M/S. UDAIPUR PHOSPHATES FERTILIZERS LTD.versusUNION OF INDIA AND ANR.
- Citation
- 2007 INSC 80
- Decided
- 31 January 2007
- Disposal
- Dismissed
- Bench
- S B SINHA
Holding
When a fertilizer manufacturer satisfies the conditions of Press Note No. 9, the re‑endorsement of capacity is deemed automatic, mandating a revision of fixed costs and a consequent reduction of the subsidy.
Summary
The appellant, Udaipur Phosphates Fertilizers Ltd., manufactured Single Super Phosphate (SSP) under the Government's Retention Price and Subsidy Scheme. It applied for re‑endorsement of its plant capacity under Press Note No. 9 (1988) based on actual production between April 1988 and March 1990. The Government approved the re‑endorsement in March 1993 with retrospective effect from April 1990, recalculated the fixed charges and sought recovery of an amount, effectively reducing the subsidy. The appellant contended that it was denied the benefit of subsidy for the period between its application and the approval. The High Court dismissed the writ petition, holding that once the criteria of Press Note No. 9 are satisfied, re‑endorsement is automatic and the fixed cost must be revised, leading to a reduced subsidy. The Supreme Court affirmed this view, stating that the appellant had already drawn excess subsidy and could not claim a loss of benefit, and dismissed the appeal.
Issues considered
- Whether re‑endorsement of capacity under Press Note No. 9 is automatic upon meeting its criteria.
- Whether the subsidy must be reduced and fixed charges revised after such re‑endorsement.
- Whether the appellant is entitled to the subsidy for the period between its application for re‑endorsement and the Government's approval.
Legislation cited
Subjects
Judgment
M/S. UDAIPUR PHOSPHATES FERTILIZERS LTD. A
v.
UNION OF INDIA AND ANR.
JANUARY 31, 2007
(S.B. SINHA AND MARKANDEY KATJU, JJ.] B
Subsidy-Subsidy of fertilizers-Determination of-Manufacturer
applied for re-endorsement of the capacity of its unit on the basis of actual
production between a specified period-Approval thereof after 3 years also C
revising fixed cost and reducing the subsidy in view of the fact that
manufacture was in excess of the endorsed capacity-Order challenged on
the ground that when re-endorsement was granted, benefit of subsidy was not
given-Single Judge as well as Division Bench of High Court rejecting the
plea of manufacturer-On appeal held: Once re-endorsement takes place on
the basis of actual manufacture, the fixed cost is bound to be revised and D
hence subsidy bound to be reduced.
Single Super Phosphate (SSP), was manufactured by the appellant. In
1982, the product was brought under a formal price control known as Retention
Price and subsidy Scheme for regulating the price and sale of SSP by
Government of India. Under the Scheme the manufacturers were obliged to E
sell their fertilizers at a subsidized price fixed by the Government which was
below the cost of production. Government was to fix the retention price of the
product The difference between the retention price and selling price as fixed
by the Government was calculated and paid to the manufacturers as subsidy.
Government issued Press Note No.1 whereby the capacity indicated in F
the industrial licence could be reconsidered with reference to the highest
production achieved during any of the previous 5 years plus I/3rd thereof
provided that was within the licensed capacity plus 25% Thereafter Press
Note No. 9 (1988) was issued which provided a Scheme for re-endorsement of
higher capacity of the fertilizers units. In accordance with the Press Note G
No.9, appellant-manufacturer applied for re-endorsement of the capacity of
the appellant unit on the b_asis of actual production between 1.4.1988 and
31.3.1990. Government accorded approval of re-endorsement in 1993 with
retrospective effect from April 1990. Order indicated that in view of the higher
31 H
32 SUPREME COURT REPORTS [2007) 2 S.C.R.
A capacity, the fixed charges had been recalculated from l.4.1990. It also
demanded recovery on the basis of recalculation.
Appellant filed Writ Petition challenging the re-calculation of the fixed
Charges and recovery. Single Judge of High Court dismissed the Writ
Petition. Division Bench of High Court also dismissed the Letters. Patent
B Appeal. Hence the Present appeal.
Dismissing the appeal, the Court
HELD 1: Once the appellant's case falls within the criteria laid down
in Press Note No.9 then the re-endoresement takes place automatically. Once
C such re-E~ndorsement takes place on the basis of actual manufacture the fixed
cost is bound to be revised and hence the subsidy is bound to be reduced. [Para
15) [36-AJ
2. The Press Note No. 9 at paragraph 2f clearly indicates that this
scheme l'i in addition and not a substitution for the facilities already available
D under any existing scheme. Hence, the grievance of the appellant that from
the date of application for re-endorsement i.e. 8.8.1990 till 31.3.1993, when
the re-endorsement was granted, the benefit of subsidy was not given is wholly
untenable on account of the fact that the appellant overdrew the subsidies on
account of the enhanced capacity which was on its own showing an admitted
E fact [Para 16) [36-B-C)
3. The appellant was duly informed that their capacity has been enhanced
with retrospective effect from 1.4.1990 onwards. It is evident that the appellant
produced more, and the appellant cannot say that no opportunity to actually
manufacture in excess of the endorsed capacity was provided to them. The
F order of approval has to be deemed to be an ex-post facto approval of the
maximum production already achieved by the appellant The benefits in terms
of the said scheme have already been availed of and drawn by the appellant
company, and in fact some amount has been found to be overdrawn. [Para 17)
(36-D-E)
G CIVIL APPELLATE JURISDICTION: Civil Appeal No. 6202 of2000.
From the Final Judgment and Order dated 6.9.1999 of the High Court of
Delhi at New Delhi in L.P.A. No. 375/ 1999.
Paul Kaur Majithia (for Prashant Bhushan) for the Appellant.
H Ashok Bhan, Kiran Bhardwaj and D.S. Mabra (for B. Krishna Prasad)
UDAIPUR PHOSPHATES FERTILIZERS LTD. v. U.0 .1. [MARKANDEY KATJU, J.) 33
for the Respondents. A
The Judgment of the Court was delivered by
MARKANDEY KATJU, J. I. This appeal has been tiled against the
impugned judgment of the Delhi High Court dated 6.9.1999 in L.P.A. No. 375
of 1999 by which the judgment of the learned Single Judge of the High Court B
dated 26.5.1999 dismissing the writ petition was upheld.
2. Heard learned counsel for the parties and perused the record.
3. The appellant is a company registered under the Indian Companies
Act and is engaged in the manufacture of fertilizers and chemicals. One of C
the products it produces is Single Super Phosphate (SSP).
4. Till 1976, the manufacture and sale of SSP was not controlled by the
Government. However, from 1976 to 1982, the manufacture of SSP was
subjected to a system of uniform subsidy whereby each manufacturer was D
given a uniform rate of subsidy.
5. In the year 1982, the Government of India brought SSP under a formal
price control known as the Retention Price and Subsidy Scheme (hereinafter
referred to as RPS) for regulating the price and sale of SSP. The scheme had
been introduced on the basis of a detailed study and recommendation of an E
Inter-Ministerial Working Group appointed by the Government. Under the
RPS, the manufacturers were obliged to sell their fertilizers at a subsidized
price fixed by the Government, which was below the cost of production. The
respondent No. 2 calculated t.he cost of production of each unit on the basis
of certain factors such as capacity, location, age of the plant, etc. and added F
a certain amount of notional profit, and the result was called the retention
price. The difference between the retention price and the selling price as fixed
by the Government was calculated and paid to the manufacturers as subsidy.
Thus, while price of the fertilizers for the consumers, namely, the farmers was
subsidized by the Government, the manufacturers were given an amount
which was calculated by the FICC on the basis ofnormative cost of production G
of the unit which was to be calculated on the assumption that the unit
performed efficiently at 90% capacity utilization.
6. On I 5.1.1986, the Department of Industrial Development, Ministry of
Industries issued Press Note No. 1 whereby the capacity indicated in the H
industrial license could be re-considered with reference to the highest
production achieved during any of the previous 5 years plus I/3rd thereof,
34 SUPREME COURT REPORTS [2007] 2 S.C.R.
A provided that was within the licensed capacity plus 25%. Thereafter, the
Department of Industrial Development, Ministry of Industry issued Press
Note No. 9 (1988 series) on 6.4.1988 w.e.f. 1.4.1988 which provided a schc~me
for re-endorsement of higher capacity of the fertilizer units. Under the said
scheme, the unit could apply for re-endorsement of an enhanced capacity on
B the basis of the best production actually achieved in any financial year
between 1.4.1988 and 31.3.1990.
7. In accordance with the abovementioned Press Note of 1988, the
appellant vide application dated 8.8.1988 applied to the Ministry of Industries
for re-endorsement of the capacity of the appellant unit on the basis of the
C actual production between 1.4.1988 and 31.3 .1990.
8. Thereafter, the respondents asked for several verifications which
were provided by the appellant. However, it is alleged that despite repeated
follow-ups, after the various verifications, respondent No. l issued letter of
approval only on 31.3 .1993, i.e. three years after the appellant had applied for
D re-endorsement, stating that they were recognizing the appellant's enhanced
capacity of74,089 MT from the earlier capacity of 66,000 MT with retrospective
effect from 1.4.1990. It was further informed that respondent No. I was
tentatively recovering an amount of Rs. 26.55 lakhs by downward revision of
the ex-works price of the appellant from 1.4.1990.
E
9. The appellant's grievance is that the Government has retrospecfrvely
re-endorsed the capacity of the appellant and reduced the price payable to
the appellant with retrospective effect, which effectively denied the appellant
from taking advantage of the re-endorsed capacity. The appellant filed the
abovementioned Special Leave Petition challenging the order dated 6.9.1999
F passed by the High Court of Delhi whereby the learned Division Bench
dismissed LPA No. 375/1999 on the ground that when the appellant had
applied for re-endorsement of the capacity, in view of the fact that the
appellant had already achieved the maximum production, thereby fulfilling the
condition of Press Note No. 9 (1988 series), then the re-endorsement was
G bound to automatically take place. Further, merely because it took some time
for inspection by the respondents, it did not mean that the re-endorsement
was not automatic.
I0. Press Note No. 9 has been quoted in detail in the impugned judgment
and hence we are not quoting it again here.
H
11. In pursuance of this Press Note the appellant made an application
'--j
UDAIPUR PHOSPHATES FERTILIZERS LTD. v. U.0.1. [MARKANDEY KAT JU, J.] 35
for re-endorsing the capacity on the basis of actual manufacture during !st A
-+· April 1988 and 31st March 1990. The I st respondent accorded approval of
re-endorsement by letter dated 31st March 1993. The said Jetter also indicated
that in view of the higher capacity the fixed charges had been re-calculated
from !st April 1990. The letter stated that on the basis of re-calculation there
would be a recovery of approximately Rs. 26.55 lakhs. A writ petition was
filed challenging the re-calculation of the fixed charges and the recovery of
B
approximate Rs. 26.55 Jakhs.
12. The learned Single Judge of the High Court dismissed the writ
>- petition on the ground that once an application was made under Press Note
No. 9, the re-endorsement was merely a formality in view of the fact that the
appellant had already achieved the maximum production. The learned Judge
c
held that as the appellant had already produced more, re-fixation of the fixed
cost was bound to take place. The learned Judge held that the fixed cost was
bound to come down. The learned Judge also held that the subsidy has been
correctly worked out on the basis of actual manufacture as undertaken by the
appellant. D
13. The learned Single Judge in his judgment has observed that the
facts as stated in the application of the appellant dated 8.8.1990 for re-
-~ endorsement of its capacity would substantiate the stand of the respondents
that the appellant-unit had already achieved maximum production and only
needed ex-post facto approval in compliance to the Press Note dated April E
6, 1988. It was also observed that it was clear that the appellant produced
more and it could not be said that no opportunity to actually manufacturing
in excess of the endorsed capacity was provided. The sanction of the
respondents vide communication dated March 31, 1993 is in the nature of ex-
post facto approval and cannot be held to be discriminatory as the fixed cost F
obviously will come down while manufacturing more and subsidy had been
i correctly working out.on that basis.
14. In appeal, the Division Bench observed that if the appellant fulfilled
the condition of Press Note No. 9 then the re-endorsement was bound to take
place automatically. Merely because the respondent would have to make an G
inspection that there was no additional investment in the plant, machinery
and equipment exceeding I0% of the book value, and such inspection takes
-i some time, does not mean that the re-endorsement was not automatic.
15. We agree with the view taken by the learned Single Judge and the
H
36 SUPREME COURT REPORTS (2007] 2 S.C.R.
A Division Bench that once the appellant's case falls within the criteria laid
down in Press Note No. 9 then the re-endorsement takes place automatically.
Once such re-endorsement takes place on the basis of actual manufacture the
fixed cost is bound to be revised and hence the subsidy is bound to be
reduced.
B 16. The Press Note No. 9 at paragraph 2f clearly indicates that this
scheme is in addition and not a substitution for the facilities already available
under any existing scheme. Hence, the grievance of the appellant that from
the date of application for re-endorsement i.e. 8.8.1990 till 31.3.1993, when the
re-endorsement was granted, the benefit of subsidy was not given is wholly
C untenable on account of the fact that the appellant overdrew the subsidies
on account of the enhanced capacity which was on its own showing an
admitted fact.
17. The appellant was duly informed that their capacity has been
enhanced with retrospective effect from 1.4.1990 onwards to 74,089 MT (which
D was the production achieved by them during 1989-90). It is evident that the
appellant produced more, and the appellant cannot say that no opportunity
to actually manufacture in excess of the endorsed capacity was provided to
them. The communication dated 31.3.1993 has to be deemed to be an ex-post
facto approval of the maximum production already achieved by the appellant.
The benefits in terms of the said scheme have already been availed of and
E drawn by the appellant company, and in fact some amount has been found
to be overdrawn.
18. In view of the above, we find no merit in this appeal. The appeal
is accordingly dismissed. No costs.
F K.K.T. Appeal dismissed.