Created byFuzzy Cloud

Supreme Court of India

M/S. B.S.N. JOSHI & SONS LTD.versusAJOY MEHTA & ANR.

Citation
2008 INSC 1495
Decided
19 December 2008
Disposal
Disposed off

Holding

The Court held that the respondents misinterpreted the Supreme Court's directions, did not willfully disobey, and therefore were not in contempt; the contract must be awarded to the petitioner.

Summary

The Supreme Court examined a contempt petition filed by M/s B.S.N. Joshi & Sons Ltd. after MAHAGENCO refused to award it a coal‑transport contract despite a prior Supreme Court order (31‑Oct‑2006) directing a fresh assessment of its eligibility. The petitioners alleged that the respondents misinterpreted the order by calculating the required five‑year coal‑handling period from the date of the judgment rather than from the tender’s financial years, and that they relied on an interim order to deny the contract. The Court held that the respondents had not read the directions in proper perspective, that the interim order merged into the final order, and that there was no room for two reasonable interpretations of the judgment. It found no willful disobedience, accepted the respondents’ apology, and directed that the contract be awarded to the petitioner for one year. The contempt petition was consequently disposed of.

Issues considered

  • Whether the respondents' refusal to award the contract amounted to willful disobedience of the Supreme Court's order dated 31‑Oct‑2006.
  • Whether the phrase ‘preceding five years’ could be interpreted as starting from the date of the judgment.
  • Whether the interim order dated 27‑Mar‑2006 bound the respondents notwithstanding the final order.
  • Whether the alleged misinterpretation and actions of the respondents constituted contempt of court.
  • Whether the petitioner satisfied the essential tender conditions and whether the court could exercise a power of relaxation.

Subjects

contempt of courttender eligibilitycoal transportation contractpublic sector undertakinginterpretation of judgmentinterim orderpower of relaxationcartel

Judgment

                       (2008] 17 S.C.R. 1352


A               MIS. B.S.N. JOSHI & SONS LTD.
                               v.
                      AJOY MEHTA & ANR.
                Contempt Petition No. 245 of 2007
                                  IN
B                 Civil Appeal No, 4613 of 2006
                                        I        ,



                      DECEMBER 19, 2008

            [S.B. SINHA AND CYRIAC JOSEPH, JJ.]
                             /




c      Contempt of Court - Disputes arising out of contract for
  transportation of coal - Judgment passed by Supreme Court
  - Contempt petition filed alleging willful disobedience of the
  judgment- Held: Alleged contemnors.did not read directions
  of the Court in their proper perspective - It was not a case
D where two interpretations of the judgment were possible -
  Apology tendereq by the alleged contemnors accepted -
  Direction passed in favour of the Petitioner.
       Respondent No.1 is Managing Director of
  Maharashtra State Power Generation Co. Ltd.
  (MAHAGENCO), a public sector undertaking.
E MAHAGENCO issued notice inviting tender for transpor:
  tation of coal. The bid of Petitioner was not accepted on
  the premise that it did not fulfill the essential condition of
  having transported the prescribed minimum quantity of
  coal for the preceding five years.
F     The matter came upto this Court, which vide
  judgment dated 31-10-2006 directed that a fresh look be
  given in rega-rd to the eligibility of the Petitioner for
  purpose of the contract and if it satisfied the tender
  conditions, the contract be awarded in its favour for a
G period of one year.
        On the allegation that respondents willfully
    disobeyed the said judgment passed by this Court,
    contempt proceedings were initiated' against them. It was
    contended that the respondents gave a twist to the said
H                                1352
                          M/S. B.S.N. JOSHI & SONS LTD. v. AJOY MEHTA &      1353
                                               ANR.

                      judgment of this Court insofar as it proceeded on the A
                      basis that the five years period should be calculated from
                      the date of the judgment and refused to grant contract
                 /
                      in. favour of the petitioner relying on an interim order
                      passed by Court and further sought to take into
                      consideration an irrelevant subsequent event.              B
                            On the aforementioned premise, it was contended
                      that the respondents must be held to have committed
                      gross contempt of this Court.
                           Disposing of the petition, the Court
                            HELD:1.1. Supply of coal and that too good quality c
                       of coal is essential for running of a thermal power station.
                       It was with that intent in mind that this Court, either at the
                       interim stage or final stage, did not intend to pass any
                       order which would hamper transportation of coal
                       resulting in stoppage of the functioning of the thermal :D
                       power station. The respondents misconstrued the order
                     · of this Court for which there was no basis that they were
                       bound by the interim order passed by this Court. [Paras
                       8 and 9] [1360-D-E]
                         1.2. One fails to understand as to how a fresh tender E
                     was floated to allot the work of liaisoning of coal and the
                     same companies who had formed a cartel were allowed
                     to carry on the contract job. [Para 10] [1361-8-C]
                          1.3. The petitioner was asked to file additional
                     documents in support of its contention that it fulfilled the F
                     essential conditions of contract, if it so intended to do. It
          ....       was, however, wholly unnecessary as only a fresh look
                     was required to be given in regard to the eligibility of the i
                     petition for the purpose of awarding the contract
                     wherefor the Scrutiny Committee was required to form an
                                                                                    G
                     opinio'n as to whether the petitioner had substantially
                     complied with the tender conditions, subject, of course, ,
                     to the fulfillment of essential conditions. [Para 11] [1361 D-
     -4   If
                     E]
                           2. The respondents committed a serious error in
                                             '                                      H
..
    1354     SUPREME COURT REPORTS              [2008) 17 S.C.R.


A calculating the quantity of coal transported for preceding
    five financial years from the date of the judgment. The
    date of the judgment was not at all relevant for the
    aforementioned purpose. The respondents did not
                                                                   '
    explain how they understood the order of this Court
B   wrongly as they had also proceeded on the basis that
    the five financial years should be counted from the date
    of calling for the tender and the date of the judgment
    separately. If they had any difficulty in understanding the
    direction of the court, they should have approached this
    Court for clarification but could not have arrived at such
c   an absurd conclusion that what was necessary to be
    considered is handling of coal by the petitioner tor the
    preceding five years from the date of passing of the
    judgment by this Court. What was necessary for them to                    ,...
                                                                               ;;


    consider was implementation of the directions issued by                    "
D   this Court in the backdrop of the events noticed by this
    Court. This Court in its judgment had not only taken into
    consideration the contentions raised by MAHAGENCO in
    regard to non-fulfillment of the essential conditions on the
    part of the. petitioner but also implications thereof at
E   some details. The respon·dents furthermore sought to
    take into consideration a purported subsequent event,
    viz, the letter dated 20.02.2007 issued by the Sanjay
    Gandhi Thermal Power Station, which was neither
    relevant nor decisive. [Paras 12 and 13][1361-E; 1362-C]
F        3. The respondents did not read the directions of the
    court in their proper perspective. They could not have
    considered the directions contained in the interim order           ..,
    passed by this Court. The interim order merged into the
    final order. In any event, even the said interim order was
    subject to the decision of the court and, thus, one fails
G   to understand as to how the interim order was found to
    be continuing despite passing of the final order. As the
    matter was required to be considered afresh, as far as the               ... I
                                                                        ~
    purpose of-considering the eligibility of the petitioner is
    concerned, they committed a-serious error insofar as the
H   eligibility criteria were applied· from the date of the
                 M/S. B.S.N. JOSHI & SONS LTD. v. AJOY MEHTA &           1355
                                      ANR.

              judgment. They furthermore did not notice that having, A
              regard to the overall situation and particularly in view of
          r   the opinion of the Scrutiny· Committee that the petitioner
              had substantially complied with the conditions and, thus,
              the general power of relaxation should have been used.
              It is, therefore, not a case where two interpretations of the
                                                                            8
              judgment of this Court were possible. [Paras 14 and 15]
              [1362-C; 1363-A]
                    4. The apology tendered by the respondents is
              accepted for the time being and it is directed that contract
              for a period of one year be granted to the petitioner in , C
              terms of the judgment dated 31.10.2006. [Para 16] [1363-
              C]
                    5. It is distressing to see that MAHAGENCO had been
              encouraging formation of a cartel and, thus, allowing the
              rate of transportation of coal to go high up. Unless a
              power generating company takes all. measures to cut 'D
              down such malpractices, the generation cost of electricity
              is bound to go higher and ultimately the same would be
              passed on to the consumers of electricity. It is hoped as
              a public sector undertaking it would take adequate and
              appropriate measures to meet the said contingency in E
              future. [Para 17] [1363-D-E]
                    CIVIL APPELLATE JURISDICTION : Contempt Petition
              (C) No. 245 of 2007.
                                              IN
                    Civil Appeal No. 4613 of 2006.                          F
'   ''f             Vikas Mehta for the Petitioner.
                  Altaf Ahmed, AS. Bhasme, Brajesh Pandey and Varun
              Thakur for the Respondents.
                  The Judgment of the Court was delivered by
                                                                                 G
                    S.B. SINHA, J.1. This contempt proceeding has been
              initiated against respondent Nos. 1 and 2 for alleged wilful
              disobedience of this Court's order dated 31.10.2006, the
              operative portion whereof reads as under:
                    " ... We, therefore, intend to give another opportunity to   H
    1356       SUPREME COURT REPORTS                  [2008] 17 S.C.R.


A       MAHAGENCO. It shall consider the offer of Appellant upon
        consideration of the matter afresh, as to whether it even
        now fulfils the essential tender conditions. If it satisfies the
        terms of the tender conditions, the contract may be
        awarded in its favour for a period of one year; but such
        contract shall take effect after one month from the date of
B
        the said agreement so as to enable the private
        Respondents herein to wind up their business. This order
        is being passed in the interest of MAHAGENCO as also
        the private Respondents herein."
        2: The Maharashtra State Power Generation Co. Ltd. (for
C short "MAHAGENCO") issued a notice inviting tender, inter alia,
   for coal liaisoning, quality and quantity supervision of its thermal
   power station. One of the conditions laid down therefor is as
   under:
          "(ii) The Bidder should have executed the work of total
D                minimum quantity of 5 (Five) Million Metric Tons per
                 year for preceding 5 years. Besides this bidder
                 should have executed the work of total quantity of
                 10 (ten) Million MT's in any of the preceding 5 (Five)
                 years. Above execution of work should be on behalf
E                of State Electricity !3oard and/or NTPC and/or other
                 State or Central Undertaking and/or the private
                 Power Generating Companies as their liaison
                 agent/coal agent, with regard to receipt and supply
                 of ttie coal including supervision on dispatch,
                 loading, movement of the coal upto destination by
F
                 Railway only."
        The term "year'' occurring therein is said to be the financial
  year. Petitioner along with various others submitted its tender,
  inter alia, on tbe premise that the petitioner did not fulfill the
  essential conditions of having transported the quantity of
G minimum five lakh tonnes of coal for the preceding five years,
  its offer was not accepted.
        3. A writ petition was filed before the Madhya Pradesh
  High Court, which having been dismissed, Civil Appeal bearing
  No. 4613 of 2006 was preferred by the petitioner upon obtaining
H special leave.
               M/S. 8.S.N. JOSHI & SONS LTD. v. AJOY MEHTA &        1357
                             ANR. [S.B. SINHA, J.]

                 One of the questions which arose for consideration before A
            this Court was as to whether MAHAGENCO committed a
        I   serious error in not taking into account the quantity of coal
            supplied by the petitioner to the Andhra Pradesh Power
            Generation Corporation Limited; as it appears from its letter
            dated 15.06.2005 that the petitioner had supplied the following
                                                                            B
            quantity of coal:
             "S. Period                Name of Colliery Quantity in MT
             No.
             01. 11.09.2003            M/s MCL Talcher 3172750.00
                    to
                   March 2004
                                                                            c
             02. 01.10.2003            M/s MCL, lbvalley 316930.00
                   to                   Area
                   31.03.2004                             -------
                                                            3489680.00
                                                            ---------~
                                                                            D
             03. 01.04.2004            M/s MCL Talcher      2774455.00
                   to
  """              10.09.2004
             04. 01.04.2004            Mis MCL lbvalley     389732.00
                   to                  Area                                 E
                   30.09.2004
                                                         ----------
                                                          3164187.00
                                                         ----------    II




                    By a judgment and order dated 31.10.2006, this Court    F
            held:
   "                 "It is, therefore, evident that total quantity of
                62,64, 135 metric tones of coal had been handled by
                Appellant for them.
                      The intention of introduction of the said clause G
                becomes self-evident from the aforementioned note. It may
                be true, as was observed by the High Court, that the
~ i             Respondents in the tender documents did not categorically
                state that the block of 365 days in respect of handling o~
                coal by the tenderes shall be taken into consideration. It H
    1358      SUPREME COURT REPORTS                  [2008) 17 S.C.R.


A       is also true that the Corporation must be held to be aware
        as to what was the true intent and purport of the said term."
      4. It was, however, found that other tenderers, viz., M/s. Nair
  Coal Services Ltd., Nagpur, M/s. Nareshkumar & Co. Ltd.,
  Nagpur and M/s. Karamchand Thapar & Brs. Ltd., Mumbai had
B formed a cartel.
        Alleged contemnor Shri Ajay Mehta, Managing Director of
    MAHAGENCO (Respondent No. 1 herein) in a note dated
    19.08.2005 stated as under:
        "On perusal of rates of Mis Nair Coal Services Ltd.,
C       Nagpur, M/s Nareshkumar & Co Ltd., Nagpur and Mis
        Karamchand Thapar & Brs. Ltd., Mumbai, it is apparent
        that they have formed a cartel. The rates quoted by these
        firms are nearly 51 crs. to 52 crs. more than that quoted
        by LT. As a goodwill gesture the above parties were called
D       for negotiations. However, they have refused to match the
        L 1 rates.
              In view of above it is in public interest and in the
        interest of MAHAGENCO a Govt. owned, public utility that
        the work is allocated to the lowest qualified bidder namely
E       M/s B.S.N. Joshi & Co."
        Ultimately, however, the said proposal was not accepted.
        5. Despite the fact that a cartel was formed, the contract
    was awarded to the members thereof. In the aforementioned
    context, this Court observed:
F                "While saying so, however, we would like to observe
        that that having regard to the fact that a huge public money       )'   .
        is involved, a public sector undertaking in view of the
        principles of good corporate governance may accept such
        tender which is economically beneficial to it. It may be true
G       that essential terms of the contract were required to be
        fulfilled. If a party failed and/or neglected to comply with the
        requisite conditions which were essential for consideration
        of its case by the employer, it cannot supply the details at
        a later stage or quote a lower rate upon ascertaining the
H       rate quoted by others. Whether an employer has power of
       MIS. B.S.N. JOSHI & SONS LTD. v. AJOY MEHTA &             1359
                     ANR. [S.B. SINHA, J.]

        relaxation must be found out not only from the terms of the A
        notice inviting tender but also the general practice
        prevailing in India. For the said purpose, the court may
        consider the practice prevailing in the past. Keeping in
        view a particular object, if in effect and substance it is found
        that the offer made by one of the bidders substantially
                                                                         8
        satisfies the requirements of the conditions of notice
        inviting tender, the employer may be said to have a general
        power of relaxation in that behalf. Once such a power is
        exercised, one of the questions which would arise for
        consideration by the superior courts would be as to
        whether exercise of such power was fair, reasonable and C
        bona fide. If the answer thereto is not in the negative, save
        and except for sufficient and cogent reasons, the writ courts
        would be well advised to refrain themselves in exercise of
        their discretionary jurisdiction."
        It was on the aforementioned premise, the Civil Appeal          D
    was allowed by this Court.
         6. Mr. Vikas Mehta, learned counsel appearing on behalf
    of the petitioner, in support of the contempt petition, would
    argue:
                                                                        E
          (i)    Alleged contemnors had from the very beginning
                 gave a twist to the said order insofar as it
                 proceeded on the basis that the five years period
                 should be calculated from the date of the order of
                 this Courts.
                                                                        F
         (ii)    MAHAGENCO refused to grant a contract in favour
                 of the petitioner relying on or on the basis of the
                 interim order passed by this Court.
         (iii)   A different stand is being taken now that the
                 petitioner should not be allotted any contract in view, G
                 of a subsequent event, viz., the letter dated
                 20.02.2007 issued by the Sanjay Gandhi Thermal
                 Power Station.
        On the aforementioned premise, the learned counsel
    would submit that the alleged contemnors must be held to have       H

\
I
    1360          SUPREME COURT REPORTS               [2008] 17 S.C.R.


A   committed gross contempt of this Court.
        7. Mr. Altaf Ahmed, learned senior counsel appearing on           ~
    behalf of the alleged contemnors, on the other hand, would
    contend that:
           (i)     the alleged contemnors might have committed a
B                  mistake in properly understanding the order of the
                   court, but the same would not mean that they have
                   committed contempt of the court.
           (ii)   The term "year" having been found by this Court to
                  mean a financial year, even if the figures supplied
c                 by the petitioner are taken into consideration, it
                  cannot be said to have satisfied the essential
                  conditions for grant of contract of transportation of
                  coal.
       In any event, the learned Senior Counsel would submit that
D the alleged contemnors are ready and willing to abide by any
  direction which may be issued by this Court.
       8. Supply of coal and that too good quality of coal is
  essential for running of a thermal power station. It was with that
  intent in mind that this Court, either at the interim stage or final
E stage, did not intend to pass any order which would hamper
  transportation of coal resulting in stoppage of the functioning
  of the thermal power station.
       9. The alleged contemnors, in our opinion, misconstrued
  the order of this Court for which there was no basis that they
F were bound by the interim order passed by this Court. For the
  sake of clarity, we may notice the interim order dated                  -,,
  27.03.2006 which reads as under:
        "Learned counsel for the petitioner submits that the main
        petition is coming up for final hearing on 17th April 2006.
G       Learned counsel appearing for respondent Nos. 2 & 3
        submits that for purposes of generating ·power, coal
        supplies have to be continued to the respondents failing
                                                                          ~     '"'
        which the entire generation of electricity shall come _to a
        standstill. Keeping in view this fact, the respondents are
H       permitted to go ahead with .iheir tender process including
      MIS. B.S.N. JOSHI & SONS LTD. v. AJOY MEHTA &               1361
                    ANR. [S.B. SINHA, J.]

         award of contract. They are free to make whatever A
         arrangement they want to make in this behalf to ensure
         continued supply of coal to them. It is, however, made clear
         that whatever arrangement is made by the respondents
         the same will be subject to the final decision of this
         Special Leave Petition."                                     B
                                  [Underlining is ours for emphasis]
          10. We, therefore, fail to understand as to how a fresh
    tender was floated to allot the work of liaisoning of coal and
    the same companies who had formed a cartel were allowed
    to carry on the contract job. We may, however, place on recor~ C
    that the contracts were awarded on the condition that the sam~
    would be subject to the final outcome and decision of this Court.
           11. Our attention has been drawn to the fact that the
    petitioner was asked to file additional documents in support of
                                                                          o
    its contention that it fulfilled the essential conditions of contract, ·
    if it so intended to do. It was, however, wholly unnecessary as
    only a fresh look was required to be given in regard to the
    eligibility of the petition for the purpose of awarding the contract
    wherefor the Scrutiny Committee was required to form ah
    opinion as to whether the petitioner had substantially complied E
    with the tender conditions, subject, of course, to the fulfillment
    of essential conditions.
          12. Alleged contemnors, in our opinion, committed a
     serious error in calculating the quantity of coal transported for
    preceding five financial years from the date of the judgment,. F
    The date of the judgment was not at all relevant for the
    aforementioned purpose. The alleged contemnors did not
    explain how they have understood the order of this Court
    wrongly as they had also proceeded on the basis that the five
    financial years should be counted from the date of calling fot
    the tender and the date of the judgment separately. If they had G
    any difficulty in understanding the direction of the court, they
    should have approached this Court for clarification but could
    not have arrived at such an absurd conclusion that what wa~
    necessary to be considered is handling of coal by the petitione~
    for the preceding five years from the date of passing of the H ·
(

•
           1362           SUPREME COURT REPORTS                 [2008] 17 S.C.R.


      A judgment by this Court.
             13. What was necessary for them to consider was
        implementation of the directions issued by this Court in the
        backdrop of the events noticed by this Court. This Court in its
        judgment had not only taken into consideration the contentions
      B raised by MAHAGENCO in regard to non-fulfillment of the
        essential conditions on the part of the petitioner but also
        implications thereof at some details.
                They furthermore sought to take into consideration a
           purported subsequent event, viz, the letter dated 20.02.2007
      c    issued by the Sanjay Gandhi Thermal Power Station, which was
<.'
           neither relevant nor decisive.
                14. The alleged contemnors, therefore, in our opinion, did
           not read the directions of the court in their proper perspective.
               We say so:
      ,0
                  (i)      because they could not have considered the
                           directions contained in the interim order passed by
                           this Court. The interim order merged into the final
                           order. In any event, even the said interim order was
                           subject to the decision of the court and, thus, we fail
                                                                                      -
      E                    to understand as to how the interim order was found
                           to be continuing despite passing of the final order.
                  (ii)    As the matter was required to be considered
                          afresh, the purpose of considering the eligibility of
                          the petitioner is concerned, they committed a
      F                   serious error insofar as the eligibility criteria were
                          applied from the date of the judgment.
                                                                                      '"
                                                                                         -
                  (iii)    They furthermore could not have ignored the note
                           of the alleged Contemnor No. 1 that the other
                           respondents in the Civil Appeal had formed a
      G                   .cartel. They furthermore did not notice that having
                           regard to the overall situation and particularly in view
                           of the opinion of the Scrutiny Committee that the
                           petitioner had substantially complied with the             •   ~



                           conditions and, thus, the general power of relaxation
      H                    should have been used.                                         ..£
  M/S. B.S.N. JOSHI & SONS LTD. v. AJOY MEHTA &               1363
                ANR. [S.8. SINHA, J.]

     15. It is, therefore, not a case where two interpretations of A
the judgment of this Court were possible.
    16. Before us an additional affidavit has been filed by Shri
Ajoy Mehta, Contemnor No. 1, stating:
    "17. I, therefore, respectfully submit that we have not flouted
    the orders passed by the Hon'ble Court and we shall abide         B
    by all directions given by this Hon'ble Court including
    awarding of the contract to Mis BSN Joshi & Sons ltd.,
    Petitioner herein, if this Hon'ble Court so directs."
     Keeping in view the aforementioned statement made
before us, we accept the apology tendered by the alleged C
contemnors for the time being and direct that the contract for a
period of one year be granted to the petitioner in terms of our
judgment dated 31.10.2006.
     17. We are distressed to see that MAHAGENCO had been
encouraging formation of a cartel and, thus, allowing the rate D
of transportation of coal to go high up. Unless a power
generating company takes all measures to cut down such
malpractices, the generation cost of electricity is bound to go
higher and ultimately the same would be passed on to the
consumers of electricity. We hope a public sector undertaking E
would take adequate and appropriate measures to meet the
said contingency in future.
     18. The contempt petition is disposed of with the
aforementioned directions.
B.B.B.                                     Petition disposed of.      F


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "contempt of court"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.