M/S. NOVA STEEL (INDIA) LTD.versusM.C.D. AND ORS.
- Citation
- 1995 INSC 11
- Decided
- 6 January 1995
- Disposal
- Dismissed
Holding
The respondents’ black‑listing order was not unwarranted or arbitrary, and the High Court was correct in declining to interfere; the Special Leave Petition is dismissed.
Summary
The petitioner, Nova Steel (India) Ltd., negotiated to supply 3,000 metric tonnes of tor steel to the respondents and received their acceptance. Despite the acceptance, the petitioner failed to execute the contract or commence supply. The respondents issued a show‑cause notice on March 19, 1993, and, after receiving no reply, debarred the petitioner from entering into any contract with them for two years. The petitioner challenged the debarment before the Delhi High Court, which refused to interfere, and then filed a Special Leave Petition before the Supreme Court. The Supreme Court held that the petitioner’s failure to perform justified the respondents’ black‑listing order, which was neither unwarranted nor arbitrary, and affirmed the High Court’s exercise of discretionary jurisdiction under Article 226. Consequently, the Special Leave Petition was dismissed.
Issues considered
- Whether the respondents’ order to blacklist and debar the petitioner for two years for non‑execution of a contract is unwarranted, arbitrary or illegal.
- Whether the High Court erred in refusing to interfere with the debarment order under its discretionary jurisdiction under Article 226 of the Constitution.
- Whether the Supreme Court should entertain the Special Leave Petition under Article 136 of the Constitution.
Subjects
Judgment
M/S. NOVA STEEL (INDIA) LTD. A
v.
~
M.C.D. AND ORS.
JANUARY 6, 1995
(K. RAMASWAMY AND N. VENKATACHALA, JJ,] B
Mercantile Law-Contract : Contract between parties-Non-execution
... of by party which agreed to supply certain materials-Show cause notice is-
sued-No reply-Therefore party deba"ed for two years-Whether unwar-
ranted or arbitrary-Held: No. c
The petitioner had negotiated and agreed to supply 3000 Metric
Tonnes of Tor Steel to the respondents, who had conveyed their accep-
tance, but the petitioner had not executed the contract. Therefore, the
petitioner was issued a show cause notice as to why it should not be
black-listed or debarred from having any dealings with the respondents. D
r Since the petitioner did not give any reply, it was debarred to enter into
contract for a period of two years. The petitioner challenged the said order
before the High Court, but was not successful. Bence this Special Leave
Petition.
Dismissing the petition, this Court E
HELD : The conduct of the petitioner constrained the respondents
to pass the order of black-listing. The exercise of the power, therefore,
cannot be said to be unwarranted nor arbitrary nor irrelevant. The High
Court, therefore, is right in declining to interfere with the offending order F
in exercise of its discretionary power under Article 226 of the Constitution.
There is no ground warranting interference under Article 136. [108-F]
CIVIL APPELLATE JURISDICTION: Special Leave Petition No.
22863 of 1994.
G
From the Judgment and Order dated 28.9.94 of the Delhi High Court
in C.W.P. No. 577 of 1994.
~'
S.C. Gupta and R.K. Sharma for the Petitioner.
The following Order of the Court was delivered : H
107
108 SUPREME COURT REPORTS (1995) 1 S.C.R.
A This special leave petition arises from the order of the Division
Bench of the High Court of Delhi dated September 28, 1994. Admittedly,
the petitioner had negotiated and agreed to supply 3000 MT of Tor Steel
to the respondents. Pursuant thereto, the respondents wrote a letter on
February 15, 1993 conveying their acceptance and requested the petitioner
to enter into the contract and also to start the supply of the steel immedi-
B ately. Admittedly, the petitioner had not executed the contract. Thereafter,
on March 19, 1993, the notice was issued to the petitioner to show cause
as to why he should not be black-listed or debarred from having any .-'t
dealings with the respondents. Even after the receipt of the notice, the
petitioner had not giyen any reply. Consequently, on April 19, 1993, the
c respm{dents had debarred the petitioner to enter into the contract for a
period of two years. The petitioner challenged the same in CWP No.
577/93. As stated earlier, the High Court refused to interfere with the
order .
. It is thus clear that the petitioner having negotiated with the respon-
D dent to supply the iron and received the acceptance in that behalf, he was
reqUired to enter into the contract and to start supply immediately, had
not done the same. Despite receipt of the notice of show cause, no reply
thereto was given .. The respondent necessarily has to take further action to
get the supply of the required steel. Therefore, they exercised the power
E and issued notice to the petitioner which would be consistent with the
principles of natural justice and passed the offending order black-listing
the petitioner for a period of two years. The conduct of the petitioner
constrained the respondents to pass the order of black-li._sting. The exercise
of the power, therefore, cannot be said to be unwarranted nor arbitrary
nor irrelevant. The High Court, therefore, is right in declining to interfere
F with the offending order in exercise of its discretionary power under
Article 226 of the Constitution. We, therefore, find no ground warranting
interference under Article 136. The S.L.P. is accordingly dismissed.
G.N. Petitioner dismissed.
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.