JAYANTILAL INVESTMENTSversusMADHUVIHAR CO-OPERATIVE HOUSING SOCIETY AND ORS.
- Citation
- 2007 INSC 26
- Decided
- 10 January 2007
- Disposal
- Appeal(s) allowed
- Bench
- ARIJIT PASAYAT
Holding
Section 7A of MOFA removes the consent requirement only for additional buildings that are part of a scheme, but does not exempt the promoter from the conveyance obligations under Sections 10 and 11, and the High Court erred in not determining whether the project involved a single building with wings or multiple buildings.
Summary
Jayantilal Investments, a promoter, was sued by MadhuVihar Co‑operative Housing Society for conveyance of title and an injunction restraining further construction on a plot in Kandivali. The Society argued that under the Maharashtra Ownership Flats Act (MOFA) the promoter must obtain flat‑takers' consent for any additional structures and convey title within a prescribed period, while the promoter relied on the amendment inserting Section 7A, claiming consent was no longer required for additional buildings. The Supreme Court examined the legislative intent behind the amendment, the distinction between "additional structures" and "additional buildings" within a scheme, and the interplay of Sections 7, 7A, 10 and 11 of MOFA. It held that Section 7A removed the consent requirement only for additional buildings that are part of a scheme, provided the plan is approved, but the promoter’s obligation to disclose the development potential and to convey title under Sections 10 and 11 remains unchanged. The Court found that the High Court had not properly determined whether the project involved a single building with multiple wings or multiple independent buildings, a factual issue critical to applying Section 7A. Consequently, the appeal was allowed and the High Court judgment set aside, with the matter remitted for reconsideration. The appeal was allowed with no order as to costs.
Issues considered
- The applicability of the amended Section 7A of MOFA to the promoter's construction of additional wings versus additional buildings.
- Whether the promoter must obtain prior consent of flat‑takers for constructing additional wings under the original Section 7.
- The promoter's obligation to convey title to the cooperative society under Sections 10 and 11 of MOFA despite the amendment.
- The interpretation of "developeability" versus "conveyance" under MOFA and the effect of the Maharashtra Amending Act No. 36/86.
Legislation cited
- Maharashtra Ownership Flats (Regulation of the Promotion of Construction, Sale, Management and Transfer) Act, 1963s. 10, s. 11, s. 3, s. 4, s. 4(1A), s. 7, s. 7A
- Urban Land Ceiling Act, 1976s. 21(1)
Subjects
Judgment
- JAYANTILAL INVESTMENTS
v.
MADHUVIHAR CO-OPERATIVE HOUSING SOCIETY AND ORS.
JANUARY 10,2007
A
[DR. ARIJIT PASAYAT AND S.H. KAPADIA, JJ.] B
Maharashtra Ownership Flats (Regulation of the Promotion
of Construction, Sale, Management and Transfer) Act, 1963 with
Amending Act 36186; ss. 3, 4, 7(1), 7(A), JO and 1J/Maharashtra Ownership
Flats (Regulation of the Promotion of Construction) Rules, 1964; Clauses C
3 and 4:
'I
I Rights and obligation ofa promoter-Sale offlats-Agreement between
promoter and buyers of flats-Construction of additional structure-
Consent of flat owners-Requirement of-Held: Amendment in Section 7
made ands. 7-A introduced by amending the Act to make position explicit D
which according to Legislature existed implicitly before amendment-
I
Obtaining ofprior consent by flat owners not required for constructing any
1 additional structure-However, approval of the plan by competent authority
necessary-Jn terms of clauses 3 and 4 of Rules, it is statutory and
mandatory on the part of promoter to give details of land amenities, E
facilities and also to make full and true disclosure of development
potentiality of the plot-High Court has failed to examine the question as
to whether the promoter had undertaken the project in question for
construction of additional building or for construction of one building
with 7 wings-Answer to the question would decide about applicability of
amended provisions of the Act, as amended and also as to whether time F
to execute the conveyance arrived at or not-Hence, matter remitted to
High Court for reconsideration-Urban Land Ceiling Act, 1976-s. 2(1).
Respondent no.1, a Co-operative Society and its members instituted a
suit against the appellant-promoter for conveyance, injunction restraining .G
__, the promoter from putting up further constructions and questioning the
validity of the sanction given by the competent authority to the amended plan
under which the competent authority sanctioned additional 2 wings applying
the newly available norms. Trial Court partly decreed the suit, permitting
the appellant-promoter to complete construction as per the amended plan.
H
677
678 SUPREME COURT REPORTS [2007] 1 S.C.R
A The trial court gave a period of three years to him for executing conveyance
in favour of the Co-operative Society under the provisions of Maharashtra
Ownership Flats (Regulation of the Promotion of Construction, Sale,
Management and Transfer) Act, 1963 (MOFA). Aggrieved, the Co-operative
Society preferred an appeal before the High Court. A cross appeal was
preferred by the appellant-promoter. High Court allowed the appeal filed
B by the Co-operative Society and dismissed the appeal filed by the appellant
directing him to convey right, title and interest and execute all relevant
documents in respect ofMadhu Vihar Scheme in favour of the Co-operative
Society and appellant was restrained permanently from making any
construction over the suit plot situated at Kandivali (West), Mumbai inter
c alia holding that under section 7 of MOFA the appellant was prohibited
from putting up additional constructions after the plan stood disclosed to
the flat takers; that the promoter was not entitled to make any alteration
!
(
t,
in the structure without prior consent of the flat takers; that the promoter
could not make any additions in the structure of the building without the )
prior consent of the society and that under Section 7 A of the amended Act,
D the prohibition was not to apply in respect of the construction of any other
additional building or structure constructed or to be constructed under a
scheme or a project of development in the lay out plan; and that the
appellant-promoter was not entitled to derive any benefit from Section 7A
ofMOFA and, he was not entitled to construct additional building in the ,•
·'
suit plot. Hence the present appeal.
E
Appellant contended that Section 7 ofMOFA enjoined the promoter,
inter alia, not to construct any additional structure without the consent of
the flat takers; that the State Legislature imposed such a restriction on the
promoter contrary to the object of the Act and, consequently, the legislature
F stepped in to change it by· enacting the Amending Act No. 36/86 and
I
making it effective retrospectively; that the Amending Act deleted the
restriction and left the promoter free to construct any additional structure
without oi>taining the consent of the flat takers in the building; that the
underlying purpose of the amendment is that maximum possible housing
as per the prevailing by-laws should be available to enable the maximum
G number of members of the public to be accommodated therein and that the
individual rights of flat takers should not be allowed to come in the way of
achievement of this public purpose; that the object behind amending Section
7 and Section 7 A is to enable the promoter to construct an additional
structure; that the object behind the amendment is to ease the problem of
H shortage of housing; that any other interpretation would defeat the very
,it.,
JAY ANTILAL INVESTMENTS v. MADHUVIHAR CO-OP. HOUSING SOCIETY 679
.. ., purpose of the amendment to Section 7 and Section 7A of the Act; that on A
facts, relying on the lay out plans, that even under the initial lay out plan
of 1985, 7 wings were to be constructed; that the sanction obtained by the
appellant for construction of 5 + 2 wings on the suit plot was in terms of
the original Plan sanctioned when 7 wings stood sanctioned; and that in
the facts and circumstances of this case, the amended provisions of
Sections 7 and 7A of MOFA were applicable and, consequently, the
B
appellant was not obliged to execute a conveyance in favour of the society
1
till the appellant is in a position to fully exploit the development potentiality
of the suit plot.
Respondent no.1-Society submitted that under MOFA there are two c
concepts, namely, developeability and conveyance; that the two concepts
operate in different fields and, therefore, Section 7 and 7A cannot override
Sections 10 and 11 read with the relevant rules; that under Section
3(m)(iii) and (iv) a promoter is required to disclose the nature, extent and
description of the common areas and facilities in its advertisement/ brochure;
D
that section 4(1) requires a promoter to enter into a written agreement in
the prescribed form; that the residual FSI in the plot or the lay out not
consumed will be available to the promoter till the registration of the
society. However, after registration of the society the remaining FSI shall
be available to the society; that Section 7A stood inserted in MOFA vide
Maharashtra Amending Act 36/86 and by the same Amending Act Section E
4(1A) was also inserted and, therefore, Section 7A has to be read with
Section 4(1A); that Section 7A does not give to the promoter the right of
developeability in eternity; that the lay out plan as well as the NOC obtained
by the promoter from the authorities was to construct a building with 7
wings; that Section 7A was not applicable to the present case since in the F
.....
present case the scheme consisted of one building with 6 to 7 wings; that
..
Section 7A applies when there is a project or scheme which indicates phase
wise development of a large plot made known to the intending flat takers;
that Section 7A in such cases does not empower the intending flat takers
to prevent construction of additional building according to such scheme;
mi. G
that Section 7A does not confer any additional benefits or rights to a
promoter to construct additional building which did not form part of the
scheme/project in the lay out disclosecl to the ~at takers; that the NOC
obtained by the promoter from the Urban Land Ceiling Authorities (ULC)
read with the lay out plan/ block plan' of 1985 as well as the agreements
with the flat takers showed that the scheme/ project/ lay out was in respect H
,,J,
680 SUPREME COURT REPORTS [2007] I S.C.R.
A of only one building with different wings; that the lay out plan does not .,. ' ,._
indicate phase wise development; and that the agreement with the flat
takers indicated the scheme for only one building and in the circumstances,
Section 7A is not attracted.
Amicus Curiae submitted that it is not open to th.~ builders to insert
B clauses in the agreement with the flat takers stating that conveyances will
be executed only after the entire property is developed; that the contention
of the promoter in the present case is that its obligation to form society and
...
execute a conveyance only after completion of the scheme is misconceived
because under Sections 10 and 11 when the builder enters into an
c agreement with the flat takers he is required to form a co-operative society
as soon as the minimum number of flat takers is reached and, thereafter,
the conveyance has to be executed in favour of the society within four
months after the formation thereof in terms of Section 11; that MOFA has
been enacted to regulate the activities of the builders and not to confer
benefits on them; and that the builder could construct any additional
D
structure without the consent of the flat purchasers. However it is pointed
out that Section 7A does not have the effect of conferring any rights on
-~
builders to claim an exemption from their obligations under Sections 10
and 11 ofMOFA.
E Allowing the appeal, the Court
HELD: 1.1. Judgment of the Bombay High Court in Ka/pita Enclave
case was based on the interpretation of unamended Section 7 of the
Maharashtra Ownership Flats (Regulation of the Promotion of Construction,
Sale, Management and Transfer) Act(MOFA). It was held that a promoter
F was not entitled to put up add!tional structures not shown in the original !'"
lay out plan without the consent of the flat takers. Thus, consent wa.s
attached to the concept of additional structure. Section 7 was accordingly
amended and Section 7A was accordingly inserted by Maharashtra Amending
,;
~ct No. 36/86 in order to make the position explicit, which according to tfll
G the legislature existed prior to amendment in the 1986 Act, implicitly. >-
Section 7 ofMOFA came to be amended and for the purpose ofremoval of
doubt, additional Section 7A came to be added. Section 7A was declared as
having been retrospectively substituted and it was deemed to be effective as
if the amended clause had been in force at all material times. t
H [Para 17] [692-B-D].
JAY ANTILAL INVESTMENTS v. MADHUVIHAR CO-OP. HOUSING SOCIETY 681
Ka/pita Enclave Co-operative Housing Society Ltd. v. Kiran Builders A
Private Ltd., (1986) MhLJ 110, referred to.
1.2. Reading Section 7 and Section 7 A of MOFA, it is clear that the
question of taking prior consent of the flat takers does not arise after
the amendment in respect of any construction of additional
structures.However, the right to make any construction of additional B
- -;
structures/ buildings would come into existence only on the approval of
the plan by the competent authority. That, unless and until, such a plan
stood approved, the promoter does not get any right to make additional
construction. [Para 17) [692-F-G]
1.3. By insertion of Section 7A, the legislature had made it clear that
c
the consent of flat takers was never the criteria applicable to construction
... of additional buildings by the promoters. The object behind the said
amendment was to give maximum weightage to the exploitation of
development rights which existed in the land. Thus, the intention behind the
amendment was to remove the impediment in construction of the additional D
buildings, if the total lay out allows construction of more buildings, subject
to compliance of the building rules or building by-laws or Development
Control Regulations. At the same time, the legislature had retained Section
3 which imposes statutory obligations on the promoter to make full and
true disclosure of particulars mentioned in Section 3(2) including the
nature, extent and description of common areas and facilities. Sub-section
E
(lA) to Section 4 of the Act was also introduced by the same amending Act
under which the promoter is bound to enter into agreements with the flat
takers in the prescribed form. [Para 17) [693-A-D]
1.4. Obligation of the promoter under MOFA to make true and full F
disclosure of the flat takers remains unfettered even after the inclusion of
Section 7 A in MOF A. That obligation remains unfettered even after the
amendment made in Section 7(1)(ii) of MOFA. That obligation is
strengthened by insertion of sub-section (lA) in Section 4 of MOFA by the
Amendment Act Therefore, every agreement between the promoter and the
flat taker shall comply with the prescribed Form V. It may be noted that, G
in that prescribed form, there is an explanatory note which inter alia states
that clauses 3 and 4 of Maharashtra Ownership Flats (Regulation of the
Promotion of Construction etc.) Rules, 1964 (MOFA) shall be statutory and
shall be retained. It shows the intention of the legislature. Clauses 3 and
4 of the Rules are declared to be statutory and mandatory by the legislature H
).
682 SUPREME COURT REPORTS [2007] l S.C.R
A because the promoter is not only obliged statutorily to give the particulars
of the land, amenities, facilities etc., he is also obliged to make full and true
disclosure of the development potentiality of the plot which is the subject
matter of the agreement. [Paras 20] [694-D-F, 695-F]
1.5. Condition of true and full disclosure flows from the obligation of
B the promoter under MOFA vide Sections 3 and 4 and Form V which
prescribes the form of agreement. This obligation remains unfettered
because the concept of developeability has to be harmoniously read with the ;. ,_
concept of registration of society and conveyance of title. Once the
entire project is placed before the flat takers at the time of the
c agreement, then the promoter is not required to obtain prior consent of the
flat takers as long as the builder put up additional construction in
accordance with the lay out plan, building rules and Development Control
Regulations etc. [Para 21] [695-H, 696-A-B]
2.1. In the impugned judgment, the High Court has failed to examine
D
the question as to whether the project undertaken in 1985 by the appellant-
promoter was in respect of construction of additional buildings or whether
the project in the lay out plan consisted of one building with 7 wings. The
question which the High Court should have examined is as to whether the
project in question consists of 7 independent buildings or whether it is one
E building with 7 wings. The answer to the above question will decide the
applicability or non-applicability of Section 7(1)(ii) ofMOFA, as amended.
The answer to the above question will decide whether the time to execute
the conveyance has arrived or not. This will also require explanation from
the competent authority/respondent no. 8. [Para 22] [696-D-F]
F ,,
2.2. In the dates and events submitted by the appellant-promoter, there
is a reference to the permission granted by Urban Land Ceiling authorities
which states that the owner/developer shall construct a building with 7
wings. One neetls to examine the application made by the promoter when .
he submitted the lay out plan in 1985. If it is the building with 7 wings
G intended to be constructed in terms of the lay out plan then the High Court
is also required to consider the effect of the judgment in the case of
Ravindra Mutneja and Ors. v. Bhavan Corporation and Ors. in which the
single Judge has held that if a building is put up as a wing of an existing I'-
building, it cannot be constructed without the prior permission of the flat
H takers. In that connection, the High Court shall also consider permission
JAYANTILAL INVESTMENTS v. MADHUVIHAR CO-OP. HOUSING SOCIETY [KAPADIA, J.] 683
dated 16.11.1984 under section 21(1) ofULC Act, application made to the A
competent authority when initial lay out plan was sanctioned, applications
for amendments to lay out plans made from time to time and also agreements
between promoter and flat takers. For the aforesaid reasons and in
view of the law enunciated in this judgment, the impugned judgment is
set aside and the matter is remitted to the High Court for reconsideration.
[Paras 22-23) (696-F-H, 697-A-C]
B
Ravindra Mutneja and Ors. v. Bhavan Corporation and Ors., (2003)
5 Born. CR 695, referred to.
CIVIL APPELLATE JURISDICTION: Civil Appeal No. 3233 of2006. C
From the Final Judgment and Order dated 16.3.2006 of the High Court
of Judicature at Bombay in F.A. Nos. 786 and 989/2004.
G.E. Vahanvati, S.G. Sunil Gupta, Kavin Gulati, Nakul Diwan, Avinash D
Pandey, Ms. Rashmi and T. Mahipal, with them for the Appellant.
M.K. Gilani, Harshad V.H., Pratap Venugopal, E. Venukumar (for
M/s. K.J. John & Co.), Pallav Shishodia, Atul Y. Chitale, Suchitra
Atul Chitale, Sujeeta Srivastava and Madhup Singhal for the Respondents. E
The Judgment of the Court was delivered by
KAPADIA, J. : l. What are the rights and obligations of a promoter
..., under the provisions of the Maharashtra Ownership Flats (Regulation of the
.
Promotion of Construction, Sale, Management and Transfer) Act, 1963 F
("MOFA") is the question which·has arisen for determination in this civil
appeal.
2. On 26.8.1980 an agreement was arrived at between the vendors and
the appellant herein (Mis Jayantilal Investments-Promoter) in respect of G
8559.57 sqm. ofland in CTS No. 1068 village Kandivili, Tehsil Borivili, Greater
Mumbai. Subsequently, under a Revised Draft Development Plan, a 44 ft.
wide road was indicated and; consequently, the area admeasuring 8559.57
sqm. stood divided. On account of this division, a plot admeasuring 6071
sqm. emerged as the suit land. On 16.11.1984 the appellant-promoter obtained
H
684 SUPREME COURT REPORTS (2007) I S.C.R
A NOC under Section 21(1) of the Urban Land Ceiling Act, 1976 ("ULC Act")
permitting it to construct a building with 7 wings and 13 7 tenements for
weaker section. The construction was to be made in accordance with the
prevailing Municipal Regulations, Town Planning requirements and Statutory
Regulations. On 21.l 0.1985 the lay out plan was sanctioned. It indicated I
building with 7 wings. At that time, due to existence of a narrow road as
B access, the promoter was entitled only to FSI of0.75. This plan was amended
in 1986, 1987, 1989, 1992 and 1994 with'out any objection from the flattakers.
At this stage, it may be mentioned that on 6.5.1986 the lay out plan was
revised and approved with 5 wings having additional floors as well as FSI
of 1.00 due to construction of 44 ft. wide DP road on the original plot
c admeasuring 8559.57 sqm. of land.
3. From time to time, agreements stood entered into between the
appellant and the flat takers for sale of flats. These agreements are dated
7.12.1985, 11.4.1987, 18.l.1989, 30.4.1989, 27.7.1991 etc.
D
4. On 12.11.1986 MOFA was amended retrospectively. Under that
amendment Section 7A was inserted excluding 'additional structures' from
the scope of Section 7(l)(ii) and thereby lifted the requirement of consent
of flat takers. However, the said amendment was restricted to the plots
falling under a scheme or a project under the lay out plan. The object behind
E enacting Section 7A was to overcome the judgment of the Bombay High
Court in the case of Ka/pita Enclave Co-operative Housing Society Ltd v.
Kiran Builders Private Ltd., (1986) MhLJ 110. On 12.4.1989 on receiving
occupation certificate, possession of flats was handed over to the flat takers.
Some flats remained to be sold. They stood in the name of the appellant-
F promoter. ~-
5. On 25.3.1991, the Development Control Regulations were framed
which resulted in an increase of FSI from I to 1.8 on account of the
introduction of the concept of TDR. For the first time under this concept,
lands stood separated from the development potential of the plot.
G Consequently, the lay out plan stood amended and the appellant obtained
sanction on 25 .5 .1992 for construction of the building in question with
6 wings by consumption of the balance FSI of 1.00. The appellant accordingly
issued an advertisement for commencement of construction in accordance t
with the amended plan. However, it is the case of the appellant that on
H account of financial paucity the construction got stuck.
(
JAYANTILALINVESTMENTS "· MADHUVIHAR CO-OP. HOUSING SOCIETY [KAPADIA, J.) 685
-,
'I 6. Respondent No. 1 is the Co-operative Society registered on 20.1.1993. A
The lay out plan was once again amended on 26.11.1994. The building in
question with 6 wings was shown· in the amended plan. The plan was duly
sanctioned. It is important to note that this plan of 1994 was sanctioned in
favour of the appellant on account of purchase of.additional TDR by the
appellant.
B
7. In 1997 on account of Slum TOR, the permissible FSI stood increased
-\ to 2 from 1.8.
8. On 12.8.1997 the Co-operative Society-respondent No. 1 and five flat
takers (members) instituted suit no. 4385/97 against the appellant-promoter c
for conveyance, injunction restraining the promoter from putting up further
constructions and questioning the validity of the sanction given by the
competent authority to the amended plan dated 29.3.2001 under which the
competent authority sanctioned 5 + 2 wings applying the newly available
FSI.
D
9. By judgment and order dated 31.3.2004 the Bombay City Civil Court
at Mumbai (trial court) partly decreed the suit, permitting the appellant to
complete construction as per the amended plan dated 29.3.2001. The trial
court gave a period of three years to the appellant for executing conveyance
in favour of the Co-operative Society under the provisions ofMOFA. Being E
aggrieved by the grant of three years time to the appellant, the Cooperative
Society (Respondent No. I herein) preferred to the Bombay High Court First
Appeal No. 786/04. A cross appeal was preferred by the appellant-promoter
being First Appeal No. 989/04 in which the appellant contended that under
the agreement between the appellant and the flat takers no time limit for F
" execution of the conveyance could be set as the appellant was entitled to
exploit the full potential of the plot in question and till such time as the
development potentiality of the plot in question stood exhausted, the
--l.. appellant was not statutorily obliged to execute a conveyance in favour of
the Co-operative Society. In this connection reliance was placed on the
provisions of Section 7A of MOFA. G
_, 10. By impugned judgment dated 16.3.2006 the Bombay High Court
~
allowed First Appeal No. 786/04 filed by the Co-operative Society and
simultaneously dismissed First Appeal No. 989/04 filed by the appellant
herein. By the impugned judgment, the High court directed the appellant to H
)
686 SUPREME COURT REPORTS [2007] l S.C.R.
,,-
A convey right, title and interest and execute all relevant documents in respect
of Madhu Vihar Scheme in CTS No. l 06811 admeasuring 6071 sqm. situated
at Village Kandivali (West), Mumbai in favour of the Co-operative Society.
By the impugned judgment, the appellant was restrained pennanently from
making any construction over the suit plot bearing CTS No. 1068/l
admeasuring 6071 sqm. situated at Kandivali (West), Mumbai. By the
B impugned judgment the High Court held, that the appellant was a promoter;
that it had floated Madhu Vihar Scheme on the said plot; that Madhu Vihar
was the Scheme/ Project undertaken for development of the plot in accordance .
with the lay out plan; and, that the said Scheme stood completed with the
construction of the flats/ shops and the garden. By the impugned judgment,
c it was further held that the Society was registered on 20.1.1993 and under
Rule 8 of the Maharashtra Ownership Flats (Regulations of the Promotion
of Construction, etc.) Rules, 1964 ("the Rules"), the appellant was statutorily
obliged to convey the title to the society which they failed to do even after
the Scheme got completed and possession of the flats stood handed over
to the flat takers. By the impugned judgment the High Court held, that there
D
was an implied trust created; that the promoter was the trustee and that the
beneficiaries were the flat takers. By the impugned judgment it was further
held, that under section 7 of MOFA the appellant was prohibited from
putting up additional constructions after the plan stood disclosed to the flat
takers; that the promoter was not entitled to make any alteration in the
E structure without the prior consent of the flat takers; that the promoter could
not make any additions in the structure of the building without the prior
consent of the society and that under Section 7A, the said prohibition was
not to apply in respect of the construction of any other additional building
or structure constructed or to be constructed under a scheme or a project •
F of development in the lay out plan. By the impugned judgment it has been
held, that the construction of Madhu Vihar started in 1985; that section 7A
was inserted in 1986 and that Madhu Vihar Scheme got completed in 1989.
According to the impugned judgment, between 1985 and 1989, the plans
were changed at least four times and that no additional wings like the one
proposed in the plan approved on 29.3.2001 was ever included in the lay out
G plans between 1985 and 1989 and, therefore, the appellant-promoter was not
entitled to derive any benefit from Section 7A of MOF A and, consequently,
the appellant was not entitled to construct additional building in the above
suit plot. Hence this civil appeal.
....
H 11. Mr. Sunil Gupta, learned senior counsel appearing on behalf of the
'-·
JAY ANTILAL INVESTMENTS"· MADHUVIHAR CO-OP. HOUSING SOCIETY [KAPADIA, J.) 687
~ appellant submitted that Section 7 of MOFA enjoined the promoter, inter A
alia, not to construct any additional structure without the consent of the
flat takers in the agreed building. This provision was applied by the Bombay
High Court in the case of Ka/pita Enclave (supra). The said judgment
prohibited the developer from constructing the additional structure in the
agreed building. Learned counsel submitted that the State Legislature
imposed such a restriction on the promoter contrary to the object of the Act
B
and, consequently, the legislature stepped in to change the basis of the
~ judgment of the Bombay High Court in Ka/pita Enclave case (supra) by
enacting the Amending Act No. 36/86 retrospectively. According to the
learned counsel, the said Amending Act deleted the said restriction and left
the promoter free to construct any additional structure without obtaining the c
consent of the flat takers in the agreed building. Learned counsel submitted
that the underlying purpose of the said amendment is that maximum possible
housing as per the prevailing by-laws should be achieved to enable the
maximum number of members of the public to be accommodated therein and
that the individual rights of flat takers should not be allowed to come in the
D
way of achievement of this public purpose. Learned counsel emphasized
that the object behind amending Section 7 and Section 7A is to enable the
promoter to construct an additional structure; that the object of Section 7
and Section 7A is to bring at par a promoter who has sought and has been
granted permission to construct building consuming the maximum FSI
available under the by-laws prevailing on the given date and a promoter who E
had sought and was given permission to construct building consuming the
maximum FSI available under the by-laws as prevailing on earlier date and
who otherwise on the given date stands in the same class as the
abovementioned promoter insofar as the question of consumption of the
---. ....., total FSI available is concerned. Learned counsel submitted that the object F
behind the amendment is to ease the problem of shortage of housing.
Learned counsel further submitted that if the above interpretation of the
amended Section 7 and 7A is not accepted, it would give rise to discrimination
between two sets of persons, namely, flat takers who are party to a new
agreement and a new construction plan and those flat takers who have been
party to an earlier agreement in an earlier construction plan. According to G
the learned counsel, if the interpretation given by him is not accepted,
.... -~
persons interested in the former piece of land shall stand facilitated whereas
persons interested in the latter piece of land shall stand vetoed, though the
building by-laws, rules etc. treat them equally. Learned counsel, therefore,
submitted that any other interpretation would defeat the very purpose of the H
688 SUPREME COURT REPORTS [2007] l S.C.R.
A amendment to Section 7 and Section 7A. On facts, learned counsel submitted,
relying on the lay out plans, that even under the initial lay out plan of 1985,
7 wings were to be constructed; that the said plan was revised on 6.5 .1986
under which the construction was restricted to 5 wings having additional
floors; that this was prior to the inclusion of Section 7A and, therefore, when
the D.C. Regulations were enacted in 1991 and the concept of TDR was
B introduced, the appellant got increased FSI of 1.8, consequent upon which
the plan was amended and 6 wings came to be sanctioned on 25.5.1992.
Similarly, when the FSI was increased to 2, the plan was got amended and
accordingly the appellant obtained a sanction for construction of 5 + 2
wings. Learned counsel, therefore, urged that the sanction obtained by the
c appellant on 29.3.2001 for construction of 5 + 2 wings on the suit plot was
in terms of the original Plan sanctioned on 21.10 .1985 when 7 wings stood
sanctioned. In the circumstances, learned counsel urged that the appellant
was entitled to construct 5 + 2 wings which was contemplated even in the
original Plan dated 21.10.1985. Accordingly it was submitted that, in the facts
and circumstances of this case, the amended provisions of Sections 7 and
D
7A of MOF A were applicable and, consequently, the appellant was not
obliged to execute a conveyance in favour of the society till the appellant
is in a position to fully exploit the development potentiality of the suit plot.
In the alternative, it is urged that, in any view of the matter, the appellant
is not entitled to execute the conveyance in favour of the society till the
E appellant exhausts the FSI of 2.
12. Mr. M. K. Ghelani, learned counsel appearing on behalf of the
society submitted that under MOF A there are two concepts, namely,
developeability and conveyance. It was urged that Section 7 and 7A deal
F with developeability of the project, while Sections IO and 11 read with Rules
8 and 9 deal with the subject of formation of Society and transfer of title.
Learned counsel urged that each of the above two concepts operate in
different fields and, therefore, Section 7 and 7A cannot override Sections 10
and 11 read with the relevant rules. It was urged, that under Section 3(m)(iii)
and (iv) a promoter is required to disclose the nature, extent and description
G of the common areas and facilities in its advertisement/ brochure; that
section 4(1) requires a promoter to enter into a written agreement in the
prescribed form and Section 4(1 A) inter alia provides that such agreements
shall contain the nature, extent and description of common areas and
facilities and, consequently, it is not open to the promoter to contract out
-
H of the prescribed form of the agreement in form V. Learned counsel pointed
JAY ANillAL INVESTMENTS 1•. MADHUVlliAR CO-OP. HOUSING SOCIETY [KAPADIA, J .] 689
out that Section 4(1) provides that such agreement shall be in Form V, that A
Form V gives a model form under which the promoter has to declare the FSI
(inherent) available in respect of the land. Under Rule 5 read with the model
form of agreement, the promoter has to declare all relevant particulars in
respect of utilization ofFSI and in cases where the promoter has utilized any
FSI of any other land or property by way of floating FSI then the particulars
of such floating FSI has to be disclosed by the promoter to the flat
B
purchasers. The residual FSI in the plot or the lay out not consumed will
be available to the promoter till the registration of the society. However, after
registration of the society the remaining FSI shall be available to the society.
Learned counsel submitted that Section 7A stood inserted in MOF A vide
Maharashtra Amending Act 36/86 and by the same Amending Act Section c
4(1A) was also inserted and, therefore, Section 7A has to be read with
Section 4(1A). Learned counsel, therefore, urged that Section 7A does not
give to the promoter the right of developeability in eternity. In the present
case, learned counsel submitted that the lay out plan as well as the NOC
obtained by the promoter from ULC authorities was to construct a building
D
with 7 wings. Learned counsel urged that Section 7A was not applicable to
the present case since in the present case the scheme consisted of one
building with 6 to 7 wings. Moreover, it was further pointed out that Section
7A applies when there is a project or scheme which indicates phase wise
development of a large plot made known to the intending flat takers. Section
7A in such cases does not empower the intending flat takers to prevent E
construction of additional building according to such scheme. As a corollary,
it was urged that Section 7A does not confer any additional benefits or
rights to a promoter to construct additional building which did not form part
of the scheme/project in the lay out disclosed to the flat takers and, in any
event, not after the obligation to convey has become operative and F
enforceable under Sections I 0 and 11 read with Rules 8 and 9 of the Rules.
Learned counsel urged that in the present case the society has been
registered in 1993. He submitted that in the present case, on facts, the
obligation to convey has become enforceable under Sections 10 and 11. He
clarified that mere formation of the society does not take away from the
promoter the rights of the promoter to the remaining development. He is not G
deprived of his rights to the unsold flats. However, it is not open to the
promoter to resort to an ingenious drafting enabling the promoter to defer
)
execution of conveyance till eternity. On facts, learned counsel pointed out
that in the present case, the NOC obtained by the promoter from the Urban
Land Ceiling authorities read with the lay out plan/ block plan of 1985 as H
690 SUPREME COURT REPORTS [2007) 1 S.C.R.
A well as the agreements with the flat takers showed that the scheme/ project/
f
lay out was in respect of only one building with different wings; that the
lay out plan does not indicate phase wise development; that the agreement
with the flat takers indicated the scheme for only one building and, in the
circumstances, Section 7A is not attracted. That in any event, it was not
open to the promoter to unilaterally change the scheme/ lay out by adding
B to it additional building and in the process remove the existing facilities and
amenities provided in the lay out plan. Learned counsel urged that on facts
of the present case, it was one building project which got completed in I 989
when occupation certificate was issued and, in the circumstances, the
promoter was not entitled to put up additional constructions.
c
13. Looking to the importance of the matter in which we were required
to harmoniously construe the provisions· of Sections 3 and 4 on one hand
with Section 7 and 7A on the other hand as also Sections IO and I I of
MOFA and keeping in mind the question of public importance, we requested
Mr. G.E. Vahanvati, learned Solicitor General of India to assist the Court,
D
keeping in mind the externalities existing in such cases coming from Mumbai.
Learned Solicitor General of India has given us written submissions. He has
reproduced the various judgments of the.Bombay High Court under MOFA.
It is submitted that, it is not open to the builders to insert clauses in the
agreement with the flat takers stating that conveyances will be executed only
E after the entire property is developed. Learned amicus curiae submitted that
the contention of the promoter in the present case is that its obligation to
form society and execute a conveyan~e only after completion of the scheme
is misconceived because under Sections I 0 and I I when the builder enters
into an agreement with the flat takers he is required to form a cooperative
F society as soon as the minimum number of flat takers is reached and,
thereafter, the conveyance has to be executed in favour of the society within
four months after the formation thereof in terms of Section I I. He submitted
that MOFA has been enacted to regulate the activities of the builders and
not to confer benefits on them. He submitted that Section 7A was inserted
only for removal of doubts and to provide that the deleted words "construct
G any additional structure" shall be deemed never to have been there
notwithstanding any judgment, decree or order of any court which means
that the builder could construct any additional structure without the consent
of the flat purchasers. However, it is pointed out that Section 7A does not
(
have the effect of conferring any rights on builders to claim an exemption
H from their obligations under -Sections IO and I I of MOF A.
L
" )
JAYANTILAL INVESTMENTS 1•. MADHUVlliAR CO-OP. HOUSING SOCIETY (KAPADIA, J.] 691
14. Before dealing with the point in issue one needs to look at original A
)
Section 7 which was in existence in the Statute prior to its amendment by
Maharashtra Amending Act No. 36/86.
15. The unamended Section 7 reads as follows:
"7.(1) After the plans, and specifications of the buildings as
B
approved by the local authority as aforesaid, are disclosed or
furnished to the person who agrees to take one or more flats, the
-; promoter shall not make-
(i) any alterations in the structures described therein in respect c
of the flat or flats which are agreed to be taken, without the
previous consent of that person; or
(ii) any other alterations in the structure of the building, [or
construct any additional structures,] without the previous
consent of all the persons who have agreed to take the flats."
D
\ (emphasis supplied)
16. The amended Section 7 reads as follows:
E
"7. After plans and specifications are disclosed no alterations
or additions without consent of persons who have agreed to
take the flats; and defects noticed within three years to be
rectified
F
(I) After the plans and specifications of the building, as
approved by the local authority as aforesaid, are disclosed
or furnished to the person who agrees to take one or
more flats, the promoter shall not make-
(i) any alterations in the structures described therein in G
respect of the flat or flats which are agreed to be taken,
--1
without the previous consent of that person;
'1 (ii) any other alterations or additions in the str,ucture ofthe
building without the previous consent of all the persons H
6CJ2. SUPREME COURT REPORTS [2007] 1 S.C.R.
.A who have agreed to take the flats in such building."
f
(emphasis supplied)
17. The judgment of the Bombay High Court in Ka/pita Enclave case
(supra) was based on the interpretation of unamended Section 7 of MOF A.
B Consequently, it was held that a promoter was not entitled to put up
additional structures not shown in the original lay out plan without the
consent of the flat takers. Thus, consent was attached to the concept of
additional structure. Section 7 was accordingly amended. Section 7A was
accordingly inserted by Maharashtra Amending Act No. 36/86. Section 7A
c was inserted in order to make the position explicit, which according to the
legislature existed prior to 19%, implicitly. Section 7 of MOFA came to be
amended and for the purpose of removal of doubt, additional s.ection 7A
came to be added by Maharashtra Act 36/86. By this amendment, the words
indicated in the parenthesis in the unamended Section 7(ii), name!y, "or
construct any additional structures" came to be deleted and consequential
D amendments were made in Section 7(1)(ii). Maharashtra Act No. 36/86
operated retrospectively. Section 7 A was declared as having been
retrospectively substituted and it was deemed to be effective as if the
amended clause had been in force at all material times. Further, it was
declared vide Section 7A that the above quoted expression as it existed
E before commencement of the Amendment Act shall be deemed never to
apply in respect of the construction of any other additional buildings/
structures, constructed or to be constructed, under a scheme or project of
development in the lay out plan, notwithstanding anything contained in the
Act or in any agreement or in any judgment, decree or order of the court.
F Consequently, reading Section 7 and Section 7A, it is clear that the question
of taking prior consent of the flat takers does not arise after the amendment
in respect of any construction of additional structures. However, the right
to make any construction of additional structures/ buildings would come
into existence only on the approval of the plan by the competent authority.
That, unless and until, such a plan stood approved, the promoter does not
G get any right to make additional construction. This position is clear when
one reads the amended Section 7(l)(ii) with Section 7A ofthe MOFA as
amended. Therefore, having regard to the Statement of Objects and Reasons
for substitution of Section 7(1)(ii) by the Amendment Act 36/86, it is clear
(
that the object was to make legal position clear that even prior to the
H amendment of 1986, it was never intended that the original provision of
JAYANTILAL INVESTMENTS '" MADHUVJHAR CO-OP. HOUSING SOCIETY [KAPADIA, J.] 693
Section 7(l)(ii) of MOFA would operate even in respect of construction of A
l
additional buildings. In other words, the object of enacting Act No. 36/86
was to change the basis of the judgment of the Bombay High Court in
Ka/pita Enclave case (supra). By insertion of Section 7A vide Maharashtra
Amendment Act 36/86 the legislature had made it clear that the consent of
flat takers was never the criteria applicable to construction of additional
buildings by the promoters. The object behind the said amendment was to
B
~
·• give maximum weightage to the exploitation of development rights which
'i existed in the land. Thus, the intention behind the amendment was to remove
the impediment in construction of the additional buildings, if the totai lay
out allows construction of more buildings, subject to compliance of the .
building rules or building by-laws or Development Control Regulations. At c
the same time, the legislature had retained Section 3 which imposes statutory
obligations on the promoter to make full and true disclosure of particulars
mentioned in Section 3(2) including the nature, extent and description of
common areas and facilities. As stated above, sub-section (IA) to Section
4 was also introduced by the legislature by Maharashtra Act 36186 under
D
which the promoter is bound to enter into agreements with the flat takers
\.
in the prescribed form. Under the prescribed form, every promoter is required
to declare the FSI available in respect of the said land. The promoter is also
.., required to declare that no part of that FSI has been utilized elsewhere, and
if it is utilized, the promoter has to give particulars of such utilization to the
flat takers. Further, under the proforma agreement, the promoter has to E
further declare utilization of FSI of any other land for the purposes of
developing the land in question which is covered by the agreement.
18. Therefore, the legislature has sought to regulate the activities of the
promoter by retaining Sections 3 and 4 in the Act. It needs to be mentioned F
-\
at this stage the question which needs to be decided is whether one building
with several wings would fall under amended Section 7(1)(ii). Section 7A
basically allows a builder to construct additional building provided the
construction forms part of a scheme or a project. That construction has to
be in accordance with the lay out plan. That construction cannot exceed the
development potentiality of the plot in qu~stion. Section l 0 of MOFA casts G
an obligation on the promoter to form a cooperative society of the flat takers
as soon as minimum number of persons required to form a society have
taken flats. It further provides that the promoter shall join the society in
respect of the flats which are not sold. He has to become a member of the
society. He has the right to dispose of the flats in accordance with the H
)
694 SUPREME COURT REPORTS [2007] 1 S.C.R.
A provisions of the MOFA. Section 11 inter alia provides that a promoter ....
shall take all necessary steps to complete his title and convey the title to
-( ,,'
the society. He is obliged to execute all relevant documents in accordance '·~
with the agreement executed under Section 4 and if no period for execution r
of the conveyance is agreed upon, he shall execute the conveyance within
the prescribed period. Rule 8 inter alia provides that where a cooperative '·
B ,.
~ ..
)
society is to be constituted, the promoter shall submit an application to the
Registrar for registration of the society within four months from the date on ·Jt:
which the minimum number of persons required to form such society (60%) ,-
.~
have taken flats. Rule 9 provides that if no period for execution of a
conveyance is agreed upon, the promoter shall, subject to his right to
c dispose of the remaining flats, execute the conveyance within four months
from the date on which the society is registered.
19. Reading the above provisions ofMOFA, we are required to balance
.the rights of the promoter to make alterations or additions in the structure
of the building in accordance with the lay out plan on the one hand
D
vis-a-vis his obligations to form the society and convey the right, title and
interest in the property to that society. The obligation of the promoter under
-(
MOFA to make true and full disclosure of the flat takers remains unfettered
even after the inclusion of Section 7A in MOFA. That obligation remains r
unfettered even after the amendment made in Section 7( l)(ii) of MOF A. That
E obligation is strengthened by insertion of sub-section (IA) in Section 4 of
MOF A by Maharashtra Amendment Act 36/86. Therefore, every agreement
~
between the promoter and the flat taker shall comply with the prescribed
Form V. It may be noted that, in that prescribed form, there is an explanatory
note which inter alia states that clauses 3 and 4 shall be statutory and shall
F be retained. It shows the intention of the legislature. Note 1 clarifies that a
model form of agreement has been prescribed which could be modified and
,... 'lo.-
adapted in each case depending upon the facts and circumstances of each
case but, in any event, certain clauses including clauses 3 and 4 shall be
treated as statutory and mandatory and shall be retained in each and every r '
individual agreements between the promoter and the flat taker. Clauses 3 and
G 4 of the Maharashtra Ownership Flats (Regulation of the Promotion of
Construction etc.) Rules, 1964 are quoted hereinbelow:
"3. The Promoter hereby agrees to observe, perform and comply
(
with all the terms, conditions, stipulations and restrictions if
H any, which may have been imposed by the concerned local
JAYANTILAL INVESTMENTS''· MADHUVIHAR CO-OP. HOUSING SOCIETY [KAPADIA, J.] 695
authority at the time sanctioning the said plans or thereafter A
and shall, before handing over possession of the Flat to the
Flat Purchaser, obtain from the concerned local authority
occupation and/or completion certificates in respect of the
Flat.
4. The Promoter hereby declares that the Floor Space Index
B
available in respect of the said land is... square metres only
and that no part of the said floor space index has been utilized
by the Promoter elsewhere for any purpose whatsoever. In
case the said floor space index has been utilized by the
Promoter elsewhere, then the Promoter shall furnish to the Flat c
Purchaser all the detailed particulars in respect of such
utilization of said floor space index by him. In case while
developing the said land the Promoter has utilized any floor
space index of any other land or property by way of floating
floor, space index, then the particulars of such floor space D
index shall be disclosed by the Promoter to the Flat Purchaser.
The residual F.A.R. (F.S.1.) in the plot or the layout not
consumed will be available to the promoter till the registration
of the society. Whereas after the registration of the Society
the residual F.A.R. (F.S.I.), shall be available to the Society."
E
(emphasis supplied)
20. The above clauses 3 and 4 are declared to be statutory and
mandatory by the legislature because the promoter is not only obliged
statutorily to give the particulars of the land, amenities, facilities etc., he is
F
also obliged to make full and true disclosure of the development potentiality
of the plot which is the. subjed matter of the. agreement. The promoter is
not only required to mak.e:disclosure·conceming the. inherent FSI, he is also
required at the stage· of lay out plan to declare whether the plot in question
in future is capable of being loaded with additional FSI/ floating FSI/ TDR.
In other words, at the time· of execution of the agreement with the flat takers G
the promoter is obliged statutorily to place before the flat takers the entire
project/ scheme, be· it a one.building. scheme or multiple number of buildings
scheme. Clause 4 shows the: effect of the formation of the Society.
21. In our view, the: above condition of true and full disclosure flows H
696 SUPREME COURT REPORTS [2007] l S.C.R.
A from the obligation of the promoter under MOFA vide Sections 3 and 4 and
Form V which prescribes the form of agreement to the extent indicated
above. This obligation remains unfettered because the concept of
developeability has to be harmoniously read with the concept of registration
of society and conveyance of title. Once the entire project is placed before
the flat takers at the time of the agreement, then the promoter is not required
B to obtain prior consent of the flat takers as long as the builder put up
additional construction in accordance with the lay out plan, building rules
and Development Control Regulations etc.
22. In the light of what is stated above, the question which needs to .•
c be examined in the present case is whether this case falls within the ambit
of amended Section 7( l )(ii) or whether it falls within the ambit of Section 7A
of MOFA. As stated above, under Section 7(1) after the lay out plans and
specifications of the building, as approved by the competent authority, are
disclosed to the flat takers, the promoter shall not make any other alterations
or additions in the structure of the building without the prior consent of the
D
flat takers. This is where the problem lies. In the impugned judgment, the
High Court has failed to examine the question as to whether the project
undertaken in 1985 by the appellant herein was in respect of construction
of additional buildings or whether the project in the lay out plan of 1985
consisted of one building with 7 wings. The promoter has kept the requisite
E percentage of land open as recreation ground/ open space. Relocation of the
tennis court cannot be faulted. The question which the High Court should
have examined is: whether the project in question consists of 7 independent
buildings or whether it is one building with 7 wings? The answer to the
above question will decide the applicability or non-applicability of Section
F 7{l)(ii) ofMOFA, as amended. The answer to the above question will decide
whether the time to execute the conveyance has arrived or not. This will also
n:quire explanation from the competent authority, namely, Executive Engineer,
"R" South Ward, Kandivali, Mumbai-400067 (Respondent No. 8 herein). In
the dates and events submitted by the appellant-promoter, there is a
reference to the permission granted bY, ULC authorities datd 16.11.1984
G which states that the owner/developer shall construct a building with 7
wings. One needs to examine the application made by the promoter when
he submitted the lay out plan in 1985. If it is the building with 7 wings
intended to b~ constructed in terms of the lay oqt plan then the High Court (
is also required to consider the effect of the judgment in the case of
H Ravindra Mutneja and Ors. v. Bhavan Corporation and Ors., (2003) 5
I
JAY ANTILAL INVESTMENTS 1·. MADHUVIHAR CO-OP. HOUSING SOCIETY [KAPADIA, J.) 697
BomCR 695 in which the learned single Judge has held that if a building is A
put up as a wing of an existing building, it cannot be constructed without
the prior permission of the flat takers. In that connection, the High Court
shall also consider Permission dated 16.11.1984 under section 21(1) ofULC
Act, application made to the competent authority when initial lay out plan
was sanctioned, applications for amendments to lay out plans made from
time to time and also agreements between promoter and flat takers.
B
23. For the aforesaid reasons and in view of the law enunciated by us
vide this judgment, the impugned judgment is set aside and the matter is
remitted to the High Court for reconsideration. As the matter has been under
litigation for a considerable length of time, we hope that due priority will be C
given for early disposal of this matter.
24. We wish to express our deep appreciation for the assistance
rendered by learned Solicitor General oflndia as amicus curiae in the matter.
25. Subject to what is stated, the appeal is allowed with no order as
D
to costs.
S.K.S. Appeal allowed.
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.