Created byFuzzy Cloud

Supreme Court of India

M/S O.N.G.C. LTD.versusASSN. OF NATURAL GAS CONSUMING INDUSTRIES AND ORS.

Citation
2004 INSC 247
Decided
12 April 2004
Disposal
IA disposed

Holding

ONGC must recompute the arrears, consider the raised points, and pay interest at the simple rate stipulated in Clause 5, not compoundable.

Summary

The Supreme Court examined applications filed by two drug‑manufacturing companies, Sarabhai Common Services and Alembic Chemicals Ltd, challenging the manner in which ONGC Ltd calculated arrears of gas price differentials and claimed interest. The Court found that ONGC had not properly considered the applicants' demands, including adjustments for payments already made, exclusion of royalty and sales tax on short‑lifted gas, a request to reduce the contracted quantity, and the applicability of the force‑majeure clause. Regarding interest, the Court held that, although the contract’s Clause 5 provides for interest, it must be at the simple rate specified, not compoundable, given the impact of the Court‑ordered price increase on the drug‑price control regime. ONGC was directed to recompute the arrears, incorporate the applicants’ points, and reduce its claim accordingly. The applications were disposed of with these directions.

Issues considered

  • Whether ONGC duly considered the applicants' contentions while computing arrears of the differential gas price.
  • Whether interest on the differential amount should be payable at a simple rate or compoundable rate under Clause 5 of the contract.
  • Whether royalty and sales tax should be excluded from the calculation of damages for short‑liftment.
  • Whether the applicants' request to reduce the contracted gas quantity from 60,000 m³/day to 50,000 m³/day should be taken into account.
  • Whether the force‑majeure clause applies to the strike and furnace‑collapse period, affecting the billing on actual usage.

Subjects

natural gasprice fixationinterest calculationshort liftmentroyaltysales taxforce majeurecontract clause 5simple interestdrug price control

Judgment

                                 MIS O.N.G.C. LTD.                                    A
                                         v
       ASSN. OF NATURAL GAS CONSUMING INDUSTRIES AND ORS.

                                  APRIL 12, 2004

                 (S. RAJENDRA BABU, DR. AR. LAKSHMANAN                                B
                           AND G.P. MA THUR, JJ.]


            Natural gas-Price fixation by ONGC-Upheld by Court-Interest on
     differential amount-Two drug manufacturing companies disputing calculation       C
     of arrears ofprincipal amount-Held, demands made by applicants have not
     been considered effectively by ONGC-Interest to be paid by them would be
     payable at stipulated rate but at simple rate ofinterest and not compoundable-
<~   ONGC shall also examine the other points raised by applicants-Interest.

           Appellant-ONGC increased the price of gas which gave rise to a D
     number of writ petitions before the High Court. Pending ,litigation, gas
     price was regulated by interim orders of the High Court and the Supreme
     Court. Ultimately, the price fixed by ONGC was upheld by the Supreme
     Court. As regards the claim of ONGC for interest on the late payment of
     differential amount, the Court held that interest would be paid at the rate
     and manner specified in the contract. However, it was made clear that E
     the case of the two drug manufacturing companies, namely, 'SCS' and
     'AL' would be dealt with separately. The two companies filed the present
     IAs. disputing the demands raised by the ONGC.

+          It was contended for the applicants that the ONGC while calculating
     the arrears of principal amount applied a higher rate of price contrary          F
     to the decision of the Court. It was contended for applicant 'AL' that
     arrears derived on account of short liftment were calculated by ONGC
     using rate for actual supply which included the sales tax and royalty on
     short-lifted quantity; that ONGC failed to consider their request for
     reduction of contracted quantity from 60,000 cubic meters to 50,000 cubic        G
     meters per day, therefore, ONGC should recompute the demand in this
     regard, and that as per the force majeure clause in the contract, ONGC
     was required to bill on actual usage quantity during the period of strike
     and furnace collapse.

                                                                                      H
    2                         SUPREME COURT REPORTS (2004] SUPP. I S.C.R.

A         Disposing of the I.As, the Court

          HELD: 1. In neither of the cases has ONGC considered the demands
    made by the applicants effectively, and determined the amount of arrears
    due from them without making appropriate adjustments for the money
    paid by them. The representations made by both these companies have
                                                                                      •
B   been dealt with in usual bureaucratic style without due consideration to
    the points raised. The points raised by them both in regard to the payment
    of interest and in rega'rd to other aspects are of substantial nature and
    cannot be brushed aside but need to be considered by ONGC
    appropriately. (5-C-E]
c         2. So far as interest is concerned, though this Court stated in the
    order made on 26.7.2001, that interest is payable in terms of clause 5 of
    the contract but that was in the normal circumstances arising in the case.        ..
    The two applicants are drug manufacturing companies and prices at which
    they sell their goods are fixed by the Drug Price Control Orders, which                ..,
D   had taken into consideration the price at which the gas was supplied, which             }

    now gets enhanced by reason of the orders of this Court. Therefore, in
    the totality of the circumstances, interest shall be payable by these two
    companies at the rate as stipulated in clause 5 of the contract but at simple
    rate of interest and not compoundable. ONGC would reduce their claim
    to that extent in the demands made by them. (5-E-H]
E
         3. In case of 'AL', ONGC shall also examine the points raised as
    regards (i) the exclusion of the royalty and sales tax on the damages for
    short liftment; (ii) the effect of their letter seeking for reductfon of supply
    from 60,000 cubic meters to 50,000 cubic meters per day; and (iii) claim
    made on the basis of force majeure clause; an~ thereafter redetermine the
F
    arrears payable by them along with interest. [6-A]

         CIVIL APPELLATE JURISDICTION : I.A. Nos. 355-365 of 2002.

                                          IN
G                                I.A. Nos. 190-200.

                                          IN
                                                                                      ..
                       Civil Appeal, Nos. 8530-40 of 1983.

H        From the Judgment and Order dated 30.7.83 of the Gujarat High Court.
          O.N.G.C. LTD.'"· ASSN. OF NATIJRAL GAS CONSUMING INDUS. [RAJENDRA BABU,J.]   3
     in S.C.A. Nos. 883, 913/79, 1897/81, 2316, 2384, 2445, 2470, 2977, 4194,              A
     4520, and 2542 of 1982.

          With I.A. Nos. 333-343/2002 in I.A. Nos. 190-200 in C.A. Nos. 8530-
     40 of 1983.
~
           Raju Ramachandran, Additional Solicitor General, Mahendra Anand,                B
     A.K. Ganguli, R.F. Nariman, P.Krishnamurthy, Collin Gonsalvas, Rajan
     Narain, Ms. Puja Sharma, Siddharth Datta, Ms Louleen Bhullar, K.R.
     Sasiprabhu, Shahid Rizvi, Manish Garg, Ms. G. Indira, M.K.S. Menon, Rakesh
     K. Sharma, Ms. Manik Karanjawala, Arnn K. Sharma, Ms. Vandana Sharma,
     V. Pal Singh, Ms. Pratibha Jain, Sushil Kumar Jain, Vinay Garg, Shri Narain,
     Sandeep Narain, Ms. Anjali Jha, Ms. B. Vijayalakshmi Menon, A. Deb Kumar,
                                                                                           c
     Sudarsh Menon, B.S. Sharma, K.V. Mohan, P.H. Parekh, Ms. Ranjeeta
     Rohatgi, Pramod B. Agarwala, Ms. Apama Bhat and Ms. P. Ramesh Kumar
     for the appearing parties.

          The Judgment of the Court was delivered by                                       D
            RAJENDRA BABU, J. A batch of writ petitions was filed in the High
     Court of Gujarat challenging the increase in the price of gas and by an
     interim order, the High Court directed ONGC to supply gas at the old rate
     ofRs.504/- per 1000 M3. Subsequently, by another order made on 29.10.1982,
     the price was raised to Rs. 1000 per 1000 M3. By an order made on 30.7.1983,          E
     the High Court allowed the writ petitions and set aside the price which had
     been determined by ONGC. Pursuant to a certificate of fitness, appeals were
     filed in this Court and this C~urt continued the interim order granted by the

,    High Court and thereby the respondents in the appeals received gas for which
     they paid a price of Rs. 1000 per 1000 M3.
                                                                                           F
            This Court, on 4.5.1990, by judgment upheld the prices fixed by ONGC
     and allowed the appeals. After the appeals were allowed, ONGC became
     entitled to receive the difference in the price of gas supplied. ONGC, in
     addition to the said principal amount, also demanded interest thereon in
     terms of Clause 5.02 of the contract. When payment was not made in
                                                                                           G
     accordance with their demands, I.A. Nos.l-1 l and 23-33 were filed lin this
     Court and this Court, by an order made on 6.4.1993, passed the orders for
     categorising the respondents into three categories. The first category being
-4   where the principal amount was allowed to be paid in instalments. Where
     such offer was not made, this Court made it clear that ONGC was entitled to
     recover the entire dues. The third category is of such cases where the                H
    4                        SUPREME COURT REPORTS [2004] SUPP. 1 S.C.R.

A   companies concerned have become sick and proceedings were pending before
    BIFR under the SICA. Subsequently, it was directed that these IAs will
    remain pending and would be listed for hearing for directions regarding
    payment of interest after the principal amount is paid. But in some of the
    cases, there is no dispute that the payment of principal amount has been
    made in terms of this Court's order.
B
          Thereafter, applications in I.A.Nos. 190-200 were filed by ONGC
    claiming inerest on the balance principal amount in terms of this Court's
    order dated 4.5.1990. This Court, after examining the matter, held as under:

           " ......... ONGC was under an obligation by virtue of the interim orders
c          to comply with the terms of the earlier contracts and to supply gas in
           the manner· provided thereunder. This part of the contract was
           performed by the ONGC who thus became entitled to ·recover from
           the industries the price which had originally been charged by them.
           For the late payment of the amount, the contract in clause 5 had
D          contemplated payment of interest at the rate and the manner specified
           therein ......... "

          However, it was made clear therein that the cases of Sarabhai Common
    Services and Alembic Chemicals Ltd. [now known as 'Alembic Ltd.'] will be
    dealt with separately and now these applications have come up for
E   consideration. ·

          There is a serious dispute between ONGC and the applicants as regards
   the demands raised by ONGC. It is contended that the ONGC while calculating
   the arrears of principal amount has applied for a higher price contrary to the         ~· (
   decision of this Court and hence the arrears of principal amount had to be
F recalculated by applying the correct rate/price in accordance with the order
   of this Court; that the arrears claimed on account of short-liftment have been
   calculated by ONGC · using the rates for actual supply which include the
   element of sales tax' and royalty on the short-lifted quantities; thatthe money
   payable for short!liftment of gas less than the minimum quantity of gas
G agreed to be purchased is neither delivered nor supplied and hence cannot be
   treated as sale and in such a case neither royalty nor tax_ is leviable and,
   therefore, they contend that the statement of arrears which cont~ined the
  ·element of royalty and sales tax will have to be recalculated by excluding the
   same; that they had made a request by a letter dated 24.6.1985 for reduction       ~
   in the contracted quantity from 60000 cubic meters per day to 50,000 cubic .
H meters per day; that since the matter was sub-judice before this Court, the
              O.N.G.C. LTD.'" ASSN. OF NATIJRAL GAS CONSUMING INDUS. [RAJENDRA BABU, J.)   5
        change in the contracted quantity could not be done. Therefore, they claim             A
        that this aspect has to be considered now that the matters have been dispo~ed
        of by ONGC and thereafter to re-compute the demands. In addition, it is also
        contended that the contract provides for force majeure and strike by workmen
        and furnace collapse are covered by this clause and ONGC is required to bill
        on actual usage quantity during the period of strike arld furance collapse.
        Again on the plea that the matter was pendint before /his Court, this aspect           B
        was not examined by ONGC. In these circumstances, it is submitted that the
        applicant is entitled to relief.

              A similar application has also been made by Mis Sarabhai Common
        Services contending that the interest payable by them on the amounts due               C
        will have to be taken note of and. there have been representations made by
        both M/s Sarabhai Common Services and also by Alembic Ltd. However, in
        neither of the cases has ONGC considered the demands made by them
    >   effectively and thereafter determined the amount of arrears due from them
        without making apropriate adjustments for the money paid by them pursuant
        to the orders of the Court or further claims arising therefrom. The                    D
        representations made by both these companies have been dealt with in usua:l
        bureaucratic style without due consideration to the points raised. We find that
        the points raised by them both in regard to the payment of interest and in
        regard to other aspects are of substantial nature and cannot be brushed aside
        as has been done now but needs to be considered by ONGC appropriately.                 E
               So far as interest is concerned, though this Court stated in the order
        made on 26. 7.200 I, that interest is payable in terms of clause 5 of the contra~t
        as contract continued to be in force till the matters were finally disposed of
)        by this Court, but that was in the normal circumstances arising in this c :ise.
         We may notice that these two cases where Sarabhai Common Services and                 F
        Alembic Chemicals Ltd. [now known as 'Alembic Ltd.'] are drug
        manufacturing companies and prices at which they sell their g~ods are fixed
        by the Drug Price Control Order, which had taken into consideration the
        price at which the gas was supplied, which now gets enhanced by reason of
        the orders of this Court.
                                                                                               G
              Th~refore, in the totality of the circumstances, we think, interest shall
        be payable by these two companies at the rate as stipulated in clause 5 of the
        contract but not compoundable but simple rate of interest. To that extent, we
        allow the applications filed by Sarabhai Common Services and direct ONGC
        to reduce their claim to th extent in the demands made by them. In case of             H
    6                          SUPREME COURT REPORTS [2004] SUPP. I S.C.R.

A   Mis Alembic Ltd. ONGC shall examine other points raised by them as regards:
    (i) the exclusion of the royalty and sales tax on the damages for shortliftment;
    (ii) the' effect of their letter seeking for reduction of supply from .60000 cubic
    meters per day to 50,000 cubic meters per day; and (iii) claim made on the
    basis of force majeure clause and thereafter redetermine the arrears payable
B   by them along with interest.

          The applications accordingly stand disposed of in terms of the aforesaid
    directions.

    R.P.                                                          I.As. disposed of.


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "natural gas"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.