Created byFuzzy Cloud

Supreme Court of India

MAHARSHI DAYANAND UNIVERSITY & ANR.versusANAND COOP. L/C SOCIETY LTD. & ANR.

Citation
2007 INSC 463
Decided
25 April 2007
Disposal
Dismissed

Holding

The Supreme Court held that there is no reason for the court to interfere with the appointment of an arbitrator; questions regarding the existence of an arbitration agreement and the applicability of clause 25A must be decided by the arbitrator under Section 16 of the Arbitration and Conciliation Act, 1996.

Summary

Maharshi Dayanand University invited tenders for construction of sheds. The respondent submitted a tender containing a clause (25A) providing for arbitration and the university accepted the tender, stipulating that work would commence from the date of acceptance but that no payment would be made until a detailed contract was signed. No formal contract was ever signed and the university later decided not to execute the work, asking the respondent to return the earnest money. The respondent invoked clause 25A and filed an application under Section 11 of the Arbitration and Conciliation Act, 1996 for appointment of an arbitrator. The district court appointed the Engineer as arbitrator, leaving any objections to be raised before the arbitrator under Section 16. The university challenged this appointment, arguing that no arbitration agreement existed because the contract was not signed. The High Court dismissed the challenge, holding that objections could be raised before the arbitrator. The Supreme Court affirmed that there is no ground for the court to interfere with the appointment of an arbitrator; the arbitrator must decide whether an arbitration agreement under Section 7 exists and whether the dispute falls within clause 25A, and the parties may raise jurisdictional objections before the arbitrator.

Issues considered

  • Whether the court can interfere with the appointment of an arbitrator under Section 11 of the Arbitration and Conciliation Act, 1996 when the parties have not signed a formal contract.
  • Whether the existence of an arbitration agreement under Section 7 of the Act must be decided by the court or can be left to the arbitrator under Section 16.
  • Whether the pre‑S.B.P. & Company dispensation (i.e., the earlier Konkan Railway decision) governs the present case.

Legislation cited

Subjects

ArbitrationAppointment of arbitratorSection 11Section 16Arbitration agreementUnexecuted contractTender clause 25APre‑S.B.P. & Company dispensation

Judgment

A                 MAHARSHI DAYANAND UNIVERSITY & ANR.
                                           v.
                    ANAND COOP. L/C SOCIETY LTD. & ANR.

                                   APRIL 25, 2007

B         [TARUN CHATTERJEE AND P.K. BALASUBRAMANYAN,JJ.]


          Arbitration and Conciliation Act, I996-Sections I I and I6-
    Appointment ofarbitrator-Interference with-Tender invited, tender submitted
C   and acceptance conveyed, time for work stipulated and payment not to be
    made until formal contract signed containing detailed specifications as
    contemplated by letter of acceptance-However, formal contract not signed-
    Party deciding not to execute contract-Contractor invoking clause in tender
    conditions for appointment of arbitrator-Application u/s I I-Appointment
    of Engineer as arbitrator leaving it to the parties to raise all objections
D   before the arbitrator uls. I 6-Correctness of-Held: Appointment of arbitrator
    calls for no interference-Since the question can be raised before the
    arbitrator u/s I 6, it must be left to be decided by the arbitrator-Instant case
    not being governed by the principles in S.B.P. & Company's case, it would
    be appropriate to leave this in these proceedings.
                                                                                            ..
E       Appellant invited tenders for construction work. Respondent no.l
  submitted the tender and the appellant accepted the same. Tender form
  submitted by the respondent contained a clause for reference of dispute to
  the arbitrator. Appellant submitted the letter of acceptance and the date of
  commencing the work to be from the date of issuance of the letter. It further
F stipulated that the document containing the detailed terms and conditions of
  the contract was to be signed by the parties otherwise no payment would be
  made; and that the contract stood concluded with the issue of this
  communication. Respondent deposited earnest money. However, the parties did
  not sign the contract. Thereafter, appellant informed the respondent that it
  had decided not to get the work executed and called upon the respondent to
G take refund of the earnest money. Respondent issued notice invoking clause           '~   ....
  25A of the tender conditions for appointment of arbitrator since the respondent
  had made arrangements for commencing the work and on cancellation it
  suffered losses. Appellant invoked clause 13 of the tender conditions that
  appellant could decide not to proceed with work and as such clause 25 A had
H                                        596
                  MAHARSHI DAYANAND UJ\'IVERSITY 1.: ANAND COOP. UC SOCIETY LTD
                                                                                  597
    no application. Respondent then filed an application under section 11 of the         A
    Arbitration and Conciliation Act, 1996 for appointment of arbitrator. Appellant
    accepted that the tender of the respondent had been accepted but was not liable
    to pay any damages in view of clause 13 of the tender. District Judge relying
    upon Konkan Railway Corporation Ltd. & Anr. v. Rani Construction Pvt.
    Ltd's* case appointed the Engineer as arbitrator in terms of the clause 25A
    of the tender conditions, leaving it to the parties to raise all objections before   B
    the arbitrator under section 16 of the Act. Appellant filed writ petition. High
    Court dismissed the writ petition holding that the appellant could raise
    objections before the arbitrator and interference with the order appointing
    an arbitrator was not called for. Hence the present appeal.

          Appellant contended that contract as contemplated by the parties
                                                                                         c
    containing the detailed terms and conditions was not signed by the parties
    and in the circumstances there was no arbitration agreement justifying the
    appointment of an arbitrator; that a question whether there was an arbitration
    clause or not, had to be decided by the court even under the dispensation; and
    that there being no concluded contract, it was just and necessary to interfere       D
    with the order appointing the arbitrator.

          Dismissing the appeal, the Court

          HELD: 1.1. There is no reason to interfere with the appointment of an
    arbitrator. Liberty is given to the parties to raise all their contentions based     E
    on lack of jurisdiction of the arbitral tribunal before the arbitrator.
,                                                                  [Para 12) [606-F)

          1.2. The instant case is governed by the procedure that was available
    when Konkan Railway Corporation Ltd. & Anr's* case held the field. That
    orders already made were not to be affected by the ratio of the decision in          F
    S.B.P. & Company's** case. Therefore, the only question for decision is
    whether the fact that the parties have not signed the contract containing the
    detailed specifications as contemplated by the letter of acceptance would
    preclude the respondent from seeking an arbitration by falling back on clause
    25A of the tender conditions. It is true that when parties during negotiations       G
    contemplate the execution of a formal agreement incorporating the terms of
    the bargain, so long as a formal agreement has not been entered into, it may
    be open to contend that there was no concluded contract between the parties.
    As against this, what is the position in a case where the tender submitted is
    accepted, its acceptance conveyed and the time for completing the work is
    stipulated to start from such acceptance, and the work was to commence on            H
    598                     SUPREME COURT REPORTS                     [2007] 5 S.C.R.

A the basis of that acceptance but no payment was to be made until a formal
    contract was signed, is the first question that arises in this case. In the
    circumstances, this is a question that must be left to be decided by the
    arbitrator, this is a question that must be left to be decided by the arbitrator,
    since in terms of S. 16 of the Act the question can be raised before the
    arbitrator. (Para IO) (605-F, G, H; 606-A, BJ
B
          1.3. Considering that the pre S.B.P & Company's case dispensation is
    dealt with, it is not necessary or proper to go into that question and decide
    the same in these proceedings. Same is the position regarding the scope of
    clause 13 of the tender and the clauses relied on by counsel for the appellant
C   in his attempt to take the present claim out of clause 25A of the tender
    conditions. Therefore, it would be appropriate to leave this question, as also
    the other questions to be decided by the arbitrator rather than trying to answer
    them at this stage in view of the fact that this case is not governed by the
    principles recognized by S.B.P. & Company's case. (Para 10) (606-B, CJ

D         1.4. The arbitrator in the first instance, has to decide whether _the
    existence of an arbitration agreement in terms of S. 7 of the Act is established
    and also to decide whether the claim now made is a claim that comes within
    the purview of clause 25A of the tender conditions in case it is found to be an
    agreement within the meaning ofS.7 of the Act. Only on deciding these two
    aspects can the arbitrator go into the merits of the claim made by the
E   respondent But it is clarified that it does not mean, that he would treat these
    two aspects as preliminary issues and decide them first; but only that he must
    decide them without fail while proceeding to finally pronounce his award.
                                                               [Para 11 J (606-D, EJ

F         .*Konkan Railway Corporation Ltd. & Anr. v. Rani Construction Pvt.
    Ltd., (2002( 2 SCC 388, relied on.

         **S.B.P. & Company v. Patel Engineering Ltd. & Anr., (2005) 8 SCC
    618 and Willington Associates Ltd v. Kirit Meta, (2000) 4 SCC 272, referred
    to.
G         CIVIL APPELLATE JURISDICTION: Civil Appeal No. 2133 of2007.

         From the Judgment and Order dated 12.03.2005 of the High Court of
    Punjab & Haryana at Chandigarh in Civil Writ Petition No. 4046 of2005.

          Nidhesh Gupta, U.N. Shukla and S. Janani for the Appellants.
H
-      MAHARSHI DAYANAND UNIVERSITY'· ANAND COOP. UC SOCIETY LTD. [BALASUBRAMANYAN. l.)   599

          The Judgment of the Court was delivered by                                            A
         P.K. BALASUBRAMANY AN, J. 1. Leave granted.

          2. In spite of service of notice and in spite of repeated conveying of
    infonnation about the posting of the petition for special leave to appeal for
    final disposal, the respondent has not chosen to appear. We think we have                   B
    waited enough for the appearance of the respondent and no further indulgence
    is warranted. Heard counsel for the appellant.

          3. The appellant invited tenders for construction of sheds near its
    Swimming Pool at an estimated cost of Rs.10.70 lakhs. Respondent No. 1
    submitted its tender. The tender fonn submitted by the respondent contained                 C
    the following clause:

            "Clause 25A. (I) If any dispute or difference of any kind whatsoever
           shall arise between the vice-Chancellor M.D.U. Rohtak, and the
           contractor in connection with or arising out of the contract, or the                 D
           execution of the work that is (i) whether before its commencement or
           during the progress of the work or after its completion, (ii) and whether
           before or after the tennination, abandonment or breach of the contract
           it shall in the first instance be referred to for being settled by the
           Executive Engineer in charge of the work at the time and he shall
           within a period of sixty days after being requested in writing by the                E
           contractor to do so, convey his decision to the contractor, and subject
           to arbitration as herein after provided, such decision in respect of
           every matter so referred, shall be final and binding upon the contractor.
           In case the work is already in progress, the contractor will proceed
           with the execution of the work on the receipt of the decision of the
           Execution Engineer-in-charge as aforesaid, with all due diligence                    F
           whether he or Vice-Chancellor, M.D.U., Rohtak requires arbitration as
           hereinafter provided or not. If the Executive Engineer, in-charge of the
           work has conveyed his decision to the contractor and no claim to
           arbitration has been filed with him by the contractor within a period
           of sixty days from the receipt of letter comprnnicating the decision, the            G
           said decision shall be final and binding upon the contractor and will
           not be subject matter of arbitration at all. If the Executive Engineer in-
           charge of the work fails to convey his decision within a period of sixty
           days, after being requested, as aforesaid, the contractor may, within
           further sixty days of the expiry of first sixty days from the date on
                                                                                                H
                                                                                               .....
    600                    SUPREME COURT REPORTS                     [2007] 5 S.C.R.
                                                                                        .I

A         which request has been made to the Executive Engineer in-charge
          request the Vice-Chancellor, that the matter in dispute be referred to
          arbitration, as hereinafter provided.

          (2) All disputes or differences in respect of which the decision not
          final and conclusive shall at the request in writing of either party,
B         made in communication sent through registered A.D. Post, be referred
          to the sole arbitration to Vice-Chancellor, M.D.U., Rohtak at the relevant
          time. It will be no objection to any such appointment that the arbitrator
          so appointed is a Government servant or that he had to deal with the
                                                                                        ,.-f   -·
          matters to which the contract relates and that in the course of his
          duties as a Government servant, he had expressed his views on all or
c         any of the matters in dispute. The arbitrator to whom the matter is
          originally referred being transferred or vacating his office, his
          successor-in-office, as such shall be entitled to proceed with the
          reference from the stage at which it was left by his procedure.

          In case the arbitration nominated by the Vice-Chancellor, M.D.U.,
D
          Rohtak is unable to act as such for any reason, whatsoever the Vice-
          Chancellor, M.D.U., Rohtak shall be competent to appoint and nominate         ~
          and other Superintending Engineer or Chief Engineer, as the case may
          be as arbitrator in his place and the Arbitrator so appointed shall be
          entitled to proceed with the reference.
E
          (3) It is also a term of this arbitration agreement that no person
          appointed by the Vice-Chancellor, M.D.U., Rohtak shall act as arbitrator
          and if for any reason that is not possible the matter shall not be
          referred to arbitration at all.

              In all cases where the aggregate amount awarded exceeds                   t
F
          Rs.25,000/- the arbitrator must invariably give reason for his award in
          respect of each claim and counter claim separately.

          (4) The arbitrator shall award against each claim and dispute raised by
          either party including any counter claim individually and that any
G         lump-sum award shall not be legally enforceable.
                                                                                        ~
                                                                                               •
          (5) The following matters shall not lie within the purview of arbitration:-

          (a) Any dispute relating to the levy of compensation as liquidated
          damages which has already been referred to the Superinten'ding
          Engineer and is being heard or/and has been finally decided by the
H
         MAHARSHI DAY ANAND UNIVERSITY v. ANAND COOP. UC SOCIETY LID. [BALASUBRAMANYAN,l]   601
    r
              Superintending Engineer in-charge of the work.                                      A
              (b) Any dispute in respect of substituted, altered, additional work/
              committed work/defective work referred by contractor for the decision
              of the Superintending Engineer, in-charge of the work if it is being
              heard or has already been decided by the said Superintending Engineer.
                                                                                                  B
              (c) Any dispute regarding the scope of the work or its execution or
    \-        suspension or abandonment has been referred by the contractor for
    '         the decision of the Vice-Chancellor, M.D.U., Rohtak and has been so
              decided finally by the Vice-Chancellor,M.D.U., Rohtak.


.             (6) The independent claim of the party other than the one getting the
              arbitrator appointed, as also counter-claims of any party will be
                                                                                                  c
              entertained by the arbitrator notwithstanding that the arbitrator had
              been appointed at the instance of the other party.

              (7) It is also a term of this arbitration agreement that where the party
              invoking arbitration is the contractor, no reference for arbitration shall D
              be maintainable unless the contractor furnishes to the satisfaction of
              the Executive Engineer in-charge of the work, a security deposit of a
              sum determined according to details given below and the sum so
              deposited shall, on the termination of the arbitration proceedings, be
              adjusted against the cost, if any, awarded by the arbitration against
              the claimant party and the balance after such adjustment in the absence E
              of any such cost being awarded, the whole of the sum will be refunded
              to him within one month from the date of the awards:

                  Amount of claims                   Rate of security deposit

             (0 For claim below                                                                   F
                  Rs. I0,000/-                       2% of amount claimed
             (ii) For claim of




-
                  Rs. I0,000/- and
                  above and                          5% of amount claimed
    i'            Below Rs.1,00,000/-
                                                                                                  G
                  and above                          7'h % of amount claimed
                  The stamp fee due on the award shall be payable by the party as
              desired by the arbitrator and in the event of such party's default the
              stamp fee shall be recoverable from any other sum due to such party
              under this or any other contract.                                                   H
    602                   SUPREME COURT REPORTS                     (2007] 5 S.C.R.
                                                                                             ·-
                                                                                       .J

A         (8) The venue of the arbitrator shall be such place or places as may
          be fixed by the arbitrator in his sole discretion. The work under the
          contract shall continue during the arbitration proceeding.

          (9) Neither party shall be entitled to bring a claim for arbitration if
          appointed for such arbitrator has not been applied within six months.
B
          (a) of the date of completing of the work as certified by the Executive
          Engineer in-charge, or
                                                                                       ,,i
          (b) of the date of abandonment of the work, or

          (c) of its non-commencement within 6 months from the date of
c         abandonment or written orders to commence the work as applicable,                  ....
          or

          (e) of the completion of the work through any alternative agency or
          means after withdrawal of the work from the contractor in whole or in
          part and/or its recession, or
D
          ( f) of receiving an intimation from the Executive Engineer in-charge of    'I-
          the work that final payment due to or recovery from the contractor had
          been determined which he may acknowledge and/or receive. Whichever
          of (a) to (e) is the latest.

E             If the matter is not referred to arbitration within the period
          prescribed above, all the rights and claim of any party under the
          contractor shall be deemed to have been forfeited and absolutely
          barred by time even for civil litigation now with standing.

          (10) It is also a term of this arbitration agreement that no question
F         relating to this contract shall be brought before any civil court without
          first involving and completing the arbitration proceedings as above,
          if the scope of the arbitration specified herein covers issues that can
          be brought before the arbitrator i.e. any matter that can be referred to
          arbitration shall not be brought before a civil court. The pendency of
          arbitration proceedings shall not disentitle the Vice-Chancellor,M.D.U.,
G
          Rohtak to terminate the contract and make alternative arrangements          >i.    ...-
          for the completion of the work.

          (I !)The arbitrator shall be deemed to have entered on the reference
          on the day he issues notices to the parties fixing the first date of
H         hearing. The arbitrator may, from time to time, with the consent of the
              MAHARSHI DAY ANAND UNIVERSITY"· ANAND COOP. UC SOCIETY LTD. [BALASUBRAMANYAN, l.]   603
    -\..           parties enlarge the initial time for making and publishing the award.                A
                   (12) It is also a term of this arbitration agreement that subject to the
                   stipulation herein mentioned, the arbitration proceedings shall be
                   concluded in poor ordinance with the provisions of the Arbitration
                   Act, 1940 or any other law in force for the time being."
                                                                                                        B
           Obviously, this tender form was signed on behalf of respondent N;i. 1 when
           it was submitted to the appellant. It was dated 12.09.2003.
      .
      )

                 4. The tender so submitted by the respondent was accepted by the
           appellant. It was stated in the letter of acceptance, dated 22.11.2003, singed
           on behalf of the appellant:                                                                  c
                   "As approved by the tender committee in its meeting held on 12.10.2003
                   and further approved by the competent authorities, the acceptance of
                   your tender for the work cited as subject, is further conveyed to you
                   on behalf of the Registrar, M.D.U., Rohtak at the rates contained in
                   your tender dated 12.9.2003. This is subject to the terms and conditions D
                   of the approved Detailed notice inviting tender (/NIT) of the above
                   works."
                                                                              (emphasis supplied)
           The date of start of the work was indicated to be "from the date of issue of
           this letter." The time limit was fixed as four months. It contained a further                E
           stipulation:

                   "You are requested to contact the SOE (C-1) M.D.U. Rohtak for taking
                   the work in hand. The document containing the detailed terms and
                   conditions of the contract are ready and you are requested to attend
                   this office on any working day for signing the same. No payment will                 F
                   be made to you unless you sign the contract agreement. The contract
                   stands concluded with the issue of this communication. "

                                                                              (emphasis supplied)

                 The respondent, admittedly deposited an earnest money of G
>   '-"'   Rs. 10,700/-.

                 5. It is the case of the appellant that the site was not demarcated. It is
           common case that a document containing detailed terms and conditions of the
           contract as envisaged by the acceptance letter was not signed by the parties.
                                                                                                        H
     604                     SUPREME COURT REPORTS                    [2007] 5 S.C.R.
                                                                                         J
A In the letter dated 8.3.2004 the appellant informed the respondent that it had
     decided not to get the work executed. The letter also called upon the respondent
     to get the earnest money of Rs. I0, 700/- refunded.

          6. The respondent issued a notice to the appellant invoking clause 25A
    of the tender conditions quoted above, calling upon the appellant to appoint
B   an arbitrator in terms of that clause on a claim that on acceptance of his
    tender, the respondent had made arrangements for commencing the work, had
    put up sheds, had engaged labourers and had procured materials and on                 -f
    cancellation, losses have been incurred and the respondent was entitled to           "
    recover the same from the appellant. The appellant took the stand that under
c   clause 13 of the tender conditions, the appellant was entitled to decide not
    to proceed with the work and no claim, as made on the side of the respondent,
    was maintainable. Clause 25A had no application. The claims were also factually
    disputed.

           7. In that context, respondent No. 1 invoked the jurisdiction of the
D District Court under Section 11 of the Arbitration and Reconciliation Act, 1996
  (for short 'the Act') seeking the appointment of an arbitrator. After referring
  to the invitation for tenders, its submission of tender, and of its acceptance,       'j..
  the respondent also disclosed that no agreement was signed between the
  parties but asserted that the conditions mentioned in the tender form were
  made applicable. The respondent requested to the court to call upon the
E appell<1.nt to produce the original tender form submitted by the respondent.
  The appellant accepted the fact that the tender of the respondent had been
  accepted. But the appellant was not liable to pay any damages in view of
  clause 13 of the tender conditions. No payment was to be made unless the
  contract agreement was signed. It also contended that the dispute that was
F sought to be raised by the respondent was outside clause 25A of the tender
  conditions relied on by the respondent.

           8. The District Judge, controlled as he then was, by the decision in
    Konkan Railway Corporation Ltd. & Anr. v. Rani Construction Pvt. Ltd.,
    [2002) 2 SCC 388, appointed the Superintending Engineer as arbitrator by
G relying on clause 25A of the tender conditions, leaving it to the parties to
    raise all objections, including the objection to his jurisdiction, before the         >..   '
    arbitrator in terms of Section 16 of the Act. Feeling dissatisfied, the appellant
    filed a writ petition before the High Court relying on the decision of this Court
    that since the order based on the application under Section 11 was an
    administrative order, a writ petition was maintainable, by referring to State of
H
                      MAHARSHI DAY ANAND UNlVERSITY v. ANAND COOP. UC SOCIETY LID. [BALASUBRAMANYAN, J.)   605
           \.
                   Orissa and Ors v. Gokulananda Jena, (2003] 6 SCC 465 AIR (2003) SC 4207.                      A
                   The High Court held that the objections sought to be raised could be raised
                   by the appellant before the arbitrator and there was no reason for the High
                   Court to interfere with the order appointing an arbitrator in the circumstances
                   of the case. It is feeling aggrieved thereby that the appellant has come up with
                   this appeal by special leave.
                                                                                                                 B
                         9. Learned counsel for the appellant submitted that no contract as
                   contemplated by the parties containing the detailed terms and conditions was
           )
           ~       signed- by the parties and in the circumstances there was no arbitration
                   agreement as understood in the Act justifying the appointment of an arbitrator.
                   Counsel brought to our notice Section 7 of the Act. Counsel also referred to
                   the fact that in the subsequent decision in S.B.P. & Company v. Patel
                                                                                                                 c
                   Engineering Ltd. & Anr., (2005] 8 SCC 618 this Court has overruled the
                   decision in Konkan Railway Corporation Ltd. & Anr. (supra) and the ratio
                   thereof is no more available to the respondent. Counsel also referred to the
                   decision in Willington Associates Ltd. v. Kirit Meta, (2000] 4 SCC 272 to
                   submit that a question whether there was an arbitration clause or not, had to                 D
                   be decided by the court even under the dispensation recognized by the earlier
               \   decision in Konkan Railway Corporation Ltd. & Anr. (supra). Counsel
                   submitted that in view of the fact that a contract in writing had not come into
                   existence by both the parties by affixing their signatures as contemplated by
                   them, there was no concluded contract in the case on hand and it was just
                                                                                                                 E
                   and necessary to interfere with the order appointing the arbitrator. As we
                   have indicated earlier, the respondent has not chosen to appear before us to
                   answer these contentions.

                          I 0. The present case is governed by the procedure that was available
           ..,     when Konkan Railway Corporation Ltd. & Anr. (supra) held the field. That                      F
                   orders already made were not to be affected by the ratio of the decision in
                   S.B.P. & Company (supra) is clear from paragraph 46 of that decision wherein
                   prior orders and proceedings have been saved. Therefore, the only question
                   for decision is whether the fact that the parties have not signed the contract
                   containing the detailed specifications as contemplated by the letter of
                   acceptance would preclude the respondent from seeking an arbitration by                       G
___.....   ~       falling back on clause 25A of the tender conditions quoted above. It is true
                   that when parties during negotiations contemplate the execution of a formal
                   agreement incorporating the terms of the bargain, so long as a formal agreement
                   has not been entered into, it may be open to contend that there was no
                   concluded contract between the parties. As against this, what is the position                 H
    606                      SUPREME COURT REPORTS                     [2007) 5 S.C.R.         ...
A in a case where the tender submitted is accepted, its acceptance conveyed              -'
    and the time for completing the work is stipulated to start from such acceptance,
    and the work was to commence on the basis of that acceptance but no
    payment was to be made until a formal contract was signed, is the first
    question that arises in this case. We think that in the circumstances, this is
    a question that must be left to be decided by the arbitrator, since in terms of
B   Section 16 of the Act the question can be raised before the arbitrator.
    Considering that we are dealing with the pre S.B.P. & Company (supra)
    dispensation, we do not think that it is necessary or proper for us to go into
    that question and decide the same in these proceedings. Same is the position         ,.{
    regarding the scope of clause 13 of the tender and the clauses relied on by
c   counsel for the appellant in his attempt to take the present claim out of clause
    25A of the tender conditions. We are, therefore, satisfied that it would be
    appropriate to leave this question, as also the other questions to be decided
    by the arbitrator rather than our trying to answer them at this stage in view
    of the fact that this case is not governed by the principles recognized by
    S.B.P. & Company (supra).
D
           11. But we make it clear that the arbitrator, in the first instance, has to
    decide whether the existence of an arbitration agreement in terms of Section
    7 of the Act is established and also to decide whether the claim now made
    is a claim that comes within the purview of clause 25A of the tender conditions
    in case it is found to be an agreement within the meaning of Section 7 of the
E
    Act. Only on deciding these two aspects can the arbitrator go into the merits
    of the claim made by the respondent. But we clarify that it does not mean,
    that he should treat these two aspects as preliminary issues and decide them
    first; but only that he must decide them without fail while proceeding to
    finally pronounce his award.
F
         12. In this view of the matter, we see no reason to interfere with the
                                                                                         ,
  appointment of an arbitrator. We dismiss this appeal giving liberty to the
  parties to raise all their contentions based on lack of jurisdiction of the arbitral
  tribunal before the arbitrator. The arbitrator will permit the appellant to amend
  or supplement the objections already filed by it if it is felt necessary by the
G appellant. We make no order as to costs.

                                                                  Appeal dismissed.
                                                                                         ~     .
    NJ.


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Arbitration"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.