Created byFuzzy Cloud

Supreme Court of India

MAHARASHTRA STATE ELECTRICITY DISTRIBUTION COMPANY LTD.versusM/S. DATAR SWITCHGEAR LIMITED & ORS.

Citation
2018 INSC 33
Decided
18 January 2018
Disposal
Dismissed

Holding

The arbitral tribunal’s findings of fact, including that MSEB’s failure to furnish the DTC lists constituted a fundamental breach justifying DSL’s termination, are conclusive; the award of damages is proper and cannot be set aside under Section 34, so the appeal is dismissed.

Summary

Maharashtra State Electricity Distribution Co. Ltd. (MSEB) awarded a contract to Datar Switchgear Ltd. (DSL) for installing Low Tension Load Management Systems. MSEB repeatedly failed to provide the list of locations (DTC lists) required for installation and also delayed renewal of the Letter of Credit. DSL terminated the contract and obtained an arbitral award of Rs.185.97 crore in damages, which was upheld by the High Court. MSEB appealed under Section 34 of the Arbitration and Conciliation Act, 1996, alleging procedural irregularities, waiver, and public‑policy violations. The Supreme Court held that the arbitral tribunal’s findings of fact, including the determination that MSEB’s failure to supply the DTC lists was a fundamental breach, are not open to appellate scrutiny; the termination was valid, the award of damages was proper, and no ground for setting aside existed. The appeal was dismissed with costs.

Issues considered

  • The appellant’s alleged fundamental breach for not supplying the DTC location lists and whether it justified termination by the respondent.
  • Whether the arbitral award can be set aside under Section 34 of the Arbitration and Conciliation Act, 1996 on grounds of public policy, waiver, or procedural irregularities.
  • The propriety of the quantum of damages awarded for installed, uninstalled, and raw‑material objects.
  • The relevance of waiver, mitigation, and the doctrine of fundamental breach to the parties’ rights.
  • The extent to which an arbitral tribunal’s findings of fact are reviewable by a court.

Legislation cited

Subjects

ArbitrationFundamental breachContract terminationSection 34Public policyDamagesWaiverMitigationLease contractArbitral awardMaster of evidence

Judgment

                        [2018] 1 S.C.R. 733                            733


   MAHARASHTRA STATE ELECTRICITY DISTRIBUTION                          A
                COMPANY LTD.
                                 v.
         M/S. DATAR SWITCHGEAR LIMITED & ORS.
                  (Civil Appeal No. 10466 of 2017)                     B
                       JANUARY 18, 2018
         [A. K. SIKRI AND ASHOK BHUSHAN, JJ.]
       Arbitration and Conciliation Act, 1996 – s.34 – Contract
between parties – Termination of, on ground of fundamental
                                                                       C
breach – Propriety of – Respondent no.2 awarded tender/contract
by appellant, in 1993-1994, for installation of Low Tension Load
Management Systems (LTLMS) at various locations – Another tender
by appellant in 1996 which was for installation of 23000 numbers
of LTLMS – Respondent no.2 participated in this tender also,
wherein work order for installation of 11760 numbers of LTLMS          D
was awarded to Respondent no.2 and balance quantities were
awarded to other tenderers – In view of large scale complaints and
issue of defective equipments supplied against 1993-1994 tender,
Respondent no.2 offered to not only supply 11760 LTLMS against
the 1996 tender but also to replace all the defective Low Tension
                                                                       E
Switched Capacitators (LTSCs) supplied against the contract of
1993-1994, with new technology LTLMS at the old lease rentals–
Appellant issued Letter of Intent– However, issues arose between
the parties during the execution of said contract– Contract
terminated by respondent no.2 – Arbitration Tribunal passed arbitral
award in favour of respondent no.2 – Challenged by appellant u/        F
s.34, dismissed by High Court – On appeal, held: Findings of facts
were arrived at by Arbitral Tribunal after appreciating the evidence
and documents on record – From these findings it stands established
that there was a fundamental breach on the part of appellant in
failing to furnish the list of locations where the contract objects
                                                                       G
had to be installed, with no fault of Respondent no.2 – Such
fundamental breach pervaded the entire contract and once
committed, the whole contract stood abrogated – Respondent No.2
was always ready and willing to perform its contractual obligations,
but was prevented by appellant from such performance –
Termination of contract by respondent No.2 was valid and justified     H
                                 733
734            SUPREME COURT REPORTS                        [2018] 1 S.C.R.


A     – No question of law is involved in the present appeal and the only
      attempt of appellant was to re-argue the matter afresh, which is
      impermissible – Costs imposed –Constitution of India – Art. 136 –
      Contract Act, 1872 – ss. 55, 63 – UNIDROIT Convention on
      International Lease – Art.13(2) – Waiver.
B           Practice and Procedure – Findings of facts by Arbitral
      Tribunal – Held: Arbitral Tribunal is the master of evidence –
      Findings of fact arrived at by the arbitrators on the basis of evidence
      on record are not to be scrutinised as if the Court was sitting in
      appeal.
C            Contract – Claim for damages – Entitlement to – Held: Once
      it is established that the party was justified in terminating the
      contract on account of fundamental breach thereof, then the said
      innocent party is entitled to claim damages for the entire contract,
      i.e. for the part which is performed and also for the part of the
      contract which it was prevented from performing.
D
             Contract – Award of damages – Principle for – Held: Injured
      party should be placed in as good a position as money could do as
      if the contract had been performed – In the instant case, applying
      the said principle, the Arbitral Tribunal rightly awarded almost the
      same amount as was invested by respondent No.2 for the project –
E     Thus, there is no question of interdicting with the same.
            Dismissing the appeal, the Court
            HELD:
      TERMINATION OF CONTRACT WAS VALID AND
F     JUSTIFIED :
             1. Categorical findings were arrived at by the Arbitral
      Tribunal to the effect that insofar as respondent No.2 was
      concerned, it was always ready and willing to perform its
      contractual obligations, but was prevented by the appellant from
G     such performance. Another specific finding which was returned
      by the Arbitral Tribunal was that the appellant had not given the
      list of locations and, therefore, its submission that respondent
      No.2 had adequate lists of locations available but still failed to
      install the contract objects was not acceptable. In fact, on this
      count, the Arbitral Tribunal has commented upon the working of
H
 MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO.                         735
       LTD. v. M/S. DATAR SWITCHGEAR LTD.

the appellant itself and expressed its dismay about lack of control     A
by the Head Office of the appellant over the field offices which
led to the failure of the contract. These are findings of facts which
were arrived at by the Arbitral Tribunal after appreciating the
evidence and documents on record. From these findings it stands
established that there was a fundamental breach on the part of
                                                                        B
the appellant in carrying out its obligations, with no fault of
respondent No.2 which had invested whopping amount of Rs.163
crores in the project. A perusal of the award reveals that the
Tribunal investigated the conduct of entire transaction between
the parties pertaining to the work order, including withholding of
DTC locations, allegations and counter allegations by the parties       C
concerning installed objects. The arbitrators did not focus on a
particular breach qua particular number of objects/class of objects.
Respondent No.2 is right in its submission that the fundamental
breach, by its very nature, pervaded the entire contract and once
committed, the contract as a whole stood abrogated. It was on
                                                                        D
the aforesaid basis that the Arbitral Tribunal came to the
conclusion that the termination of contract by respondent No.2
was in order and valid. The proposition of law that the Arbitral
Tribunal is the master of evidence and the findings of fact which
are arrived at by the arbitrators on the basis of evidence on record
are not to be scrutinised as if the Court was sitting in appeal now     E
stands settled by catena of judgments pronounced by Supreme
Court without any exception thereto. The award of the Arbitral
Tribunal having been affirmed by the Single Judge as well as the
Division Bench of the High Court, that too after dealing with
each and every argument raised by the appellant in detail, which
                                                                        F
was negatived, the Respondent no.2 is correct in his argument
that there is no question of law which is involved herein and the
only attempt of the appellant was to re-argue the matter afresh,
which was impermissible. [Paras 43, 52] [766-C-H; 767-A-B;
772-C]
AWARD OF DAMAGES :                                                      G

      2.1 The appellant cannot now turn around and raise
objection to the award of damages which were measured having
regard to the loss suffered by respondent No.2 in terms of lease
rent for reasonable period for which it would have been entitled
                                                                        H
736           SUPREME COURT REPORTS                      [2018] 1 S.C.R.


A     to otherwise. The injured party should be placed in as good a
      position as money could do as if the contract had been performed.
      In the instant case, applying the aforesaid principle, the Arbitral
      Tribunal, for the purpose of classification, considered a 30%
      reduction in lease rent to compute damages for installed objects,
      50% reduction in lease rent to compute damages for manufactured
B
      but uninstalled objects and the bare cost of raw materials for the
      objects not manufactured. No pendente lite interest was awarded,
      though the proceedings went on for five and a half years. Thus,
      the Arbitral Tribunal awarded almost the same amount as was
      invested by respondent No.2 for the project. Interest was awarded
C     only @ 10% per annum from the date of the award as opposed to
      the prevailing bank rate of about 21%. The aforesaid being a
      reasonable and plausible measure adopted by the Arbitral Tribunal
      for awarding the damages, there is no question of interdicting
      with the same. [Paras 54-56] [772-H; 773-B, F-H; 774-A]
D           Union of India & Ors. v. Sugauli Sugar Works (P) Ltd.
            (1976) 3 SCC 32 : [1976] 3 SCR 614 – relied on.
            2.2 Once it is established that the party was justified in
      terminating the contract on account of fundamental breach
      thereof, then the said innocent party is entitled to claim damages
E     for the entire contract, i.e. for the part which is performed and
      also for the part of the contract which it was prevented from
      performing. There is no infirmity in the manner in which damages
      are awarded in favour of respondent No.2. [Paras 58, 59] [774-
      E-F; 775-D]

F     RE : MITIGATION OF DAMAGES
            3. The Arbitral Tribunal dealt with this aspect and held
      that the contract objects were custom built. The Single Judge as
      well as the Division Bench of the High Court has given its
      imprimatur to the aforesaid findings. It, therefore, becomes
G     apparent that the objects in question were manufactured by
      respondent No.2 to suit the specific needs of the appellant as
      they could not be used otherwise. Therefore, there was no
      possibility on the part of respondent No.2 to make an endeavour
      to dispose of the same in order to mitigate the losses. [Paras 60,
      61] [775-F; 776-B-C]
H
 MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO.                737
       LTD. v. M/S. DATAR SWITCHGEAR LTD.

     Waman Shriniwas Kini v. Ratilal Bhagwandas & Co.          A
     [1959] Supp. 2 SCR 217; Jagad Bandhu Chatterjee v.
     Smt. Nilima Rani & Ors. (1969) 3 SCC 445; Babulal
     Badriprasad Varma v. Surat Municipal Corporation &
     Ors. (2008) 12 SCC 401 : [2008] 7 SCR 564 – held
     inapplicable.
                                                               B
     Dwarka Prasad vs. State of M.P and another; ONGC v.
     Comex; Prakash Kharade v. Dr. Vijay Kumar Khandre
     and Others; Grandhi v. Vissamastti; Mirza Javed
     Murtaza v. U.P. Financial Corporation Kanpur and
     another; Firm Bhagwandas Shobhalal Jain, a Registered
     firm and Anr. v. State of Madhya Pradesh AIR 1966         C
     MP 95; Shin Satellite Public Co. Ltd. v. Jain Studios
     Ltd., (2006) 2 SCC 628 : [2006] 1 SCR 933; Beed
     District Central Coop. Bank Ltd. v. State of
     Maharashtra & Ors. (2006) 8 SCC 514 : [2006] 6 Suppl.
     SCR 895; Daruka & Co. v. Union of India & Ors.            D
     (1973) 2 SCC 617: [1974] 1 SCR 570; Food
     Corporation of India v. Yousuff and Co. [Decision
     dated 17.11.1980 of Kerala High Court (DB) in A.S.
     No. 31 of 1976; Associate Builders v. Delhi Development
     Authority (2015) 3 SCC 49; Juggilal Kamlapat v.
     Pratapmal Rameshwar (1978) 1 SCC 69 : [1978]              E
     2 SCR 219; S. Munishamappa v. B. Venkatarayappa
     & Ors. (1981) 3 SCC 260 – referred to.
     Suisse Atlantique Societe d’Armament SA v. NV
     Rotterdamsche Kolen Centrale 1966 A.C. 361 – referred
     to.                                                       F
                     Case Law Reference
AIR 1966 MP 95                  referred to          Para 31
[2006] 1 SCR 933                referred to          Para 31
[2006] 6 Suppl. SCR 895         referred to          Para 31   G
[1974] 1 SCR 570                referred to          Para 31
[1959] Supp. (2) SCR 217        held inapplicable    Para 33
(1969) 3 SCC 445                held inapplicable    Para 33
[2008] 7 SCR 564                held inapplicable    Para 33   H
738             SUPREME COURT REPORTS                           [2018] 1 S.C.R.


A     (2015) 3 SCC 49                      referred to              Para 43
      (1981) 3 SCC 260                     referred to              Para 43
       [1978] 2 SCR 219                     referred to             Para 47
       [1976] 3 SCR 614                     relied on               Para 55
B           CIVIL APPELLATE JURISDICTION : Civil Appeal No. 10466
      of 2017.
            From the Judgment and Order dated 19.10.2013 of the High Court
      of Judicature at Bombay in Appeal No. 166 of 2009.
            Vikas Singh, Sr. Adv., Chandra Prakash, Prashant Chawan, Ravi
C
      Prakash, Ms. Deepika Kalia, Kapish Seth, Varun Aggarwal, Ms. Srishti,
      Advs. for the Appellant.
            Rafique Dada, Sr. Adv., Mukul Taly, Ms. Swati Deshpande, Jatin
      Zaveri, Neel Kamal Mishra, Advs. for the Respondents.
D           The Judgment of the Court was delivered by
             A. K. SIKRI, J. 1. The appellant herein had awarded a contract
      to the respondent. Dispute had arisen leading to the constitution of an
      Arbitral Tribunal (having regard to the Arbitration Agreement contained
      in the contract between the parties) and those arbitration proceedings
E     culminated in the Arbitral Award dated June 18, 2004. An application
      under Section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter
      referred to as the ‘Act’) was filed by the appellant, questioning the
      correctness of the Award which was dismissed by the learned Single
      Judge of the High Court vide orders dated March 18, 2009 and April 30,
      2009 thereby affirming the Arbitral Award. Intra-court appeal
F     thereagainst, which was preferred by the appellant, has been dismissed
      by the Division Bench of the High Court vide judgment dated October
      19, 2013. It is the validity of that judgment which is the subject matter of
      the instant appeal.
            2. With the aforesaid preliminary comments on the nature of
G     proceedings, we turn to the events that took place, in a chronological
      manner, that are relevant for deciding the lis:
      EVENTS :
            The respondent was awarded a contract for installation of Low
      Tension Load Management Systems (LTLMS) at various locations by
H
 MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO.                             739
  LTD. v. M/S. DATAR SWITCHGEAR LTD. [A. K. SIKRI, J.]

the appellant during the year 1993-1994. The respondent participated in     A
another tender in the year 1996 for installation of approximately 23000
numbers LTLMS. The appellant awarded a work order dated January
15, 1997 for installation of 11760 numbers of LTLMS to the respondent
against the above tender of 1996 and the balance quantities were
awarded to other tenderers. According to the appellant, against the
                                                                            B
installation made by the respondent previously in the year 1993-1994,
there were large scale complaints and the issue of defective equipments
having been supplied by the respondent which issue was being raised in
the press repeatedly. In view of the criticism faced by the respondent,
the respondent voluntarily offered to not only supply 11760 LTLMS against
the order placed in January 1997 but also undertook to replace all          C
defective Low Tension Switched Capacitators (LTSCs) supplied by them
against the previous contract of 1993-1994 with new technology LTLMS
and charge the old lease rentals against the replaced LTSC during the
pendency of the earlier contract. The appellant accepting the package
offer by the respondents issued Letter of Intent in respect of 12555
                                                                            D
numbers panel of 1993-1994 contract objects to be replaced by new
panels along with additional quantity of 23672 numbers fresh panels.
The appellant finally placed a composite work order dated March 27,
1997 with the respondent to:
  (i)     Supply 11,760 numbers equipments against the tender of 1996-
          1997 contract. B-I Locations;                                     E

  (ii) 12,555 numbers replacement of equipments against the 1993-
       1994 contract – B-II locations; and
  (iii)    23,672 numbers equipments which was a package with the B-
          II locations – B-III locations.                                   F
      Clause 5.1 of the letter of Work Order dated March 27, 1997
provided as under:
          “The supply and installation of the LM Systems shall commence
          within four months from the date of this work order or opening
          of Letter of Credit or receipt of complete list of locations of   G
          DTCs whichever is later. The entire supply and installation of
          LM System covered under schedules at Annexure – B-I,
          Annexure – B-II and Annexure – B-III shall be completed within
          twenty months thereafter.”
                                                                            H
740            SUPREME COURT REPORTS                           [2018] 1 S.C.R.


A            3. During the execution of the said contract, some issues arose
      between the parties. As per the respondents, the appellant primarily
      committed two kinds of breaches, namely, the appellant did not supply
      the list of location where the contract objects had to be installed and,
      further, the appellant also did not renew the Letter of Credit (LC) through
      which the lease rentals were being paid for the installed objects. A
B
      series of correspondence was exchanged between the parties on the
      aforesaid two counts as the appellant maintained that it had not committed
      any fault in respect of any of the aforesaid aspects. As against the total
      number of 47497 LTLMS to be installed by the respondents, it installed
      17294 numbers and thereafter terminated the contract vide letter dated
C     February 19, 1999 alleging breaches on the part of the appellant which
      according to the respondent entitled the respondent to terminate the
      contract. The respondent undertook to maintain 17,294 contracts objects
      installed by them on the condition that lease rental of the same would be
      paid by the appellant. The respondent further claimed that they had
      manufactured 14,206 numbers objects which were waiting to be installed
D
      for which locations were not intimated by the appellant.
             4. As per the appellant, under the original tender of 1996, the
      respondent was only entitled to supply and maintain 11760 contract objects
      and 12555 replacement of 1993/94 contract was as a package, with
      23672 supply of contract objects and, failure to replace the contract
E     objects of 1993/94 completely disentitled the respondent from the right
      to supply any contract object under the additional quantities of 23672
      contract objects awarded as package beyond the ratio in which the B-II
      locations were replaced vis-a-vis the additional quantity awarded in B-
      III locations. Thus, the partial termination by the respondent was illegal
F     and arbitrary because as against 12,555 B-II locations, the respondent
      had installed only 2,014 equipments and thus they were aware of 10,541
      B-II locations which were for replacement basis. Hence it was incorrect
      on their part to suggest that they had a right to terminate the contract
      due to non-supply of list of locations.
G           5. A meeting was held between the officials of the appellant and
      representatives of the respondent and it was duly recorded in the Minutes
      of Meeting dated March 11, 1999 that the Chairman of the appellant had
      informed the respondent that the maps were readily available in the
      Kolhapur zone and requested the respondent to take up the work
      immediately. However, the respondent stated that it was not in a position
H
 MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO.                                741
  LTD. v. M/S. DATAR SWITCHGEAR LTD. [A. K. SIKRI, J.]

to start the work immediately. The appellant wrote letter dated April 5,       A
1999 to the respondent bringing out its extreme dissatisfaction in the
manner in which the work was being carried out by the respondent and
calling upon the respondent to stick to the implementation of the
programme as per the terms and conditions of the Work Order. The
respondent by letter dated April 21, 1999 terminated the contract in its
                                                                               B
entirety and refused to maintain even the objects installed by them.
       6. Dispute having arisen; for adjudicating these disputes, Arbitral
Tribunal in terms of Arbitration Agreement was constituted. The Tribunal
commenced its proceedings on February 19, 1999 and on June 18, 2004
passed a final award directing the appellant to pay Rs.185,97,86,399/- to
the respondent as damages which included:                                      C

  (i) Rs. 109 crores towards the installed object.
  (ii) Rs. 71 crores towards the objects manufactured by the respondent
        which were ready for installation which they claimed could not
        be installed due to lack of list of locations; and
                                                                               D
  (iii) Rs. 6.52 crores towards raw material allegedly purchased by
        the respondent for the manufacture of remaining equipments.
       7. As aforesaid, before the arbitrators, the respondents had
primarily contended two defaults by the appellant. First, that the appellant
did not supply the list of locations where the contract objects had to be
                                                                               E
installed and second, that the appellant did not renew the LC through
which the lease rentals were being paid for the installed objects.
      8. The Arbitral Tribunal, however, found no fault with the appellant
as regards non-renewal of the LC observing that the respondent had
terminated the contract in its entirety on April 21, 1999 whereas the LC
was valid upto April 30, 1999.                                                 F

       The finding regarding non-renewal of LC by the Arbitral Tribunal
was affirmed by the learned Single Judge (Justice D.K. Deshmukh)
vide judgment dated August 3, 2005 when the Award was initially set
aside. The said finding was also affirmed by the Ld. Division Bench of
the Bombay High Court vide its judgment dated October 22, 2008.                G
However, partly allowing the appeal of the respondent, the judgment of
the learned Single Judge dated August 3, 2005 was set aside and the
matter was remanded back for fresh consideration. While adopting this
course of action, the Division Bench in its judgment dated October 22,
2008 observed as under:                                                        H
742            SUPREME COURT REPORTS                         [2018] 1 S.C.R.


A            “44. The Court if decides an application under Section 34 should
             either expressly or impliedly say that the award was being set
             aside because it was contrary to the terms of the contract or the
             Award was in any way violative of the public policy or the award
             was contrary to the substantive law in India viz., Sections 55 and
             73 of the Indian Contract Act or the award was vitiated by
B
             perversity in evidence in contract or the adjudication of a claim
             has been made in respect whereof there was no dispute or
             difference or the award was vitiated by internal contradictions.
             In the present judgment which is under challenge, we have not
             found any such findings either expressly or impliedly though in
C            the pleadings the issues were raised which should be the subject
             matter of a petition under Section 34 of the Act of 1996.
             Therefore, we find that it will be necessary for this Court to set
             aside the judgment impugned and remand the case back for
             adjudication afresh in accordance with the parameters set out
             by Section 34 of the 1996 Act.
D
             45. In view of the above, the appeal is allowed. Impugned
             judgment and order dated 3rd August 2005 passed by the learned
             Judge of this Court in Arbitration Petition No. 374 of 2004 is set
             aside. The case is remanded back for adjudication afresh in
             accordance with the parameters set out by Section 34 of the
E            Arbitration and Conciliation Act, 1996.”
             9. After the remand, the learned Single Judge (Justice Roshan
      Dalvi) by order dated March 18, 2009 rejected the case of the appellant
      on the ground that no case under Section 34(2)(iv) of the Act had been
      made out by the appellant. The aforesaid order dated March 18, 2009
F     of the learned Single Judge was challenged by the appellant before the
      Division Bench of the Bombay High Court. The Division Bench, while
      hearing the appeal, passed the following order on April 21, 2009:
             “1. Learned counsel for the petitioner has tried to submit before
             this Court that certain arguments quoted by the learned Single
G            Judge in the impugned judgment were not argued by him and
             they have been put up by the learned Single Judge in his mouth.
             Under these circumstances we find it appropriate to direct the
             petitioner to approach the Ld. Single Judge seeking correction
             and/or withdrawal and/or the modification of the submission which
             are put up in his mouth. After appropriate orders are passed by
H            the Ld. Single Judge, appeal be placed for admission.
 MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO.                                743
  LTD. v. M/S. DATAR SWITCHGEAR LTD. [A. K. SIKRI, J.]

        2. Appeal No. 165 of 2009 be heard along with this Appeal.             A
        3. Since contentions raised before the Ld. Single Judge are in
        dispute as stated above and the Petitioner has been directed to
        approach the Ld. Single Judge for the purpose of correction and/
        or modification, and also in view of the fact that the impugned
        order has not attained finality for the purpose of being considered    B
        by us, we find it inappropriate to consider Notice of Motion (being
        Notice of Motion No. of 2009) for interim relief at this stage.
        The said notice of motion will be considered after the appropriate
        orders are passed by the Ld. Single Judge on approach to the
        Ld. Single Judge by the Petitioner.”
                                                                               C
      10. The learned Single Judge by order dated April 30, 2009 clarified
her order by saying that although the appellant has argued the matter
challenging the award being beyond the contract between the parties
and being opposed to public policy, the learned Single Judge in her
considered opinion rejected the same under Section 34(2)(iv) of the Act.
                                                                               D
      11. Appeal of the appellant was thereafter listed before the Division
Bench in which order dated May 2, 2009 was passed staying the Award
upon the condition that the appellant deposits the principal amount and
submits bank guarantee qua the interest awarded by the arbitrators.
This order was challenged by both the parties by filing their respective
SLP. This Court while hearing these SLPs, modified the order of the            E
High Court, directing the appellant to deposit Rs.65 crores with the
Bombay High Court and furnish a bank guarantee in the sum of Rs.200
crores. Amount of Rs.65 crores was allowed to be withdrawn by the
appellant upon furnishing bank guarantee subject to the outcome of the
appeal before the High Court.                                                  F
       12. In the appeal before the High Court, the appellant raised certain
additional grounds. Thereafter, the matter was heard finally and vide
impugned judgment, the appeal of the appellant has been dismissed by
the High Court.
ORDER OF THE HIGH COURT                                                        G
       13. Before adverting to the arguments that are advanced by Mr.
Vikas Singh, learned senior counsel appearing for the appellant and reply
thereto of Mr. Rafique Dada, learned senior counsel who appeared for
the respondent, it would be wise to scan through the impugned judgment
of the Division Bench in order to understand and appreciate the line of        H
744            SUPREME COURT REPORTS                          [2018] 1 S.C.R.


A     reasoning which is the basis of justifying and upholding the order of the
      learned Single Judge and dismissing the objections of the appellant to the
      award rendered by the Arbitral Tribunal. In a very elaborate judgment,
      which runs into more than 150 pages, the High court has discussed various
      facets of the case under the following heads:
B       1.    Brief Synopsis and chronology of events.
        2.    Remand
        3.    Submissions and finding on interpretation of the order of Apex
              Court dated 25/8/2009 passed in SLP filed by MSEB, challenging
              the order of remand passed by the Division Bench of this Court
C             headed by Bilal Nazki, J
        4.    Notice of Motion No.3227 of 2010
        5.    Notice of Motion No.461 of 2010.
        6.    Scope of interference under Sections 34 and 37 of the said Act;
D             the interpretation of the term “public policy” and; power of the
              Court to interfere on that ground.
        7.    Points (i) to (vi) extensively urged by MSEB
        8.    Submissions and finding on Point No.(i) Whether the Arbitral
              Tribunal and the learned Single Judge were justified in coming to
E
              the conclusion that the MSEB had committed breach of contract
              by not supplying DTC Lists?
        9.    Submissions and finding on Point No.(ii) Whether the contract
              was one complete contract and the same could not be split up as
              argued by the Claimants?
F
        10. Submissions and finding on Point No.(iii) Whether Claimants/
            DSL waived their right to receive complete lists of locations;
            and on Point No (iv) Whether the Award is contrary to the public
            policy as mentioned under Section 34 of the Arbitration and
            Conciliation Act, 1996?
G
        11. Submissions and finding on Point No. (iv) Whether the Award is
            contrary to the Public Policy as mentioned under Section 34 of
            the Arbitration and Conciliation Act, 1996? (v) Whether the
            damages were properly awarded? and (vi) Whether the aspect
            of mitigation was properly considered?
H
 MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO.                                 745
  LTD. v. M/S. DATAR SWITCHGEAR LTD. [A. K. SIKRI, J.]

  12. Chamber Summonses filed by MSEB                                           A
  13. Conclusion.
        14. After narrating the scope of the work and the gist of the dispute
which led to initiation of arbitration proceedings, the High Court noted
that respondent filed its claims under various heads aggregating to
Rs.1053,06,78,342/- and the counter claims of the appellant were to the         B
tune of Rs.1273,70,26,669/- crores approximately. Appellant had
examined as many as 26 witnesses in support of its case whereas the
respondent had examined its Managing Director who was in charge of
the project. After conclusion of the evidence and hearing the arguments,
the Arbitral Tribunal partly allowed the claims of the respondent, holding      C
that respondent was entitled to a sum of Rs. 1,79,15,87,009/- (Rs.
185,97,86,399 – 6,81,99,390) along with interest @ 10% per annum payable
from the date of the Award till realisation. Cost of rupees one crore was
also awarded. Counter claims of the appellant were dismissed. After
taking note of the aforesaid facts in brief, the High Court dealt with the
contention of the appellant herein that the matter needed to be remanded        D
back to the learned Single Judge on the ground that the submission of
the appellant that the Award was against the public policy had not been
considered by the learned Single Judge. After comprehensive discussion,
this argument has been rejected authoritatively. In the process, the High
Court also dealt with the submissions predicated on Order dated August          E
25, 2009 passed by this Court in special leave petition which was filed by
the appellant whereby order of remand passed by Division Bench of the
High Court, in the earlier round was challenged. Notice of Motion Nos.
3227 of 2010 and 461 of 2010 also came to be included in the discussion
while dealing with the aforesaid issue. Thereafter, the High Court has
discussed the scope of interference under Sections 34 and 37 of the Act,        F
with particular reference to the ground of challenge on the basis that the
award is against “Public Policy of India”. After referring to the law on
this pivotal aspect, the High Court noted the points of arguments advanced
by the appellant affirming part of challenge to the Award. Six points
which were advanced by the appellant in this behalf are as under:               G
  (i)   Whether the Arbitral Tribunal and the learned Single Judge were
        justified in coming to the conclusion that the MSEB had
        committed breach of contract by not supplying DTC Lists?
  (ii) Whether the contract was one complete contract and the same
       could not be split up as argued by the Claimants?                        H
746             SUPREME COURT REPORTS                            [2018] 1 S.C.R.


A       (iii) Whether Claimants/DSL waived their right to receive complete
              lists of locations?
        (iv) Whether the Award is contrary to the public policy as mentioned
             under Section 34 of the Arbitration and Conciliation Act, 1996?
        (v) Whether the damages were properly awarded?
B
        (vi) Whether the aspect of mitigation was properly considered?
              15.Thereafter, discussion ensued on each of the aforesaid issue,
      one-by-one. On the first point, the High Court has concluded that the
      Arbitral Tribunal was justified in coming to conclusion that the appellant
C     had committed breach of the contract by not supplying DTC list. While
      so concluding, the High Court went into the events which took place in
      this behalf, gist of the evidence as well as the manner in which the issue
      was upraised by the Arbitral Tribunal. The High Court has held that the
      finding which was given by the Arbitral Tribunal, after taking into
      consideration the rival contentions raised in the claim and in the written
D     statement on this aspect is a finding of fact which was given after
      examining the material on record. The High Court further noted that
      this finding was upheld by the learned Single Judge also and the manner
      in which the learned Single Judge dealt with the issue has been taken
      note of. This being a finding of fact, as per the High Court it was not
E     possible for it to substitute its own view to the views taken by the Arbitral
      Tribunal or the learned Single Judge and arrive at different conclusion,
      even if two views were possible. Notwithstanding the same, the Division
      Bench again examined this very issue on merits after going through the
      various clauses in the contract entered into between the parties. Taking
      particular note of clauses 5.2 and 5.3, the Division Bench has affirmed
F     the findings of the Arbitral Tribunal in the following manner:
        “46. Clause 5.2 is also relevant since it stipulates about the manner in
             which installation/replacement work was to be carried out by
             DSL. The work was to be completed in three Zones, viz.,
             Kolhapur Zone, Nasik Zone and Aurangabad Zone. In clause
G            5.2 sequence of Zones was mentioned in which the work was to
             be carried out and it was as under:-
        (a) Kolhapur Zone
        (b) Nasik Zone. Work to be commenced on completion of work in
            Kolhapur Zone.
H
MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO.                              747
 LTD. v. M/S. DATAR SWITCHGEAR LTD. [A. K. SIKRI, J.]

 (c) Aurangabad Zone. Work to commence on completion of work in             A
     Nasik Zone.
     The sequence therefore was that, first in Kolhapur Zone B-I, B-
     II, B-III objects were to be installed and, thereafter, in Nasik
     again B-I, B-II, B-III objects were to be installed and finally in
     Aurangabad, B-I, B-II and B-III objects were to be installed.          B
     The said schedule of completion of work, however, was changed
     from time to time and, finally, again, in December, 1998 MSEB
     informed DSL to follow the schedule as per clause 5.2.
     47. Clause 5.3 lays down that supply, erection at site and
     commissioning of the contract objects was to be done within a          C
     stipulated time. It also clarified that time is the essence of the
     contract and if there was delay in performance due to any reason
     MSEB would be entitled to claim liquidated damages. The
     chronology of events indicates that on 14/7/1997, MSEB by its
     letter informed DSL that Lists of DTC locations were ready
     with the Circle Offices and DSL should collect the same. The           D
     case of DSL in brief is that though it was represented by MSEB
     that Lists were ready and available on 14/7/1997, Lists were not
     supplied and, as a result, installations could not be done and as
     many as 120 letters had to be written by DSL to MSEB,
     requesting them to supply the Lists. Secondly, sequence of             E
     completion of work also was changed from time to time and
     suddenly on 21/12/1998 Circle Engineer informed DSL that
     sequence as per clause 5.2 of the work order had to be adhered
     to and, DSL was therefore constrained to send a letter of
     termination dated 19/02/1999 and even thereafter in a meeting
     which was held on 11/3/1999 between the Chairman of the                F
     MSEB, DSL and other two parties who were awarded the
     contract, as mentioned in clause 17 of the minutes of the meeting,
     the Chairman informed DSL that the Lists were readily available
     in Kolhapur Zone and asked Mr. Datar to take up the work under
     B-II and B-III schedule immediately and the Chairman directed          G
     that CEs present in the meeting that it was the Board’s
     responsibility to give the list with maps to the agencies and
     expeditious steps should be taken in that regard. It was, therefore,
     contended that as late as 11/3/1999, the Chairman himself had
     conceded that the Lists were not made available to DSL. In this
                                                                            H
748            SUPREME COURT REPORTS                          [2018] 1 S.C.R.


A            context, certain letters assume importance regarding change of
             sequence of work. The work order dated 27/3/1997 shows that
             the work initially had to be done in Kolhapur Zone, then in Nasik
             Zone and finally in Aurangabad Zone. Thereafter, Chief Engineer,
             MSEB by his letter dated 4/11/1997 changed the sequence and
             directed that the work should be completed initially in Nasik Zone
B
             in respect of B-I, B-II, B-III Lists, then in Kolhapur Zone and
             finally in Aurangabad Zone. This sequence was again modified
             by the Chief Engineer’s letter dated 25/5/1998 and modification
             was made in the sequence of schedule and sequence of zone
             continued and work could be completed at any stage in any Zone.
C            Again, third modification was made by Chief Engineer’s letter
             dated 17/6/1998 and there was modification in respect of Zones
             and work could be carried out in any Zone in any sequence.
             Then there was fourth modification by Chief Engineer’s letter
             dated 21/12/1998 and direction was given to strictly adhere to
D            the original work order sequence. According to DSL, because
             the Lists were not supplied though the contract objects/gadgets
             were ready for installation and though they were taken to the
             sites at the respective Zones, they could not be installed and
             were lying stranded causing monetary loss on account of
             transportation, manual labour etc. and non-installation of contract
E            objects resulted in DSL not getting benefit of lease rentals.”
             16. Interestingly, before the Division Bench, the appellant had
      raised certain additional points on this aspect, which were not argued
      before the Tribunal or even before the learned Single Judge, viz., the
      non-supply of DTC locations did not amount to breach of fundamental
F     term of the contract which led to termination of contract by the
      respondent. We would like to reproduce, at this stage, this part of
      discussion as well:
             “48. It must be noted here that before the learned Single Judge
             and before this Court, some of the points which were never
G            urged before the Tribunal had been sought to be urged. In the
             written submissions which have been tendered before us and
             what was urged before us was that the Arbitral Tribunal had
             committed serious error by holding that non- supply of DTC
             locations amounts to breach of fundamental term of contract
H            which led to termination of contract by Respondents/Claimants.
 MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO.                                    749
  LTD. v. M/S. DATAR SWITCHGEAR LTD. [A. K. SIKRI, J.]

       It has been contended before us that since each contract object             A
       was a separate lease contract, the Arbitrator’s Award has to be
       considered in three parts (i) qua uninstalled objects, (ii) qua installed
       objects and (iii) damages in respect of the objects not even
       manufactured and it has to be noted here that Tribunal has framed
       one of the points as under:-
                                                                                   B
       (A) Whether the Claimants were ready and willing to perform
           their part of the contract and if so, whether Respondents
           prevented the Claimants from doing so?
       While answering this point, the point was discussed in two parts.
       Firstly, whether the Claimants were ready and willing to perform            C
       their part of the contract and, secondly, whether Respondents
       have prevented the Claimants from doing so. In this context,
       after having held that Claimants were ready and willing to
       perform their part of the contract, while considering the second
       point, the Tribunal had taken into consideration the question of
       supply of DTC Lists and whether it was a fundamental term of                D
       the contract. After having held that MSEB had prevented DSL
       from performing their part of the contract even though they were
       ready and willing to do so, the question of damages has been
       thereafter separately considered and on that point Tribunal has
       adopted a particular method of calculation of damages. In our               E
       view, it is not permissible for MSEB to now change their
       submissions in this manner. However, even if the submissions,
       as advanced before us by MSEB, are taken into consideration,
       they are devoid of merits.”
      17. Thereafter, the High Court took note of another argument of              F
the appellant herein, namely, the contract was terminated by the
respondent on account of non-renewal of Letter of Credit in view of
respondent’s letter dated February 19, 1999. However, the High Court
did not accept the said argument as valid and rejected the same.
Thereafter, the High Court has recorded its specific findings on Point
No. 1 and we reproduce relevant portion thereof as under:                          G
       “In our view from the material on record, it is abundantly clear
       that supply of DTC Lists was a fundamental term of the Work
       Order and MSEB had miserably failed in complying with the
       said fundamental term and there was a breach on the part of the
       MSEB in supplying the DTC locations which eventually                        H
750    SUPREME COURT REPORTS                             [2018] 1 S.C.R.


A     prevented DSL from installation of contract objects. It has to be
      noted here that after the work order was issued by MSEB, DSL
      had to make necessary arrangements for the purpose of carrying
      out the process of installation of the contract objects. This included
      procurement of raw material from a foreign country, starting the
      process of manufacturing gadgets, making arrangements for
B
      transportation of these contract objects to the places where the
      said gadgets were to be installed, employment of trained, skilled
      and other staff, making available vehicles for transporting these
      contract objects to the DTC location where they were to be
      installed and, finally, coordinating with the Officers of MSEB so
C     that after the contract objects were installed, a Certificate of
      installation could be given by the Officers of MSEB so that from
      that point onwards, lease rentals could become payable to DSL.
      It has to be borne in mind that the nature of the Work Order was
      such that it was in the interest of DSL to ensure that the contract
      objects are installed and certificates to that effect are obtained
D
      from the Officers of MSEB. It does not sound to reason that
      after having invested huge amount of almost Rs 163 crores, as
      observed by the Tribunal in the Award, DSL would not install the
      objects because it was in their interest to get the objects installed
      so that returns on their huge investment would start thereafter.
E     It is inconceivable therefore that though DTC Lists were
      available, DSL would not install the contract objects. Various
      facts and figures were given by MSEB to show that DTC
      locations were known to DSL and yet they had failed in installing
      the contract objects is without any substance. It cannot be
      forgotten that, initially, the sequence of installation was Kolhapur,
F
      Nasik and Aurangabad. This sequence was later on changed to
      Nasik, Kolhapur and Aurangabad. This was again changed and
      permission was given to DSL to install the objects at any time at
      any place and, lastly, again, this was changed and direction was
      given to DSL to adhere to the sequence as per the Work Order.
G     This being the position, even assuming that B-II Lists were
      available, DSL could not have installed these contract objects
      because they were asked to follow the schedule again by letter
      dated 21/12/1998 and, therefore, even if the lists were available,
      it was not possible for DSL to simultaneously install all those
      objects since they were told to adhere to the sequence in the
H
 MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO.                               751
  LTD. v. M/S. DATAR SWITCHGEAR LTD. [A. K. SIKRI, J.]

        Work Order if the lists of locations under B-I were not given,        A
        even assuming that they had B-II lists of locations they could not
        have and were not actually allowed to install at the said B-II
        locations. It has come on record that more than 10,000 objects
        were manufactured and ready for installation. There is no earthly
        reason why DSL would fail to install the objects which were
                                                                              B
        inspected and ready for installation. The only obvious reason
        would be that they were unable to do so on account of various
        orders which were passed by MSEB from time to time
        preventing them from performing their obligation. MSEB has
        not examined any of its Superintending Engineers who were in
        charge of supplying the Lists. The cumulative effect of all the       C
        material which has been brought on record is that it clearly
        demonstrates the failure on the part of MSEB in supplying the
        Lists of DTC locations which was a fundamental term of the
        contract.”
       18.Coming to point no. 2, the High Court noted that this point was     D
not urged before the Tribunal or before the learned Single Judge, namely,
the contract was not one complete contract. For this reason, held the
High Court, it was not permissible for the appellant to urge the same for
the first time before it.
       19. Point nos. 3 and 4 were taken up together for discussion.          E
Insofar as point no. 3 is concerned, the Court noted that relevant
provisions in the light of which this point was to be examined, were
Sections 39, 53, 55 and 63 of the Contract Act. The High Court found
that when Chief Engineer of the appellant had written a letter dated
December 21, 1998 informing the respondent that work had to be carried
as per the original schedule given in the Work Order, viz., Kolhapur,         F
Nasik and Aurangabad and a further direction was given not to install
objects at B-III locations, only at that stage the appellant had refused to
perform their part of promise. Only, thereafter, notice was given by
respondent on February 19, 1999 and finally the contract was terminated
on April 21, 1999. Therefore, there was no waiver of right of acquiescence    G
on the part of the respondent and, thus, argument of the appellant could
not be accepted that the respondent had waived their right to terminate
the contract. The High Court also held that the question of waiver or
acquiescence is a question of fact and since there was a finding of fact
by the Arbitral Tribunal (which was upheld by the Single Judge as well)
                                                                              H
752             SUPREME COURT REPORTS                           [2018] 1 S.C.R.


A     that there was no waiver or acquiescence on the part of the respondent,
      such an argument was not even available to the appellant in appeal under
      Section 37 of the Act. On this basis, the Division Bench rejected the
      contention of the appellant that the respondent waived its right to receive
      complete list of locations. In the process, the High Court has also rejected
      the contention of the appellant that as a consequence of waiver of right
B
      to receive list of DTC locations, the only option which was available to
      the respondent was to have given notice to the appellant that it was
      accepting the performance of the promise other than at the time agreed
      upon or that the respondent was entitled to any compensation.
             20.With the aforesaid findings on Point no. 3, the High Court
C     rejected the contention of the appellant that the award of damages was
      against the public policy.
             21. Thereafter, the High Court discussed the question of quantum
      of damages as raised in Point No. 5. It went through the exercise done
      by the Arbitral Tribunal in this behalf, i.e., the manner in which the
D     damages are calculated by the Tribunal. It found that the Tribunal had
      appreciated to determine the damages payable to the respondent in
      respect of lease rent for duration of seven years for 17294 contract
      objects which were installed and a figure of Rs. 108,02,53,173/- in this
      behalf was arrived at. In respect of 14206 stranded objects, the Tribunal
E     held that the damages which were payable on account of aforesaid
      stranded objects were to the tune of Rs. 14,28,55,536/- for a period of
      one year at the rate of Rs. 10,056/- per year for each contract object
      and for a duration of five years Rs. 71,42,77,680/-. As regards those
      objects which were not manufactured, the Arbitral Tribunal took into
      consideration the value of unused imported raw material. On that basis
F     it came to the conclusion that damages in respect of imported raw material
      left unused for 16487 contract objects were Rs. 6,52,55,546/-. In this
      manner, it arrived at a total figure of Rs. 185,97,86,399/- and deducted a
      sum of Rs. 6,81,99,390/- which was paid by the appellant to the respondent
      pursuant to interim orders passed by the Tribunal.
G           22. After taking note of the manner in which the Tribunal awarded
      the damages, the High Court noted the challenge of the appellant’s
      counsel to the award of damages, which were as under:
              (i)   Since there was no breach committed by the appellant and
                    that the respondent had no right to terminate the contract,
H                   no damages were payable.
 MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO.                               753
  LTD. v. M/S. DATAR SWITCHGEAR LTD. [A. K. SIKRI, J.]

        (ii) Since the cost of contract object was on an average of Rs.       A
             9,000/- per object, the respondent, at the best, was entitled
             to nominal profit of 10-15% on the said cost. Therefore,
             the Arbitral Tribunal had granted excessive damages.
        (iii) The damages were wrongly awarded for objects not even
              manufactured and such an award was in violation of public       B
              policy as mentioned in Section 34 of the Act.
        (iv) According to the understanding of the appellant, the contract
             was coming to an end on March 19, 1999 and the contract
             objects, therefore, should have been manufactured by it.
             Thus, failure to manufacture the same did not entitle them       C
             to claim any damages qua the objects not manufactured.
        (v) Since the contract was novated, the respondent was obliged
            to manufacture the objects as and when the lists were
            supplied to it and, therefore, the question of payment of any
            compensation qua the objects not manufactured did not             D
            arise.
        (vi) There was no default qua the installed or qua uninstalled
             objects and on this ground also the Tribunal was not justified
             in granting any compensation whatsoever.
        (vii) In respect of the installed objects, the only breach was non-   E
              renewal of the Letter of Credit. Likewise, in respect of
              un-installed objects, the only breach was non-submission
              of lists of locations. Insofar as non-renewal of Letter of
              Credit is concerned Arbitral Tribunal had decided this issue
              in favour of the appellant and, therefore, no damages were      F
              awardable. In respect of uninstalled objects, the respondent
              had 16473 lists of location and they were obliged to maintain
              2500 buffer stock. However, the respondent had
              manufactured only 14206 objects, therefore, there was no
              question of payment of any damages qua uninstalled objects.
                                                                              G
      23. Since this issue was connected with Point No. 6, i.e., mitigation
of damages, the High Court dealt with the argument of mitigation as
well. Here, contention of the appellant was that according to the
respondents the breach, if at all, took place only on December 21, 1998
when permission for simultaneous installation in B-III was withdrawn
and no steps whatsoever to remedy the breach thereafter were taken            H
754            SUPREME COURT REPORTS                            [2018] 1 S.C.R.


A     by the respondents. This showed that the respondents had not tried to
      mitigate their loss and were not entitled to get damages. Here the
      argument of the respondent was also noted and after considering the
      respective arguments, the High court has not found any substance in the
      submissions of the appellant. It has given following reasons for adopting
      this course of action:
B
             “73. We agree with the submissions made by the learned Senior
             Counsel appearing on behalf of DSL for the following reasons:
               First of all, it has to be noted that Arbitral Tribunal in its Award
               has recorded a finding of fact that MSEB had committed breach
               of the contract by not supplying the lists of DTC locations and
C
               this breach was a fundamental breach of the agreement.
               Secondly, it is held that MSEB had prevented DSL from
               performing its part of the contract and, therefore, they were
               entitled to get damages. The Arbitral Tribunal, thereafter, relying
               on the Judgment of the Supreme Court in Union of India v/s.
D              Sugauli Sugar (Pvt.) Ltd. [(1976) 3 SCC 32)] has observed
               that innocent party who has proved the breach of contract to
               supply what he had contracted to get, such a party should be
               placed in as good a situation as if the contract had been
               performed and, therefore, damages which the Claimants/DSL
               were entitled to have to be determined on the said principle.
E
               The Tribunal has then held that lease rent is one of the measures
               for ascertaining damages and, in that context, after relying on
               the Work Order, came to the conclusion that entitlement of the
               Claimants was to secure lease rent accrued from the date of
               installation of the contract objects. In this context, therefore,
F              for the sake of convenience the question of quantum of
               damages was considered with reference to (a) installation of
               contract objects, (b) stranded objects and (c) objects not
               manufactured. The submission of the learned Senior Counsel
               appearing on behalf of MSEB that the Arbitral Tribunal had
               split up the contract into three parts, though the contract was
G
               one single contract, is without any substance. It has to be
               noted that the Arbitral Tribunal first came to the conclusion
               that there was a breach on the part of MSEB in supplying the
               lists of DTC locations. Having held, that there was a breach
               and that the Claimants/DSL were entitled to claim compensation,
H              while ascertaining the amount of compensation, for the sake
    MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO.                                  755
     LTD. v. M/S. DATAR SWITCHGEAR LTD. [A. K. SIKRI, J.]

             of convenience, it has considered the aspect of granting               A
             damages in the above manner. The entire thrust of the argument
             of MSEB, therefore, is misconceived. MSEB has tried to give
             a twist to their tale by contending that 17,294 contract objects
             being installed, there was no question of awarding damages
             for the installed objects and, secondly, since termination of Letter
                                                                                    B
             of Credit was held not to be illegal, it was not open for the
             Arbitral Tribunal to have awarded damages for the uninstalled
             objects and the objects which were not manufactured. This
             submission is totally misconceived, firstly because it has been
             consistently held that the Arbitral Tribunal alone is competent
             to decide the manner of calculation of damages which are to            C
             be awarded as also the method which is to be adopted by the
             Tribunal. In the present case, the Arbitral Tribunal has held
             that lease rent is one of the measures for ascertaining damages.
             The Apex Court in McDermott vs. Burn Standard [(2006) 11
             SCC 181] has observed as under:-
                                                                                    D
             “106. We do not intend to delve deep into the matter as it is an
             accepted position that different formulae can be applied in
             different circumstances and the question as to whether damages
             should be computed by taking recourse to one or the other
             formula, having regard to the facts and circumstances of a
             particular case, would eminently fall within the domain of the         E
             arbitrator.
             110. As computation depends on circumstances and methods
             to compute damages, how the quantum thereof should be
             determined is a matter which would fall for the decision of the
             arbitrator. We, however, see no reason to interfere with that          F
             part of the award in view of the fact that the aforementioned
             formula evolved over the years, is accepted internationally and,
             therefore, cannot be said to be wholly contrary to the provisions
             of the Indian law.”
       24. Citing few more judgments and after extensively quoting                  G
therefrom1, the High Court proceeded further with the discussion as
follows:
1
    (a) Dwarka Das v. State of M.P. and Another
    (b) ONGC v. Comex
    (c) Prakash Kharade v. Dr. Vijay Kumar Khandre and Others
    (d) Grandhi v. Vissamastti
    (e) Mirza Javed Murtaza v. U.P. Financial Corporation Kanpur and another        H
756            SUPREME COURT REPORTS                              [2018] 1 S.C.R.


A            “The Arbitral Tribunal, therefore, after having adopted lease rent
             as one of the methods of ascertaining damages has thereafter
             considered what damages should be awarded by way of lease
             rentals on installed objects, stranded objects and the objects not
             manufactured. In our view, it is not possible to find fault with the
             finding of the Arbitral Tribunal on the measure and method for
B
             ascertaining and calculating the damages which have been
             adopted by it to arrive at the final figure of compensation to be
             payable to the Claimants/DSL.
             It is also quite well settled position in law that once it is established
             that the party was justified in terminating the contract on account
C            of fundamental breach of contract then, in that event, such an
             innocent party is entitled to claim damages for the entire contract,
             i.e., for the part which is performed and also for remaining part
             of the contract which it was prevented to perform. This principle
             is quite well settled in number of cases. The Tribunal, therefore,
D            was perfectly justified in calculating the damages in the aforesaid
             manner. In this view of the matter we do not propose to deal
             with the judgments on which reliance is sought to be placed by
             MSEB.
             So far as the question of mitigation is concerned, the Tribunal
E            has specifically held that the contract objects were unique objects
             which had to be manufactured according to the specifications
             laid down by the MSEB and, therefore, these contract objects
             could not be disposed of in the open market. Even if the said
             contract objects were dismantled, value would become nil. The
             Tribunal also observed that Datar deposed with reference to
F            Exhibit-C-16 that efforts were made to sell the contract objects
             stranded in the factory to other Electricity Boards but those efforts
             did not succeed. The question of mitigation, therefore, was
             considered by the Tribunal and the submissions of MSEB were
             not accepted. In our view, reasoning given by the Tribunal cannot
G            be faulted.”
             25. According to the High Court, the Arbitral Tribunal had awarded
      damages in a most conservative manner and, thus, committed no
      illegalities in awarding these damages. At the end, the High Court dealt
      with the Chamber Summons which were filed by the appellant and on
H     detailed discussion thereupon, dismissed all these Summons.
 MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO.                                  757
  LTD. v. M/S. DATAR SWITCHGEAR LTD. [A. K. SIKRI, J.]

       26. As a consequence, the appeal of the appellant stood dismissed.        A
ARGUMENTS OF THE APPELLANT :
       27 Mr. Vikas Singh referred to the tender of 1993-94, pursuant to
which the respondent had installed 12,555 numbers of LTSC, and
submitted that the respondent was maintaining the same but large scale
complaints about the inefficiency of LTSC was received with the                  B
appellant. Having regard to this criticism faced by the respondent, it
volunteered to replace the installations made in the earlier contract and
charge the old rental in respect of the same. In the meantime, pursuant
to tender of the year 1996 for installation, the respondent was awarded
work for installation of 11,760 contract objects. Going by the said              C
assurance, the appellant awarded a work order dated March 27, 1997
for replacement of 12,555 panels of earlier contract objects plus installation
of 23,672 LTMS panels and the work order finally became as under:
        (i)   Supply 11,760 numbers equipments against the tender of
              1996-1997 contract. B-I Locations;                                 D
        (ii) 12,555 numbers replacement of equipments against the
             1993-94 contract – B-II locations; and
        (iii) 23,672 numbers equipments which was given as a package
              with the B-II Locations – B-III locations.
                                                                                 E
       28. Mr. Vikas Singh referred to Clause 5.1 of the contract as per
which entire supply and installation of L.M. Systems covered by schedules
at Annexures – B-I, B-II and B-III was to be completed within twenty
months. He thereafter read out the correspondence that was exchanged
between the parties and on that basis, he sought to argue that as per the
appellant, the list of locations was ready on July 14, 1997 but it is the        F
respondent who was facing difficulties in installation of the contract objects
and violating the terms of the contract with impunity. The respondent
had even withdrawn money in excess of its entitlement. Vide letter dated
December 21, 1998, the appellant had written to the respondent to do
installation of B-I and B-II first before B-III locations, as by that date,
                                                                                 G
the respondent had already installed 17,294 objects out of which B-II
was only 2014. However, the respondents in their reply dated March
21, 1998 asserted their right to install the objects at B-III locations
simultaneously. He further pointed out that in their letter dated February
18, 1999, the respondent admitted having received Rs.4.34 crores in
excess of their entitlement, however, on the very next date, i.e. on             H
758             SUPREME COURT REPORTS                            [2018] 1 S.C.R.


A     February 19, 1999, it sought to terminate the contract qua the uninstalled
      objects numbering 30,695 but volunteered to maintain the installed objects
      provided that the rent for the same was forthcoming. It was argued that
      since the payment of rent was by means of an irrevocable LC, and since
      the LC was valid on February 19, 1999, the offer of maintaining 17,294
      objects was clearly accepted by the appellant as the appellant did not
B
      cancel the LC in spite of termination of the contract qua uninstalled
      objects on February 19, 1999. In other words, the LC continued to
      remain alive even after termination of the contract on February 19, 1999
      in order to make payment of future rentals qua the uninstalled objects.
      In spite thereof, the respondent, vide its communication dated April 21,
C     1999, terminated the contract. It was submitted in the aforesaid backdrop
      that the action of the respondents was clearly illegal. It was further
      argued that the findings of the Arbitral Tribunal that the appellant had
      committed the fundamental breach of the contract in not providing the
      complete list of the contract objects to the respondents is clearly erroneous
      which is patently illegal and contrary to the terms of the contract. It was
D
      submitted that the entire premise of the Arbitral Tribunal to record this
      finding was on the basis of the letter of the appellant dated December
      21, 1998 which had only debarred the respondent from installing B-III
      locations as the respondent was indulging in the malpractice of charging
      bills higher than what they were entitled to which is proved by the credit
E     note given by the respondents themselves on February 18, 1999. The
      said letter did not debar the respondent from installing the B-II locations
      which were 10,541 remaining to be installed on February 19, 1999. The
      Arbitral Tribunal recorded a perverse finding which resulted in patent
      illegality in the award that by letter dated December 21, 1998 the appellant
      had debarred the respondent from installing the B-II locations when
F
      clearly neither the same was mentioned in the said letter nor was the
      same understood contemporaneously by the respondent in their response
      dated December 23, 1999 wherein they merely protested from being
      denied the opportunity to install the B-III objects. The Arbitral Tribunal
      accordingly committed a grave mistake in holding that the appellant had
G     committed a fundamental breach when clearly on the date of termination
      the respondent had with them 10541 B-II locations and admittedly 1633
      B-I locations in Kolhapur Zone and they were under an obligation under
      the contract to maintain 2500 buffer objects and hence the respondent
      had only 14026 contract objects at that time whereas they were required
      to maintain at least 14,674 contract objects on the said date.
H
 MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO.                                   759
  LTD. v. M/S. DATAR SWITCHGEAR LTD. [A. K. SIKRI, J.]

        29. Next submission of Mr. Vikas Singh, learned senior counsel,           A
was that the Arbitral Tribunal gave a specific finding that the LC was
valid till April 30, 1999 and there was no default on the part of the appellant
in this behalf, which finding was also confirmed by the learned Single
Judge as well as by the Division Bench which had heard the appeal in
the first round. Therefore, there was no occasion whatsoever for the
                                                                                  B
Arbitral Tribunal to award damages qua the installed objects as there
was no default alleged and there was no default held to have been
committed by the appellant qua the same.
        30. Much emphasis was laid by the learned senior counsel for the
appellant on the order dated August 3, 2005 passed by the learned Single
Judge in the appellant’s petition under Section 34 of the Act (in the first       C
round), whereby the learned Single Judge had decided the case in favour
of the appellant holding that there could not be any direction for payment
of damages in respect of the installed objects as no default was found by
the Arbitral Tribunal and, therefore, the Tribunal committed a grave
mistake in awarding compensation in respect thereof. In order dated               D
August 3, 2005, the learned Single Judge had also held that the Arbitral
Tribunal had committed illegality by awarding compensation in respect
of the objects manufactured but not installed while permitting the
respondents to retain the same. Likewise, the award was faulted with
to the extent that the Arbitral Tribunal awarded the amount for the raw
material available with the respondent, without directing the respondent          E
to handover the said raw material to the appellant. Though, this order
dated August 3, 2005 was set aside by the Division Bench in appeal
which was preferred by the respondent, submission of the learned senior
counsel was that it was erroneously set aside on the only ground that the
Single Judge while allowing Section 34 petition had not specifically              F
mentioned the particular section under which the petition had been allowed
when clearly the order of the learned Single Judge had been passed on
the ground that the award is against the public policy of India and hence
it was clearly referable to Section 34(2)(b)(ii) of the Act. Hence, there
was no occasion or necessity to remand the matter back to the Single
Judge of the High Court. Since the direction by the Division Bench were           G
to the Single Judge was to decide the matter in a time bound manner,
even before the appeal against the order of the Division Bench could be
heard by the Supreme Court, the learned Single Judge of the Bombay
High Court rejected Section 34 petition on a completely erroneous premise
as if that the appellant had argued the case under Section 34(2)(iv) when         H
760               SUPREME COURT REPORTS                               [2018] 1 S.C.R.


A     admittedly no arguments had been raised under the said Section and the
      entire arguments as well as the written submission were only with regard
      to the award being contrary to the public policy which is under Section
      34(2)(b)(ii). In this manner, submitted the learned senior counsel, the
      learned Single Judge went beyond the mandate of the Division Bench
      while dismissing the petition of the appellant in its entirety under Section
B
      34 of the Act and the Division Bench has also erred in giving its imprimatur
      to such an order of the Single Judge.
             31. Continuing his submissions with great emphasis, Mr. Vikas
      Singh further argued that an important issue which need consideration is
      as to whether the contract was one complete contract and whether the
C     same could or could not be split up as argued by the respondents. He
      referred to the provisions of the contract, the relevant correspondence
      and the submission of the respondents witnesses to refute the respondents
      contention that the contract was one bargain and there was no right to
      split up the same. He also referred to the certain judgments2 to contend
D     that the contract in question can be held to be clearly severable and it is
      the duty of the Courts to severe the enforceable part vis-à-vis the
      unenforceable part.
              32. Touching upon the facet of the uninstalled object, it was
      submitted that in terms of the work order, the supply and installation was
E     to commence from the date of the work order or opening of LC or
      receipt of complete list of locations of DTCs, whichever is later. On
      July 14, 1997, the appellant wrote to the respondents that the list of
      locations was available with the circle office. The respondents assumed
      July 14, 1997 as the date of making available the complete list of locations
      without actually receiving the said list from the circle office. The clause
F     very clearly provided the four month period to commence from the date
      of receipt of list of complete locations and admittedly the respondent did
      not receive the list of locations on July 14, 1997 nor any time thereafter
      till they started installation on November 18, 1997, considering the four
      month period to start from July 19, 1997 i.e. the date of receipt of the
G     2
          Firm Bhagwandas Shobhalal Jain, a Registered firm and Anr. v. State of Madhya
          Pradesh, AIR 1966 MP 95; Shin Satellite Public Co. Ltd. v. Jain Studios Ltd.,
          (2006) 2 SCC 628; Beed District Central Coop. Bank Ltd. v. State of Maharashtra
          & Ors., (2006) 8 SCC 514, Daruka & Co. v. Union of India & Ors., (1973) 2 SCC
          617 and Food Corporation of India v. Yousuff and Co., Kerala High Court (DB)
          (17.11.1980) A.S. No. 31 of 1976 at Page 2296 (starting from 2280-2297 of volume
H         X)
    MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO.                              761
     LTD. v. M/S. DATAR SWITCHGEAR LTD. [A. K. SIKRI, J.]

communication dated July 14, 1997. Clearly, the respondent had enough           A
time after July 14, 1997 to insist upon the complete list of locations before
any installation was started by them on November 18, 1997. Therefore,
argued the learned senior counsel, it is the respondent which committed
breach of contract in not completing the work.
       33. Mr. Vikas Singh once again emphasised the submission which           B
was made before the learned arbitrator as well as the High Court, that
there was a waiver by the respondent in respect of list of DTC location
and the consequences of such a waiver had to flow as per Section 55
read with Section 63 of the Contract Act. It was submitted that this
Court has held in the case of Waman Shriniwas Kini v. Ratilal
Bhagwandas & Co.3 at para 13 “waiver is the amendment of a right                C
which normally everybody had a liberty to waive. A waiver is nothing
unless it amounts to a release it signifies nothing more than an intention
to insist upon the right”. Accordingly, once the waiver takes place, the
clause with regard to providing the complete list does not remain a
fundamental term of the contract and the respondent would not be entitled       D
to claim any damages for the non-supply of the list. He also referred to
the decision in Jagad Bandhu Chatterjee v. Smt. Nilima Rani &
Ors.4 wherein at para 5, it is stated “it is open to a promisee to dispense
with or remit, wholly or in part, the performance of the promise made to
him or he can accept instead of it any satisfaction which he thinks fit.”
He also relied upon the judgment in Babulal Badriprasad Varma v.                E
Surat Municipal Corporation & Ors.5 and pointed out that in that case,
the Court has considered various judgments on the issue of waiver in
paragraph 42 to 49, which laid down that waiver amounts to abandonment
of right in such a way that the other parties entitled to plead the
abandonment by way of confession and avoidance if the right is thereafter       F
asserted and is either expressed or implied from the conduct. Number
of other judgments laying down the same proposition of law were also
referred to.
       34. Additionally, it was submitted that the appellant had on June
17, 1998 permitted the respondent to make feeder-wise installation              G
irrespective of B-I, B-II and B-III locations. Between June 17, 1998
to December 21, 1998 i.e. for a period of more than six months, the
respondents had all the B-II locations available to them which is 12,555
3
  1959 Supp. (2) SCR 217
4
  (1969) 3 SCC 445
5
  (2008) 12 SCC 401                                                             H
762            SUPREME COURT REPORTS                           [2018] 1 S.C.R.


A     out of which they only installed 2014 and they did not install 10541 B-II
      locations which were the locations where the respondent had themselves
      installed the contract objects against tender of 1993 and 1994 and were
      maintaining the said objects at the time when the present tender was
      awarded and hence were in the complete knowledge of the said locations.
      The endeavour was to show that the respondent was aware of sufficient
B
      number of locations, even B-II locations and, therefore, there was no
      reason to terminate the contract and, in fact, it is the respondent which
      had failed to perform its obligations under the contract and was, thus,
      responsible for the breach thereof. On that premise, the submission
      was that award of the Arbitral Tribunal qua the uninstalled object is
C     patently illegal and it also shocks the conscience of the Court and is
      liable to be set aside as being opposed to public policy. Specifically
      adverting to the damages awarded qua installed objects, it was argued
      that the work order clearly provided that each contract object was a
      separate contract between the appellant and the respondent and, therefore,
      it was incumbent upon the Arbitral Tribunal to decide as to what fault
D
      had been committed by the appellant qua the installed objects before
      granting any damages for the same. Absence of this exercise, contended
      the learned senior counsel, had rendered the award illegal and in violation
      of public policy as mentioned in Section 34 of the Act.
             35.While questioning the damages awarded in respect of objects
E     not even manufactured; quantum of damages awarded by the Tribunal
      and failure on the part of the respondent to mitigate the losses, the same
      arguments were advanced which were taken before the High Court as
      well. It is also submitted that the High Court committed serious error in
      rejecting the chamber summons.
F     ARGUMENTS IN REPLY BY THE RESPONDENT:
            36. Mr. Dada, learned senior counsel appearing for the respondent,
      strongly refuted all the aforesaid submissions of the appellant and made
      earnest effort to show that the entire approach of the Arbitral Tribunal in
      dealing with the issues and awarding the damages was correct in law
G     and this award was rightly held by the learned Single Judge as well as
      the Division Bench of the High Court.
             37. At the outset, Mr. Dada emphasized the crucial nature of the
      contract in question, which was essentially for operating lease for ten
      years in respect of energy saving devices which were to be installed by
H     respondent No.2 on the locations to be given by the appellant herein.
 MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO.                                763
  LTD. v. M/S. DATAR SWITCHGEAR LTD. [A. K. SIKRI, J.]

He pointed out that since it was a contract for operating these devices        A
on lease basis, entire investment was to be made by respondent No.2
and the appellant was only to give the lease rent, that too on the condition
that contract objects were working satisfactorily. Further, the contract
being a ‘lease’ contract, the ownership of the equipment had to remain
with respondent No.2 and was never to be transferred to the appellant.
                                                                               B
In the aforesaid scenario, argued the learned senior counsel for
respondent No.2, respondent No.2 could perform its part of the contract
of installation of objects only on furnishing the DTC locations. He argued
that the appellant failed to discharge this obligation and, thus, committed
fundamental breach of the contract. This has been held so by the Arbitral
Tribunal and this very finding was upheld by the High Court as well.           C
Submission was that this being a finding of fact, the breach of contract
on the part of the appellant stands established.
       38. Elaborating on this aspect, it was contended that the appellant
made an unequivocal representation to respondent No.2 on 14.07.1997
that complete lists for DTC locations, including Schedule B-II, are ready      D
with the district offices. Respondent No.2 acted upon the said
representation and commenced installation in November 1997. On
20.04.1998, the appellant threatened respondent No.2 with liquidated
damages and warned that time will not be extended for installation. This
letter glossed over the fact that DTC locations were withheld by the
district offices of the appellant. Both parties were ad idem that time had     E
started to run and installation was to be completed before 18.03.1999
(twenty months from 18.07.1997, i.e. the date of receipt of the letter
dated 14.07.1997 from the appellant). Despite rigorous follow up and
distress appeals by respondent No.2 through more than 120 letters, the
appellant did not furnish complete lists of DTC locations. On 21.12.1998,      F
the appellant directed the work to proceed strictly in the sequence –
Kolhapur, Nasik and Aurangabad Zones, with further sequences B-1,
B-2 and B-3. The appellant stopped work under B03 indefinitely without
assigning any reason. However, even till 19.02.1999, respondent No.2
was not provided with complete list of B-I locations in Kolhapur. Despite
representation of 11.02.1999 from Technical Member of the appellant to         G
give lists within four days, i.e. by 15.02.1999, no lists were received.
Realizing the futility of expecting cooperation from the appellant,
respondent No.2 terminated the contract on 19.02.1999.
      39. It was further submitted that respondent No.2 still ‘offered’ to
maintain the 17294 installed objects (however, the appellant was admitting     H
764             SUPREME COURT REPORTS                           [2018] 1 S.C.R.


A     installation of only 7000 contract objects as of July 199, as stated by
      respondent No.2 in the interim application filed before the Arbitrators),
      provided that payment was made without demur or dispute – obviously
      alluding to the financial blockade by NIL performance certificates and
      fabrication of failure reports. Respondent No.2 gave the appellant seven
      days to convey if the said “offer” was acceptable. Admittedly, the
B
      appellant did not accept the offer and proceeded to make a counter
      claim against respondent No.2 on the footing that respondent No.2 had
      abandoned the entire contract on 19.02.1999, including that for installed
      objects.
              40.It was next argued by Mr. Dada that after the disputes were
C     referred to the Arbitral Tribunal, it went into the length and breadth of
      each issue in minute detail. This Tribunal consisted of eminent retired
      Judges who scanned through the deposition of witnesses produced before
      it as well as other documentary evidence. 125 sittings, over a period of
      five years, were held in the process, which culminated into a fully reasoned
D     and unanimous award dated 18.06.2004 running into 150 pages, as per
      which the matter was decided in favour of respondent No.2 and against
      the appellant. His argument was that most of the submissions of the
      appellant were questioning the findings of facts only and this Court would
      not embark on such a journey and decide correctness thereof in exercise
      of its jurisdiction under Article 136 of the Constitution.
E
           41.We find adequate force in the aforesaid submission of Mr.
      Dada. Let us first take note of these findings:
      FINDINGS OF FACTS :
            42.Reasoning contained in the Award reveals following salient
F     findings returned by the Arbitral Tribunal:
              (i)   The appellant prevented respondent No.2 from performing
                    the contract.
              (ii) Respondent No.2 was ready and willing to perform the
                   contract all throughout.
G
              (iii) The appellant chose not to examine any of its Superintending
                    Engineers who were in-charge for giving DTC locations to
                    respondent No.2 and, as found by the Arbitral Tribunal, they
                    were the kingpins of each circle for performance of the
                    contract.
H
MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO.                              765
 LTD. v. M/S. DATAR SWITCHGEAR LTD. [A. K. SIKRI, J.]

     (iv) There is considerable merit in the submission of respondent       A
          No.2 that the Minutes of the Meeting dated 24.06.1998 is a
          fabricated document.
     (v) It is not possible to accede to the submission of the appellant
         that respondent No.2 had adequate lists of locations
         available and still failed to install the contract objects.        B
     (vi) It is obvious that there is something seriously wrong in the
          working of the appellant. Once a letter is listed in the
          affidavit of documents, it is surprising how the letter was
          not traceable. Be that as it may, the fact remains that prior
          to the date of termination of contract, at least in three         C
          Circles, the appellant had directed stoppage of installation
          work.
     (vii) It is unfortunate that the Head Office of the appellant lacked
           control over the field offices and which ultimately led to the
           failure of the project. It is futile to even suggest that the    D
           breach was not a fundamental one.
     (viii) Respondent No.2 was ready and willing to perform their
            part of the contract while the appellant committed a breach
            by failure to supply DTC locations as per the terms of the
            contract.                                                       E
     (ix) Respondent No.2 invested Rs.163 crores in the project.
     (x) The appellant failed to prove that deductions effected in
         the Performance Certificates were proper.
     (xi) The appellant indulged in tampering the commissioning
                                                                            F
          reports produced on record. The attempt does not behove
          to a statutory body and requires to be deprecated. The
          attempt made by the appellant by producing documents
          which are tampered with and which are not genuine indicates
          that the appellant was willing to go to any extent to make
          allegations against respondent No.2.                              G
     (xii) The appellant did not make available large number of
           documents disclosed in the affidavit of documents on the
           ground that the same are not available.
     (xiii) Counter claim of the appellant is misconceived and is nothing
                                                                            H
766             SUPREME COURT REPORTS                            [2018] 1 S.C.R.


A                   short of counter blast to the claim made against respondent
                    No.2.
              (xiv) It was the appellant and appellant alone who had committed
                    fundamental breaches of the terms of the work order.
              (xv) The appellant has raised untenable and unsustainable
B                  defences which led to considerable delay in concluding the
                   proceedings.
                These are findings of facts based upon the material evidence
              that emerged on the record of the case.

C     TERMINATION OF CONTRACT WAS VALID AND
      JUSTIFIED :
              43. Categorical findings are arrived at by the Arbitral Tribunal to
      the effect that insofar as respondent No.2 is concerned, it was always
      ready and willing to perform its contractual obligations, but was prevented
D     by the appellant from such performance. Another specific finding which
      is returned by the Arbitral Tribunal is that the appellant had not given the
      list of locations and, therefore, its submission that respondent No.2 had
      adequate lists of locations available but still failed to install the contract
      objects was not acceptable. In fact, on this count, the Arbitral Tribunal
      has commented upon the working of the appellant itself and expressed
E     its dismay about lack of control by the Head Office of the appellant over
      the field offices which led to the failure of the contract. These are
      findings of facts which are arrived at by the Arbitral Tribunal after
      appreciating the evidence and documents on record. From these findings
      it stands established that there is a fundamental breach on the part of the
F     appellant in carrying out its obligations, with no fault of respondent No.2
      which had invested whopping amount of Rs.163 crores in the project. A
      perusal of the award reveals that the Tribunal investigated the conduct
      of entire transaction between the parties pertaining to the work order,
      including withholding of DTC locations, allegations and counter allegations
      by the parties concerning installed objects. The arbitrators did not focus
G     on a particular breach qua particular number of objects/class of objects.
      Respondent No.2 is right in its submission that the fundamental breach,
      by its very nature, pervades the entire contract and once acted committed,
      the contract as a whole stands abrogated. It is on the aforesaid basis
      that the Arbitral Tribunal has come to the conclusion that the termination
      of contract by respondent No.2 was in order and valid. The proposition
H
    MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO.                                      767
     LTD. v. M/S. DATAR SWITCHGEAR LTD. [A. K. SIKRI, J.]

of law that the Arbitral Tribunal is the master of evidence and the findings            A
of fact which are arrived at by the arbitrators on the basis of evidence
on record are not to be scrutinised as if the Court was sitting in appeal
now stands settled by catena of judgments pronounced by this Court
without any exception thereto6.
       44. At this stage, we may deal with the contention of the appellant              B
to the effect that the arbitrators have themselves recorded a finding that
the LC was still in operation and had not expired and, therefore, the
finding of the Tribunal that the contract was terminated validly was self
contradictory.
       45. Though this contention appears to be attractive in the first                 C
blush, we find no substance in the same on deeper examination thereof.
It was rightly contended by Mr. Dada that the Arbitral Tribunal has held
that since the contract was terminated on 19.02.1999, the appellant was
not required to renew the LC. In other words, since there was no contract
in existence after 19.02.1999, there could not be a breach. It is apt to
quote the following discussion from the award of the arbitrators:                       D

           “24...The grievance of the Claimants that by not renewing letter
           of credit which expired on April 30, 1999, the Respondents have
           committed the breach, cannot be accepted. In the first instance,
           the Claimants cannot complain about non-renewal of Letter of
           Credit on April 30, 1999 when the claimants themselves have                  E
           terminated the contract by notice dated February 19, 1999.
           Secondly, the claimants have invoked the arbitration on April 13,
           1999 and these events having taken place prior to April 30, 1999,
           there was no point in Respondents renewing Letter of Credit for
           the benefit of the Claimants.”                                               F
        46. By the aforesaid analysis, the Arbitral Tribunal did not accept
the contention of respondent No.2, which was predicated on non-renewal
of the LC. However, the context in which these observations are made
is abundantly clear. The Arbitral Tribunal had confined the discussion
revolving around the contention of respondent No.2 as to why the LC                     G
was not extended even after 30.04.1999. In this hue, it was observed
that there was no reason or rationale in doing so when the contract had
itself come to an end as it had been terminated by respondent No.2 itself
6
    (See – Associate Builders v. Delhi Development Authority, (2015) 3 SCC 49, and S.
     Munishamappa v. B. Venkatarayappa & Ors., (1981) 3 SCC 260)
                                                                                        H
768               SUPREME COURT REPORTS                            [2018] 1 S.C.R.


A     vide notice dated 19.02.1999. It would not follow therefrom that
      respondent No.2 was wrong in terminating the contract. Insofar as the
      termination of the contract is concerned, the Arbitral Tribunal dealt with
      the issue specifically and on independent examination thereof had came
      to the conclusion that respondent No.2 was justified in the said action as
      there were other breaches on the part of the appellant. It is to be borne
B
      in mind that non-renewal of LC was not the only breach alleged by
      respondent No.2, which had asserted various other acts of breach on
      the part of the appellant. In this behalf, Mr. Dada drew our attention,
      and rightly so, to the letter dated 18.11.1998 which is contemporaneous
      to the letter of termination, wherein respondent No.2 categorically alleged
C     fabrication of Commissioning Reports of installed objects and the financial
      blockade created by the issue of NIL Performance Certificates by the
      appellant. This letter is referred to in the letter of 19.02.1999 by
      incorporating references contained in the letter dated 23.12.1998.
      Respondent No.2, in its Statement of Claim, has also asserted the
      harassment and deliberate breach of the appellant in the course of
D
      installation of objects such as fabrication of failure reports and
      commissioning reports, obstructing payments by bogus deductions in
      performance certificates and other wrong practices of the appellant staff.
      The serious grievances of respondent No.2 in respect of installed objects
      were considered at length by the Arbitral Tribunal and accepted the
E     same.
             47.We have already referred to these findings hereinabove.
      Learned senior counsel appearing for respondent No.2 referred to the
      judgment of this Court in Juggilal Kamlapat v. Pratapmal
      Rameshwar7 wherein it has been held that repudiation of a contract
F     can be justified on the basis of any ground that existed in fact, even
      though not stated in the correspondence. Following passage from the
      said judgment needs a quote:
                 “23. It was also contended that the defendant not having raised
                 the plea in their correspondence with the plaintiff that the delivery
G                orders tendered were defective, was estopped from justifying
                 their requisition of the contracts on that around. As the High
                 Court has pointed out no case of estoppel was pleaded by the
                 plaintiff and, therefore, it was the plaintiff who should be
                 precluded from raising the question of estoppel. Apart from that,
      7
          (1978) 1 SCC 69
H
 MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO.                               769
  LTD. v. M/S. DATAR SWITCHGEAR LTD. [A. K. SIKRI, J.]

       the law permits defendant to justify the repudiation on any ground     A
       which existed at the time of the repudiation whether or not the
       ground was stated in the correspondence. (See Nune
       Sivayya v. Maddu Ranganayakulu, AIR 1935 PC 67 : 62 IA
       89, 98).”
       48.One more aspect needs to be adverted to at this stage which         B
incidentally arises in view of the submission of Mr. Vikas Singh, learned
senior counsel appearing for the appellant.
       49. It was argued that respondent No.2 should have installed
objects at least under category B-2, even if there was breach on the part
of the appellant in supplying locations for categories B-1 and B-3. This      C
was refuted by learned senior counsel appearing for respondent No.2
on the ground that the Arbitral Tribunal had specifically considered and
rejected this argument and the approach of the arbitrators is even upheld
by the learned Single Judge as well as the Division Bench of the High
Court. We may point out that the Arbitral Tribunal has dealt with this
aspect in the following manner:                                               D

       “Datar was asked a specific question as to how the Claimants
       did not install the contract objects in category B-II and the answer
       of the witness was in four parts. The witness claimed that (a)
       the contract was entered into considering the commercial efficacy
       of installing given quantity of B-I and B-III categories to counter    E
       balance low revenue from B-II category. The witness claimed
       that as the Respondents did not supply the list of categories B-I
       and B-III, the Claimants were entitled to withhold installation of
       category B-II; (b) The annually installed at Nasik under B-II
       category was install at Nasik under B-II category was relatively       F
       less obstructive in Nasik Circle; (c) the locations under category
       B-II were intervened with locations of categories B-I and B-III
       and it was practically unviable to install objects of category B-II
       selectively. The list of B-II category was also required to be re
       identified by the Respondents separately as was done for the
       Nasik Circle and (d) the Respondents unilaterally willingly            G
       revoked the permission granted earlier to install simultaneously
       by letter dated December 21, 1998. Some of the reasons given
       by the witness cannot be termed as unreasonable in the facts
       and circumstances of the case. It cannot be overlooked that in
       respect of installation of objects under category B-II, the            H
770            SUPREME COURT REPORTS                            [2018] 1 S.C.R.


A            Claimants were entitled only to the rates fixed under year 1993
             and 1994 contract till the expiration of six year period while in
             respect of categories B-I and B-III, the lease rentals were
             considerably high.
                 In any event, it does not lie in the mouth of the Respondents
B            to urge that the claimants should have installed contract objects
             under category B-II when specific directions were given on
             December 21, 1998 to install objects under category B-II only
             after completion of installation under category B-I. The
             Respondents claimed that 16,477 locations were available on
             February 19, 1999 but that is not correct because taking into
C            consideration 10,541 locations of category B-II the available
             locations out of B-I and B-III categories were 5,932.”
           50.The Division Bench dealt with this contention in the following
      manner:
D            “In our view from the material on record, it is abundantly clear
             that supply of DTC Lists was a fundamental term of the Work
             Order and MSEB had miserably failed in complying with the
             said fundamental term and there was a breach on the part of the
             MSEB in supplying the DTC locations which eventually
             prevented DSL from installation of contract objects. It has to be
E            noted here that after the work order was issued by MSEB, DSL
             had to make necessary arrangements for the purpose of carrying
             out the process of installation of the contract objects. This included
             procurement of raw material from a foreign country, starting the
             process of manufacturing gadgets, making arrangements for
F            transportation of these contract objects to the places where the
             said gadgets were to be installed, employment of trained, skilled
             and other staff, making available vehicles for transporting these
             contract objects to the DTC location where they were to be
             installed and, finally, co-ordinating with the Officers of MSEB
             so that after the contract objects were installed, a Certificate of
G            installation could be given by the Officers of MSEB so that from
             that point onwards, lease rentals could become payable to DSL.
             It has to be borne in mind that the nature of the Work Order was
             such that it was in the interest of DSL to ensure that the contract
             objects are installed and certificates to that effect are obtained
H            from the Officers of MSEB. It does not sound to reason that
 MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO.                                771
  LTD. v. M/S. DATAR SWITCHGEAR LTD. [A. K. SIKRI, J.]

       after having invested huge amount of almost Rs 163 crores, as           A
       observed by the Tribunal in the Award, DSL would not install the
       objects because it was in their interest to get the objects installed
       so that returns on their huge investment would start thereafter.
       It is inconceivable therefore that though DTC Lists were
       available, DSL would not install the contract objects. Various
                                                                               B
       facts and figures were given by MSEB to show that DTC
       locations were known to DSL and yet they had failed in installing
       the contract objects is without any substance. It cannot be
       forgotten that, initially, the sequence of installation was Kolhapur,
       Nasik and Aurangabad. This sequence was later on changed to
       Nasik, Kolhapur and Aurangabad. This was again changed and              C
       permission was given to DSL to install the objects at any time at
       any place and, lastly, again, this was changed and direction was
       given to DSL to adhere to the sequence as per the Work Order.
       This being the position, even assuming that B-II Lists were
       available, DSL could not have installed these contract objects
                                                                               D
       because they were asked to follow the schedule again by letter
       dated 21/12/1998 and, therefore, even if the lists were available,
       it was not possible for DSL to simultaneously install all those
       objects since they were told to adhere to the sequence in the
       Work Order if the lists of locations under B-I were not given,
       even assuming that they had B-II lists of locations they could not      E
       have and were not actually allowed to install at the said B-II
       locations. It has come on record that more than 10,000 objects
       were manufactured and ready for installation. There is no earthly
       reason why DSL would fail to install the objects which were
       inspected and ready for installation. The only obvious reason
                                                                               F
       would be that they were unable to do so on account of various
       orders which were passed by MSEB from time to time
       preventing them from performing their obligation. MSEB has
       not examined any of its Superintending Engineers who were in
       charge of supplying the Lists. The cumulative effect of all the
       material which has been brought on record is that it clearly            G
       demonstrates the failure on the part of MSEB in supplying the
       Lists of DTC locations which was a fundamental term of the
       contract.”
      51.We agree with the contention of respondent No.2 that these
are pure findings of facts and there is no perversity therein. It may,         H
772            SUPREME COURT REPORTS                            [2018] 1 S.C.R.


A     however, be pointed out that out of 12555 B-2 category objects under
      the work order, 9515 objects were to be installed in Kolhapur Zone, i.e.
      76% of the said category. Vide letter dated 14.07.1997, the Chief
      Engineer, Kolhapur Zone admittedly directed respondent No.2 to first
      complete new installation (B-1 and B-3) and only thereafter take up
      installation under category B-2. The locations for B-1 and B-3 from
B
      Kolhapur were admittedly never furnished. Therefore, this contention
      of the appellant also warrants a rejection.
              52. The award of the Arbitral Tribunal having been affirmed by
      the learned Single Judge as well as the Division Bench of the High
      Court, that too after dealing with each and every argument raised by the
C     appellant in detail, which is negatived, we hold that Mr. Dada is correct
      in his argument that there is no question of law which is involved herein
      and the only attempt of the appellant was to re-argue the matter afresh,
      which was impermissible.
      AWARD OF DAMAGES :
D
             53.Refuting the argument of the appellant that there was no breach
      in respect of 17294 installed objects and, therefore, no damages were
      payable in that behalf, Mr. Dada pointed out that the appellant had itself
      submitted before the Arbitral Tribunal as under:

E             “The respondents submitted that the claimants at the most would
              be entitled to the costs of the objects installed, i.e. cost of 17294
              contract objects. Alternatively it was submitted that the claimants
              would be entitled to lease rent for reasonable period after
              deducting the cost of maintenance and taking out of print outs.”

F             He also pointed out that identical submission is to be found in the
      written submissions filed by the appellant before the Arbitral Tribunal at
      para 13. According to him, the arbitrators accepted the said submission
      of the appellant and awarded damages. The appellant is, therefore, not
      at all entitled to invoke public policy to challenge the award on the said
      premise. This aspect has been considered by the Division Bench at
G     para 73, which has already been reproduced above.
             54. We see substance in the contention of respondent No.2 and
      are of the opinion that the appellant cannot now turn around and raise
      objection to the award of damages which are measured having regard
      to the loss suffered by respondent No.2 in terms of lease rent for
H     reasonable period for which it would have been entitled to otherwise.
    MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO.                                 773
     LTD. v. M/S. DATAR SWITCHGEAR LTD. [A. K. SIKRI, J.]

       55. That apart, we also find that the Arbitral Tribunal, while              A
awarding the damages, has relied upon the judgment of this Court in
Union of India & Ors. v. Sugauli Sugar Works (P) Ltd.8 wherein a
cardinal principle of damages had been laid down to the effect that the
injured party should be placed in as good a position as money could do as
if the contract had been performed. Following passage from the said
                                                                                   B
judgment was kept in mind by the Arbitral Tribunal:
           “22. The market rate is a presumptive test because it is the general
           intention of the law that, in giving damages, for breach of contract,
           the party complaining should, so far as it can be done by money,
           be placed in the same position as he would have been in if the
           contract had been performed. The rule as to market price is             C
           intended to secure only an indemnity to the purchaser. The market
           value is taken because it is presumed to be the true value of the
           goods to the purchaser. One of the principles for award of
           damages is that as far as possible he who has proved a breach
           of a bargain to supply what he has contracted to get is to be           D
           placed as far as money can do it, in as good a situation as if the
           contract had been performed. The fundamental basis thus is
           compensation for the pecuniary loss which naturally flows from
           the breach. Therefore, the principle is that as far as possible the
           injured party should be placed in as good a situation as if the
           contract had been performed. In other words, it is to provide           E
           compensation for pecuniary loss which naturally flows from the
           breach. The High Court correctly applied these principles and
           adopted the contract price in the facts and circumstances of the
           case as the correct basis for compensation.”
       56. In the instant case, applying the aforesaid principle, the Arbitral     F
Tribunal, for the purpose of classification, considered a 30% reduction in
lease rent to compute damages for installed objects, 50% reduction in
lease rent to compute damages for manufactured but uninstalled objects
and the bare cost of raw materials for the objects not manufactured.
No pendente lite interest was awarded, though the proceedings went                 G
on for five and a half years. Thus, the Arbitral Tribunal awarded almost
the same amount as was invested by respondent No.2 for the project.
Interest was awarded only @ 10% per annum from the date of the
award as opposed to the prevailing bank rate of about 21%.
8
    (1976) 3 SCC 32                                                                H
774                SUPREME COURT REPORTS                         [2018] 1 S.C.R.


A            The aforesaid being a reasonable and plausible measure adopted
      by the Arbitral Tribunal for awarding the damages, there is no question
      of interdicting with the same.
             57. It may be noted that Mr. Dada had argued that it was incumbent
      upon the Arbitral Tribunal to take into account the practices of leasing
B     trade when making the award, having regard to the provisions of Section
      28(3) of the Indian Contract Act, 1872. He had drawn our attention to
      Article 13(2) of UNIDROIT Convention on international lease, which
      stipulates as under:
                 “Where the lessee’s default is substantial, then subject to
C                paragraph 5 the lessor may also require accelerated payment of
                 the value of the future rentals, where the leasing agreement so
                 provides, or may terminate the leasing agreement and after such
                 termination:
                 (a) recover possession of the equipment; and
D                (b) recover such damages as will place the lessor in the position
                     in which it would have been had the lessee performed the
                     leasing agreement in accordance with its terms.”
             58. In the aforesaid backdrop, we agree with the approach of the
      High Court in spelling out the proposition of law that once it is established
E     that the party was justified in terminating the contract on account of
      fundamental breach thereof, then the said innocent party is entitled to
      claim damages for the entire contract, i.e. for the part which is performed
      and also for the part of the contract which it was prevented from
      performing. We may usefully refer to the following dicta laid down in
F     Suisse Atlantique Societe d’Armament SA v. NV Rotterdamsche
      Kolen Centrale9:
                 “...if facts of that kind could be proved I think it would be open
                 to the arbitrators to find that the respondents had committed a
                 fundamental or repudiatory breach. One way of looking at the
                 matter would be to ask whether the party in breach has by his
G
                 breach produced a situation fundamentally different from
                 anything which the parties could as reasonable men have
                 contemplated when the contract was made. Then one would
                 have to ask not only what had already happened but also what
      9
          1966 A.C. 361 (pages 397-398)
H
 MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO.                                 775
  LTD. v. M/S. DATAR SWITCHGEAR LTD. [A. K. SIKRI, J.]

       was likely to happen in future. And there the fact that the breach       A
       was deliberate might be of great importance.
       If fundamental breach is established the next question is what
       effect, if any, that has on the applicability of other terms of the
       contract. This question has often arisen with regard to clauses
       excluding liability, in whole or in part, of the party in breach. I do   B
       not think that there is generally much difficulty where the innocent
       party has elected to treat the breach as a repudiation, bring the
       contract to an end and sue for damages. Then the whole contract
       has ceased to exist, including the exclusion clause, and I do not
       see how that clause can then be used to exclude an action for
       loss which will be suffered by the innocent party after it has           C
       ceased to exist, such as loss of the profit which would have
       accrued if the contract had run its full term...”
                                                       (emphasis supplied)
     59. We, thus, do not find any infirmity in the manner in which             D
damages are awarded in favour of respondent No.2.
RE : MITIGATION OF DAMAGES
      60. Mr. Rafique Dada also countered the argument of the
appellant on mitigation of damages with the submission that this aspect
was specifically considered and the contention of the appellant in this         E
behalf was rejected not only by the Arbitral Tribunal but by the High
Court as well. He referred to the relevant portion of the discussion in
the award as well as the judgments.
       We find that the Arbitral Tribunal has dealt with this aspect and
held that the contract objects were custom built in the following manner:       F
       “55. Respondents submitted that the Claimants did not make
       any efforts to mitigate the loss suffered. The submission is without
       any merit for more than one reason. In the first instance, the
       contract objects manufactured in pursuance of the orders of the
       Respondents were custom built i.e. to the specifications laid down       G
       by the Respondents and these contract objects cannot be disposed
       in open market. Datar deposed with reference to Exh. C 16 that
       efforts were made to sell the contract objects stranded in the
       factory to other Electricity Boards but those efforts did not
       succeed. It was contended by the Respondents that the claimants
                                                                                H
776             SUPREME COURT REPORTS                            [2018] 1 S.C.R.


A             should have dismantled the stranded contract objects and sold
              the components thereof. The submission is only required to be
              slated to be rejected. Once an electronic instrument is dismantled,
              then the value almost becomes nil. In any event, the Claimants
              have established that efforts were made to mitigate the loss.”
B            61. The learned Single Judge as well as the Division Bench of the
      High Court has given its imprimatur to the aforesaid findings. It, therefore,
      becomes apparent that the objects in question were manufactured by
      respondent No.2 to suit the specific needs of the appellant as they could
      not be used otherwise. Therefore, there was no possibility on the part of
      respondent No.2 to make an endeavour to dispose of the same in order
C     to mitigate the losses.
      RE : WAIVER
             62. The argument of the appellant on waiver is also successfully
      met by respondent No.2. Submission of Mr. Dada, on this argument,
D     was that both parties went to trial before the Arbitral Tribunal on the
      basis that the time to start work under the contract had commenced
      with reference to letter dated 14.07.1997 of the appellant signed by the
      Chief Engineer who was the competent authority under the contract.
      The same Chief Engineer insisted, by letter dated 20.04.1998, that
      liquidated damages would be imposed if the work was not completed in
E     time. We may point out that the Arbitral Tribunal considered and rejected
      this argument of waiver, as set up by the appellant, in the following
      words:
              “18... It was then contended that the Claimants had waived the
              right to receive the lists of locations from the Respondents. By
F             reference to clause 5.1 of the work order, it was submitted that
              the Claimants were to commence installation within four months
              from (a) the date of the work order; (b) opening of Letter of
              Credit and (c) on receipt of complete list of locations, whichever
              is later. It was contended that the Claimants were entitled to
G             wait till all the lists were supplied to installation, but as the
              Claimants commenced installation even though the entire lists
              were not supplied, it should be concluded that the Claimants have
              waived their right. The submission is desperate and wholly unfair.
              The Respondents were in a hurry to complete the installation
              within a period of 20 months with an object to save the large
H             amount lost due to loss of energy. Merely because the Claimants
 MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO.                                777
  LTD. v. M/S. DATAR SWITCHGEAR LTD. [A. K. SIKRI, J.]

        acted in a reasonable manner and did not insist upon the terms         A
        of the contract, it is absurd to suggest that the Claimants waived
        their right to complain about non-supply of lists of locations. It
        was then submitted that the Claimants had installed contract
        objects on the oral instructions and on the basis of chits issued
        by some of the Officers of the Respondents and that was contrary
                                                                               B
        to the terms of the work order which provided that installation
        should be only on locations, the lists of which are given in
        accordance with the format at Annexure ‘E’ to the work order.
        It was also submitted that on 155 locations at Jalgaon, Dhule and
        Aurangabad, the lists were received by the Claimants from
        Authorities who were not competent to issue such lists. The            C
        submission has no merit because while undertaking such a huge
        project, the parties were not keen on strict compliance of each
        and every term and condition of the contract. Such an instance
        would have defeated the contract at once because the contract
        had to be carried out over a large area and with the interaction
                                                                               D
        of large number of people. These factors cannot establish that
        the claimants have waived their right to complaint about the failure
        to supply lists of location...”
       63. Mr. Vikas Singh, learned senior counsel appearing for the
appellant, referred to and relied upon various judgments in support of his
contention. These judgments deal with the scope of interference in the         E
awards passed by the arbitrators. It is not even necessary to deal with
these judgments inasmuch as, on the facts of this case, as discussed in
detail hereinabove, none of the judgments gets attracted. Likewise, effort
on the part of the appellant to rely upon the judgment of the learned
single Judge of the High Court in the first round is futile as that was set    F
aside by the Division Bench and matter was remitted back to the single
Judge of the High Court to decide it afresh.
RE: ORDER ON CHAMBER SUMMONS
       64. Three chamber summons were taken out by the appellant
during the pendency of this appeal before the Division Bench. By these         G
chamber summons, the appellant intended to amend the petition which
was filed by it under Section 34 of the Act as well as the appeal. The
High Court after detailed discussion in the impugned judgment rejected
these summons. We find that the amendment sought was highly belated.
Arbitration petition filed under Section 34 of the Act was sought to be        H
778            SUPREME COURT REPORTS                        [2018] 1 S.C.R.


A     amended after a delay of eight years. Further, the amendment in the
      appeal, taking those very grounds on which amendment in the arbitration
      petition was sought, was sought after a delay of 3½ years. The High
      Court, thus, rightly rejected these summons and it is not necessary to
      have any elaborate discussion on these aspects.
B          65. In the ultimate analysis, having found no merit in any of the
      arguments raised by the appellant, the appeal is dismissed with costs.


      Divya Pandey                                           Appeal dismissed.

C




D




E




F




G




H


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Arbitration"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.