Created byFuzzy Cloud

Supreme Court of India

M/S SAM BUILT WELL PVT. LTD.versusDEEPAK BUILDERS & ORS.

Citation
2017 INSC 1232
Decided
14 December 2017
Disposal
Appeal(s) allowed

Holding

In the absence of malafides or perversity, courts must not interfere with the technical evaluation of tenders, and the Single Judge's reliance on expert committee reports was correct.

Summary

The dispute concerned a notice inviting tenders (NIT) for constructing an educational campus, which required bidders to have completed similar large‑scale projects. Respondent No. I was found ineligible by three expert committees, a finding upheld by the Single Judge of the High Court. The Division Bench, however, set aside that judgment, held that Respondent No. I was eligible and directed the award of the contract to it. On appeal, the Supreme Court examined whether the court could intervene in the technical evaluation of tenders absent any malafides or perversity. Relying on precedents, the Court held that judicial review in tender matters is limited and courts must defer to the technical expertise of the evaluating committees. Consequently, the Division Bench had exceeded its jurisdiction, the Single Judge’s decision was affirmed, and the award of the tender was restored to the appellant, who is willing to match the lower bid.

Issues considered

  • Whether the High Court Division Bench erred in setting aside the Single Judge's decision on the eligibility of Respondent No. I in a tender process.
  • Whether courts may interfere with technical evaluation of tenders when no malafides or perversity is evident.
  • Whether the principle of judicial restraint applies to the appraisal of expert committee reports in tender evaluations.

Subjects

tendereligibility criteriatechnical evaluationjudicial reviewjudicial restraintexpert committeecontract awardadministrative law

Judgment

                         [2017] 14 S.C.R. 479


                M/S SAM BUILT WELL PVT. LTD.                               A
                                  v.
                   DEEPAK BUILDERS & ORS.
                  (Civi!Appea!No. 21858of2017)
                        DECEMBER 14, 2017                                  B

           [R. F. NARIMAN AND NAVIN SINHA, JJ.]
        Contract - Tender - In the instant case, the NIT invited bids
from contractors who had engaged in construction of educational
 buildings - The technical evaluation report stated that the eligibility
criteria contained in NIT was not met by respondent no. I - The
                                                                           c
other two expert bodies also reiterated the ineligibility of respondent
 no. I - Respondent no. I filed writ petition which was dismissed by
 the single judge of High Court - However. Division Bench of High
 Court allowed the appeal of respondent no. I holding that there
 was no malafides in the instant case and respondent no.I was              D
 eligible qnd directing the respondent no.2 to consider the case of
 respondent no. I along with other eligible bids - Ultimately, award
 was given to respondent no.I since it quoted amount less than that
 of appellant - On appeal, held: The three expert committees
 scrutinized the tender of respondent no.I and found him ineligible        E
- The impugned judgment of the Division Bench of the High Court
 expressly stated that no malafides were involved in the instant case
 - Equally, while setting aside the judgment of the single judge. the
 Division Bench did not state that the three expert committees have
 arrived at a perverse conclusion - In tender matters, s'cope of
judicial review is limited - Not having found malafides or perversity      F
 in the technical· expert reports. any appreciation by the Court itself
 of technical evaluation, best left to technical experts, would be
 outside its ken - As a result. the single judge was correct in placing
 reliance on the three expert committee reports - The Division Bench.
 in setting aside the said judgment. has clearly gone outside the          G
 bounds ofjudicial review - Award of tender to the appellant is.
 restored as it is willing to match the offer of respondent no.I -
 Administrative law - Judicial review.


                                                                           H
                                  479
480           SUPREME COURT REPORTS                     [2017] 14 S.C.R.


A           Allowing the appeal, the Court
        HELD: 1. Not having found malafides or perversity in the
  technical expert reports, the principle of judicial restraint kicks
  in, and any appreciation by the Court itself of technical evaluation,
  best left to technical experts, would be outside its ken. As a
B result, the Single Judge was correct in his reliance on the three
  expert committee reports. The Division Bench, in setting aside
  the said judgment, has clearly gone outside the bounds of judicial
  review. [Para 1111486-E-F)
        2. The appellant, has stated that the appellant is willing to
C match the offer of Respondent No.1. The said statement is
  recorded and it is ordered that the tender awarded to Respondent
  No.1 based upon the Division Bench judgment, must be set aside,
  and the award of the tender to the Appellant must be restored. It
  will be open to Respondent No.2 to accept appellant's offer that
  the project will be executed at the amount indicated by
D Respondent No.1. [Para 12)(486-G-H)
            A/cons Infrastructure Ltd. v. Nagpur Metro Rail Corpn.
            Ltd. (2016) 16 sec 818 : [2016) 3 SCR 551;
            Montecarlo Ltd. v. NTPC Ltd. (2016) 15 SCC 272 :
            12016) 8 SCR 224 - referred to.
 E
                             Case Law Reference
            [2016] 3 SCR 551         referred to            Para9
            [2016) 8 SCR 224         referred to            Para 10
 F         CIVIL APPELLATE JURISDICTION: Civil Appeal No. 21858
      of2017.
            From the final Judgment and Order dated 04.08.2017 of the High
      Court of Punjab and Haryana at Chandigarh in CA CWP No.14/2017.
         K.V. Vishwanathan, Sr. Adv., Sridhar Potaraju, Arjun Singh, Mrs.
 G Arnita Gupta, Ms. Madhvi Khanna, Ms. Vrinda Bhandari, Advs. for the
   Appellant.
            Mukul Rohatgi, Sr. Adv., Ms. Ranjeeta Rohatgi, Ashish Batra,
      S.S. Shamshery, V. Balaji, G. S. Makker, Advs. for the Respondents.

H
   MIS SAM BUILT WELL PVT. LTD. v. DEEPAK BUILDERS                                      481


       The Judgment of the Court was delivered by                                       A
       R. F. NARIMAN, J. 1. Leave granted.
       2. The present appeal involves a notice inviting tenders (NIT)
dated 16'h March, 2017 by which the director of the Institute ofNano
Science and Technology, Mohali, invited percentage rate composite bids
from eligible firrriS/contractors in a two bid system for construction of               B
the Institute of Nano Science and Technology Campus at knowledge
City, Sector 81, Mohali, consisting of research, academic and
administrative buildings together withhoste~ residential, amenity and utility
buildings. The estimated cost of the said project was Rs.162.18 crores,
with earnest money payable being Rs.1.72 crores. The period of                          C
completion was stated to be 20 months and the last date for submission
of tender was 1O•h April, 2017. Clause 8 of the said NIT is important and
states as under:
       "8. Contractors/bidders who fulfill the following minimum criteria
       shall be eligible to apply. Joint ventures/consortium are not
       accepted.                                                                        D
         (a) Should have satisfactorily completed the works as mentioned
             below during the last date of submission of bids.
       (i) Three similar completed works each costing not less than
            Rs.64.9 crores, or
                                                                                        E
       (ii) Two similar completed works each costing not less than Rs.97.3
            crores,
       (iii) One similar completed work of aggregate cost not less than
            Rs.129.7 crores.
       Similar work shall mean work of "construction of institutional/
                                                                                        F
educational buildings campus with minimum five storeys RCC framed
structure building including electric~ plumbing, fire fighting, HVAC works
under composite contract executed in India in a single contract."
       3. Several persons submitted their bids, including Respondent No. I,
who claimed that it had done "similar work" as follows:
    Sr.      Name of work       Completion date   Current cost         Remarks
                                                                                        G
    No.                                           • fter addition of
                                                  1•1. ner annum
     I       Construction ot'   31.03.2016        Rs. 97.76 Cr.        It has
             District                             Current enhanced     basement
             Administrative                       value as per         plus S storeys
             complex at                           clause 2.2.4         RCC framed
             S ector-76, SAS                      Rs. 97 .76 er x      structure
             Nagar, Mohali                        107%"'
                                                  Rs.104.60 Cr.                         H
482            SUPREME COURT REPORTS                                [2017] 14 S.C.R.


A     '2.     Coostrnction of 05.10.2011           Rs.62.65 er. Qment    It has oosement
              Office Building                      enhanced value as     pl us six storeys
              of PlUlj ab Mandi                    per clause 2.2.4      RCCfrmncd
              Board, Phase-11,                     Rs. 6225cr x 114%     structure
              SANagar,                             =70.96cr.
              Mohali
      ,3      Construction of    16.03.2015        Rs. 172.32 er         It has height of
 B    '       Jang-e-Azadi                                               42 meters i.e.
              Memorial Project                                           IIXlre than 8
              at Kartaipur,                                              storeys RCC
              J alandhar (Phase-                                         framed
              !)                                                         structm·e
          4   Construction of   23. J 22015: 14    Wotk of Phase 2 for   It has oosenent
 c            Judicial Court
              Ccmplex at
                                courts out of 25
                                courts were
                                                   remaining courts in
                                                   progress. Work of
                                                                         pl us 5 storeys
                                                                         RCCfrmncd
              Sector 76, SAS    imugurated on      Rs. 75 28 er. was     structure
              Nagai; Mohali     23•d Dec., 2015    corr;ileted upto
                        -
                                and are            31.03.2017 and
                                functioning        balance work in
                                from the           progress
 D                              btri !ding Work
                                of Phase 2 for
                                remaining
                                courts in
                                proo:ress.
          5                     Total Value        Rs.423.16 Cr.
          4. Pre-bid meetings were conducted in March, 2017 and ultimately
 E
   Respondent No.I submitted its tender on 7th April, 2017. 5 out of 16
   bidders, who initially came forward, participated in the tender process.
   Admittedly, a technical evaluation report dated 24'h April, 2017 stated
   that the eligibility criteria contained in Clause 8 of the NIT was not met
   by Respondent No. l. This was reiterated by two other expert bodies,
 F namely, Tata Consultancy Services and the Building Works Committee
   of the Institute. Respondent No.2 then addressed a letter to Respondent
   No. I informing it about its ineligibility. On 3rd May, 2017, Respondent
   No.I filed a Writ Petition which was dismissed by the learned Single
   Judge stating that "similar work", which requires to be considered under
 G Clause 8 of the NIT, would be work which involves not only construction
   ot administrative blocks, but also several other buildings. Looking at the
   four projects, the last of which was admittedly kept out of consideration,
   it was found that none of the work could be said to be "similar" in nature
   and referring to the fact that three specialists had stated that Respondent
   No. l was ineligible, the Court adopted the hands-offposture, considering
 H
   M/S SAM BUILT WELL PVT. LTD. v. DEEPAK BUILDERS                            483
   '.             [R. F. NARIMAN, J.]

the limited parameters of judicial review. However, by the impugned A
judgment dated 4'h August, 2017, the Division Bench of the High Court
allowed the appeal of Respondent No. I and set aside the judgment of
the learned Single Judge stating that though there was no malafides in
the present case, the judgment of the learned Single Judge was incorrect
and that, therefore, Respondent No. I was clearly eligible. The appeal B
was then disposed of by directing Respondent No. 2 to consider
Respondent No.l's bid, along with other eligible bids, and award the
contract after assessing the bids on all permissible criteria.
        5. Pursuant to the said judgment, we have been informed that the
tender was ultimately awarded on 20'h August, 2017 to Respondent No. I,
inter alia, for the reason that Respondent No. l quoted a figure of roughly   C
4 to 5 crores less than that of the Appellant. Further, even though we
are in December, 2017, the Appellant has, admittedly, not yet left the site
of construction and resultantly Respondent No. I has not yet commenced
work.                                                                 .
        6. Dr. A.M. Singhvi, learned senior counsel appearing on behalf D
 of the Appellant, has taken us through three expert committee reports in
 the present case. According to the learned senior counsel, it is incorrect
 to state that the National Building Code of India, 2016, which is framed
by the Bureau oflndustrial Costs and Prices, does not apply to the facts
of the present case inasmuch as the special conditions of the tender E
 specifically make the said Code applicable and that, therefore, the expert
 committee reports based, inter alia, on the provisions of the Code, cannot
 be interfered with. Also, according to the learned senior counsel, the
·learned Single Judge correctly appreciated that in tender matters, judicial
 review \s very limited and argued before us that the Division Bench,
 while setting aside the judgment of the learned Single Judge, has not F
 kept in view the parameters _of judicial review of tenders. Equally,
 according to the learned senior counsel, it being clear that there arc no
 rnalafides or perversity involved, it would not be possible for a Writ Court,
 sitting in judicial review, to interfere with the tender process as has been
 done by the Division Bench.                                                   G
        7. Per contra, Shri Mukul Rohatgi, learned senior counsel
 appearing for Respondent No. I, supported the impugned judgment and
 stated that the National Building Code oflndia was only made applicable
,in so far as safety aspects of the buildings are concerned. This being
                                                                              H
484           SUPREME COURT REPORTS                         [2017] 14 S.C.R.


A the case, according to him, all the expert committee reports in relying
  upon the provisions of the said Code could not have done so. Also,
  according to him, one look at the three projects that have been carried
  out by Respondent No. I would show that they are all projects consisting
  of buildings which have basement plus 5 or more storeys and that,
  therefore, it is clear that they were "similar works" within the meaning
B
  of the expression contained in Clause 8 of the NIT, as these were nothing
  other than institutional buildings that were constructed by Respondent
  No.I.
         8. Dr. Singhvi, in rejoinder, stated that none of the three works
  could possibly be called "similar work" because an entire complex had
C to be constructed, and similar work was also defined to mean,
  "construction ofinstitutional/educational buildings campus with minimum
  five storeys RCC framed structure building ... ". According to the
  Iearned senior counsel, one building, albeit of 5 storeys or more, would
  not suffice.
D        9. Having heard learned counsel for both parties, it is important to
   set out the parameters for judicial review in cases like the present one.
   In a similar case, namely, Afcons Infrastructure Ltd. v. Nagpur
   Metro Rail Corpn. Ltd., (2016) 16 SCC 818 at 825-26, paragraph
   4.2(a) of Section Ill of the tender conditions in that case again spoke of
 E a certain minimum number of "similar contracts" as previous work
   experience. The question before this Court was whether an inter-state
   high speed railway project could be similar to metro civil construction
   work. After laying down the parameters ofjudicial review and referring
   to various judgments for the same, this Court held:
 F         "15. We may add that the owner or the employer of a project,
           having authored· the tender documents, is the best person to
           understand and appreciate its requirements and interpret its
           documents. The constitutional courts must defer to this
           understanding and appreciation of the tender documents, unless
           there is mala fide or perversity in the understanding or appreciation
 G         or in the application of the terms of the tender conditions. It is
           possible that the owner or employer of a project may give an
           interpretation to the tender documents that is not acceptable to
           the constitutional courts but that by itself is not a reason for
           interfering with the interpretation given.
 H
  M/S SAM BUILT WELL PVT. LTD. v. DEEPAK BUILDERS                          485
                 [R. F. NARIMAN, J.]

      16. In the present appeals, although there does not appear to be     A
      any ambiguity or doubt about the interpretation given
      by NMRCL to the tender conditions, we are of the view that even
      i£Jhere was such an ambiguity or doubt, the High Court ought to
      have refrained from giving its own interpretation unless it had
      come to a clear conclusion that the interpretation given             B
      by NMRCL was perverse or mala fide or intended to favour one
      of the bidders. This was certainly not the case either before the
      High Court or before this Court."
       10. In Montecarlo Ltd. v. NTPC Ltd., (2016) 15 SCC 272 at
288, this Court referred to various judgments, including the judgment in
Afcons Infrastructure Ltd. (supra), and concluded as follows:              c
      "26. We respectfully concur with the aforesaid statement oflaw.
      We have reasons to do so. In the present scenario, tenders are
      floated and offers are invited for highly complex technical subjects.
      It requires understanding and appreciation of the nature of work
      and the purpose it is going to serve. It is common knowledge in D
      the competitive commercial field that technical bids pursuant to
      the notice inviting tenders are scrutinised by the technical experts
      and sometimes third-party assistance from those unconnected with
      the owner's organisation is taken. This ensures objectivity. Bidder's
      expertise and technical capability and capacity must be assessed E
      by the experts. In the matters of financial assessment, consultants
      are appointed. It is because to check and ascertain that technical
      ability and the financial feasibility have sanguinity and are workable
      and realistic. There is a.multi-prong complex approach; highly
      technical in nature. The tenders where public largesse is put to
      auction stand on a different compartment. Tender with which we F
      are concerned, is not comparable to any scheme for allotment.
      This arena which we have referred requires technical expertise.
      Parameters applied are different. Its aim is to achieve high degree
      of perfection in execution and adherence to the time schedule.
      But, that does not mean, these tenders will escape scrutiny of G
      judicial review. Exercise of power of judicial review would be
      called for if the approach is arbitrary or mala fide or procedure
      adopted is meant to favour one. The decision-making process
      should clearly show that the said maladies are kept at bay. But

                                                                           H
486           SUPREME COURT REPORTS                          [2017] 14 S.C.R.


A          where a decision is taken that is manifestly in consonance with
           the language of the tender document or subserves the purpose
           for which the tender is floated, the court should follow the principle
           of restraint. Technical evaluation or comparison by the court would
           be impermissible. The principle that is applied to scan and
           understand an ordinary instrument relatable to contract in other
B
           spheres has to be treated differently than interpreting and
           appreciating tender documents relating to technical.works and
           projects requiring special skills. The owner should b~ allowed to
           carry out the purpose and there has to be allowance of free play
           in the joints."
c        11. We have already noticed that three expert committees have
  scrutinized Respondent No. I's tender and found Respondent No. I to be
  ineligible. The impugned judgment of the Division Bench of the High
  Court expressly states that no malafides are involved in the present case.
  Equally, while setting aside the judgment of the learned Single Judge, the
D Division Bench does not state that the three expert committees have
  arrived at a perverse conclusion. To merely set aside the judgment of
  the learned Single Judge and then jump to the conclusion that Respondent
  No.l's tender was clearly eligible, would be directly contrary to the
  judgments aforestated. Not having found malafides or perversity in the
  technical expert reports, the principle of judicial restraint kicks in, and
E any appreciation by the Court itself of technical evaluation, best left to
  technical experts, would be outside its ken. As a result, we find that the
  learned Single Judge was correct in his reliance on the three expert
  committee reports. The Division Bench, in setting aside the aforesaid
  judgment, has clearly gone outside the bounds of judicial review. We,
F therefore, set aside the judgment of the Division Bench and restore that
  of the learned Single Judge.
           12. Dr. Singhvi, learned senior counsel appearing for the Appellant,
    has stated that the Appellant is willing to match the offer of Respondent
    No.l. We record the aforesaid statement and order that the tender
G · awarded to Respondent No. I dated 20th August, 2017, based upon the
    Division Bench judgment, must be set aside, and the award of the tender
    to the Appellant must be restored. We hasten to add that it will be open
    to Respondent No.2 to accept Dr. Singhvi's offer that the project will be
    executed at the amount indicated by Respondent No. l.

H
   MIS SAM BUILT WELL PVT. LTD. v. DEEPAK BUILDERS                           487
                  [R. F. NARIMAN, J.]

       13. The appeal is allowed in the aforesaid terms with no order as     A
to costs.


Devika Gujral                                              Appeal allowed.


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "tender"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.