Created byFuzzy Cloud

Supreme Court of India

KANCHAN UDYOG LIMITEDversusUNITED SPIRITS LIMITED

Citation
2017 INSC 480
Decided
19 June 2017
Disposal
Dismissed

Holding

The breach was not the dominant cause of loss; the appellant is not entitled to expectation or reliance damages.

Summary

Kanchan Udyog Ltd. entered into a bottling agreement with United Spirits Ltd. for a non‑alcoholic beverage plant, relying on the respondent to supply concentrate. The agreement was terminated by United Spirits in March 1988 and the plant ceased operations in May 1989. The appellant claimed damages for loss of anticipated profits and costs of the plant, alleging breach, but the High Court initially awarded damages which were later set aside by the Division Bench. The Supreme Court held that the breach was not the dominant cause of the appellant’s losses, that the projected profits in the loan application were speculative and not a proper basis for damages, and that the appellant failed to mitigate its losses and had waived its rights by continuing to accept supplies from another source. Consequently, the appellant was not entitled to either expectation or reliance damages, and the appeal was dismissed.

Issues considered

  • The breach of the bottler's agreement by United Spirits was the cause of Kanchan Udyog's loss of anticipated profits.
  • Whether the appellant could recover expectation loss, reliance loss, or both under the Indian Contract Act.
  • Whether the appellant failed to mitigate its losses as required by Section 73 of the Contract Act.
  • Whether the appellant's conduct amounted to waiver, estoppel or acquiescence under Section 63.
  • Whether the loan‑application profit projections were admissible evidence for assessing damages.
  • Whether a novation of the contract occurred under Sections 62 and 8 of the Contract Act.

Legislation cited

Subjects

contract breachdamagesexpectation lossreliance lossmitigationwaivernovationSection 73Section 63Indian Contract Actnon‑alcoholic beverage bottling

Judgment

                         [2017] 7 S.C.R. 175


                  KANCHAN UDYOG LIMITED                                 A
                                  v.
                    UNITED SPIRITS LIMITED
                   (Civil Appeal No. 1168 of 2007)
                           JUNE 19, 2017                                B

          (RANJAN GOGOi AND NAVIN SINHA, JJ.]
        Contract Act, 1872 - ss. 73, 63 :-- Damages for wrongful
termination of contract - Appellant entered into an agreement with
respondent for establishment of non-alcoholic beverages bottling
plant - The concentrate (essence), for preparation of the no~'- 'C
alcoholic beverage, was to be supplied by the respondent - Loan
advanced to the appellant by State Industrial Development
Corporation(WBIDC) for esta.blishment of the bottling plant -
Bottlers agreement was terminated by the respondent, on which
appellant .ftled suit - Single Judge of High Court decreed suit in D
favour of appellant awarding damages towards loss of anticipated
profits and costs for installation of the plant - Division Bench in
appeal reversed the decree and dismissed the suit - Propriety -
 Held: Proper - It cannot be held that the breach alone was the
 cause for loss of anticipated profits, much less it was the primary or E
 dominant reason - As per materials on records, appellant had
 thanked respondent for its advertising support - Appellant had
 acknowledged that it would continue to suffer losses for jive-six
 years while seeking long term credit for supply of concentrates and
 had failed to deploy adequate manpower as per its own projections,
 this itself demonstrated the poor financial condition of the appellant F
 - Losses were reflected in its balance sheet - It cannot be held that
 breach by the respondent was the dominant cause for loss of
 anticipated profits - Appellant failed to take steps to mitigate its
 losses, as it stopped lifting concentrates from another company after
 having done so for nearly a year without any explanation and didn't
                                                                          G
 take steps to sell the unit after its closure, rather did that belatedly
 after seven years - Therefore, appellant failed to abide by its own
 obligations and lacked adequate infrastructure, .finances and
 manpower to run its business.
       Contract - 'Reliance loss' and 'Expectation loss' - Discussed.
                                                                         H
                                  175
176          SUPREME COURT REPORTS                       [2017) 7 S.C.R.



A          Dismissing the appeal, the Court
           HELD: 1. In the facts of the present case, it cannot be
 .· held that ·the breach alone was the cause for loss of anticipated
    profits, much less was it the primary or d-0minant reason. The
    appellate court has adequately discussed the appellant's letter
B ~hanking the r.es.pondent for its advertising support. With
    reference to evidence, the appellant court has also adequately
   .discussed that the appellant failed to take steps to mitigate it
    losses urtder the Explanation to Section 73 of the Act. There is
    no reason to come to any different condusion from the materials
    on record. If concentrates were available from Mis. VEC, the
c appellant had to offer an explan.ation why it stopped lifting the
    same after havi.ng done so for nearly a year, and ·could have
    continued with the business otherwise and earned profits. It could
    also have taken steps to sell the unit after its closure in May,
    1989 rather than to do so belatedly in 1996. No reasonable steps
D had been displayed as taken by the appellant for utilisatfon of its
    bottling plant by negotiations with others in the business. Nothing
    had been demonstrated of the injury that would have been caused
    to it thereby. (Paras 25, 27)(189-F; 191-D-F(
          2.1 That leaves the question with regard to reliance loss
 E and  the  expectation loss. Whether the two could be maintainable
   simultaneously or were mutually exclusive? The primary object
   for protection of expectation interest, has been described as to
   put the innocent party in the position which he would have
   occupied had the contract been performed. The general aim of
   the law being to protect the innocent party's defeated financial
 F expectation and compensate him for his loss of bargain, subject
   to the rules of causation and remoteness. The purpose of
   protection of reliance interest is to put the plaintiff in the position
   in which he would have been if the contract had never been made.
   The loss may include expenses incurred in preparation by the
 G innocent party's own performance, expenses incurred after the
   breach or even pre-contract expenditure but subject to
   remoteness. (Para 28](191-G-H; 192-A-B]
         2.2 The appellant had failed to establish its claim that the
   breach by the respondent was the cause for loss of anticipated
 H profits, that the profitability projection in its loan application was
  KANCHAN UDYOG LIMITED v. UNITED SPIRITS LIMITED                177


a reasonable basis for award of damages towards loss of A
anticipated profits. The appellant had failed to abide by its own
obligations under Exhibit 'C' and lacked adequate infrastructure,
finances and manpower to run its business. It also failed to take
reasonable steps to mitigate its losses. The appellant was not
entitled to any expectation loss towards anticipated profits, and B
thus, any grant of reliance loss would tantamount to giving a
benefit to it for what was essentially its own lapses.(Paras 30,
31)[193-C, E-F)
     Wellesley Partners LLP v. Withers LLP (2015) EWCA
     Civ 1146; M. Lachia Shetty & Sons Ltd. vs. Coj}ee
     Board, Bangalore (1980) 4 SCC 636 : [1981] 1 SCR            c
     884; McDermott International Inc v. Burn Standard Co.
     Ltd. & Ors. (2006) 11 SCC 181 : [2006) 2 Suppl. SCR
     409; Galoo Ltd. & Ors. v. Bright Grahame Murray &
     Anr: (1994) 1 WLR 1360; Mis. Murlidhar Chiranjilal
     v. Mis. Harishchandra Dwarkadas & Anr. (1962] 1 SCR         D
     653; BSNL v. BPL Mobile Cellular Ltd. (2008) 13 SCC
     597 : (2008) 8 SCR 729; P. Dasa Muni Reddy v. P.
     Appa Rao, (1974) 2 SCC 725 : [1975) 2 SCR 32;
     Wam'an Shriniwas Kini v. Ratilal Bhagwandas & Co.
     [1959) Suppl. 2 SCR 21; Parabola case (2011) QB
     477 - referred to. ·                                        E

     Payzu v. Saunders (1919) 2 KB 581; Cullinane vs.
     British Rema Manufacturing Co. Ltd. (1954) 1 QB 292;
     C&P Haulage vs. Middleton (1983) 3 All ER 94 - relied
     on.
      Pollock and Mu/la, 14'h edition; Chitty on Contracts,      F
      26'h edn. (1989) Vol.2, pp.1128-1129, para 1785 -
      referred to.
                      Case Law Reference
      (2015) EWCA Civ 1146           referred to    Paras
                                                                 G
      [19811 1 SCR 884               referred to    Para 7
      [2006] 2 Suppl. SCR 409        referred to    Para9
      (1994) 1 WLR 1360              referred to    Para 10
      [1962] 1 SCR 653               referred to    Para 10
                                                                 H
178                  SUPREME COURT REPORTS                     [2017] 7 S.C.R.


    A           (1919) 2 KB 581                 relied on        Para 10
                (1954) 1 QB 292                  relied on       Para 11
                 .
                (1983) 3 All ER 94               relied on       Para 11
                [2008] 8 SCR 729                 referred to     Para 21
    B           [1975] 2 SCR 32                  referred to     Para 22
                [1959] Suppl. 2 SCR 21           referred to     Para 23
                (2011) QB 477                    referred to     Para 26
•
    C           CIVIL APPELLATE JURISDICTION: Civil Appeal No. 1168 of
        2007.
              From the Order dated 14.01.2005 of the High Court of Calcutta
        in APDT No. 1 of 2000 and APD No. 14 of 2000 and SN No. 839 of
        1990.
    D          Paras Kuhad, Sr. Adv., Prateek Jalan, Siddharth Bhatnagar,
        Sanjeev Kapoor, Snehal Kakrania, Ankit Yadav, Ms. Aditi Tripathi and
        Jatin Chaturvedi (for Mis. Khaitan & Co.), Advs. for the Appeliant.
              Jaideep Gupta, Sr. Adv., Ni~!'!j_ Gupta, Kuna! Chatterjee, Saurav
        Gupta, Ms. Anshu Gupta, Advs. for the Respondent.
    E
                The Judgment of the Court was delivered by
               NAVIN SINHA, J. 1. The appellant's suit, C.S. No.839of1990,
        for damages and wrongful termination of contract, was decreed by the
        learned Single Judge on 02.12.1999. It has been reversed in appeal
    F   preferred by the respondent, on 14.01.2005 inAPD No.14 of2000, and
        the suit dismissed .
            . 2. The appellant entered into an agreement with the respondent
      for establishment of a non-alcoholic beverages bottling plant at Dankuni,
      West Bengal, and sale under the respondent's trade mark, 'Thrill', 'Rush',
    G 'Sprint', and 'McDowell's Sparkling Soda.' The respondent provided
      technical consultancy for establishment of the plant, incorporated in the
      Project Engineering Services Agreement dated 11.09.1985. A Bottler's
      agreement dated 26.10.1985 was separately executed, valid for ten years
      with a renewal option, containing the respective rights and obligations of
      the parties, along with a Marketing agreement. The concentrate
    H
  KANCHAN UDYOG LIMITED v. UNITED SPIRITS LIMITED                               179
                [NAVIN SINHA, J.]

(Essence), for preparation of the non-alcoholic beverage, was to be             A
supplied by the respondent. The beverage was to be sold in specified
districts of West Bengal, as provided for in the marketing agreement.
        3. The appellant, on 15.12.1985 applied for loan, Exhibit 'C', to
the West Bengal Industrial Development Corporation (hereinafter referred
to as 'the WBIDC') for establishment of the bottling plant at an estimated      B
cost ofRs.226.80 lakhs. In accordance with procedures, it was processed
by the West Bengal Consultancy Organisation Ltd. (hereinafter referred
to as 'WEBCON'), which independently prepared a techno-economic
feasibility report, 'Exhibit F 1'. Loan was then advanced to the appellant
by the WBIDC, and the West Bengal State Financial Corporation.
Commercial production commenced on 01.01.1987. The bottler's
agreement was terminated by the respondent on 16.03.1988. Commercial
production at the plant ceased in May, 1989, and the suit was instituted
by the appellant in 1990. The learned Single Judge decreed the Suit,
awarding damage_s for Rs.2,73,38,0001- towards loss of anticipated profits,
and a sum ofRs.1,60,00,0001- towards costs for installation of the plant,       D
after deducting Rs.9 .05 lakhs payable by the appellant to the respondent
as consultancy charges. The respondent was held liable to pay to the
appellant a sum of Rs.4,24,33,0001- with interest@ I 0% from the date
of suit till payment. The Division Bench in appeal reversed the decree,
and dismissed the Suit.
                                                                                E
       4. Sri Paras Kuhad, learned senior counsel appearing for the
appellant, submitted that the bottler's agreement valid for ten years, was
terminated unilaterally and prematurely by the respondent on 16.03.1988,
contrary to clause 26 of the agreement. The appellant had never denied
performance of its obligations under the agreement. The appellant had
not signed and returned the termination letter, in acceptance, as reiterated    F
by the respondent on 25.07.1988. The appellant did not sign any fresh
agreement with Mis. Venkateswara Essence & Chemicals Pvt. Ltd.
(hereinafter referred to as 'VEC') for supply of concentrates by it, in
lieu of the respondent. The acceptance of concentrates by the appellant
directly from Mis. VEC for a short time span, under clause 5 of the             G
agreement, cannot be construed either as novation of the original contract
under Section 62 of the Indian Contract Act (hereinafter referred to as
'the Act'), or acquiescence to any new arrangement by substitution of a
new contract. It was an act done under compulsion, and not voluntarily.
A novation of contract, can take place only by mutual consent in a tripartite
                                                                                H
180             SUPREME COURT REPORTS                          [2017] 7 S.C.R.


A      arrangement. In absence of any fresh tripartite agreement executed
       between the parties, it is futile to contend novation. The respondent also
       continued to deal with the appellant under the original agreement, even
      ·while it sought to persuade the appellant to sign the fresh agreement.
         5. The respondent was the domain expert. Relying on its
B assurance,  the appellant had made a business investment. A reasonable
  profit was, therefore, naturally expected. The loss ofanticipated profits
  was due to the failure of the respondent to provide adequate aggressive
  marketing and advertisement support under the bottler's agreement, in
  an extremely competitive market. The assumption of the respondents
  that there existed a market for their brand products 'Thrill', 'Rush',
C 'Sprint', was totally misconceived, believing in which the appellant had
  made the investment. A party committing breach of contract, was liable
  for such damages as are estimated as not unlikely to result from the
  breach, at the time of making of the contract. The appellate court erred
  in relying upon future events, to hold that the appellant could not be
D foreseen to earn profits. Any temporary difficul.ties that the appellant
  may have had in its own operations, were not insurmountable, and could
  have easily been overcome, if the respondent had facilitated smooth
  running of the business and earning of profits thereby. The claim for
  damage was required to be assessed by a broad estimation, taking into
  consideration all significant factors, evaluating the chances for earning
E profit, and not determination of actual profitability. Reliance was placed
  on Wellesley Partners LLPv. Withers LLP, (2015) EWCA Civ 1146.
              6. The claim for loss of anticipated profits was not based on the
       WEBCON report, 'Exhibit FI'. Neither was it based on 'Exhibit WI',
       the report prepared by Dr. Baisya, the then technical survey manager of·
 F     the respondent. It was based on Exhibit 1C', the loan application submitted
       by the appellant to the WBIDC along with enclosures, containing details
       of profitability, cash flow, cost of production and estimation of sales. It
       was prepared with the assistance of Dr. Baisya, duly proved by Sri
       Binod Khaitan of the appellant.· The appellate court did not express any
 G     reservation about the sufficiency ofproofregarding the document. The
       fact that it may not have been established to the satisfaction of the court,
       that it was jointly prepared with Dr. Baisya, does not detract from its
       contents or admissibility of the same. The agenda notes of the meeting
       of WBIDC dated 19.02.1986 which considered the profitability
       projections based on its own market survey report, was also duly proved
 H
  KANCHAN UDYOG LIMITED v. UNITED SPIRITS LIMITED                              181
              . [NAVIN SINHA, J.]

by the appellant's witness Sri Binod Khaitan. The original minutes, and A
the application for financial assistance had been summoned by the court ·
from WBIDC by subpoena. These were cumulatively sufficient to assess
estimated loss of production and the profitability that would have accrued
ifthe business had remained operational. This loss of profitability was
therefore clearly irt contemplation of the parties at the time of entering B
into the contract, and which alone would be the relevant dat~ for
assessment of claim for damages. The breach by the respondent of the
bottler's agreement was the direct cause for loss of anticipated profits.
Alternately, the causation had to be determined in a holistic manner by a
cumulative assessment. The claim for loss of profitability is based on
gross profits, and not net profits, as in that event several heads of claims C
regarding expenses would automatically get covered. The Project
Services Agreement demonstrates that success of the business was
primarily the responsibility of the respondent, dependent on the fulfillment
of its obligations.
        7. The appellant had taken all reasonable steps for mitigation of D.
damages as available to it, by exploring alternate use of its bottling plant
by other bottlers, including sale of the plant, relying on the Explanation to
Section 73 of the Act. The appellate court, despite noticing the efforts
made by the appellant, erred in applying the test for success of the
endeavor, instead of the endeavor made. The appellant was not expected
to take such steps involving unreasonable expenses, risk or injury to E
itself. The respondents were required to affirmatively demonstrate that
the appellant had acted unreasonably, despite availability of opportunity,
in its duty to mitigate the loss. Reliance was placed on M. Lachia
Shetty & Sons Ltd.. vs. Coffee Board, Bangalore, (1980) 4 SCC 636.
Even if the responde.nt were to succe\:d on this aspect, the only· F
consequence would be in the matter for computation of damages only,
and not its denial completely.
       8. The bottling plant set up by the respondent under the Project
Services Agreement was specific to their product and needs. It was not
saleable in open market. The investment of Rs.2.52 crores in                   G
establishment of the plant, by the appellant, was borne out from its balance
sheets. The learned Single Judge erroneously awarded Rs.1.60 crores
only. It has been unjustifiably set aside in appeal. The claim for
establishment cost of the plant, and loss of anticipated profitability, do
not constitute a double claim for damages. Capital cost was claimed
                                                                               H
182            SUPREME COURT REPORTS                            [2017) 7 S.C.R.


A     towards cost of the plant, it having become non-operational and stood
      scrapped. Loss of profitability was confined to loss of net profits that
      would accrue by operation of the plant. The claim for costing, including
      the capital cost of the project, and profitability are distinct issues. If
      the plant had remained operational, the investment cost and profitability
      both would have accrued.
B
          9. Sri Jaideep Gupta, learned senior counsel appearing for the
   respondent, referring to clause 7 of the bottler's agreement, submitted
   that it was not a business partnership agreement. The appellant was
   unable to run its business for more than one reason, attributable to it
   alone. The change in excise regime dated 22.09.1987, made it an
 c economic   compulsion to route concentrates through Mis. VEC to avoid
   higher excise duty, which in turn would affect the price and saleability of
   the product, ultimately to the detriment of the appellant itself. At the
   Bangalore meeting, twelve out of fourteen bottlers, agreed for the new
   arrangement. The appellant also started to place orders and received
 D concentrates directly from Mis. VEC from April 1988 but abruptly
   stopped doing so in May, 1989. The claim for damages was raised
   belatedly only thereafter by filing the suit in 1990, and after the appellant
   had shut down the plant because of its own inability to run the business.
   There had been no breach by the respondent. The original agreement
   underwent a novation sub silentio, in the facts of the case, under Sections
 E 8 and 62 of the Act, even ifit had not been formally reduced to writing.
   Reliance was placed on McDermott l11ternatio11al /11c vs. Burn
   Sta11dard Co. ltd. & Ors., (2006) 11 SCC 181. Alternately, if the
   supply of concentrates was accepted by the appellant from Mis. VEC
   in view of clause 5 of the bottler's agreement, there had not been any
 F termination of the contract by the respondent. The appellant had further
   acquiesced to the new arrangement for supply of concentrates, and by
    its conduct had waived the claimed legal rights under the bottler's
    agreement.
              10. The termination of the contract was not the causation or
 G    dominant cause for loss of anticipated profits. Reliance was placed on
      Ga/oo Ltd. & Ors. vs. Bright Grahame Murray & A11r., (1994) I
      WLR 1360. The appellant rested its claim for loss of expected profitability
      before the High Court on Exhibit 'Fl' and 'Wl ',but failed to prove both
      the documents in accordance with law. In the present appeal, for the
      first time, it was now being claimed on the basis o(]:'.:xhibit 'C'. Annexure
 H
  KANCHAN UDYOG LIMITED v. UNITED SPIRITS LIMITED                               183
                [NAVIN SINHA, J.]

'M' to the plaint, the claimed loss of profitability is only a reproduction of A
Exhibit 'C'. The latter has already been the subject of independent
consideration in Exhibit' FI' the WEB CON report. The appellant failed
to prove that Exhibit 'C' was prepared jointly with Mr. Baisya. There
was absolutely no material to demonstrate any real or substantial chance
for earning profit by the appellant. Profit projections made in a loan B
application for viability ofa project to avail finance, are mere speculative
assumptions and cannot be a yardstick to claim loss of anticipated profits.
The appellant also failed to take steps to mitigate its losses under Section
73 of the Act for 'remedying the inconvenience caused' by the breach
either by utilisation of the plant for bottling by others, availing concentrates
from Mis. VEC or selling the plant immediately after closure in May, C
1989 to fetch a higher rate, but did so belatedly in 1996. Reliance was
placed on Mis. M11rlidhar Chiranjila/ vs. Mis. Harishchandra
Dwarkadas & Anr., (1962) I SCR 653 and Payzu v. Saunders, ( 1919)
2 KB 581.
       11. The appellant cannot claim both reliance loss with regard to D
the investment in establishment of the plant, and expectation loss with
regard to anticipated profitability from the plant, simultaneously. If no
profit was likely to accrue from the plant, award of reliance loss would
confer a windfall on the appellant and would increase the damages in
proportion to the appellant's own inefficiency rather than in gravity of
the breach and offend the principles of causation. Reliance was placed E
on Pollock and Mulla, 14'h edition, C11/li11a11e vs. British Rema
Manufacturing Co. Ltd., (1954) I QB 292 and C&P Haulage vs.
Middleton, (1983) 3 All ER 94. The respondent cannot be made the
undertaker for the inability of the appellant to run its business profitably
for lack of sufficient business acumen. The award of Rs. 1.60 crores F
towards establishment cost of the plant is also erroneous. It does not
take into consideration the depreciation of the plant, and assigns no reason
for fixation of the quantum.
         12. We have considered the submissions. The learned Single Judge
referring to Section 73 of the Act, on basis of the averments made in the       G
plaint, allowed the claim for loss ofanticipated profits relying upon Exhibit
'F ! ', the WEBCON report, and Exhibit 'W l ', the report prepared by
Dr. R.K. Baisya, holding that the respondent having committed breach
of the agreement, was obliged to put the appellant in the same position
by grant of compensation, as the appellant would have been if the contract
                                                                                H
184            SUPREME COURT REPORTS                         [2017] 7 S..C.R.


A     had been performed. The appellant was also entitled to cost of the plant,
      as it was useless for any other purpose. The appellant was unable to
      mitigate its damages as the product did not find acceptability, and the
      efforts of the parties to persuade Pepsi and Coca Cola to utilise the
      bottling plant, also came to naught. The appellant was awarded
      Rs.2, 73,38,000/- towards loss of anticipated profits for ten years and a
B
      sum of sum of Rs.1.60 lakhs towards the cost of plant, being the price it
      fetched in the auction sale to Cadbury-fry by the West Bengal Financial
      Corporation. A negative finding was returned in one line, on the issue if
      the suit was barred by waiver and acquiescence, without any discussion.
            13. The appellate court examined the copious oral and documentary
c   evidence in detail, and has rendered reasoned findings. It was held that
    Exhibit 'FI' and Exhibit 'WI' had not been proved in accordance with
    law, and therefore, were inadmissible in evidence. Serious doubt was
    expressed, for reasons discussed, if the latter had even ever been tendered
    in evidence, holding that the two documents could not form the basis for
D awarding damages for loss of anticipated profits. We need not deliberate
    on the issue any further, as in appeal before us, the appellant has pressed
    the claim only on basis of the loan application, Exhibit 'C', submitted by.
    it to the WBIDC. Annexure 'M' to the plaint, the claim for loss of
    anticipated, profits was held to be a reproduction of Exhibit 'C'. The
    WEBCON report, Exhibit 'Fl' was based on independent assessment
E including consideration of Exhibit 'C'. The primary document, Exhibit
    'Fl' not having been proved, any assumptions in Exhibit 'C' already
  ' considered in the latter, could not be the basis for a profit projection.
    Th\:re was no evidence in support of the claim that Exhibit 'C' had been
    prepared in associatiO!]. with Dr. R.K. Baisya. No adverse inference
F could be drawn against the respondent and it was for the appellant to
    have summoned Dr. Baisya as a witness to prove its case, since he had
    since resigned and left the Company.
          14. Contrary to the claim of the appellant, that the plant would be
   a profitable enterprise in the second year of its operation ending March,
 G 1988, the appellant itself acknowledged in its letter dated 09.05.1988,
   that the appellant would make losses in the next six years upto 1992-93,
   requesting for supplies of concentrates on credit for five years. The
   business of the appellant failed to take off due to lack of business acumen,
   its inability to manage its own finances, and failure to deploy manpower
   distribution in accordance with its own projections in the loan application
 H
   KANCHAN UDYOG LIMITED v. UNITED SPIRITS LIMITED                                 185
                 [NAVIN SINHA, J.]

 submitted by it to the WBIDC. The respondent had provided sufficient              A
 advertising and marketing support to the appellant, and its expenditure
 for the same was far in excess of that made by the appellant, whose
 bank account reflected severe lack of financial resources, leading to its
 inability to make payments to its bottle suppliers, for the concentrates,
 consultancy fees etc.
                                                                                   B
          15. In the bottlers conference on 15.10.1987 at Bangalore;
  consequent to the new excise regime, twelve out of fourteen bottlers
  had agreed to the new arrangement for supply of concentrates by Mis
· VEC, instead of the respondent. The appellant also placed orders on Ml
  s VEC, and received supplies of concentrates directly from March, 1988
  till January, 1989 even while it continued to avail marketing services           C
  from the respondent also. Thus business relations continued between
  the parties even after termination of the bottler's agreement.
        16. A unilaterally projected profitability in a loan application, which
 is a mere assumption, cannot be the basis for assessment of damages
 especially when the appellant conceded that it would not be in a position D
 to earn profit till 1992-93. No evidence had been led with regard to the
 actual course of the market for cold drinks during 1987-88, and whether
 other bottlers had made profits. The appellant had failed to demonstrate
 any real and substantial chance of earning profit, considering that there .
 was no brand acceptance by the consumers also.                                 E·
        17 .. Considering the principle of causation to award loss of
 anticipated profits by breach ofagreement, it was·held in the facts of the
 case, that it was not the result of the breach, but was a composition of
 various factors like lack of brand acceptance, financial crunch of the· ·
 appellant and lack ofadequate infrastructure by it. The claim for damages F
 was therefore, remote as there was not even a speculated chance for
 making profit by the appellant.
        18. The appellant had failed to take steps for mitigation of damages.
 It was the respondent which had pursued matters with Pepsi for utilisation
 of the appellant's plant. The appellant had failed to satisfy that the proposal   G
 could not go through for reasons not attributable to it. Likewise, the
 further details desired by Coca Cola do not appear to have been furnished
 by the appellant. Even though the plant stopped operation in May, 1989
 when it was relatively new, no effort was made for sale and/orutilisation
 of plant till its auction sale in 1996.                                      ·
                                                                                   H
186            SUPREME COURT REPORTS                            [2017] 7 S.C.R.



A        19. Relevant to the discussion, is the bottler's agreement. Clause
  7 of the same stipulated that the Company and the bottler were not
  partners or agents of each other. The bottler was required to make
  sufficient investment to meet the best quality standards, and satisfy every
  demand of beverages, within the specified territory by promoting and
  developing the merchandise in a proper and vigorous manner so as to
B
  compete effectively with other competing brands. The availability of
  trained personnel for the purpose was the responsibility of the appellant.
  It was required to prepare a marketing programme before October of
  the current year, for the next year. The expenses for advertising and
  promotional activities would attract the Company's participation and be
C normally not less than 50% of the agreed quantum. The appellant was
  also at liberty to develop its own promotional campaigns locally. The
  agreement thus contained the mutual rights and obligations. Though the
  appellant contends lack of adequate advertising and market support by
  the respondent, nothing has been demonstrated with regard to the steps
D taken by it to fulfill its obligations under the agreement. This assumes
  relevance in view of findings of the appellate court, regarding the financial
  crunch faced by the appellant, its failure to pay suppliers of concentrates
  and bottles, requesting for deferred payment of the same, the request
  not to insist on payment of consultancy fees, and inability to deploy
   sufficient manpower as per its own projection contained in the loan
E application on which it seeks to rely.
             20. Clause 5 of the bottler's agreement provided for supply of
      concentrates by the respondent, or from such suppliers as shall be
      nominated by it. Twelve out of fourteen bottlers had agreed at the
      Bangalore convention on 15.10.1987 to the new a.rrangement for supply
 F    of concentrates through M/s. VEC. The appellant also commenced
      placement of orders directly and received concentrates from Mis. VEC
      since 22.04.1988 and continued to do so even after its letter dated
      11.01.1989, by placing orders on 08.03.1989 till it finally discontinued
      after closure of the plant in May, 1989. It is not the case of the appellant,
      based on evidence, that M/s. VEC failed to supply concentrates, or that
 G    it did not meet standards, or was insufficient to meet its marketing
      obligations, much less that any other of the twelve bottlers had
      complained in this regard. The bottling ofMcDowells Sparkling Soda
      was an entirely different issue and could have been continued by the
      appellant notwithstanding the controversy regarding the concentrates.
 H
      KANCHAN UDYOG LIMITED v. UNITED 'SPIRITS LIMITED                              187
                    [NAVIN SINHA, J.]

    The plea of the responqen.ts for novation of the contract referring to          A
    Section 8 and 62 of the Act, sub silentio finds support from the
    observations in McDermott International Inc. (supra) as follows:
           "151. Clause 5 of the contract categorically states that MIT was
           to procure the material which was to be reimbursed by BSCL.
           The extra amount incurred by MII for procuring materials having          B
           extra thickness, therefore, was not payable. To the aforementioned
           extent, there has been a novation of contract. MU had never
           asserted, despite forwarding of the contention of ONGC, that it
           would not comply therewith. It, thus, accepted in sub_silentio."
          21. The novation ofa contract could take place sub silentio was           c
    also noticed in BSNL vs. BPL Mobile Cellular Ltd., (2008) 13 SCC
    597 as follows:
           "45 ..... They might have also been held bound if they accepted
           the new rates or the periods either expressly or sub silentio .. ... "
             22. The learned Single Judge framed an issue also with regard to D
     waiver, estoppel and acquiescence, then answered it in the negative in.a
     singular line, without any discussion. Waiver and acquiescence may be
-- --express or implied. Much will again depend on the nature oftne contract,
     and the facts of each case. Waiver involves voluntary relinquishment of
     a known legal right, evincing awareness of the existence of the right and E
     to waive the same. The principle is to be found in Section 63 of the Act.
     If a party entitled to a benefit under a contract, is denied the.saine,
     resulting in violation of a legal right, and does not protest, foregoing.its
      legal right, and accepts compliance in another form amtnmnner, issU:es
     will arise with regard to waiver or acquiescence by conduct. In the facts
     of the present case, the conduct of the appellant in placing orders and F
      receiving supply of concentrates directly from M/s. VEC, for a period
     of nearly one year, and continuing to do so even after it wrote to the
      respondent in this regard, without recourse to any legal remedies for
     denial of its legal right to receive concentrates from the respondent,
      undoubtedly amounts to waiver by conduct and acquiescence by it to G
      the new arrangement. The plea that it was done under compulsion, and
      not voluntarily, is devoid of any material, substance and evidence. It is
      unacceptable and merits no consideration. Alternatively, if it was an
      assignment under Clause 5 of the agreement, there had been no termination
      of the contract by the respondent. Waiver by conduct was considered in
                                                                                    H
188            SUPREME COURT REPORTS                           [2017) 7 S.C.R.


A P.. Dasa Muni Reddy vs. P. Appa Rao, (1974) 2 SCC 725, observing as
  follow5:
            "13. Abandonment of right is much more than mere waiver,
          · acquiescence or !aches ..... Waiver is an intentional relinquishment
            of a known right or advantage, benefit, claim or privilege which
B           except for such waiver the party would have enjoyed. Waiver
            can also be a voluntary surrender ofa right. The doctrine of waiver
            has been applied in cases where landlords claimed forfeiture of
            lease or tenancy because of breach of some condition in the
            contract of tenancy. The doctrine which the courts of law will
            recognise is a rnle ofjudicial policy that a person will not be allowed
 c          to take inconsistent position to gain advantage through the aid of
            courts. Waiver some times partakes of the nature of an election.
            Waiver is consensual in nature. It implies a meeting of the minds:•,
            It is a matt.er of mutual intention. The doctrine does not depend on
            misrepresentation. Waiver actually requires two parties, one party
 D          waiving and another receiving the benefit of waiver.. T.here can
            be waiver so intended by one party and so understood by the
            other. The essential element of waiver is that there must be a
             voluntary and intentional relinquishment ofa right. The voluntary
             choice is the essence of waiver. There should exist an opportunity·.
             for choice between the relinquishment and an enforcement of the
 E           right in question ..... "
            23. Waiver could also be deduced from acquiescence, was
      considered in Waman Shriniwas Kini vs. Ratila/ Bhagwandas & Co.,
      1959 Supp (2) SCR 21, observing as follows:

 F          "13 ...... Waiver is the abandonment of a right which normally
            everybody is at liberty to waive. A waiver is nothing unless it
            amounts to a release. It signifies nothing more than an intention
            not to insist upon the right. Tt may be deduced from acquiescence
            or may be implied .... "

 G           24. Exhibit 'C' was a loan application, submitted by the appellant
      to the WBJDC. There is no evidence that it was prepared together with
      the respondent. The intent and purpose of a loan application is entirely
      different, relevant only for the purpose of the borrower vis-a-vis the
      lender. The most fundamental characteristic a prospective lender will
      want to examine in a loan application are assessment of the Credit History
 H
  KANCHAN UDYOG LIMITED v, UNITED SPIRITS LIMITED                            189
                [NAVIN SINHA, l]

of the Borrower, Cash Flow History and Projections for the·Eusiness, A
Collateral that· is Available to Secure the Loan and Character of the
Borrower. The profitability projections in such an application are _only
broad estimates based on assumptions and presumptions of the borrower
intended to convince the lender o.fthe viability of its project, in absence
of which the loan application itself may not be considered. The appellant's B
projections in it of assumed estimated profit<ibility for viability of the
project also went completely awry from.its own admission that there
was no likelihood of profit in the next 5 to 6 years. Viability of the
project for sanction ofloan cannot lead to an automatic presumption.of
profits, in the facts of the case, especially when there is evidence that
the appellant did not even deploy manpower in accordance with the c
projections made by it in the loan application. It was not sanctioned on
basis of the assumption of the appellant for earning profits. The loan
was sanctioned by the WBIDC on basis of the techno-economic feasibility
report by WEBCON Exhibit 'Fl'. The loan application, after
consideration, lost its independent identity and got subsumed in Exhibit D
'Fl' .Annexure 'M' to the plaint containing the projected estimated
profitability was only a reproduction of Exhibit 'C'. The primary document
was Exhibit 'Fl', which took into consideration Exhibit 'C' also. The
former being inadmissible in evidence, as not having been proved in
accordance with law, the appellant cannot seek to prove indirectly what
it has been unable to prove directly. The conclusion of the appellate E
court that Exhibit 'F-1' being the primary document, the claim for loss of
anticipated profits on basis of Exhibit 'C' was unsustainable, cannot be
faulted with.
       25. In the facts of the present case, it cannot be held that the
breach alone was the cause for loss of anticipated profits, much less        F
was it the primary or dominant reason. The appellate court has adequately
discussed the appellant's letter dated 04.07.1987 thanking the respondent
for its advertising support. During the year 1986-87, the· respondent
spent Rs.2,05, 13,376.14 for advertising purposes evident from its balance
sheet. Similarly, in 1987-88, it spent Rs.1,65,87,158.73 towards
advertisement and sale promotions. On the contrary, for the year ending      G
31.03.1987, the appellant spent Rs.6,68,856.00 towards advertisement
and in the year 1987-88 it spent only Rs.39,288.00. The fact that it was
unable to pay for the concentrates seeking deferred payment,
acknowledgement on 09.05.1988 that it would continue to suffer loss for
                                                                             H
                       '/
190           SUPREME COURT REPORTS                          [2017] 7 S.C.R.


A the next six years upto 1992-93 seeking long term credit for five years
  for supply of concentrates and its acknowledgement in letter dated
  27.04.1987 that due to "many factors already discussed with you we
  have not been able to run the factory and the sales of our product have
  not picked up in the market", and not to press for payment of consultancy
  fees, failure to deploy adequate manpower as per its own projections
B
  demonstrates the poor financial condition of the appellant as the prime
  reason for its inability to run the plant and earn profits. As against a
  value ofRs.4,26,685.19 of raw materials in 1989, the appellant had an
  over draft ofRs.13,89,000.00. It had a credit entry of Rs.5,135.00 only
  in July, 1988 in its account with the State Bank of India. The current
C account with the Union Bank of India reflected a balance of
  Rs. l ,28,619.25 on 28.03.1989. The Bank balance on 31.03.1989 reflected
  from its balance sheet was only Rs.43,345 .38, and its loss as reflected in
  the balance sheet on 31.03.1987 was Rs.18,47,018.11. In the facts of
  the present case, it cannot be held that the breach by the respondent
D was the cause, much less the dominant cause for loss of anticipated
   profits by the appellant. In Galoo Ltd. (supra) the emphasis was on the
   common sense approach, holding that the breach may have given the
  opportunity to incur the loss but did not cause the loss, in the sense in
   which the word "cause" is used in the law. The following passage
   extracted therein from Chitty on Contracts, 26'h ed. ( 1989) Vol. 2, pp.
E 1128-1129, para 1785 may be usefully set out:
            "The important issue in remoteness of damage in the law of
            contract is whether a particular loss was within the reasonable
            contemplation of the parties, but causation must also be proved:
            there must be a causal connection between the defendant's breach
 F          of contract and the plaintiff's loss. The courts have avoided laying
            down any formal tests for causation: they have relied on common
            sense to guide decisions as to whether a breach of contract is a
            sufficiently substantial cause of plaintiff's loss."
             26. Wellesley Partners LLP (supra) itself carves out an exception
 G    to the principle that a contract breaker is liable for damage resulting
      from his breach, if at the time of making the contract, a reasonable
      person in his shoes would have had damage of that kind in mind as not
      unlikely to result from a breach. After noticing The Achilleas (2009) AC
      61 it was observed:
 H          "69 ...... The Achilleas shows that there may be cases, where
 KANCHAN UDYOG LIMITED v. UNITED SPIRITS LIMITED                              191
               [NAVIN SINHA, J.]

      based on the individual circumstances surrounding the making of A
      the contract, this assumed expectation is not well founded.
     The observations noticed therein from para 23 and 24 of the
Parabola case (2011) QB 477 are also considered relevant as follows:
       "23 ....The next task is to quantify the loss. Where that involves a
       hypothetical exercise, the court does not apply the same balance       B
       of probability approach as it would to the. proof of past facts .
     . Rather, it estimates the loss by making the best attempt it can to
       evaluate the chances, great or sma!l (unless those cham;:es amount
       to no more than remote speculation) taking·all significant factors
       into consideration.                                                     C.
      24 ..... The judge had to make a reasonable assessment and different
      judges might come to different assessments without being
      unreasonable. An appellate court will be slow to interfere with
      the judge's assessment.
        27. The appellate court with reference .to evidence has adequately D
discussed that the appellant failed to take steps to mitigate it losses under
the Explanation to Section 73 of the Act. We find no reason to come to
any different conclusion from the materials on record. If concentrates
were available from Mis. VEC, the appellant had to offer an explanation
why it stopped lifting the same after having done so for nearly a year, E
and could have continued with the business otherwise and earned profits
as observed in Payzu Ltd. (supra). lt could also have taken steps to sell
the unit after its closure in May, 1989 rather than to do so belatedly in
1996. No reasonable steps had been displayed as taken by the appellant
forutilisation of its bottling plant by negotiations with others in the business.
Nothing had been demonstrated of the injury that would have been caused F
to it thereby.
       28. That leaves the question with regard to reliance loss and the
expectation loss. Whether the two could be maintainable simultaneously
or were mutually exclusive? ln Pullock & Mulla, 141h Edition, Volume
II, page 1174, the primary object for protection of expectation interest,      G
has been described as to put the innocent party in the position which he
would have occupied had the contract been performed. The general
aim of the law being to protect the innocent party's defeated financial
expectation and compensate him for his loss of bargain, subject to the
rules of causation and remoteness. The purpose of protection of reliance
                                                                               H
192              SUPREME. COURT REPORTS                         [2017] 7 S.C.R.



A     interest is to put the plaintiff in the position in which he would have been
      if the contract had never been made. The loss may include expenses
      incurred in preparation by the innocent party's own performance,
      expenses incurred after the breach or even pre-contract expenditure
      but subject to remoteness. The following passage from the same is
      considered appropriate for extraction:
B
               "No Recovery for Both, the Expectation Loss and the Reliance
      loss."
               Although the rules as to damages seek to protect both the
               expectation and the reliance interests, the innocent party cannot
c              ordinarily recover both expectation loss, viz., loss of profit, and
               reliance loss, viz., expenses incurred in reliance on the promise;
               that would involve double counting. He ha·s to choose between
               the two measures.
               However, he cannot claim reliance losses to put himself in a better
D              position that if the contract had been fully performed: else, the
               award of damages for reliance losses would confer a windfall on
               the plaintiff, and would increase the. damages in proportion to the
               claimant's inefficiency in performance, rather than in proportion
               to the gravity of the breach, and probably of normal principles of
               causation. In such cases, therefore, the plaintiff can recover the
 E             loss. on account of the wasted expenditure or outlay only to the
               extent of the expected gain; and the onus of proving lies on the
               party committing the breach to show that the reliance costs (or
               any part of them) would not have been recouped, and would still
               have oeen wasted, had the contract been performed."
 F            29. In C & P Haulage (supra), which considers Cullinane (supra)
      also, it has been observed as follows:
               "The law of contract compensates a plaintiff for damages resulting
               from the defendant's breach; it does not .compensate a plaintiff
               for damages resulting from his making a bad bargain. Where it
 G             can be seen that the plaintiff would have incurred a loss on the
               contract as a whole, th~ expenses he has incurred are losses flowing
               from entering into the contract, not losses flowing from the
               defendant's breach. In these circumstances, the true consequence
               of the defendant's breach is that the plaintiff is released from his
               obligation to complete the contract-or in other words, he is saved
 H
  KANCHAN UDYOG LIMITED v. UNITED SPIRITS LIMITED                               193
                [NAVIN SINHA, J.]

      from incurring further losses. If the law of contract were to move A
      from compensating for the consequences of breach to
      compensating for the consequences of entering into contracts,
      the law would run contrary to the normal expectations of the world
      of commerce. The burden of risk would be shifted from the plaintiff
      to the defendant. The defendant would become the insurer of the
                                                                            B
      plaintiff's' enterprise. Moreover, the amount of damages would
      increase not in relation to the gravity or consequences of the breach
      but in relation to the inefficiency with which the plaintiff carried
      out the contract. The greater his expenses owing to inefficiency,
      the greater the damages."
       30. In view.of the conclusion, that the appellant was not entitled       c
to any expectation loss towards anticipated profits, for reasons discussed,
any grant of reliance loss would tantamount to giving a benefit to it for
what was essentially its own lapses. There are no allegations of any
deficiency in the plant. Contrary to its claim ofRs.2.52 crores towards
cost of the plant, the learned Single Judge awarded Rs.1.60 crores without      D
any discussion for the basis of the same_. Though the appellant had
preferred a cross appeal, it did not press the same.
       31. The aforesaid discussion leads to the inevitable conclusion
that the appellant had failed to establish its claim that the breach by the
respondent was the cause for loss of anticipated profits, that the              E
profitability projection in its loan application was a reasonable basis for
award of damages towards loss of anticipated profits. The appellant had
failed to abide by its own obligations under Exhibit 'C' and lacked
adequate infrastructure, finances and manpower to run its business. It
also failed to take reasonable steps to mitigate its losses. The appeal
lacks merit and is dismissed.                                                   F


Ankit Gyan                                                  Appeal dismissed.


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "contract breach"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.