KHALEEL AHMED DAKHANIversusTHE HATTI GOLD MINES CO. LTD.
- Citation
- 2000 INSC 154
- Decided
- 27 March 2000
- Disposal
- Dismissed
- Bench
- D P WADHWA
Holding
The Raichur court should not have entertained the execution application because the award was not final and the exclusive‑jurisdiction clause made the Bangalore court the proper forum for any enforcement or setting‑aside proceedings.
Summary
The appellant, a building contractor, was awarded a contract by the respondent, a Karnataka government company, to construct a school. The contract contained an arbitration clause (clause 35) stipulating that any dispute would be arbitrated and that enforcement actions would be heard only in courts at Bangalore. An arbitrator appointed under S.11 of the Arbitration and Conciliation Act, 1996 rendered an award, which the respondent sought to set aside by filing an application under S.34 in the Bangalore Civil Court. While that application was pending, the contractor filed an execution application under S.36 in the Raichur District Court, leading to attachment of the respondent’s movable property. The Raichur court held that the Bangalore court lacked jurisdiction and entertained the execution, but the Karnataka High Court set aside those orders. The Supreme Court held that the award had not attained finality, the exclusive‑jurisdiction clause was binding, and the pending S.34 application meant the Raichur court should not have entertained the execution; consequently, the High Court’s decision was affirmed.
Issues considered
- Whether the District Court at Raichur could entertain an execution application under S.36 when a S.34 application for setting aside the award was pending in the Bangalore Civil Court.
- Whether the exclusive‑jurisdiction clause in the contract (clause 35) barred the Raichur court from enforcing the award.
- Whether the award had attained finality for purposes of enforcement.
Legislation cited
- Arbitration and Conciliation Act, 1996s. 11, s. 2(e), s. 34, s. 36
- Code of Civil Procedure, 1908s. 20
Subjects
Judgment
KHALEEL AHMED DAKHANI A
v.
THE HATTI GOLD MINES CO. LTD.
MARCH 27, 2000
[D.P. WADHWA AND DORAISWAMY RAJU, JJ.] B
Arbitration and Conciliation Act, 1996 :
Ss. 11, 34-Govemment Company-Awarding contract for construction
ofbuilding in Raichur district-Dispute between parties-Arbitration-Award- C
Application by company to set aside award.filed in Civil Court at Bangalore- ·
Thereafter contractor filing execution application in District Court, Raichur-
Raichur court holding that Banglore court had no jurisdiction, and ordering
attachment ofproperties of company-Held, Raichur court erred in holing that
Bangalore court had no jurisdiction-Application u/s. 34 having been filed
earlier, Raichur court should not have entertained the execution application. D
The appellant, a building contractor, was awarded a contract by the
respondent, Government a company in Karnataka, for construction of a
school building in District Raichur. Clause 35 of the agreement constitut-
ing the arbitration clause provided that only courts at Bangalore would
have jurisdiction in the matter, Since there arose snme disputes, an E
arbitrator was appointed under S.11 of the Arbitration aud Conciliation
Act, 1996. Arbitration proceedings were held at Bangalore and an award
was made. The company filed in the Court of Principal City Civil Judge,
Bangalore an application under S.34 of the Act for setting aside the
award. Thereafter the contractor filed an application for execution of the F
award in the Court of Principal District Judge, Raichur. On this applica-
tion, orders for attachment of movable properties of the company were
issued. The company filed an application before Principal District Judge,
Raichur for lifting the attachment, and brought to his notice that an
application under S.34 of the Act was already pending before the City
G
Civil Judge, Bangalore. The Principal District Judge held that the
Bangalore court had no jurisdiction in the matter and dismissed the
application. The revision filed by the company was allowed by the High
Court. Aggrieved, the contractor filed the present appeal.
Dismissing the appeal, this Court
575
576 SUPREME COURT REPORTS [2000) 2 S.C.R.
A HELD : The Principal District Judge, Raichur should not have
entertained the application for execution and ordered attachment of mov-
able properties of the respondents. Though he had jurisdiction in the
matter, he erred in holding that the Principal City Civil Judge, Bangalore
had no jurisdiction. It can always be said, in view of S.20 of the Code of
Civil Procedure, .1908, that only one court will have jurisdiction to try the
B '~.
suit. It is not that the Princip:\l City Civil Court, Bangalore is not a court
within t':te meaning of S.2(e) of the Arbitration and Conciliation Act, 1996.
The question whether the Principal City Civil Judge, Bangalore has juris-
diction in the matter or not is still pending with him in the proceedings
under S.34 of the Act which were filed earlier in time than the execution
c application filed by the appellant in District Court at Raichur. The award
had not attained finality. Besides, the Principal District Judge, Raichur also
did not take notice of clause 35 of the contract which constituted arbitra-
tion agreement between the parties which specifically provided that only
the courts in Bangalore would have jurisdiction to entertain any claim for
D enforcement of the award. The High Court took a correct view of the
matter and rightly set aside the impugned orders. [582-B, 581-B-C, 582-C]
Patel Roadways Limited, Bombay v. Prasad Trading Company, (1991] 4
sec 270, referred to.
CIVIL APPELLATE JURISDICTION Civil Appeal No. 2232 of
E
2000.
From the Judgment and Order dated 29/30.7.99 of the Karnataka High
Court in C.R.P. No. 1876 of 1999.
Rajiv Dutta and Ms. Enakshi Kulshrestha for the Appellant.
F
Ms. Indu Malhotra and Ms. Monika Arora for the Respondent.
The Judgment of the Court was delivered by
D.P. WADHWA, J. We grant leave to appeal.
G
This appeal is directed against judgment dated 29/30.7.1999 of the
High Court of Karnataka given in revision filed by the respondent whereby
High Court set aside the orders dated 24.5.1999 and 21.6.1999 of the
Principal District Judge, Raichur. By order dated 24.5.1999 the Principal
District Judge, Raichur issued warrants of attachment of moveable properties
H of the respondent as described in the applir,ation for execution filed by the
K.A. DAKHANI v. HATTI GOLD MINES CO. LTD. [D.P. WADHWA, J.] 577
appellant. By order dated 21.6.1999 the learned Principal District Judge A
dismissed the application of the respondent praying for lifting of the
attachment already issued against it.
Appellant is a building contractor. Respondent is a Government
company of the Government of Karnataka under the Companies Act, 1956.
Respondent awarded the contract for construction of a school building at Hatti B
in District Raichur to the appellant. An agreement dated 9.3.1995 was duly
entered into. Clause 35 of the agreement contained the arbitration clause.
Disputes and differences having arisen appellant moved the Chief Justice of
the High Court of Karnataka under Section 11 of the Arbitration and
Conciliation Act, 1996 (for short the 'Act') for appointment of an arbitrator. c
The application was allowed and Mr. H.S. Bhat, Chief Engineer (retired),
who was resident of Bangalore was appointed as an arbitrator with ~.direction
to complete the arbitration proceedings and to submit his Award within four
months. Arbitration proceedings were held at Banglore where also the Award
dated 28.8.1998 was made. Arbitrator awarded some of the claims of the
appellant while disallowing a few others. Respondent filed application for D
setting aside the Award by making an application under Section 34* of the
34. Application .for setting aside arbirral award. (I) Recourse to a court against an arbitral award
may be made only by an application for setting aside such award in accordance with sub-section
(2) and sub-section (3).
(2) An arbitral award may be set aside by the Court only if -
E
(a) the party making the application furnishes proof that -
(i) a party was under some incapadty; or
(ii) the arbitration agreement is not valid under law to which the parties have subjected
it or, failing any indication thereon, under the law for the time being in force; or
(iii) the party making the application was not given proper notice of the appointment of
an arbitrator or of the arbitral proceedings or was otherwise unable to present his case;
or F
(iv) the arbitral award deals with a dispute not contemplated by or not falling within the
terms of the submission to arbitration, or it contains decisions on matters beyond the
scope of the submission to arbitration :
Provided that, if the decisions on matters submitted to arbitration, can be
separated from those not so submitted, only that part of the arbitral award which
contains decisions on matters not submitted to arbitration may be set aside; or G
(v) the composition of the arbitral tribunal or the arbitral procedure was not in
accordance with the agreement of the parties, unless such agreement was in conflict
with a provision of this Part from which the parties cannot derogate, or, failing such
agreement, was not in accordance with this part; or
(b) the court finds that -
(i) the subject-matter of the dispute is not capable of settlement by arbitration under the
\aw for the time being in force, or H
578 SUPREME COURT REPORTS [2000] 2 S.C.R.
A Act in the court of Principal City Civil Judge, Bangalore. While this
application was pending appellant as decree-holder filed an application for
execution of the Award in the court of Principal District Judge, Raichur. It
was on this application that orders for attachment of properties of the
respondent were issued. When respondent sought lifting of its attachment by
filing an application, the same was dismissed. Aggrieved respondent went to
B
the High Court in revision. High Court allowed the revision of the respondent
and set aside the two orders of the Principal District Judge, Raichur which
we have mentioned above. Now it is the appellant who has come to this
Court.
c It would appear that by filing the execution application in the court at
Raichur appellant wanted to enforce the Award under Section 36** of the Act.
When the court at Raichur issued warrants of attachment it was not aware of
pehdency of the application of the respondent under Section 34 of the Act in
the court at Bangalore. Appellant had made no mention in his application
about the pendency of the proceedings at Bangalore. However, when the
D respondent filed application before the Principal District Judge, Raichur for
lifting of the order of attachment it was brought to his notice the pendency
of the application under Section 34 of the Act (or setting aside the Award.
Now, the learned Principal District Judge, Raichur held that Principal City
Civil Court, Bangalore had no jurisdiction to entertain the application under
E (ii) the arbitral award is in conflict with the publi·~ policy of India.
E.xplanarion. - Without prejudice to the generality of sub-clause (ii), it is hereby declared,
for the avoidance of any doubt, that an award is in conflict with the public policy of India if
the making of the award was induced or affected by fraud or corruption or was in violation of
section 75 or section 81.
(3) An application for setting aside may riot be made after three months have elapsed from the
F date on which the party making that application had received the arbitral award or, if request had
been made under section .33, frorrN:he date on which that request had been disposed of by the
arbi tral tribunal : '"-
Provided that if the court is satisfied that the applicant was prevented by sufficient cause
from . making the application within the said period of three months it may entertain the
application within a further period of thirty days, but not thereafter.
(4) On receipt of an application under sub-section(!), the court may, where it is appropriate
G and it is so requested by a party, adjourn the proceedings for a period of time determined by
it in order to give the arbitral tribunal an opportunity to resume the arbitral proceedings or to
take such other action as in the opinion of arbitral tribunal will eliminate the grounds for setting
aside the arbitral award. ·
** 36. Enforr:emenr. - Where the time for making an application to set aside the arbitral award
under section 34 has expired of such application having been made,· it has been refused, the
award shall be enforced under the Code of Civil Procedure, 1908 (5 of 1908) in the same manner
H as if it were a decree of the court.
K.A. DAKHANI v. HATII GOLD MINES CO. LTD. [D.P. WADHWA, J.] 579
Section 34 of the Act. On this premise he dismissed the application of the A
'trspondent and confirmed the order of attachment.
In support of his argument that court at Bangalore would have no
jurisdiction Mr. Rajiv Dutta, learned counsel for the appellant, referred to a
decision of this Court in Patel Roadways Limited, Bombay v. Prasad Trading
Company, [1991] 4 SCC 270. In this case Patel Roadways Limited had its B
principal office at Bombay and branch offices at various other places. Prasad
Trading Company entrusted certain consignments of goods to Patel Roadways
Limited at its subordinate office in the State of Tamil Nadu for delivery at
Delhi. The goods reached Delhi but in damaged conditions. Prasad Trading
Company instituted a suit for damages in the court at Madras within whose c
jurisdiction the subordinate offices of Patel Roadways Limited were situated
and where the goods were entrusted for transport. A plea was raised by the
Patel Roadways Limited in its defence that when the contract was entered
into between the parties it was agreed that only Bombay court would have
jurisdiction and as such court in Madras had no jurisdiction. It was in this
context that this Court considered clause (a) of Section 20 and explanation D
thereto in Code of Civil Procedure (for short 'Code')*. The question which
was before this Court was as to whether in view of the relevant clause in the
contract between the parties the court at Bombay alone had jurisdiction and
the jurisdiction of the courts at Madras where the suit was instituted was
barred. It was submitted by. the Patel Roadways that apart from the courts E
within whose territorial jurisdiction the goods were delivered to the appellant
for transport, the courts at Bombay also had jurisdiction to entertain a suit
arising out of the contract between the parties in view of the Explanation to
* 20 Other suits io be instituted where defendants reside or cause of action arises. - Subject
to the limitations aforesaid, every suit shall be instituted in a Court within the local limits of F
--- whose jurisdiction -
(a) the defendant, or each of the defendants where there are more than one, at the time
of the commencement of the suit, actually and voluntarily resides, or carries on
business, or personally works for gain; or
(b) any of the defendants, where the~ are more than one, at the time of the commence-
ment of the suit, actually and voluntarily resides, or carries on business, or personally
works for gain, provided that in such case either the leave of the Court is given, or the G
defendants who do not reside, or carry on business, or personally work for gain, as
aforesaid, acquiesce in such institution; or
(c) the cause of action, wholly or in part, arises.
Explanation. A corporation shall be deemed to carry on business at its sole or principal office 1
in India or, in respect of any cause of action arising at any place where it has also a subordinate .:l T
office, at such place. tt
580 SUPREME COURT REPORTS (2000] 2 S.C.R.
A Section 20 of the Code inasmuch as the principal office of the appellant was
situated in Bombay. According to it since .courts at two places namely
Madras and Bombay had jurisdiction in the matter, the jurisdiction of the
courts in Madras was ousted by the clause in the contract whereunder the
parties had agreed that jurisdiction to decide any dispute under the contract
would be only in the courts at Bombay. Consequently the courts where the
B
suit was instituted had no jurisdiction to entertain it. This Court said that "the
explanation is really an Explanation to clause (a) viz. as to where the
corporation can be said to carry on business. This, it is clarified, will be the
place where the principal office is situated (whether or not any business
actually is carried on there) or the place where a business is carried on giving
c rise to a cause of action (even though the principal office of the corporation
is not located there) so long as there is a subordinate office of the corporation
situated at such place. The linking together of the place where the cause of
action arises with the place where a subordinate office is located clearly
shows that the intention of the legislature was that, in the case of a
D corporation, for the purposes of clause (a), the location of the subordinate
office, within the. local limits of which a cause of action arises, is to be the
relevant place for the filing of a suit and not principal place of business. If
the intention was that the location of the sole or principal office as well as
the location of the subordinate office (within the limits of which a cause of
action arises) are to be deemed to be places where the corporation is deemed
E Lo be carrying on business, the disjunctive "or" will nol be there. Instead,
the second part of the Explanation would have read "and, in respect of any
cause of action arising at any place where it has a subordinate office,. also
at such place". It, therefore, held that the explanation provides an alternative
locus for the Corporation's place of business, not an additional one. Thus,
F this Court was of the view that clause (c) was not attracted to confer
jurisdiction on courts at Bombay and the appellant has admittedly its
subordinate offices at M!idras where the goods in· the case were delivered to
-
it for the purpose of transport the Court at Bombay had no jurisdiction at all
to entertain the suit and that the parties could not confer jurisdiction on the
courts at Bombay by an agreement.
G
In view of the decision of this Court in Patel Roadways Limited,
Bombay v. Prasad Trading Company, [1991] 4 SCC 270, it cannot be said that
the Principal District Judge, Raichur had no jurisdiction to entertain the matter.
But then the question arises, as rightly posed by the High Court, if in the given
H facts and circumstances of the case, could the Principal District Judge,
K.A. DAKHANI v. HAITI GOLD MINES CO. LTD. [D.P. WADHWA, J.) 581
Raichur had made to orders whicl;l are impugned, particularly, when it was A
brought to his notice pendency of the proceedings under Section 34 of the
Act in the Court of Principal City Civil Judge, Bangalore where the appellant
itself.·had filed a CAVEAT under Section 148A of the Code and also an
application under Section 9* of the Act seeking interim relief. Learned
Principal District Judge, Raichur also did not take notice of clause 35 of the
B
contract which constituted arbitration agreement between the parties which
specifically provided that only the courts in Bangalore would have jurisdiction
~- to entertain any claim for enforcement of the award. Principal District Judge,
Raichur had no doubt jurisdiction in the matter but his holding that the
Principal City Civil Judge. Bangalore would have no jurisdiction does not
commend to us. It cannot always be ·said, in view of Section 20 of the Code, c
that only one court will have jurisdiction to try the suit It is not that the
Principal City Civil Court, Bangalore is not a court within the meaning of
Section 2(e)** of the Act. Whether Principal City Civil Judge, Bangalore has
jurisdiction in the matter or not is still pending with him which proceedings
were filed earlier in time than the execution application by the appellant in the D
* 9. Interim measures, etc. by court. - A party may, before or during arbitral proceedings or at
any time after the making of the arbitral award but before it is enforced in accordance with
section 36, apply to a court-
(i) for the appointment of a guardian for a minor or a person of unsound mind for the purpose
of arbitral proceedings, or
(ii) for an interim measures of protection in respect of any of the following matters, namely-
E
(a) the preservation, interim custody or sale of any goods which are the subject-matter of
the arbitration agreemen~
(b) securing the amount in dispute in the arbitration;
(c) the detention, preservation or inspection of any property or thing which is the subject-
matter of the dispute in arbitration, or as to which any question may arise therein and
authorising for any of the aforesaid purposes any person to enter upon any land or building F
in the possession of any party, or authorising any samples to be taken or any observation
to be made, or experiment to be tried, which may be necessary or expedient for the purpose
of obtaining full information or evidence;
(d)interim injunction or the appointment of a receiver;
(e) such other interim measure of protection as may appear to the court to be just and
convenient, G
and the Court shall have the same power for making orders as it has for the purpose of, and in
relation to, any proceedings before it
** "Court" means the principal Civil Court of original jurisdiction in a district, and inchldes the
High Court in exercise of its ordinary original civil jurisdiction, having jurisdiction to decide
the questions forming the subject matter of the arbitration if the same had been the subject
matter of a suit, but does not include any civil court of a grade inferior to such principal
Civil Court, or any Court of Small Causes" H
582 SUPREME COURT REPORTS [2000) 2 S.C.R.
A District Court at Raichur. The award had not attained finality. In these
circumstances we are of the view that the Principal District Judge, Raichur
should not have entertained the application for execution and order attach-
ment of movable properties of the respondents. The High Court referred to
the concession by both the parties that all the applications under the Act had
to be treated as original suits and if the court finds that it had no jurisdiction
B
to entertain, it cannot dismiss the suit but has to return the same for the
presentation to the proper Court. Whatever may be the concession of the
parties, we are of the view in the circumstances of the present case Principal
District Judge, Raichur should have stayed his hands and should not have
entertained the execution application by the appellant. High Court took a
C correct view of the matter and rightly set aside the impugned orders.
We; therefore, find no merit in the appeal. It is. dismissed with costs.
R.P. Appeal dismissed.
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.