 sqm. of land.

          3. From time to time, agreements stood entered into between the
    appellant and the flat takers for sale of flats. These agreements are dated
    7.12.1985, 11.4.1987, 18.l.1989, 30.4.1989, 27.7.1991 etc.
D
          4. On 12.11.1986 MOFA was amended retrospectively. Under that
    amendment Section 7A was inserted excluding 'additional structures' from
    the scope of Section 7(l)(ii) and thereby lifted the requirement of consent
    of flat takers. However, the said amendment was restricted to the plots
    falling under a scheme or a project under the lay out plan. The object behind
E   enacting Section 7A was to overcome the judgment of the Bombay High
    Court in the case of Ka/pita Enclave Co-operative Housing Society Ltd v.
    Kiran Builders Private Ltd., (1986) MhLJ 110. On 12.4.1989 on receiving
    occupation certificate, possession of flats was handed over to the flat takers.
    Some flats remained to be sold. They stood in the name of the appellant-
F   promoter.                                                                         ~-




          5. On 25.3.1991, the Development Control Regulations were framed
    which resulted in an increase of FSI from I to 1.8 on account of the
    introduction of the concept of TDR. For the first time under this concept,
    lands stood separated from the development potential of the plot.
G   Consequently, the lay out plan stood amended and the appellant obtained
    sanction on 25 .5 .1992 for construction of the building in question with
    6 wings by consumption of the balance FSI of 1.00. The appellant accordingly
    issued an advertisement for commencement of construction in accordance             t
    with the amended plan. However, it is the case of the appellant that on
H   account of financial paucity the construction got stuck.
             (

                 JAYANTILALINVESTMENTS "· MADHUVIHAR CO-OP. HOUSING SOCIETY [KAPADIA, J.)   685
  -,
        'I            6. Respondent No. 1 is the Co-operative Society registered on 20.1.1993.    A
                 The lay out plan was once again amended on 26.11.1994. The building in
                 question with 6 wings was shown· in the amended plan. The plan was duly
                 sanctioned. It is important to note that this plan of 1994 was sanctioned in
                 favour of the appellant on account of purchase of.additional TDR by the
                 appellant.
                                                                                                  B
                       7. In 1997 on account of Slum TOR, the permissible FSI stood increased
        -\       to 2 from 1.8.

                       8. On 12.8.1997 the Co-operative Society-respondent No. 1 and five flat
                 takers (members) instituted suit no. 4385/97 against the appellant-promoter      c
                 for conveyance, injunction restraining the promoter from putting up further
                 constructions and questioning the validity of the sanction given by the
                 competent authority to the amended plan dated 29.3.2001 under which the
                  competent authority sanctioned 5 + 2 wings applying the newly available
                  FSI.
                                                                                                  D
                       9. By judgment and order dated 31.3.2004 the Bombay City Civil Court
                 at Mumbai (trial court) partly decreed the suit, permitting the appellant to
                 complete construction as per the amended plan dated 29.3.2001. The trial
                 court gave a period of three years to the appellant for executing conveyance
                 in favour of the Co-operative Society under the provisions ofMOFA. Being         E
                 aggrieved by the grant of three years time to the appellant, the Cooperative
                 Society (Respondent No. I herein) preferred to the Bombay High Court First
                 Appeal No. 786/04. A cross appeal was preferred by the appellant-promoter
                 being First Appeal No. 989/04 in which the appellant contended that under
                 the agreement between the appellant and the flat takers no time limit for        F
         "       execution of the conveyance could be set as the appellant was entitled to
                 exploit the full potential of the plot in question and till such time as the
                 development potentiality of the plot in question stood exhausted, the
--l..            appellant was not statutorily obliged to execute a conveyance in favour of
                 the Co-operative Society. In this connection reliance was placed on the
                 provisions of Section 7A of MOFA.                                                G

_,                     10. By impugned judgment dated 16.3.2006 the Bombay High Court
        ~
                 allowed First Appeal No. 786/04 filed by the Co-operative Society and
                 simultaneously dismissed First Appeal No. 989/04 filed by the appellant
                 herein. By the impugned judgment, the High court directed the appellant to       H
                                                                                      )
    686                  SUPREME COURT REPORTS                   [2007] l S.C.R.

                                                                                          ,,-
A   convey right, title and interest and execute all relevant documents in respect
    of Madhu Vihar Scheme in CTS No. l 06811 admeasuring 6071 sqm. situated
    at Village Kandivali (West), Mumbai in favour of the Co-operative Society.
    By the impugned judgment, the appellant was restrained pennanently from
    making any construction over the suit plot bearing CTS No. 1068/l
    admeasuring 6071 sqm. situated at Kandivali (West), Mumbai. By the
B   impugned judgment the High Court held, that the appellant was a promoter;
    that it had floated Madhu Vihar Scheme on the said plot; that Madhu Vihar
    was the Scheme/ Project undertaken for development of the plot in accordance .
    with the lay out plan; and, that the said Scheme stood completed with the
    construction of the flats/ shops and the garden. By the impugned judgment,
c   it was further held that the Society was registered on 20.1.1993 and under
    Rule 8 of the Maharashtra Ownership Flats (Regulations of the Promotion
    of Construction, etc.) Rules, 1964 ("the Rules"), the appellant was statutorily
    obliged to convey the title to the society which they failed to do even after
    the Scheme got completed and possession of the flats stood handed over
    to the flat takers. By the impugned judgment the High Court held, that there
D
    was an implied trust created; that the promoter was the trustee and that the
    beneficiaries were the flat takers. By the impugned judgment it was further
    held, that under section 7 of MOFA the appellant was prohibited from
    putting up additional constructions after the plan stood disclosed to the flat
    takers; that the promoter was not entitled to make any alteration in the
E   structure without the prior consent of the flat takers; that the promoter could
    not make any additions in the structure of the building without the prior
    consent of the society and that under Section 7A, the said prohibition was
    not to apply in respect of the construction of any other additional building
    or structure constructed or to be constructed under a scheme or a project                    •
F   of development in the lay out plan. By the impugned judgment it has been
    held, that the construction of Madhu Vihar started in 1985; that section 7A
    was inserted in 1986 and that Madhu Vihar Scheme got completed in 1989.
    According to the impugned judgment, between 1985 and 1989, the plans
    were changed at least four times and that no additional wings like the one
    proposed in the plan approved on 29.3.2001 was ever included in the lay out
G   plans between 1985 and 1989 and, therefore, the appellant-promoter was not
    entitled to derive any benefit from Section 7A of MOF A and, consequently,
    the appellant was not entitled to construct additional building in the above
    suit plot. Hence this civil appeal.
                                                                                                ....
H         11. Mr. Sunil Gupta, learned senior counsel appearing on behalf of the
                '-·
                      JAY ANTILAL INVESTMENTS"· MADHUVIHAR CO-OP. HOUSING SOCIETY [KAPADIA, J.)   687

       ~              appellant submitted that Section 7 of MOFA enjoined the promoter, inter           A
                      alia, not to construct any additional structure without the consent of the
                      flat takers in the agreed building. This provision was applied by the Bombay
                      High Court in the case of Ka/pita Enclave (supra). The said judgment
                      prohibited the developer from constructing the additional structure in the
                      agreed building. Learned counsel submitted that the State Legislature
                      imposed such a restriction on the promoter contrary to the object of the Act
                                                                                                        B
                      and, consequently, the legislature stepped in to change the basis of the
       ~              judgment of the Bombay High Court in Ka/pita Enclave case (supra) by
                      enacting the Amending Act No. 36/86 retrospectively. According to the
                      learned counsel, the said Amending Act deleted the said restriction and left
                      the promoter free to construct any additional structure without obtaining the     c
                      consent of the flat takers in the agreed building. Learned counsel submitted
                      that the underlying purpose of the said amendment is that maximum possible
                       housing as per the prevailing by-laws should be achieved to enable the
                       maximum number of members of the public to be accommodated therein and
                       that the individual rights of flat takers should not be allowed to come in the
                                                                                                        D
                       way of achievement of this public purpose. Learned counsel emphasized
                       that the object behind amending Section 7 and Section 7A is to enable the
                       promoter to construct an additional structure; that the object of Section 7
                       and Section 7A is to bring at par a promoter who has sought and has been
                       granted permission to construct building consuming the maximum FSI
                       available under the by-laws prevailing on the given date and a promoter who      E
                       had sought and was given permission to construct building consuming the
                       maximum FSI available under the by-laws as prevailing on earlier date and
                       who otherwise on the given date stands in the same class as the
                       abovementioned promoter insofar as the question of consumption of the
---.   .....,          total FSI available is concerned. Learned counsel submitted that the object      F
                       behind the amendment is to ease the problem of shortage of housing.
                       Learned counsel further submitted that if the above interpretation of the
                       amended Section 7 and 7A is not accepted, it would give rise to discrimination
                       between two sets of persons, namely, flat takers who are party to a new
                       agreement and a new construction plan and those flat takers who have been
                       party to an earlier agreement in an earlier construction plan. According to      G
                       the learned counsel, if the interpretation given by him is not accepted,
....   -~
                       persons interested in the former piece of land shall stand facilitated whereas
                       persons interested in the latter piece of land shall stand vetoed, though the
                       building by-laws, rules etc. treat them equally. Learned counsel, therefore,
                       submitted that any other interpretation would defeat the very purpose of the     H
    688                   SUPREME COURT REPORTS                    [2007] l S.C.R.

A   amendment to Section 7 and Section 7A. On facts, learned counsel submitted,
    relying on the lay out plans, that even under the initial lay out plan of 1985,
    7 wings were to be constructed; that the said plan was revised on 6.5 .1986
    under which the construction was restricted to 5 wings having additional
    floors; that this was prior to the inclusion of Section 7A and, therefore, when
    the D.C. Regulations were enacted in 1991 and the concept of TDR was
B   introduced, the appellant got increased FSI of 1.8, consequent upon which
    the plan was amended and 6 wings came to be sanctioned on 25.5.1992.
    Similarly, when the FSI was increased to 2, the plan was got amended and
    accordingly the appellant obtained a sanction for construction of 5 + 2
    wings. Learned counsel, therefore, urged that the sanction obtained by the
c   appellant on 29.3.2001 for construction of 5 + 2 wings on the suit plot was
    in terms of the original Plan sanctioned on 21.10 .1985 when 7 wings stood
    sanctioned. In the circumstances, learned counsel urged that the appellant
    was entitled to construct 5 + 2 wings which was contemplated even in the
    original Plan dated 21.10.1985. Accordingly it was submitted that, in the facts
    and circumstances of this case, the amended provisions of Sections 7 and
D
     7A of MOF A were applicable and, consequently, the appellant was not
    obliged to execute a conveyance in favour of the society till the appellant
    is in a position to fully exploit the development potentiality of the suit plot.
    In the alternative, it is urged that, in any view of the matter, the appellant
    is not entitled to execute the conveyance in favour of the society till the
E   appellant exhausts the FSI of 2.

           12. Mr. M. K. Ghelani, learned counsel appearing on behalf of the
    society submitted that under MOF A there are two concepts, namely,
    developeability and conveyance. It was urged that Section 7 and 7A deal
F   with developeability of the project, while Sections IO and 11 read with Rules
    8 and 9 deal with the subject of formation of Society and transfer of title.
    Learned counsel urged that each of the above two concepts operate in
    different fields and, therefore, Section 7 and 7A cannot override Sections 10
    and 11 read with the relevant rules. It was urged, that under Section 3(m)(iii)
    and (iv) a promoter is required to disclose the nature, extent and description
G   of the common areas and facilities in its advertisement/ brochure; that
    section 4(1) requires a promoter to enter into a written agreement in the
    prescribed form and Section 4(1 A) inter alia provides that such agreements
    shall contain the nature, extent and description of common areas and
    facilities and, consequently, it is not open to the promoter to contract out
                                                                                       -
H   of the prescribed form of the agreement in form V. Learned counsel pointed
    JAY ANillAL INVESTMENTS 1•. MADHUVlliAR CO-OP. HOUSING SOCIETY [KAPADIA, J .]   689

    out that Section 4(1) provides that such agreement shall be in Form V, that           A
    Form V gives a model form under which the promoter has to declare the FSI
    (inherent) available in respect of the land. Under Rule 5 read with the model
    form of agreement, the promoter has to declare all relevant particulars in
    respect of utilization ofFSI and in cases where the promoter has utilized any
    FSI of any other land or property by way of floating FSI then the particulars
    of such floating FSI has to be disclosed by the promoter to the flat
                                                                                          B
    purchasers. The residual FSI in the plot or the lay out not consumed will
    be available to the promoter till the registration of the society. However, after
    registration of the society the remaining FSI shall be available to the society.
    Learned counsel submitted that Section 7A stood inserted in MOF A vide
    Maharashtra Amending Act 36/86 and by the same Amending Act Section                   c
    4(1A) was also inserted and, therefore, Section 7A has to be read with
    Section 4(1A). Learned counsel, therefore, urged that Section 7A does not
    give to the promoter the right of developeability in eternity. In the present
     case, learned counsel submitted that the lay out plan as well as the NOC
     obtained by the promoter from ULC authorities was to construct a building
                                                                                          D
     with 7 wings. Learned counsel urged that Section 7A was not applicable to
     the present case since in the present case the scheme consisted of one
     building with 6 to 7 wings. Moreover, it was further pointed out that Section
     7A applies when there is a project or scheme which indicates phase wise
     development of a large plot made known to the intending flat takers. Section
     7A in such cases does not empower the intending flat takers to prevent               E
     construction of additional building according to such scheme. As a corollary,
     it was urged that Section 7A does not confer any additional benefits or
     rights to a promoter to construct additional building which did not form part
     of the scheme/project in the lay out disclosed to the flat takers and, in any
     event, not after the obligation to convey has become operative and                   F
     enforceable under Sections I 0 and 11 read with Rules 8 and 9 of the Rules.
     Learned counsel urged that in the present case the society has been
     registered in 1993. He submitted that in the present case, on facts, the
     obligation to convey has become enforceable under Sections 10 and 11. He
     clarified that mere formation of the society does not take away from the
     promoter the rights of the promoter to the remaining development. He is not          G
     deprived of his rights to the unsold flats. However, it is not open to the
     promoter to resort to an ingenious drafting enabling the promoter to defer
)
     execution of conveyance till eternity. On facts, learned counsel pointed out
     that in the present case, the NOC obtained by the promoter from the Urban
     Land Ceiling authorities read with the lay out plan/ block plan of 1985 as           H
    690                   SUPREME COURT REPORTS                    [2007) 1 S.C.R.

A   well as the agreements with the flat takers showed that the scheme/ project/
                                                                                      f
    lay out was in respect of only one building with different wings; that the
    lay out plan does not indicate phase wise development; that the agreement
    with the flat takers indicated the scheme for only one building and, in the
    circumstances, Section 7A is not attracted. That in any event, it was not
    open to the promoter to unilaterally change the scheme/ lay out by adding
B   to it additional building and in the process remove the existing facilities and
    amenities provided in the lay out plan. Learned counsel urged that on facts
    of the present case, it was one building project which got completed in I 989
    when occupation certificate was issued and, in the circumstances, the
    promoter was not entitled to put up additional constructions.
c
          13. Looking to the importance of the matter in which we were required
    to harmoniously construe the provisions· of Sections 3 and 4 on one hand
    with Section 7 and 7A on the other hand as also Sections IO and I I of
    MOFA and keeping in mind the question of public importance, we requested
    Mr. G.E. Vahanvati, learned Solicitor General of India to assist the Court,
D
    keeping in mind the externalities existing in such cases coming from Mumbai.
    Learned Solicitor General of India has given us written submissions. He has
    reproduced the various judgments of the.Bombay High Court under MOFA.
    It is submitted that, it is not open to the builders to insert clauses in the
    agreement with the flat takers stating that conveyances will be executed only
E   after the entire property is developed. Learned amicus curiae submitted that
    the contention of the promoter in the present case is that its obligation to
    form society and execute a conveyan~e only after completion of the scheme
    is misconceived because under Sections I 0 and I I when the builder enters
    into an agreement with the flat takers he is required to form a cooperative
F    society as soon as the minimum number of flat takers is reached and,
    thereafter, the conveyance has to be executed in favour of the society within
    four months after the formation thereof in terms of Section I I. He submitted
    that MOFA has been enacted to regulate the activities of the builders and
    not to confer benefits on them. He submitted that Section 7A was inserted
    only for removal of doubts and to provide that the deleted words "construct
G   any additional structure" shall be deemed never to have been there
    notwithstanding any judgment, decree or order of any court which means
    that the builder could construct any additional structure without the consent
    of the flat purchasers. However, it is pointed out that Section 7A does not
                                                                                          (
    have the effect of conferring any rights on builders to claim an exemption
H   from their obligations under -Sections IO and I I of MOF A.
           L
"          )




               JAYANTILAL INVESTMENTS 1•. MADHUVlliAR CO-OP. HOUSING SOCIETY (KAPADIA, J.]   691

                    14. Before dealing with the point in issue one needs to look at original        A
      )
               Section 7 which was in existence in the Statute prior to its amendment by
               Maharashtra Amending Act No. 36/86.

                     15. The unamended Section 7 reads as follows:

                        "7.(1) After the plans, and specifications of the buildings as
                                                                                                    B
                        approved by the local authority as aforesaid, are disclosed or
                        furnished to the person who agrees to take one or more flats, the
      -;                promoter shall not make-

                        (i)    any alterations in the structures described therein in respect       c
                               of the flat or flats which are agreed to be taken, without the
                               previous consent of that person; or

                        (ii)   any other alterations in the structure of the building, [or
                               construct any additional structures,] without the previous
                               consent of all the persons who have agreed to take the flats."
                                                                                                    D

      \                                                                    (emphasis supplied)

                     16. The amended Section 7 reads as follows:
                                                                                                    E
                         "7.   After plans and specifications are disclosed no alterations
                               or additions without consent of persons who have agreed to
                               take the flats; and defects noticed within three years to be
                               rectified

                                                                                                    F
                               (I)    After the plans and specifications of the building, as
                                      approved by the local authority as aforesaid, are disclosed
                                      or furnished to the person who agrees to take one or
                                      more flats, the promoter shall not make-

                               (i)    any alterations in the structures described therein in        G
                                      respect of the flat or flats which are agreed to be taken,
--1
                                      without the previous consent of that person;

      '1                       (ii)   any other alterations or additions in the str,ucture ofthe
                                      building without the previous consent of all the persons      H
     6CJ2.                SUPREME COURT REPORTS                   [2007] 1 S.C.R.

.A                      who have agreed to take the flats in such building."
                                                                                     f

                                                            (emphasis supplied)

           17. The judgment of the Bombay High Court in Ka/pita Enclave case
     (supra) was based on the interpretation of unamended Section 7 of MOF A.
B    Consequently, it was held that a promoter was not entitled to put up
     additional structures not shown in the original lay out plan without the
     consent of the flat takers. Thus, consent was attached to the concept of
     additional structure. Section 7 was accordingly amended. Section 7A was
     accordingly inserted by Maharashtra Amending Act No. 36/86. Section 7A
c    was inserted in order to make the position explicit, which according to the
     legislature existed prior to 19%, implicitly. Section 7 of MOFA came to be
     amended and for the purpose of removal of doubt, additional s.ection 7A
     came to be added by Maharashtra Act 36/86. By this amendment, the words
     indicated in the parenthesis in the unamended Section 7(ii), name!y, "or
     construct any additional structures" came to be deleted and consequential
D    amendments were made in Section 7(1)(ii). Maharashtra Act No. 36/86
     operated retrospectively. Section 7 A was declared as having been
     retrospectively substituted and it was deemed to be effective as if the
     amended clause had been in force at all material times. Further, it was
     declared vide Section 7A that the above quoted expression as it existed
E    before commencement of the Amendment Act shall be deemed never to
     apply in respect of the construction of any other additional buildings/
     structures, constructed or to be constructed, under a scheme or project of
     development in the lay out plan, notwithstanding anything contained in the
     Act or in any agreement or in any judgment, decree or order of the court.
F    Consequently, reading Section 7 and Section 7A, it is clear that the question
     of taking prior consent of the flat takers does not arise after the amendment
     in respect of any construction of additional structures. However, the right
     to make any construction of additional structures/ buildings would come
     into existence only on the approval of the plan by the competent authority.
     That, unless and until, such a plan stood approved, the promoter does not
G    get any right to make additional construction. This position is clear when
     one reads the amended Section 7(l)(ii) with Section 7A ofthe MOFA as
     amended. Therefore, having regard to the Statement of Objects and Reasons
     for substitution of Section 7(1)(ii) by the Amendment Act 36/86, it is clear
                                                                                     (
     that the object was to make legal position clear that even prior to the
H    amendment of 1986, it was never intended that the original provision of
           JAYANTILAL INVESTMENTS '" MADHUVJHAR CO-OP. HOUSING SOCIETY [KAPADIA, J.]    693

           Section 7(l)(ii) of MOFA would operate even in respect of construction of            A
      l
           additional buildings. In other words, the object of enacting Act No. 36/86
           was to change the basis of the judgment of the Bombay High Court in
           Ka/pita Enclave case (supra). By insertion of Section 7A vide Maharashtra
           Amendment Act 36/86 the legislature had made it clear that the consent of
           flat takers was never the criteria applicable to construction of additional
           buildings by the promoters. The object behind the said amendment was to
                                                                                                B
~

·•         give maximum weightage to the exploitation of development rights which
      'i   existed in the land. Thus, the intention behind the amendment was to remove
           the impediment in construction of the additional buildings, if the totai lay
           out allows construction of more buildings, subject to compliance of the .
           building rules or building by-laws or Development Control Regulations. At            c
           the same time, the legislature had retained Section 3 which imposes statutory
           obligations on the promoter to make full and true disclosure of particulars
           mentioned in Section 3(2) including the nature, extent and description of
           common areas and facilities. As stated above, sub-section (IA) to Section
           4 was also introduced by the legislature by Maharashtra Act 36186 under
                                                                                                D
            which the promoter is bound to enter into agreements with the flat takers
      \.
            in the prescribed form. Under the prescribed form, every promoter is required
           to declare the FSI available in respect of the said land. The promoter is also
..,        required to declare that no part of that FSI has been utilized elsewhere, and
           if it is utilized, the promoter has to give particulars of such utilization to the
           flat takers. Further, under the proforma agreement, the promoter has to              E
            further declare utilization of FSI of any other land for the purposes of
            developing the land in question which is covered by the agreement.

                  18. Therefore, the legislature has sought to regulate the activities of the
           promoter by retaining Sections 3 and 4 in the Act. It needs to be mentioned          F
      -\
           at this stage the question which needs to be decided is whether one building
           with several wings would fall under amended Section 7(1)(ii). Section 7A
           basically allows a builder to construct additional building provided the
           construction forms part of a scheme or a project. That construction has to
           be in accordance with the lay out plan. That construction cannot exceed the
           development potentiality of the plot in qu~stion. Section l 0 of MOFA casts          G
           an obligation on the promoter to form a cooperative society of the flat takers
           as soon as minimum number of persons required to form a society have
           taken flats. It further provides that the promoter shall join the society in
           respect of the flats which are not sold. He has to become a member of the
           society. He has the right to dispose of the flats in accordance with the             H
                                                                                       )
    694                   SUPREME COURT REPORTS                    [2007] 1 S.C.R.

A   provisions of the MOFA. Section 11 inter alia provides that a promoter                        ....
    shall take all necessary steps to complete his title and convey the title to
                                                                                           -(       ,,'
    the society. He is obliged to execute all relevant documents in accordance                     '·~

    with the agreement executed under Section 4 and if no period for execution                      r
    of the conveyance is agreed upon, he shall execute the conveyance within
    the prescribed period. Rule 8 inter alia provides that where a cooperative                      '·
B                                                                                                   ,.
                                                                                                    ~ ..
                                                                                                        )
    society is to be constituted, the promoter shall submit an application to the
    Registrar for registration of the society within four months from the date on                  ·Jt:
    which the minimum number of persons required to form such society (60%)                ,-
                                                                                                  .~
    have taken flats. Rule 9 provides that if no period for execution of a
    conveyance is agreed upon, the promoter shall, subject to his right to
c   dispose of the remaining flats, execute the conveyance within four months
    from the date on which the society is registered.

           19. Reading the above provisions ofMOFA, we are required to balance
    .the rights of the promoter to make alterations or additions in the structure
     of the building in accordance with the lay out plan on the one hand
D
     vis-a-vis his obligations to form the society and convey the right, title and
     interest in the property to that society. The obligation of the promoter under
                                                                                           -(
     MOFA to make true and full disclosure of the flat takers remains unfettered
     even after the inclusion of Section 7A in MOFA. That obligation remains                        r
     unfettered even after the amendment made in Section 7( l)(ii) of MOF A. That
E    obligation is strengthened by insertion of sub-section (IA) in Section 4 of
     MOF A by Maharashtra Amendment Act 36/86. Therefore, every agreement
                                                                                                   ~
     between the promoter and the flat taker shall comply with the prescribed
     Form V. It may be noted that, in that prescribed form, there is an explanatory
     note which inter alia states that clauses 3 and 4 shall be statutory and shall
F    be retained. It shows the intention of the legislature. Note 1 clarifies that a
     model form of agreement has been prescribed which could be modified and
                                                                                           ,...    'lo.-

     adapted in each case depending upon the facts and circumstances of each
     case but, in any event, certain clauses including clauses 3 and 4 shall be
     treated as statutory and mandatory and shall be retained in each and every                   r '



     individual agreements between the promoter and the flat taker. Clauses 3 and
G    4 of the Maharashtra Ownership Flats (Regulation of the Promotion of
     Construction etc.) Rules, 1964 are quoted hereinbelow:

             "3.   The Promoter hereby agrees to observe, perform and comply
                                                                                            (
                   with all the terms, conditions, stipulations and restrictions if
H                  any, which may have been imposed by the concerned local
JAYANTILAL INVESTMENTS''· MADHUVIHAR CO-OP. HOUSING SOCIETY [KAPADIA, J.]    695

               authority at the time sanctioning the said plans or thereafter        A
               and shall, before handing over possession of the Flat to the
               Flat Purchaser, obtain from the concerned local authority
               occupation and/or completion certificates in respect of the
               Flat.

         4.    The Promoter hereby declares that the Floor Space Index
                                                                                     B
               available in respect of the said land is... square metres only
               and that no part of the said floor space index has been utilized
               by the Promoter elsewhere for any purpose whatsoever. In
               case the said floor space index has been utilized by the
               Promoter elsewhere, then the Promoter shall furnish to the Flat       c
               Purchaser all the detailed particulars in respect of such
               utilization of said floor space index by him. In case while
               developing the said land the Promoter has utilized any floor
               space index of any other land or property by way of floating
               floor, space index, then the particulars of such floor space          D
               index shall be disclosed by the Promoter to the Flat Purchaser.
               The residual F.A.R. (F.S.1.) in the plot or the layout not
               consumed will be available to the promoter till the registration
               of the society. Whereas after the registration of the Society
               the residual F.A.R. (F.S.I.), shall be available to the Society."
                                                                                     E
                                                            (emphasis supplied)

      20. The above clauses 3 and 4 are declared to be statutory and
mandatory by the legislature because the promoter is not only obliged
statutorily to give the particulars of the land, amenities, facilities etc., he is
                                                                                     F
also obliged to make full and true disclosure of the development potentiality
of the plot which is the. subjed matter of the. agreement. The promoter is
not only required to mak.e:disclosure·conceming the. inherent FSI, he is also
required at the stage· of lay out plan to declare whether the plot in question
in future is capable of being loaded with additional FSI/ floating FSI/ TDR.
In other words, at the time· of execution of the agreement with the flat takers      G
the promoter is obliged statutorily to place before the flat takers the entire
project/ scheme, be· it a one.building. scheme or multiple number of buildings
scheme. Clause 4 shows the: effect of the formation of the Society.

     21. In our view, the: above condition of true and full disclosure flows         H
    696                   SUPREME COURT REPORTS                    [2007] l S.C.R.

A   from the obligation of the promoter under MOFA vide Sections 3 and 4 and
    Form V which prescribes the form of agreement to the extent indicated
    above. This obligation remains unfettered because the concept of
    developeability has to be harmoniously read with the concept of registration
    of society and conveyance of title. Once the entire project is placed before
    the flat takers at the time of the agreement, then the promoter is not required
B   to obtain prior consent of the flat takers as long as the builder put up
    additional construction in accordance with the lay out plan, building rules
    and Development Control Regulations etc.

          22. In the light of what is stated above, the question which needs to            .•
c be examined in the present case is whether this case falls within the ambit
    of amended Section 7( l )(ii) or whether it falls within the ambit of Section 7A
    of MOFA. As stated above, under Section 7(1) after the lay out plans and
    specifications of the building, as approved by the competent authority, are
    disclosed to the flat takers, the promoter shall not make any other alterations
    or additions in the structure of the building without the prior consent of the
D
    flat takers. This is where the problem lies. In the impugned judgment, the
    High Court has failed to examine the question as to whether the project
    undertaken in 1985 by the appellant herein was in respect of construction
    of additional buildings or whether the project in the lay out plan of 1985
    consisted of one building with 7 wings. The promoter has kept the requisite
E   percentage of land open as recreation ground/ open space. Relocation of the
    tennis court cannot be faulted. The question which the High Court should
    have examined is: whether the project in question consists of 7 independent
    buildings or whether it is one building with 7 wings? The answer to the
    above question will decide the applicability or non-applicability of Section
F   7{l)(ii) ofMOFA, as amended. The answer to the above question will decide
    whether the time to execute the conveyance has arrived or not. This will also
    n:quire explanation from the competent authority, namely, Executive Engineer,
    "R" South Ward, Kandivali, Mumbai-400067 (Respondent No. 8 herein). In
    the dates and events submitted by the appellant-promoter, there is a
    reference to the permission granted bY, ULC authorities datd 16.11.1984
G   which states that the owner/developer shall construct a building with 7
    wings. One needs to examine the application made by the promoter when
    he submitted the lay out plan in 1985. If it is the building with 7 wings
    intended to b~ constructed in terms of the lay oqt plan then the High Court        (
    is also required to consider the effect of the judgment in the case of
H   Ravindra Mutneja and Ors. v. Bhavan Corporation and Ors., (2003) 5




                                                                                            I
JAY ANTILAL INVESTMENTS 1·. MADHUVIHAR CO-OP. HOUSING SOCIETY [KAPADIA, J.)   697

BomCR 695 in which the learned single Judge has held that if a building is          A
put up as a wing of an existing building, it cannot be constructed without
the prior permission of the flat takers. In that connection, the High Court
shall also consider Permission dated 16.11.1984 under section 21(1) ofULC
Act, application made to the competent authority when initial lay out plan
was sanctioned, applications for amendments to lay out plans made from
time to time and also agreements between promoter and flat takers.
                                                                                    B

       23. For the aforesaid reasons and in view of the law enunciated by us
vide this judgment, the impugned judgment is set aside and the matter is
remitted to the High Court for reconsideration. As the matter has been under
litigation for a considerable length of time, we hope that due priority will be     C
given for early disposal of this matter.

     24. We wish to express our deep appreciation for the assistance
rendered by learned Solicitor General oflndia as amicus curiae in the matter.

     25. Subject to what is stated, the appeal is allowed with no order as
                                                                                    D
to costs.

S.K.S.                                                          Appeal allowed.


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "MOFA"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.