M/S. BUILD INDIA CONSTRUCTION SYSTEMversusUNION OF INDIA
- Citation
- 2002 INSC 268
- Decided
- 7 May 2002
- Disposal
- Appeal(s) allowed
- Bench
- R C LAHOTI
Holding
The 1986 amendment does not apply to the 1985 contract, so the arbitrator was not bound to give a reasoned award, and the plea for such an award was not timely raised.
Summary
The appellant entered into a 1985 construction contract with the Union of India that contained an arbitration clause but did not require a reasoned award. In 1986 the Government amended the General Conditions of Contract, adding a provision that arbitrators must give reasons when the claim exceeds Rs 1 lakh, effective 30 days after the amendment. A dispute later led to an arbitrator’s award without reasons; the High Court’s Single Judge upheld the award, but the Division Bench set it aside and remitted it for a reasoned award, relying on the 1986 amendment. The Supreme Court held that the amendment could not alter the arbitration clause of the 1985 contract because contract terms can be varied only by mutual agreement, and the amendment’s effective date was after the contract was formed. Moreover, the plea for a reasoned award was not raised before the arbitrator or the Single Judge and therefore could not be entertained at the appellate stage. Consequently, the appeal was allowed, the Division Bench’s order set aside, and the Single Judge’s decision restored.
Issues considered
- Whether the 1986 amendment to the General Conditions of Contract applies to the 1985 contract and thereby obliges the arbitrator to give a reasoned award.
- Whether the plea for a reasoned award was properly raised at the appellate stage.
Subjects
Judgment
y
A M/S. BUILD INDIA CONSTRUCTION SYSTEM
v.
--<-
UNION OF INDIA
MAY 7, 2002
•,
B [R.C. LAHOTI AND B.N. AGRA WAL, JJ.]
/
Arbitration-Parties entering into contract in I 985-Arbitration
clause providing for reference of dispute to arbitrator but not for reasoned 'I"
award-Subsequent amendment in I 986 in the general conditions of contract
c that if value of claim exceeds Rs. I lakh arbitrator to give reasoned award-
Dispute leading to cancellation of contract-Reference to arbitrator-
Award-Held, amendment of 1986 does not apply to general conditions of
contract as applicable to parties-Hence, arbitration clause should not be
read as amended-Arbitrator not oblige to give reasoned award-Terms of
D contract between the parties could not be varied except by mutual
agreement-Further amendment to general conditions, coming into effect
after the date of amendment, cannot have any relevance for interpreting
arbitration clause much before the date of amendment coming into effect. c..
Practice and procedure-Plea not raised in objection petition, cannot
E be urged at appellate stage.
Appellant entered into a contract with the respondent-Government for
construction work in 1985. Contract contained an arbitration clause by which
disputes could be referred to an arbitrator. However, arbitration clause did not
F provide for a reasoned award or a speaking award by the arbitrator.
Subsequently in 1986 Government amended the general conditions of the
.... -....;...
contract providing that if the value of the claim exceeds Rs. 1 lakh, arbitrator
shall pass reasoned award. This amendment was effective on 30th day after
the date of amendment. Disputes arose between the parties leading to
cancellation of contract by the respondents. Disputes were referred to an
G arbitrator in accordance with the arbitration agreement. Arbitrator passed an -
award without giving reasons. Single Judge of High Court made award rule of
the Court. However, Division Bench directed the award to be set aside and
remitted back the award to the arbitrator for proceeding afresh and making a
reasoned award. ·
H 866
BUILD INDIA CONSTRUCTION SYSTEM v. U.0.1. 867
The question that arose in appeal before this Court was whether the A
_, amendment of 1986 applies to the general conditions of contract as applicable
to the parties, and therefore, the arbitration clause should have been read as
amended casting an obligation on the arltitrator to give a reasoned award.
In appeal before this Court, appellant submitted that the amendment of
1986 applies only to the contracts entered into on and after that date and in B
any case the respondent could not have amended the general conditions of
contract all by themselves and without the consent of the appellant and,
therefore, the arbitration clause governing the parties was the one as contained
in the general conditions of contract which existed and were applicable on the
date on which the contract was entered into between the parties. C
Respondent submitted that the acceptance letter signed by the appellant
should be read and interpreted as the appellant having authorized the
respondent to amend the general conditions of contract and also as the appellant
having agreed to bind itself by the general conditions of contract as modified
from time to time and, therefore, the parties and the arbitrator should all be D
held bound by the amendment of 1986 and any award given in breach of the
arbitration clause as amended should be held as void.
Allowing the appeal, the Court
HELD: 1. The letter of acceptance signed by the appellant cannot be so E
read as to spell out the appellant having conferred any authority on the
respondent to modify or alter the terms of the contract except by mutual
agreement and to bind itself by such variations. The arbitration clause is
contained in the contract entered into between the parties. Its terms could not
have varied except by mutual agreement. Moreover the amendment itself F
provides for its coming into effect on 30th day after the date of the amendment
That amendment clearly cannot have any relevance for interpreting the
arbitration clause contained in the contract entered into between the parties
much before the date of amendment coming into effect. J872-F-H; 873-AJ
2. The reference to arbitrator does not suggest an obligation having been G
cast on the arbitrator to give reasons for the award. Such a plea urged in this
Court, was not taken by the respondent before the arbitrator. Even in the
objections filed, the validity of the award has not been specifically questioned
on the ground of its having been given in breach of any obligation of arbitrator
to give reasons. The judgment of the Single Judge does not show such a plea H
868 SUPREME COURT REPORTS [2002] 3 S.C.R.
A having been urged before him. In the objection petition there is a vague and
general plea raised that rejecting the claims forming subject matter of cross
objection and allowing the claims of the appellant without assigning any reason
was bad. Such an omnibus and general plea cannot be read as submitting that
the amendment applied to the contract between the parties and that in view of
the amended arbitration clause the unreasoned award was bad. It appears that
B the plea was for the first time raised at the appellate stage before the Division
Bench. Unwittingly, the Division Bench fell into the error of entertaining such
a plea and disposing of the appeal by upholding the same though the plea was
not even available to the respondents to be raised at that stage.1873-B-E)
c Calcutta
Benode Behary Roy v. The General Assurance Society Ltd., AIR (1950)
232 and Food Corporation of India. v. Jagadish Chandra Saha,
11995) Suppl. 4 SCC 521, referred to. ,
Lombard Tricity Finance ltd v. Paton, (1989) 1 All ER 919, referred to.
D Anson's Law of Contract (27th Edition, 1998, at p. 494 and Treital's Law
of Contract (10th Edition, 1999. at p.55), referred to.
-
CIVIL APPELLATE JURISDICTION: Civil Appeal No. 3364 of2002. "-
From the Judgment and Order dated 9.10.2000 of the Mumbai High
E Court in A. No. 805 of 2000.
Rakesh Singh and Arun K. Sinha for the Appellant.
Prateek Jalan, R.N. Poddar and B.V. Balaram Das for the Respondent.
F The Judgment of the Court was delivered by
R.C. LAHOTI, J. Leave granted. "'
In response to a Notice Inviting Tenders (NIT) issued by the respondent
on 12.9.1984, the appellant submitted the tender based on the tender document
G issued by the respondents. The tender submitted by the appellant was accepted.
On 22.2.1985, the appellant signed a letter to the following effect:-
"CA No (GE) B-10 of 8586 Serial Page No. 23
(General Conditions of Contract-IAFW-2249) 1976(Print)
H Lump Sum Contract For IAFW-2159
BUILD INDIA CONSTRUCTION SYSTEM v. U.O.l. [R.C. LAHOT!, J.) 869
_, Tenn Contract for Artificers Work (IAFW-1821) A
Measurement Contract-IAFW-1779 and I 779A
I. A copy of GENERAL ~OND!TIONS OF CONTRACTS (IAFW-2249
I 976 Print) with Errata No. I to 27 and Amendment No. I to 27 has been
supplied to me/us and is in my/our possession. !/We have read and B
understood the provisions contained in the aforesaid GENERAL
CONDITIONS OF CONTRACTS before submission of this tender and
I/We agree that l/We shall abide by the tenns and conditions thereof,
as modified, if any elsewhere in these tender documents.
2. It is hereby further agreed and declared by me/us, that the GENERAL C
CONDITIONS OF CONTRACTS-IAFW-2249 (1976 PRINT) including
Conditions 70 there pertaining to settlement of disputes by arbitration
containing 30 pages (Serial Page Number I to 30) with Errata Numbers
I to 27 and amendment Numbers I to 27 fonn Part of these Tender
documents.
D
Sd/- Sd/-
Singature of Contractor Accepting Officer
Dated: .................. "
E
The respondent accepted the tender and a contract was entered into
between the parties on 29.5. I 985. It is not in dispute that the contract contains
an arbitration clause requiring all disputes, between the parties to the contract
(other than those for which the decision of the CWE or any other person is
by the contract expressed to be final and binding) shall, after written notice
by either party to the contract to the other of them, be referred to the sole F
arbitration of an Engineer Officer to be appointed by the authority mentioned
in the tender documents. There are other. recitals contained in the arbitration
clause which are not relevant for our purpose. What is relevant to mention
is that the clause does not provide for a reasoned award or a speaking award
being given by the arbitrator. There is nothing in the arbitration clause G
spelling out an obligation on the part of the arbitrator clause spelling out an
obligation on the part of the arbitrator to give reasons for the findings arrived
at by him.
On 4.9.1986, the Government of India, Ministry of Defence, New Delhi
sanctioned an amendment in the general conditions of the contract which H
870 SUPREME COURT REPORTS [2002] 3 S.C.R.
A reads as under:- .><.-
"Amendment No. Page No. Particulars
48 24 Condition 70 Sub para 9. Add the
1978 Print followfog at the end of the sub paras;
B "If the value of the claims or counter
claims in an arbitration reference
exceeds Rs. I lakh the arbitration shall
give reasons for the award.
2. Sanction of the Government is also
c accorded for incorporation of the
above mentioned amendment at the
appropriate place in the earlier prints
ofIAFW 2249.
3. This amendment shall come into
D effect from 3.10.1986."
Disputes arose between the parties leading to cancellation of contract
by the respondent on 3.11.1987 and again on 4.4.1990. On 31.5. I 99 I, the
..
respondents appointed a Senior Engineer Officer as the sole arbitrator in
accordance with the arbitration agreement. On 28.9. I 995, the arbitrator published
E his award allowing the appellant's claim to the extent of Rs. 80,000 only and
rejecting the respondents' counter claim. The award was made a rule of the
court by the learned Single Judge of the High Court. In an appeal preferred
by the respondents, the decree passed by the learned Single Judge has been
set aside by the Division Bench of the High Court which has also directed
the award to be set aside and remitted back to the arbitrator for proceeding
F afresh and making a reasoned award. For doing so the Division Bench has
relied on the amendment dated 4th September, l 986 and held it to be applicable
to the contract between the parties. Feeling aggrieved by the judgment of
Division Bench, the appellant has preferred this appeal by special leave.
G The singular question arising for decision in this appeal is whet~er the
amendment dated 4.9. I 986 applies to the general conditions of contract as
applicable to the parties, and therefore, the arbitration clause should have
been read as amended casting an obligation on the arbitrator to give a
reasoned award.
H Shri Rakesh Singh, learned counsel for the appellant, has submitted that
BUILD JND!A CONSTRUCTION SYSTEM v. U.0.1. [R.C. LAHOT!, J.] 871
the amendment date 4.9. ! 986 applies only to the contracts entered into on and A
->
after that date and in any case the respondents could not have amended the
general conditions of contract all by themselves and without the consent of
the appellant and, therefore, the arbitration clause governing the parties was
the one as contained in the general conditions of contract which existed and
were applicable on 29.5.1985, the date on which the contract was entered into
between the parties. Shri Prateek Jalan, learned counsel for the respondents, B
has, however, submitted that the acceptance letter signed by the appellant on
22.2.1985 should be read and interpreted as the appellant having authorized
the respondents to amend the general conditions of contract and also as the
appellant having agreed to bind itself by the general conditions of contract
as modified from time to time and, therefore, the parties and the arbitrator C
should all be held bound by the amendment dated 4.9.1986 and any award
given in breach of the arbitration clause as amended should be held as void.
A plain reading of the acceptance letter dated 22.2.1985 signed by the
appellant clearly suggests a copy of general conditions of contract with (i)
errata numbers I to 27, and (ii) amendment numbers 1 to 27 having been D
supplied by the respondents to the appellants and having been read and
)
understood by the appellant followed by appellant's agreement to abide by
the terms and conditions thereof. The expression 'as modfied', qualifies the
terms and conditions contained in the general conditions of contract as on
and till that day. There is nothing contained in the acceptance letter, either E
expressly or by necessary implication, to spell out the appellant having
authorized the respondents to carry out modifications in the ter~S and
conditions of the contract otherwise than by mutual agreement and to hold
the appellant bound by such modifications though not consented to by him
and though not even brought to his knowledge.
F
The learned counsel for the respondents has placed forceful reliance on
a single bench decision of Calcutta High Court in Benode Behary Ray v. The
General Assurance Society ltd., AIR (1950) Calcutta 232, as also on a few
other authorities. Benode Behary Roy's case (supra) related to a service
dispute. The plaintiff took up an employment with the respondent company
the bye"iaws whereof provided for the release of gratuity on retirement. G
Subsequently the company amended the bye-laws and provision for gratuity
was deleted. The plaintiff laid a claim for gratuity submitting that on the date
of plaintiffs entering into contract of employment with the company there
was a provision for gratuity and the bye-laws could not have been amended
without the consent of the plaintiff so as to take away his right to gratuity. H
872 SUPREME COURT REPORTS [2002] 3 S.C.R.
A The learned single Judge held that the letter of appointment did not make
gratuity an express term in the contract of service and the claim for gratuity
could only be based on the bye-laws. The bye-laws contained an express
provision that they could be altered or added to at any time by the Board of
Directors. The contract did not give the plaintiff any vested right, in fact or .
in law, to the gratuity. Right to claiin gratuity depended not on the contract
B but on the bye-laws and such right could arise only "on retirement". In this
background the learned single Judge of Calcutta High Court laid down the
principle that there is nothing repugnant to the law of contract to have as one
of the express terms of the contract itself that it will be alterable at the
instance of one party alone. If one contracting party gives to the other
C contracting party the right to alter the terms of the contract between them the
Court ought to uphold the sancity of a contract. But then it is necessary for
the Courts to examine with care the terms and true construction of such
contract; else there is the risk or danger of misdirected righteousness in the
name of sanctity of contract.
D The abovesaid analysis of Benode Behary Roy's case (supra) clearly
points out that reliance thereon by learned counsel for the respondents is "
entirely misconceived so far as the facts of the present case are concerned.
Shri Jalan also invited our attention to a few passages from Anson's Law of
·'
Contract (27th Edition, 1998, at p. 494 ), Treital Law of Contract ( l 0th Edition,
E 1999, at p.55) and speech of Staughton LJ in Court of Appeal in Lombard
Tricity Finance Ltd. v. Paton, ( 1989) l All ER 919, taking the view that a
contra2t may also give one of the parties the power unilaterally to vary the
obligations and if such power can be spelled out from the terms of the
contract and is held to be lawful then a unilateral variation of obligation by
one party shall be binding on the other party to the contract. On principle,
F there may not be a dispute with the legal proposition so forcefully advanced
by the learned counsel. However, the question is of its applicability to the
case at hand. As we have already pointed out, the letter of acceptance dated
22.2.1985 cannot be so read as to spell out the appellant having conferred any
authority on the respondents to modify or alter the terms of the contract
except by mutual agreement and to bind itself by such variations. The
G arbitration clause is contained in the contract entered into between the parties.
Its terms could not have been varied except by mutual agreement. Moreover
the amendment dated 4.9.1986 itself provides for its coming into effect from
3. 10. 1986, i.e. on 30th day after the date of the amendment. That amendment
clearly cannot have any relevance for interpreting the arbitration clause
H contained in the contract entered into between the parties much before the
1
.....
BUILD INDIA CONSTRUCTION SYSTEM v. U.0.1. [R.C. LAHOTI, J.] 873
-> date of amendment coming into effect. A
There are several other factors which preclude the respondents from
urging such a plea. The reference to arbitrator does not suggest an obligation
--r having been cast on the arbitrator to give reasons for the award. Such a plea,
as has been urged in this Court, was not taken by the respondents before
the arbitrator. Even in the objections filed in the court, the validity of the B
' award has not been specifically questioned on the ground of its having been
given in breach of any obligation of arbitrator to give reasons as spelled out
~
by the arbitration clause. The judgment of the learned single Judge does not
show such a plea having been urged before him. In the objection petition
there is a vague and general plea raised that rejecting the claims forming
subject matter of cross objection and allowing the claim of the appellant
c
without assigning any reason was bad. Such an omnibus and general plea
cannot be read as submitting that the amendment dated 4.9.1986 applied to
the contract between the parties and that in view of the amended arbitration
clause the unreasoned award was bad. It appears that the plea was for the
first time raised at the appellate stage before the Division Bench of the High D
Court. Unwittingly the Division Bench fell into the error of entertaining such
)
a plea and disposing of the appeal by upholding the same though the plea
was not even available to the respondents to be raised at that stage.
At the end, the learned counsel for the respondents made an alternative
submission that assuming the ground which prevailed with the Division
E
Bench for setting aside the award does not ttppeal to this court, then the
matter should be sent back to the Division Bench for dealing with such other
• obj.ections to the validity of the award as may be available to the respondents .
Reliance was placed on Food Corporation of India v. Jagdish Chandra
.... Saha, [ 1995) Suppl. 4 SCC 521. In the facts and circumstances of this case, F
< we are not inclined to accept that submission. The Judgment of the Division
Bench does not show any plea, other than the one on which the decision of
the Division Bench is based, having been taken before the Division Bench
yet not having been dealt with by the Division Bench as unnecessary in view
of its opinion formed on one of the pleas raised by 'he appellants. The learned
single Judge has noted in his judgment-"the entire arguments of the learned G
counsel were on the facts of the case. He has not pointed out any legal flaw
or error in the award of the arbitrator. Thus, there is no substance in the
objection raised". We do not also find any other plea deserving consideration
having been taken up either in the objection petition before the learned single
Judge or before the Division Bench which may call for a remand by this Court H
y
,_
....
874 SUPREME COURT REPORTS (2002) 3 S.C.R. i
t-
A for further hearing. ><:-
For the foregoing reasons, the appeal is a11owed. The judgment of the
Division Be~ch is set aside and the decision dated 20th October, 1999 by the
learned single Judge is restored.
B N.J. Appeal allowed.
F
!
r
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.