KAUSHIK NARSINHBHAI PATEL & ORS.versusM/S S.J.R. PRIME CORPORATION PRIVATE LIMITED
- Citation
- 2024 INSC 542
- Decided
- 22 July 2024
- Disposal
- Case Partly allowed
- Bench
- C T RAVIKUMAR
Holding
A party that has forfeited its right to file a written statement may participate in the proceedings but cannot introduce new pleadings or facts through written submissions; the forum must base its decision on the material before it and may compute compensation as per established precedent.
Summary
The appellants, a group of flat buyers, filed a consumer complaint against the developer, M/s S.J.R. Prime Corporation, alleging delayed possession and various charges. The NCDRC ordered the developer to pay delayed compensation and to construct promised amenities, but the developer had previously been declared by the Supreme Court to have forfeited its right to file a written statement. Despite this, the developer submitted written submissions introducing new pleadings, which the appellants argued should not have been permitted. The Supreme Court held that forfeiture of the right to file a written statement bars a party from introducing new pleadings, though it may still participate and cross‑examine witnesses. Consequently, the Court ruled that the NCDRC could not rely on the developer’s written submissions for factual findings, but upheld the method of calculating compensation as in R.V. Prasannakumaar’s case, modifying the due‑date for possession. The appeal was allowed in part, directing the NCDRC to compute interest from September 2014 and to verify possession dates for each buyer.
Issues considered
- Whether a party whose right to file a written statement is forfeited may file written submissions introducing pleadings to resist the claim.
- What is the scope of participation allowed to such a party in consumer forum proceedings after forfeiture of the right to file a written statement?
- Whether the forfeiture of the right to file a written statement obliges the forum to decide in favour of the complainant.
- Whether the NCDRC correctly fixed the due date for possession and the method of calculating delayed compensation.
Legislation cited
Subjects
Judgment
[2024] 7 S.C.R. 823 : 2024 INSC 542
Kaushik Narsinhbhai Patel & Ors.
v.
M/s S.J.R. Prime Corporation Private Limited
(Civil Appeal No. 8176 of 2022)
22 July 2024
[C.T. Ravikumar* and Sanjay Kumar, JJ.]
Issue for Consideration
Whether a party whose right to file written statement is closed can
file written submissions to introduce pleadings to resist the claim
against it; and if not, then what is the scope of its participation of
in the proceedings once the right to file written submissions has
closed. Lastly, what is the impact of the forfeiture of the right to
file a written statement.
Headnotes†
Consumer Protection Act, 2019 – Developer filed written
submissions – Defiance of earlier order of Supreme Court
closing Developer’s right to file a written statement:
Held: The Supreme Court passed an order closing the right of
the Respondent to file a written statement in the proceedings
before the NCDRC, however, the Order permitted the Respondent
to participate in the proceedings – The Respondent is bound by
the earlier Order of the Supreme Court, and could have not been
permitted to introduce its case through written submissions – The
objections raised by the Respondent cannot be looked to the extent
it carried pleadings, which could have been let in through a written
statement. [Paras 13, 18]
Code of Civil Procedure, 1908 – Impact of forfeiture of
opportunity to file written statement – Party would have the
right to participate in the proceedings and cross-examine the
witnesses:
Held: All the provisions of the Code of Civil Procedure, 1908 are
not applicable to proceedings before Consumer Forums under the
Consumer Protection Act, 2019, except to the extent it is provided
under Section 38(9) of the Consumer Protection Act – In the
absence of specific provisions dealing with the consequence of
forfeiture of the right to file a written statement, it is appropriate to
* Author
824 [2024] 7 S.C.R.
Digital Supreme Court Reports
refer to the provisions in the CPC to know the general law on this
question – Reliance placed on the Judgment in Nanda Dulal Pradhan
& Anr. vs. Dibakar Pradhan & Anr. 2022 SCC OnLine SC 822,
which laid down that even if the defendant/opposite party failed to
file a written statement and, in that matter, even if forfeiture of the
right to file written statement has occasioned, it would not disentitle
the party from participating the proceedings before the court, without
filing a written statement – In such circumstances, the said party
would also be have the right to cross-examine the witness(es), if
any, of the plaintiff/complainant – Closure of the right to file written
statement bars the party from bringing in pleadings, indirectly to
introduce its case. [Paras 14, 18]
Code of Civil Procedure, 1908 – Order VI – A party cannot
make out a case on the basis of evidence for which he has
laid no foundation in the pleadings:
Held: Order VI Rule 1 and 2 of the CPC provide that every pleading
shall contain only a statement of the facts, but not the evidence
by which it is to be proved – The rigours of the rule of pleadings
is evident from Rule 7 of Order VI, CPC, which mandates that
‘no pleading shall, except by way of amendment, raise any new
ground of claim or contain any allegation of fact inconsistent with
the previous pleadings of the party pleading the same’ – Reliance
placed on the Judgment of a Division Bench of the Karnataka
High Court in Nalini Sunder vs. GV Sunder AIR 2003 Kar 86,
wherein it was held that a party could not make out a case on
the basis of evidence for which he/she has laid no foundation in
the pleadings.[Paras 16, 17]
Civil law – Forfeiture to file written statement does not by itself
make it obligatory to pass an order in favour of the Complainant:
Held: Even when the opposite party’s right to file a written statement
is forfeited, that by itself, will not make it obligatory on the part
of the NCDRC to pass an order in favour of the complainant, in
case the complainant failed to establish its case – This power is
to be read into the jurisdiction of a body with adjudicating power –
There is a difference between a situation of non-filing of a written
statement owing to forfeiture of the right to file a written statement
and absence of denial of specific pleadings of complainant in the
written statement. In the latter case, absence of denial of specific
pleadings on facts they can be taken as admitted. [Para 19]
[2024] 7 S.C.R. 825
Kaushik Narsinhbhai Patel & Ors. v.
M/s S.J.R. Prime Corporation Private Limited
Case Law Cited
Nanda Dulal Pradhan & Anr. v. Dibakar Pradhan & Anr. [2022]
7 SCR 483 : 2022 SCC OnLine SC 822; Nalini Sunder v. GV
Sunder AIR 2003 Kar 86; R.V. Prasannakumaar & others. v. Mantri
Castles Private Limited & Another [2019] 5 SCR 821 : (2020) 14
SCC 769 – referred to.
List of Acts
Code of Civil Procedure, 1908; Consumer Protection Act, 2019.
List of Keywords
Consequence of non-filing of written statement; Forfeiture of right
to file written statement.
Case Arising From
CIVIL APPELLATE JURISDICTION: Civil Appeal No.8176 of 2022
From the Judgment and Order dated 15.09.2022 of the National
Consumer Disputes Redressal Commission (NCDRC), New Delhi in
Consumer Complaint No.945 of 2019
Appearances for Parties
Mr. Ajit Kumar Sinha, Sr. Adv., Govind Jee, Kartikeya Khanna,
Omanakuttan K K, Ayush Mishra, Mrs. Parul Dhurve, Advs. for the
Appellants.
Balaji Srinivasan, Devamshu Behl, Advs. for the Respondents.
Judgment / Order of the Supreme Court
Judgment
C.T. Ravikumar, J.
1. The appellants, 46 in numbers, along with respondent Nos.2 to 6
herein (proforma respondents) filed Consumer Case No. 945 of
2019, against Respondent No.1 herein, complaining of deficiency in
service raising various grounds, which culminated in the impugned
order dated 15.09.2022 of the National Consumer Disputes Redressal
Commission (NCDRC), New Delhi. Allured by the representation of
the first respondent-builder, each of the appellants booked separate
flats in its declared project namely, ‘Fiesta Homes by SJR Prime’. A
826 [2024] 7 S.C.R.
Digital Supreme Court Reports
Construction Agreement dated 31.03.2012 was entered into between
the complainant and Respondent No.1 (Annexure P-2). Going by
Clause 6.1 of the Construction Agreement, possession of flats was
liable to be handed over, after completion of the construction, on or
before March, 2014, with a grace period of six months. However,
considerable delay had occurred in completing and handing over
possession of flats and as per the complainants, it was after about
four years down the timeline that possession was handed over to
them. Deficiency in construction aggravated the situation and made
the appellants and the proforma respondents (hereinafter referred for
brevity, ‘the complainants’ unless otherwise specifically mentioned)
to approach the NCDRC by filing the aforesaid complaint seeking
the following reliefs: -
“i. Pay to each of the complainants & to each buyer having
same interest, compensatory interest @ 18% p.a. for
abnormal & inordinate delay in handing over possession
of flats to complainants, computing the total period of delay
as indicated in Para 11.11 of the Consumer Complaint;
ii. Refund the illegally charged car parking fee to
complainants & to each buyer having same interest with an
interest @ 18% p.a. & to hold the OP guilty of committing
unfair and restrictive trade practice against the complainants
& also against each buyer having same interest;
iii. Refund to the complainants & to all buyers having same
interest, the excess and illegally charged “legal fee” at the
actual with an interest @ 18% p.a. and also to declare the
OP guilty of committing unfair & restrictive trade practice
against the complainants and also against each buyer
having same interest;
iv. Refund to the complainants & to all buyers having same
interest, fee charged towards BESCOM & BWSSB charges
after deducting as per actual with an interest @ 18% p.a.
& also to declare the OP guilty of committing unfair and
restrictive trade practice against the complainants & also
against each buyer having same interest; and/or
v. Direct OPs to provide in time bound manner, Green
Jogging Track and Convenience Store as promised in
[2024] 7 S.C.R. 827
Kaushik Narsinhbhai Patel & Ors. v.
M/s S.J.R. Prime Corporation Private Limited
Brochure, else pay compensation of Rupees Five Lakhs
to each complainant and to each buyer having same
interest; and/or
vi. Pass any other and/or further relief, which this Hon’ble
Commission thinks fit and proper, in the facts and
circumstances of the case, in favour of the complainants
and against the OP.”
2. The complaint was partially allowed by the NCDRC as per the impugned
order dated 15.09.2022. Before considering the rival contentions
raised before us, it is worthwhile to refer to certain vital facts.
3. The complainants filed Consumer Complaint No.945 of 2019 in May,
2019. Subsequent to its filing, the first respondent-builder issued
certain e-mails to complainants between January, 2020 to June,
2020, addressing them individually and requiring them to contact
its legal department in connection with the grievance raised in C.C.
No.945 of 2019. Though this was done during the pendency of the
Consumer Complaint, and that too, in respect of the grievance raised
in C.C. No.945 of 2019, notice to the first respondent remained
unserved. Thereupon, the NCDRC passed an order on 27.01.2021
on the following lines: -
“Notice of the complaint still remains unserved. Issue
fresh notice of the Complaint along with all pending
applications to the Opposite Party under Section 38 (3)
(a) of the Consumer Protection Act, 2019 making it clear
that if the Opposite Party wishes to contest the allegations
in the Complaint, it may file the Written Statement within
thirty days of the receipt of notice in the complaint, failing
which its right to file Written Statement may be closed.”
4. The aforesaid order was challenged by the appellants before this
Court in Civil Appeal No.715 of 2021 which was allowed as per
(Annexure P-18, referred as such in the SLP) order dated 11.08.2021.
Taking note of certain indisputable and undisputed factual position,
this Court arrived at the conclusion that the first respondent-builder
was well aware of the pendency of the C.C. No.945 of 2019 before
the NCDRC and went on to hold thus: -
“The conduct on the part of respondent-builder in not
filing written statement does not entitle him to any further
828 [2024] 7 S.C.R.
Digital Supreme Court Reports
benefit. It must, therefore, be declared that the respondent
has forfeited his right to have filed written statement and
it is hereby declared so.
The appeal, therefore, stands allowed. The C.C.No.945 of
2019 shall now be proceeded further without the written
statement of the respondent-builder. It shall however,
be open to the respondent-builder to participate in the
proceedings.”
5. We will refer to the contentions raised based on Annexure P-18
order and its tenability or otherwise, a little later. Subsequent to
Annexure P-18 order, NCDRC considered C.C. No.945 of 2019,
which culminated in the order impugned in this appeal.
6. Heard, Mr. Ajit Kumar Sinha, Senior Counsel appearing for the
appellants and Mr. Balaji Srinivasan, learned counsel for the first
respondent.
7. A scanning of the impugned order would reveal that the NCDRC
has recorded a clear finding that there occurred delay in handing
over the flats to the appellants. As a necessary sequel to such
finding and findings on the other allied grievance and claims, the
impugned order was passed on 15.09.2022. The operative portion
of the impugned order reads thus: -
“In view of the aforesaid discussions, the complaint is
partly allowed. The opposite party is directed to pay
delayed compensation in the shape of interest @ 6 %
per annum on the deposit of the complainants from due
date of possession as determined for each buyer in the
manner as provided in paragraph-8 of the judgment till the
date of offer of possession and construct Green Jogging
Track and Convenience Store, within a period of two
months from the date of this judgement.”
8. It is to be noted that despite the nature of the impugned order and
creation of liability on the first respondent, as above, the complainants
alone have chosen to prefer appeal and the first respondent No.1
has not chosen to challenge the same. In the said circumstances,
the findings of NCDRC on delayed handing over of the flats to the
complainants and on non-construction of Green Jogging Track and
Convenience Store can only be taken as having become final. Ergo,
[2024] 7 S.C.R. 829
Kaushik Narsinhbhai Patel & Ors. v.
M/s S.J.R. Prime Corporation Private Limited
the scope of this appeal is limited to a few questions, which we will
discuss and deal with later.
9. For a proper disposal of this appeal, it is apposite to refer to paragraph
8 of the impugned order, which reads as follows: -
“In the present case, due date of possession was
September, 2014, while “occupancy Certificate” was
obtained 17.05.2017 and possession was delivered
thereafter. The complainants have not given date-wise
payment schedule. Schedule-E of this agreement contained
“Construction Linked Payment Plan” under which, total sale
consideration was payable in 12 instalments on different
levels of the construction. As such for the purposes of
delayed compensation, we think it appropriate that due
date of possession will be considered after expiry of six
month from the payment of 11th instalment by the home
buyer. The developer would be entitled for further six
months as grace period. The developer shall pay delayed
compensation in the shape of interest @ 6% per annum
on the deposit of the complainants from the due date of
possession as determined in accordance of above formula
till the date of actual possession.”
10. One of the main contentions of the appellants is that ignoring
Annexure P-18 order of this Court, the NCDRC virtually permitted
the first respondent to introduce facts to dispute their claims
and complaints inasmuch as the opportunity offered to the first
respondent by NCDRC to file written submissions was utilised by
the first respondent to introduce new facts to resist their claims and
contentions. Such newly introduced facts and factors by the first
respondent through written submissions, obviously, weighed with
NCDRC in adopting the formula followed in paragraph 8 of the
impugned order, for the purpose of computation of compensation
payable to the complainants, it is contended.
11. We will straight away verify the verity of the aforesaid contentions
with reference to Annexure P-18 order dated 11.08.2021, firstly,
to see whether the same was overreached and then, subject to
its answer and consequences of its defiance. A bare perusal of
Annexure P-21, which is the written submissions on behalf of the first
respondent herein (opposite party therein) filed before the NCDRC
830 [2024] 7 S.C.R.
Digital Supreme Court Reports
and marked as such in this proceeding, without any peradventure
would go to show that in and vide the said written submissions, the
first respondent had introduced some pleadings to resist the claims
and the contentions of the complainants in CC No.945 of 2019 and
eventually, to offer its explanation for the delay in handing over
possession of the flats. The raison d’etre for our remarks would
be unravelled by a mere perusal of Annexure P-21. Paragraph 3
thereof, opens thus: -
“The complainants do not deserve any compensation as,”
(underline supplied)
12. Thenceforth, under para 3 (i) to 3 (iii), the respondents gave the
reasons therefor. Through paragraph 4 of Annexure P-21, the
respondent introduced further reasons to support its stand that the
complainants do not deserve compensatory interest for the delay
in handing over possession of flats. It is to be noted that even after
taking a stand at paragraph 5 thereof that there was no delay at all
from its part, the first respondent proceeded to explain the delay
in paragraph 6. The statements made in the further paragraphs of
Annexure P-21 also carry, either the case of the first respondent or
its explanations/reasons to counter the claim of the complainants.
To put it pithily, the first respondent, on being given the opportunity
to file written submission, made use of it to make good its failure
to file a written statement despite the fact that its right to file the
same was declared as forfeited by this Court.
13. We are at a loss to understand as to how, such an opportunity could
have been utilised by the first respondent in defiance to the specific
directions of this Court under Annexure P-18 order and to file a
written submission of such a nature. Under Annexure P-18 order, this
Court declared that the first respondent had forfeited its right to file
a written statement and then permitted, rather, directed to proceed
further without the written statement of the first respondent-builder.
True that even then its right to participate in the proceedings was
protected, presumably, taking into account the position of law in that
regard. We will deal with the scope of such permitted participation
as also the consequence of the act of defiance of Annexure P-18
order depending on its degree of defiance and its impact. In doing
so, we will have to keep reminded of the principle of law that what
cannot be done directly, cannot be done indirectly.
[2024] 7 S.C.R. 831
Kaushik Narsinhbhai Patel & Ors. v.
M/s S.J.R. Prime Corporation Private Limited
14. The discussion as above, would take us to the next question as to
what is the impact of forfeiture of opportunity to file written statement?
We are fully aware of the fact that all the provisions in the Code
of Civil Procedure, 1908, (for short ‘the CPC’) are not proprio
vigore applicable to proceedings before Consumer Forums created
under the Consumer Protection Act, 2019, except to the extent it is
provided under Section 38 (9) of the Consumer Protection Act. Be
that as it may, in the absence of specific provisions dealing with the
consequence of forfeiture of the right to file a written statement, it
is only appropriate to refer to the provisions and positions dealing
with such situations in the CPC to know the general law on this
question. In this context, it is worthy to refer to a decision of this
Court in Nanda Dulal Pradhan & Anr. v. Dibakar Pradhan & Anr.1
It was held therein thus: -
“……as observed and held by this Court in the case of
Sangram Singh (supra) on setting aside the ex parte
decree and on restoration of the suit the parties to the
suit shall be put to the same position as they were at the
time when the ex parte judgment and decree was passed
and the defendants may not be permitted to file the written
statement as no written statement was filed. However,
at the same time they can be permitted to participate in
the suit proceedings and cross examine the witnesses.
In that view of the matter the impugned judgment and
order passed by the High Court is unsustainable. Still, on
setting aside the ex parte judgment and decree, though
the defendants who had not filed the written statement,
can be permitted to participate in the suit and cross
examine the witnesses. Therefore, the High Court is not
right in observing that as no written statement was filed
by the defendants, the reopening of the suit by setting
aside ex parte judgment and decree will become futile.
As observed hereinabove the High Court has not at all
observed anything on the correctness of the order passed
by the First Appellate Court setting aside the ex-parte
judgment and decree on merits.
1 [2022] 7 SCR 483 : 2022 SCC OnLine SC 822
832 [2024] 7 S.C.R.
Digital Supreme Court Reports
15. Thus, the position is that even if the defendant/opposite party failed
to file a written statement and, in that matter, even if forfeiture of the
right to file written statement has occasioned it would not disentitle
that party from participating in the further proceedings, without filing
a written statement and in such circumstances, the said party would
also be having the right to cross-examine the witness(es), if any, of
the plaintiff/complainant.
16. In the contextual situation, it is also appropriate to refer to Rule 1
& 2, Order VI of the CPC which reads thus:-
“Pleading. - “Pleading” shall mean the plaint or written
statement.”
Rule 2, Order VI, in so far as, reads thus: -
“(1) Every pleading shall contain, and contain only, a
statement in a concise form of the material facts on which
the party pleading relies for his claim or defence, as the
case may be, but not the evidence by which they are to
be proved.”
17. The rigour of the rule of pleadings is evident from Rule 7 of Order
VI, CPC, which mandates that ‘no pleading shall, except by way of
amendment, raise any new ground of claim or contain any allegation
of fact inconsistent with the previous pleadings of the party pleading
the same’.
18. In the context of the aforesaid provisions under the CPC, it is apt to
refer to a decision of a Division Bench of the Karnataka High Court
in Nalini Sunder v. GV Sunder.2 It was held therein that a party
could not make out a case on the basis of evidence for which he/
she has laid no foundation in the pleadings. It is fairly settled that
no amount of evidence can prove a case of a party who had not
set up the same in his/her pleadings, it was further held therein.
According to us, it is the correct proposition of law. In the absence of
any specific provisions dealing with non-filing of written statements/
forfeiture of the right to file a written statement, taking note of the
general position as above, it can only be held that it should bar
the opposite party in a proceeding before the Consumer Redressal
2 AIR 2003 Kar 86
[2024] 7 S.C.R. 833
Kaushik Narsinhbhai Patel & Ors. v.
M/s S.J.R. Prime Corporation Private Limited
Forums to bring in pleadings, indirectly to introduce its/his case
and evidence to support such case. In the situations mentioned
above, the right of the opposite party is confined to participate in
the proceedings without filing a written statement and to cross-
examine witness(es), if any, examined by the complainant(s). It be
the position of law, the first respondent who is bound by Annexure
P-18 order could not have been permitted to introduce its case to
defend the case of the complainants through written submissions
though it was rightly permitted to participate in the proceedings.
There is no case for the first respondent that it sought permission
to cross-examine Kaushik Narsinhbhai Patel who filed affidavit of
evidence and produced documentary evidence. At any rate, no
such case was put forth by the first respondent and no grievance
of denial of such opportunity was also raised. In the circumstances
expatiated above, in view of Annexure P-18 order the reply and
objection filed by the first respondent herein in this proceeding also
cannot be looked to the extent it carries pleadings relating its case,
the reasons and objections which could have been let in through a
written statement. In short, the first respondent could be permitted
only to argue the legal questions arising based on authorities
and provisions of law as also regarding lapses or laches and the
consequential non-admissibility or otherwise of evidence, let in by
the appellants.
19. Having held as above, the next question to be looked into is whether
NCDRC had given weight to any such pleadings and contentions
taken by the first respondent in its written submissions and/or whether
the decision of NCDRC is based on any fact, factors or data furnished
by the first respondent beyond the extent permissible on account
of the legal trammel of forfeiture of its opportunity to file a written
statement. At this juncture, we may hasten to add that even when
the defendant’s/opposite party’s right to file a written statement is
forfeited that by itself will not make it obligatory on the part of the
NCDRC to pass an order in favour of a complainant in case the
complainant concerned failed to establish its case. This power is
to be read into the jurisdiction of a body with adjudicating power.
This is because there is distinct difference between a situation of
non-filing of a written statement pursuant to a declaration that the
opposite party had forfeited the right to file a written statement and
absence of denial of specific pleadings of complainant in the written
834 [2024] 7 S.C.R.
Digital Supreme Court Reports
statement filed by an opposite party. Certainly, in the latter case,
absence of denial of specific pleadings on facts they can be taken
as admitted. In the case on hand, it is to be noted that actually as
per order dated 27.01.2021, NCDRC had granted time to the first
respondent to file a written statement with a caution that in case of
failure to file the same within the stipulated time, the right to file a
written statement would be closed. It is this order dated 27.01.2021
that was challenged by the complainants that ultimately culminated
in Annexure P-18 order of declaration of forfeiture.
20. A close scrutiny of the impugned order in juxtaposition with the written
submissions filed by the first respondent would go to show that
NCDRC had not actually accepted the case of the first respondent
raised in defence in its written submissions or in that matter, no reason
or objection raised in the written statement was also adverted to,
for rendering its decision on the complaint. In such circumstances,
though the action on the part of the first respondent who suffered
Annexure P-18 order, in bringing on record its case and contentions
to resist the case and contentions of the complainants, cannot be
appreciated, the contention of the appellants based on the same
became inconsequential. As stated earlier, in view of Annexure
P-18 order, we are also not going to advert to any case, claims or
contentions of the first respondent raised in its reply and objection
filed in this proceeding, except to the legally permissible limit, in case
any such material is available on record. We have already concurred
with the decision of the Karnataka High Court in Nalini Sunder’s
case (supra) that a party could not make out a case on the basis of
evidence for which he/she had laid no foundation in the pleadings.
In the absence of a written statement, naturally, there can be no
pleadings, in the case, for the first respondent in the eyes of law.
Though the first respondent participated in the proceeding before
the NCDRC, it could not bring-forth anything admissible in view of
the impact of forfeiture under Annexure P-18 order.
21. The discussion as above would lead to the last question as to
whether the impugned order invites interference on any other
ground. The core contention of the appellants that while passing
the impugned order, NCDRC failed to consider the relevance and
impact of Clause 6.1 of the Construction Agreement. No doubt, it is a
matter that requires consideration. Clause 6 of the said Construction
Agreement reads thus: -
[2024] 7 S.C.R. 835
Kaushik Narsinhbhai Patel & Ors. v.
M/s S.J.R. Prime Corporation Private Limited
“6) COMPLETION & DELIVERY OF POSSESSION:
6.1) The possession of the Schedule ‘C’ apartment in
Schedule ‘A’ Property will be delivered by the Second
Party to the First Party after completion of construction
as far as possible on or before the month of March year
2014 with Six months grace period additionally.
6.2) ….
6.3) In case of delay in delivery of the apartment for
reasons other than what is stated above, the Second
Party is entitled to a grace period of Six months and if
the delay persists, the Second Party shall pay the First
Party damages at Rs. 2/- (Rupees Two Only) per Sq. Ft.
super built up area per month of delay of the Schedule ‘C’
Apartment till delivery, provided the First Party has/ have
paid all the amounts payable as per this Agreement and
within the stipulated period and has not violated any of
the terms of this agreement and Agreement to Sell….”
22. A perusal of Clause 6.1 of the Construction Agreement would reveal
that it specifically mentions the promised date for handing over the
possession viz., the due date for handing over possession as ‘on or
before March, 2014’. True that in terms of Clause 6.1, additionally,
six months grace period is available to the first respondent-builder.
Thus, going by the terms of Construction Agreement, the due date
for handing over possession of flats could have been, rather should
have been fixed only in terms of Clause 6.1 of the said Agreement.
However, the impugned order would reveal that without considering
Clause 6, the due date for handing over of possession of flats was
fixed by the NCDRC by reckoning six months grace period from the
date of payment of instalment No.11 (eleven), by the home buyer.
Therefore, the question is which among the two methods is legally
permissible. While the appellants contend that the former is bound
to be followed in the matter of fixing the due date for handing over
possession of flats, the first respondent would contend that the
method adopted by the NCDRC is just and reasonable and there
is no warrant or justifiable reason for any kind of interference. The
decision in R.V. Prasannakumaar & Others. v. Mantri Castles
836 [2024] 7 S.C.R.
Digital Supreme Court Reports
Private Limited & Another.,3 referred to by the NCDRC, itself
would answer this issue. In R.V. Prasannakumaar’s case (supra),
going by the terms of the flat purchase agreement, possession of
flats was liable to be handed over to the buyers on 31.01.2014.
In that case about two years delay had occurred in the matter
of handing over of possession. Consequently, NCDRC took the
due date for handing over of possession with reference to the flat
purchase agreement and fixed it as 01.02.2014. The fixation of the
due date for possession as 01.02.2014 was upheld by this Court in
R.V. Prasannakumaar’s case (supra). If that be so, in the absence
of any exceptional circumstances, NCDRC should have fixed the
date for possession in the same manner as has been done in R.V.
Prasannakumaar’s case (supra), viz., in terms of the conditions
in the Construction Agreement. True that in view of the specific
condition for grant of six months grace period additionally to the
buyer, the due date for possession in terms of Clause 6.1 of the
agreement ought to have been fixed by reckoning six months from
March, 2014, the promise date for handing over the flats mentioned
in the Construction Agreement. A scanning of the impugned order
would reveal no exceptional circumstances for making deviation
from the formula followed in R.V. Prasannakumaar’s case (supra)
for fixing the due date for possession. NCDRC observed that the
complainants have failed to give date-wise payment schedule. We
are at a loss to understand as to how that can be a reason for
fixing the due date for possession in total disregard to the method
adopted in R.V. Prasannakumaar’s case (supra). The discussion
in paragraph 8 would suggest that NCDRC after taking into account
the fact that Schedule-E of the agreement contained ‘Construction
Linked Payment Plan’ whereunder the sale consideration was to
be paid in 12 instalments on different levels of construction, formed
the opinion that the fixation of due date for possession is closely
linked with payment of instalments as mentioned in Schedule-E.
We have no hesitation to hold that there is no rationale for such a
conclusion for the reason that as it was arrived at without considering
the relevant condition contained in Clause 6.1 of the Construction
3 [2019] 5 SCR 821 : (2020) 14 SCC 769
[2024] 7 S.C.R. 837
Kaushik Narsinhbhai Patel & Ors. v.
M/s S.J.R. Prime Corporation Private Limited
Agreement which relates to fixation of due date for possession.
True that Schedule-E contained ‘Construction Linked Payment Plan’
and it provides for payment in 12 instalments on different levels of
construction. Certainly, it was so incorporated to obligate the buyer
to pay the due instalment depending upon the stage of construction.
Hence, delay in effecting construction cannot be a reason for denying
compensation, which was also contemplated under Clause 6 of the
Construction Agreement. The effect of ‘Construction Linked Payment
Plan’ is that it obligates the builder to complete construction up to
a particular required level at the given point of time and upon such
accomplishment, obligates the buyer to effect the due instalment.
According to us, the non-furnishing of a date-wise payment schedule
could not have been a reason for deviating from the formula
followed in the matter of fixation of due date of possession in R.V.
Prasannakumaar’s case (supra). That apart, in the case on hand,
the fact is that the complainants have effected the payment of
sale consideration and were handed over possession of flats. The
compensation is claimed by the complainants for the considerable
concutation in construction and in handing over possession of flats.
At any rate, in the circumstances obtained in this case and especially
taking note of the fact that owing to the forfeiture of the right to file
a written statement, the first respondent-builder did not make out
any exceptional circumstance, the NCDRC was not justified in not
following the formula followed in R.V. Prasannakumaar’s case
(supra) in the matter of fixing the due date for possession for the
purpose of computing compensation for the delay. In this context,
it is also to be noted that in R.V. Prasannakumaar’s case (supra),
the NCDRC found that payment in the shape of interest at the rate
of 6% per annum on the deposit of home buyers from the due date
of possession till the offer of possession is the adequate method
to compensate the buyers for the delay. This court only found
the course of action adopted by NCDRC as just and reasonable.
In the case on hand, NCDRC rightly followed the same method
adopted in R.V. Prasannakumaar’s case (supra) and the claimants
are entitled to compensation in the shape of interest at 6% per
annum from the due date of possession till the date on which the
respective complainant-buyers are offered possession. In the said
circumstances and in view of the decision in R.V. Prasannakumaar’s
838 [2024] 7 S.C.R.
Digital Supreme Court Reports
case (supra), on this issue, the only modification required is with
respect to the method adopted for fixing the due date for possession,
in the manner mentioned earlier. Though the complainants
contended that they are entitled to be compensated in the manner
provided under clause 6 of the agreement, in view of the decision
in R.V. Prasannakumaar’s case (supra), we are of the view that
compensation in the shape of interest at the rate of 6% per annum
for the period mentioned earlier would be in tune with the formula
followed in R.V. Prasannakumaar’s case (supra). This is because
such a course was adopted in R.V. Prasannakumaar’s case (supra)
despite the stipulation for payment of compensation at the rate of
Rs.3/sq. ft. per month for delayed handing over of possession. It is
to be noted that in the case on hand, the stipulation for payment
of compensation for delayed handing over of possession is only at
the rate of Rs.2/sq. ft. per month.
23. True that the complainants claimed for refund of charge for car parking
fee charged, with interest. The same was declined by NCDRC by
assigning the reason that the said question was decided in favour
of the developer by NCDRC in CC/913/2016 viz., in RV Prassana
Kumars 47 Ors. vs. Mantri Castles Pvt. Ltd. was confirmed by
this Court in R.V. Prasannakumaar’s case (supra). In that view of
the matter, we decline to interfere with the finding of NCDRC on
the claim for refund of car parking charge.
24. Paragraph 9 of the impugned order would reveal that the prayer
for refund of legal fee realised by the developer for execution of
conveyance deed was declined by NCDRC on the ground that the
complainants had not adduced any evidence based on which legal
fee could be determined by it. We are not inclined to interfere with
the said finding of NCDRC, as well. The same is the position with
respect to the claim for refund of legal fee charge for conveyance on
the ground that it was charged excessively. As relates the prayer to
provide Green Jogging Track and Convenience Store as promised in
the brochure, NCDRC has already issued directions for constructing
them within the time stipulated thereunder.
25. In the circumstances, this appeal is allowed in part by modifying the
formula formulated under paragraph 8 of the impugned judgment
by NCDRC in the matter of payment of compensation for delay in
handing over possession of flats and it is ordered that the liability
[2024] 7 S.C.R. 839
Kaushik Narsinhbhai Patel & Ors. v.
M/s S.J.R. Prime Corporation Private Limited
of the developer to pay interest at the rate of 6% per annum shall
be from the due date for possession fixed as above viz., from
September, 2014 till the date on which the respective complainant-
buyers are offered possession.
26. Needless to say, that NCDRC in execution of impugned order as
modified by this judgment, shall verify with reference to each flat
purchaser the date on which offer of possession has been made to
him/her and fix the liability on the builder in the manner mentioned
above.
27. Pending application(s), if any, stands disposed of.
Result of the case: Appeal Partly allowed.
†
Headnotes prepared by: Vidhi Thaker, Hony. Associate Editor
(Verified by: Kanu Agrawal, Adv.)
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.