M/S. R. K. INDUSTRIES (UNIT-II) LLPversusS.C/S.T SHIPBREAKERS ASSOCIATION & ORS.
- Citation
- 2019 INSC 768
- Decided
- 16 July 2019
- Disposal
- Appeal(s) allowed
- Bench
- R F NARIMAN
Holding
Clause 5.4's reservation requirement applies only to the plots that are sought to be auctioned, not to the total number of plots.
Summary
The Gujarat Maritime Board issued a tender to auction eight vacant ship‑recycling plots, reserving four for ST and two for SC candidates. The SC/ST Shipbreakers Association challenged the reservation, arguing that the 2015 Regulations required reservation to be calculated on the total number of plots (20) rather than the eight being auctioned. The High Court agreed with the challengers and quashed the tender, directing reservation on the basis of total plots. On appeal, the Supreme Court examined clause 5.4 of the 2015 Regulations in the context of clauses 5.1 and 5.2, which deal only with plots to be auctioned. It held that "the plots" in clause 5.4 refers solely to the plots slated for auction, so reservation must be applied to those eight plots only. Consequently, the High Court's judgment was set aside and the appeal was allowed, leaving the reservation for the eight plots intact and directing future auctions to follow this interpretation.
Issues considered
- Whether clause 5.4 of the Gujarat Maritime Board Ship Recycling Regulations, 2015 mandates reservation of plots for SC/ST on the basis of total plots or only the plots being auctioned.
- How the expression "the plots" in clause 5.4 should be interpreted in light of clauses 5.1 and 5.2.
- Whether the High Court's interpretation and consequent quashing of the tender were legally correct.
Subjects
Judgment
[2019] 10 S.C.R. 295 295
M/S. R. K. INDUSTRIES (UNIT-II) LLP A
v.
S.C/S.T SHIPBREAKERS ASSOCIATION & ORS.
(Civil Appeal No.5609 of 2019)
JULY 16, 2019 B
[R.F. NARIMAN, SANJIV KHANNA AND SURYA KANT, JJ.]
Gujarat Maritime Board (Conditions and Procedures for
Granting Permission for Utilizing Ship Recycling Plots) Ship
Recycling Regulations, 2015:
C
Clause 5.4 – Allocation of plots for reserved categories –
Whether reservation to be given out of the total plots or only out of
the plots that were sought to be auctioned – Held: If clause 5.4 is
interpreted keeping in view the context of Clauses 5.1 and 5.2, the
expression “the plots” contained in clause 5.4 has reference only
D
to plots that are sought to be auctioned – Therefore, reservation is
to take place out of the plots sought to be auctioned and not out of
the total plots.
Allowing the appeal, the Court
HELD: 1. The marginal note of clause 5.4 of the Gujarat E
Maritime Board (Conditions and Procedures for Granting
Permission for Utilizing Ship Recycling Plots) Ship Recycling
Regulations, 2015 indicates the drift of the provision as
“Allocation for the reserved categories”. If one would ask the
question as to what is to be allocated, the answer is to be found in
clause 5.1 and 5.2. What is to be allocated, therefore, is only F
plots which are newly developed; plots which are already vacant;
and plots which have fallen vacant on account of cancellation/
termination of the permission. Clause 5.2 is even more explicit
in its language. In that it states “All such plots” are to be
auctioned. Once clause 5.4 is interpreted keeping in view the G
context of clauses 5.1 and 5.2, it is obvious that the expression
“the plots” contained in clause 5.4 has reference only to plots
that are to be auctioned, which are mentioned in clauses 5.1 and
5.2. Once this is so, the expression “plots” must take colour
H
295
296 SUPREME COURT REPORTS [2019] 10 S.C.R.
A from the context in which it is placed. Indeed, the definition
clause is itself expressly subject to context to the contrary.
Therefore, the opinion of the High Court that reservation is to
take place only out of the total plots and not the plots to be
auctioned, cannot be agreed to. [Paras 16, 17 and 18] [302-D-G]
B 2. In the case of reservation of vacant plots of a smaller
number that are put to auction, it is for the Board to work the
reservation policy contained in the 2015 Regulations in a non-
arbitrary fashion, giving effect to reservation. The judgment of
the High Court is set aside. However, it is made clear that there
being no challenge by any General candidate to the reservation
C made out of the eight plots of six plots in favour of SC and ST
candidates, this reservation will continue only for the purpose of
the auction of eight plots. All future tenders/auctions will abide
by the interpretation given in this judgment. [Para 18][303-A-B]
CIVIL APPELLATE JURISDICTION: Civil Appeal No.5609 of
D 2019
From the Judgment and Order dated 16.04.2018 of the High Court
of Gujarat at Ahmedabad in Special Civil Application No. 5509 of 2017
Shekhar Naphade, Sr. Adv., Kunal Cheema, Ms. Aditi Parkhi,
E Abhikalp P. Singh, Ms. Laxmi S. Iyer, Advs. for the Appellant.
Tushar Mehta, SG, Anupam Lal Das, Sr. Adv., Rajendra Singhvi,
K. K. L. Gautam, Ms. Arundhati Chakraborty, Sanjeev Malhotra,
Gursharan Virk, Nakul Mohta, Ms. Misha Rohatgi, Lalit Mohan, Apoorv
Shukla, Anirudh Singh, Krishanu Barua, Ms. Prabhleen Kaur, Advs. for
F the Respondents.
The Judgment of the Court was delivered by
R. F. NARIMAN, J. 1. Leave granted.
2. The challenge in the instant appeal is by a person who was not
a party before the High Court. The reason why we have heard Mr.
G Shekhar Naphade, learned senior counsel appearing on behalf of the
appellant, and why we have given his client leave to appeal, is only to set
right the interpretation to The Gujarat Maritime Board (Conditions &
Procedures for granting permission for Utilizing Ship Recycling Plots)
H
M/S. R.K. INDUSTRIES (UNIT-II) LLP v. S.C/S.T 297
SHIPBREAKERS ASSOCIATION & ORS. [R.F. NARIMAN, J.]
Ship Recycling Regulations, 2015 (hereinafter referred to as ‘2015 A
Regulations’ for brevity).
3. The skeletal facts necessary to decide this case are as follows:
4. In February, 2017, the Gujarat Maritime Board issued a tender
for auction of eight vacant plots at Alang-Sosiya Ship Recycling Yard,
District Bhavnagar, for the reasons best known to it, as it chose to do so B
despite the fact that on this date, 20 vacant plots were available for
auction. Considering the 2015 Regulations supra, the Gujarat Maritime
Board decided that out of these plots, four should be reserved for ST
category, two for SC category and two would go to the General category.
Respondent Nos. 1, 2 and 3 before us, viz. the S.C./S.T. Shipbreakers C
Association, filed Special Civil Application No. 5509 of 2017 before the
High Court of Gujarat at Ahmedabad on 14.03.2017 in which it challenged
the allocation of plots to SC and ST candidates stating that the Regulations,
if properly read, would necessarily mean that the reservation of 14 per
cent and 7 per cent for ST category and SC category respectively, should
be of the total number of plots that are available and not merely those D
that are sought to be auctioned. If this were to be so, then all the eight
plots would have to be reserved for SC and ST candidates inasmuch as
the total reservation quota as a percentage of the total number of plots
had not been reached. On 22.04.2017, the tender notice issued by the
Gujarat Maritime Board was stayed by the High Court, and by the E
impugned judgment dated 16.04.2018, the High Court held that not only
would all the eight plots that were subject matter of the auction notice be
reserved for the ST and SC candidates but that, even for the remaining
number, i.e., if 20 plots were to be taken as a block, all 20 would have to
be reserved for ST and SC candidates inasmuch as the quota for these
candidates, going by the percentage of total plots, had not been reached. F
In this view of the matter, the High Court quashed the tender notice and
directed the Gujarat Maritime Board as follows:
“12. In view of the above and for the reasons stated above, Special
Civil Application No. 5509 of 2017 is allowed. It is held and
directed that respondent GMB shall make reservation of 7% plots G
belonging to SC Category and 14% of plots to ST Category out of
/considering the Total Plots and not Vacant Plots as on today (as
contended on behalf of the GMB). The respondent GMB is also
H
298 SUPREME COURT REPORTS [2019] 10 S.C.R.
A directed to simultaneously hold the auction of all the vacant plots
and apply the reservation as directed herein above i.e., including
all the vacant plots bigger size plots and / or smaller size plots.
Consequently, the impugned tender at Annexure F (collectively)
issued by the respondent no. 2 in February 2018 for 8 plots at
Alang-Sosiya Ship Recycling Yards is hereby quashed and set
B
aside and the respondent GMB is directed to invite fresh tenders/
bids in light of the present judgment and order. The said exercise
shall be completed at the earliest but not later than six months
from today. Rule is made absolute to the aforesaid extent. No
costs.”
C 5. Shri Shekhar Naphade, learned senior counsel appearing on
behalf of the appellant herein, has attempted to argue his peculiar facts
before us in which he sought to challenge the fact that the plot licensed
to him has itself been set up for auction, together with the fact that since
he wishes to amalgamate with the neighbouring plot, this amalgamation
D would become impossible if all vacant plots were to be reserved for ST
and SC categories, as was required by the impugned judgment. We
may state that we are not going into the individual facts of Shri Naphade’s
client’s case. Suffice it is to state that we are granting his client a
limited permission to file a special leave petition against the impugned
judgment challenging its correctness. It will be open for him, in separate
E proceedings, to challenge action taken against his client by the Gujarat
Maritime Board up to date, including action taken by the Maritime Board
pursuant to our judgment. All contentions in this behalf are left open
both to his client as well as to the Gujarat Maritime Board.
6. Shri Naphade has assailed the High Court’s interpretation of
F the 2015 Regulations by painstakingly taking us though the history of
various regulations, pointing out the difference between the earlier
regulations and the present Regulation, and ultimately pointing out that
clause 5.4 of the 2015 Regulations must be read as an adjunct to clauses
5.1 and 5.2. As a result of this, clause 5.4 cannot be read torn out of
G context along with the definition of “plot” contained in the Regulations
so as to arrive at the result arrived at by the High Court. In his submission,
therefore, having regard to the fact that the earlier Regulation of 2006
specifically spoke of reservation “out of total plots” which language is
missing from the current Regulation, it is clear that the context of the
H
M/S. R.K. INDUSTRIES (UNIT-II) LLP v. S.C/S.T 299
SHIPBREAKERS ASSOCIATION & ORS. [R.F. NARIMAN, J.]
current Regulation requires reservation only of the plots that are sought A
to be auctioned.
7. To this, Shri Gursharan Virk, learned counsel appearing for the
Gujarat Maritime Board, argued that the issue today is really academic
inasmuch as Shri Naphade’s client should not be allowed permission to
file the special leave petition at all. The Board has since taken a decision B
to follow the Gujarat High Court’s judgment. He also argued before us
that if the Gujarat High Court’s judgment were not followed, incongruous
results might follow. He gave us an example, by which, assuming that
only three plots were vacant and were auctioned, it would be impossible
to work out a reservation of 14 per cent and 7 per cent of these three
plots. So, obviously, what is meant by reservation is reservation only out C
of the total plots. Even otherwise, according to him, the appellant ought
not to be granted any relief given the fact that he has woken only at this
late stage.
8. We have also heard Mr. Rajendra Singhvi, learned counsel
appearing for respondent Nos. 1-3, who has argued that the tender notice D
of February, 2017, could be said to fall between two stools. It could only
be upheld if, according to him, the High Court’s judgment were right,
because it is only if reservation is taken of total plots – six out of eight
plots would be reserved. If the contrary construction is adopted, it is
obvious that, at best, perhaps, one plot could be reserved. The Gujarat E
Maritime Board, therefore, though it ought to have reserved all eight,
has really followed the principle of reservation from out of total number
of plots, which is the correct principle to be followed in the facts of this
case.
9. Having heard learned counsel for all the parties, we may F
first go to The Gujarat Maritime Board (Conditions and Procedure for
granting permission for Utilising Shipbreaking Plots) Regulations, 1994
(hereinafter referred to as 1994 Regulations’ for brevity). In these
Regulations, paragraph 9 laid down reservation for ST and SC candidates
as follows:
G
“9. Out of plots which were vacant as on 3rd August, 1992 or fell
vacant thereafter, or any new plot which is developed thereafter
7 per cent of these plots shall be reserved for granting permission
to Co-operative Societies all of whose members belong to
H
300 SUPREME COURT REPORTS [2019] 10 S.C.R.
A Scheduled Castes, and 14% plots shall be reserved for Co-
operative Societies all of whose members belong to Scheduled
Tribes. All the terms and conditions specified in the Government
of Gujarat, Roads & Buildings Department Vernaculars Resolution
No. 2 LPW-1290-25435-GH dated 3rd August, 1992 shall be treated
as forming part of these Regulations ——————— Scheduled
B
Caste/ Scheduled Tribe applicants included in the list from category
—— in Regulation 4, shall be permitted to utilize plots on reservation
basis on fulfillment of ——— terms and conditions specified in
those Regulations and in the Schedule hereto and thereafter, —
——— other applicants of SC/ST categories, permission for
C utilizing the plots shall be granted on tender-cum-auction basis.”
10. A perusal of paragraph 9 of the 1994 Regulations would show
that reservations were to be based only on three categories of plots viz.,
those that were vacant on 03.08.1992; or those that fell vacant thereafter;
or any new plot which is developed thereafter. A reading of these
D Regulations would show, therefore, that reservation at this juncture, was
not from out of the total number of plots but only of the three categories
mentioned hereinabove.
11. The 1994 Regulations were supplanted by the Gujarat Maritime
Board (Conditions and Procedures for granting permission for Utilising
E Shipbreaking Plots) Regulations, 2006 (hereinafter referred to as ‘2006
Regulations’ for brevity) by clause 9 by which reservations for plots
were made as follows:
“9. Out of total plots 7 per cent of these plots shall be reserved for
granting permission to Co-operative Societies of all of whose
F members belong to Scheduled Castes, and 14% plots shall be
reserved for Co-operative Societies of all of whose members
belong to Scheduled Tribes. All the terms and conditions specified
in the Government of Gujarat, Roads & Buildings Department
Vernacular Resolution No. LPW-1290-25435-GH dated 3rd August,
1992 and Government of Gujarat, Port & Fisheries Department
G Resolution No. WKS-1099-CM, MLA 82 (17) GH dated 4/1/2000
shall be treated as forming part of these Regulations.
Explanation for the purpose of these Regulations before calculating
7% for the Co-operative Societies belonging to the members of
H
M/S. R.K. INDUSTRIES (UNIT-II) LLP v. S.C/S.T 301
SHIPBREAKERS ASSOCIATION & ORS. [R.F. NARIMAN, J.]
Scheduled Caste and 14% for the Cooperative Societies belonging A
to the members of Scheduled Tribe categories, the Chief Executive
Officer & Vice Chairman shall reserve 10 plots for granting
permission for ship recycling activities on ship to ship basis as
provided in Regulation herein above.”
12. The scheme of these Regulations would clearly show that B
there has been a vital change in the reservation policy insofar as vacant
plots to be auctioned are concerned. The vital change is contained in
the opening words of clause 9 which states “’Out of total
plots’………………………………….”
13. This situation obtained until the present 2015 Regulations were C
enacted, substituting the 2006 Regulations. By these Regulations, a new
Chapter 5 was inserted. What is relevant for our purpose are paragraphs
5.1 to 5.4 which read as under:
“5.1 The Chief Executive Officer may grant permission to use
plots for ship recycling in respect of- D
a. a plot which is newly developed
b. a plot which his vacant
c. a plot which has fallen vacant on account of cancellation/
termination of the permission.
E
5.2 Procedure : All such plots, shall be offered for use for ship
recycling after following the procedure of Tender-cum-
Auction.
5.3 Tender-cum-Auction:
The upset price for tender cum auction will be Rs.540/- per F
sqm per year. The terms and conditions of the tender
document shall be fixed by the Board.
5.4 Allocation for the Reserved Categories:
7% and 14% of the plots shall be reserved for Scheduled G
Castes and Scheduled Tribes respectively for granting
permission for utilization of ship recycling plots.”
14. The bone of contention between the parties is, what is the
meaning of the expression “the plots” contained in paragraph 5.4. The
H
302 SUPREME COURT REPORTS [2019] 10 S.C.R.
A High Court has held that “the plots” must be read with the definition of
“plot” contained in the Regulations, which is contained in paragraph 15
as follows:
15.“Plot” means piece of land adjacent to waterfront or otherwise
earmarked by the Board for the purpose of ship recycling having
B dimensions specified in the permission letter. This shall include
existing plot or plots that may be developed in future within the
ship recycling yard under the Gujarat Maritime Board.”
15. If this interpretation is to be accorded, then the High Court is
right in stating that the expression “the plots” would include total plots
C and not merely plots to be auctioned.
16. It is important to first notice the context of paragraph 5.4 of
the 2015 Regulations. The marginal note of clause 5.4 indicates the drift
of the provision as follows:
“Allocation for the reserved categories”.
D
17. If one would ask oneself the question as to what is to be
allocated, the answer is to be found in clause 5.1 and 5.2. What is to be
allocated, therefore, is only plots which are newly developed; plots which
are already vacant; and plots which have fallen vacant on account of
cancellation/termination of the permission. Clause 5.2 is even more
E explicit in its language. In that it states “All such plots” are to be auctioned.
Once clause 5.4 is interpreted keeping in view the context of clauses 5.1
and 5.2, it is obvious that the expression “the plots” contained in clause
5.4 has reference only to plots that are to be auctioned, which are
mentioned in clauses 5.1 and 5.2. Once this is so, the expression “plots”
F must take colour from the context in which it is placed. Indeed, the
definition clause is itself expressly subject to context to the contrary.
18. This being the case, it is a little difficult to agree with the High
Court that reservation is to take place only out of the total plots and not
the plots to be auctioned. In point of fact, the 2015 Regulations are an
express departure from the earlier Regulations of 2006, which, in turn,
G
were a departure from the earlier Regulations of 1994. The argument
of Mr. Virk that if only three vacant plots were to be auctioned, reservation
of 21% of this figure would be impossible is an argument which flies in
the face of the express language of the 2015 Regulations, coupled with
the fact that the preceding 2006 Regulations, which had the words “Out
H
M/S. R.K. INDUSTRIES (UNIT-II) LLP v. S.C/S.T 303
SHIPBREAKERS ASSOCIATION & ORS. [R.F. NARIMAN, J.]
of the total plots…….” is missing in the 2015 Regulations. In the case A
of reservation of vacant plots of a smaller number that are put to auction,
it is for the Board to work the reservation policy contained in the 2015
Regulations in a non-arbitrary fashion, giving effect to reservation as
authored by us hereinabove. This being so, we set aside the judgment of
the High Court. However, it is made clear that there being no challenge
B
by any General candidate to the reservation made out of the eight plots
of six plots in favour of SC and ST candidates, this reservation will
continue only for the purpose of the auction of eight plots. All future
tenders/auctions will abide by the interpretation given by us in our judgment
today.
19. With these observations the appeal is allowed. C
20. The protection granted by our order dated 29.03.2019 will
continue for a period of four weeks. The appellant, as has been stated
hereinabove, is free to adopt whatever proceedings is available to him in
law. Any challenge made by the appellant in proceedings hereafter
would be heard on its own merits. All the contentions therein are open D
to the appellant as well as the Gujarat Maritime Board.
Kalpana K. Tripathy Appeal allowed.
E
F
G
H
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.