N.B.C.C. LTD.versusJ.G. ENGINEERING PVT. LTD.
- Citation
- 2010 INSC 2
- Decided
- 5 January 2010
- Disposal
- Case Partly allowed
- Bench
- TARUN CHATTERJEE
Holding
The arbitrator’s mandate terminates automatically when the time fixed by the parties expires without their consent, and the High Court’s termination was proper, but its appointment of a new arbitrator was invalid for not observing Section 11(8).
Summary
The parties entered into a construction contract with an arbitration clause. After several arbitrators were appointed and the proceedings stalled, the High Court fixed a six‑month deadline for a newly appointed arbitrator to render an award, which was later extended by mutual consent of the parties to 30 September 2005. The arbitrator failed to publish the award within that period, and the respondent applied under Section 14 of the Arbitration and Conciliation Act, 1996, for termination of the arbitrator’s mandate. The High Court terminated the mandate and appointed a new arbitrator. The Supreme Court held that the arbitrator’s mandate automatically terminated when the time fixed by the parties expired without their consent, and the High Court was correct in terminating the mandate. However, the Court set aside the High Court’s appointment of a new arbitrator because it did not consider the qualifications and other requirements under Section 11(8) of the Act, and remitted the matter for fresh appointment. The appeals were partly allowed.
Issues considered
- The arbitrator’s mandate under Section 14(1)(a) terminates automatically upon expiry of the time fixed by the parties without their consent for extension.
- Whether the court can extend the time for making and publishing an award when the arbitration agreement provides a procedure for extension.
- The validity of the High Court’s appointment of a new arbitrator under Section 11(6) without complying with Section 11(8).
Legislation cited
- Arbitration and Conciliation Act, 1996s. 11(6), s. 11(8), s. 14(1)(a), s. 14(1)(b), s. 14(2), s. 15(2)
Subjects
Judgment
[2010) 1 S.C.R. 109
N.B.C.C. LTD. A
v.
J.G. ENGINEERING PVT. LTD.
Civil App~al No. 8 of 2010
JANUARY 5, 2010
B
[TARUN CHATIERJEE AND AFTAB ALAM, JJ.]
Arbitration and Conciliation Act, 1996:
s.14(1) - Termination of mandate of arbitrator- Failure c
on part of arbitrator to conclude the arbitration proceedings/
publish the award within the time limit fixed by parties or such
extended time as consented by parties - Held: The mandate
of arbitrator is liable to be terminated - Arbitration -
Efficacious remedy. D
Dispute arose between the parties and matter was
referred to arbitration. Due to some reasons, arbitration
proceedings were not concluded. Respondent filed
application before High Court seeking removal of the
arbitrator. High Court directed appellant to appoint a new E
arbitrator and further directed the arbitrator so appointed
to conclude the arbitration proceedings within six
months. After the expiry of six months, both the parties
extended the time to conclude arbitration. The arbitrator
failed to publish the award within the extended time. F
Respondent filed application before High Court for
a declaration that the mandate of the arbitrator stood
terminated. High Court by its order dated 23.3.2006.
terminated the mandate of the arbitrator on the ground G
of delay in making the award. High Court further by order
dated 21.9.2007 appointed a sole arbitrator to adjudicate
the disputes between the parties. These appeals were
filed against orders dated 23.3.2006 and 21.9.2007.
109 H
110 SUPREME COURT REPORTS [2010] 1 S.C.R.
A Partly allowing the appeals and remitting the matter
to High Court, the Court
HELD: 1. A perusal of arbitration agreement revealed
that the arbitrator had power to enlarge the time to make
and publish the award by mutual consent of the parties.
8
Therefore, without the consent of both the parties to the
dispute, arbitrator had no power to further extend the time
beyond that which is fixed. It is an admitted position that
the respondent did not give any consent for extension
C of time. Thus, the arbitrator had no power to further
enlarge the time to make and publish the award and
therefore his mandate had automatically terminated after
the expiry of the time fixed by the parties to conclude the
proceedings. Arbitration is an efficacious and alternative
way of dispute resolution between the parties. There is
D no denying the fact that the method of arbitration has
evolved over the period of time to help the parties to
speedily resolve their disputes through this process and
in fact the Arbitration and Conciliation Act recognizes this
aspect and has elaborate provisions to cater to the needs
E of speedy disposal of disputes. The present case
illustrates that inspite of adopting this efficacious way of
resolving the disputes between the parties through the
arbitration process, there was no outcome and the
arbitration process lingered on for a considerable length
F of time which defeated ttie notion of the whole process
of resolving the disputes through arbitration. The
contention of the appellant therefore cannot be justified
that since the dispute was highly technical in nature, it
had to be dealt with elaborately by the arbitrator and that
G he was justified in being late. High Court correctly fixed
the time for the arbitration to be concluded within a period
of six months from the appointment of the fourth
arbitrator considering the time that was spent for the
arbitration process prior to his appointment. That apart,
H even assuming that the arbitration process involved
N.B,c.c~ LTD. v. J.G. ENGINEERING PVT. LTD. 111
highly technical and complex issues, which was time A
consuming, even then, it was open for the arbitrator or
for the parties to approach the Court for extension of time
to conclude the arbitration proceeding which was not
done either by the arbitrator or by any of the parties. As
correctly noted by High Court in its impugned judgment, B
there was no cogent reason for the delay in making and
publishing the award by the arbitrator. He already had the
relevant materials at his disposal and could base his
findings on the observations made by the three arbitrators
who were appointed prior to him. [Para 5] [118-8-H; 119- c
A-DJ
Jatinder Nath v. Mis Chopra Land Developers Pvt. Ltd.
& Anr. AIR 2007 SC 1401; General Manager, Department of
Telecommunications, Thiruvananthapuram v. Jacob Sia
Kochuvarkey Kalliath (Dead) by LRs. And Others 2003 (9) D
SCC 662; National Aluminum Co. Ltd. Vs. Pressteel &
Fabrications (P) Ltd. and Another 2004 (1) SCC 540, held
inapplicable.
2. It is true that apparently there is no provision under E
the Act for the Court to fix a time limit for the conclusion
of an arbitration proceeding, but the Court can opt to do
so in the exercise of its inherent power on the application
of either party. Where however the arbitration agreement
itself provides the procedure for enlargement of time and F
the parties have taken recourse to it, and consented to
the enlargement of time by the arbitrator, the Court cannot
exercise its inherent power in extending the time fixed by
the parties in the absence of the consent of either of them.
The arbitrator had not concluded the proceedings as had G
been agreed to by the parties within the time fixed for
doing so. The mandate of the arbitrator was terminated
only because of the fact that the arbitrator having failed
to conclude his proceedings within time did not warrant
to be continued as an arbitrator in the absence of the
H
112 SUPREME COURT REPORTS [2010] 1 S.C.R.
A consent of both the parties. The arbitrator had become
functus officio in the absence of extension of time to make
and publish the award. After the said date, the arbitrator
had no authority to continue with the arbitration
proceedings. It is clear from a bare reading of sub section
B 1 (a) of section 14 of the Act, the mandate of an arbitrator
shall terminate if he fails to act without undue delay. In
the present case, it is clear that the arbitrator had
extended the time provided to it without any concrete
reasons whatsoever and thus his mandate was liable to
C be terminated. Sub section 1(b) further states that the
mandate of an arbitrator shall also stand to be terminated
if he withdraws from his office or the parties agree to the
termination of his mandate. The perusal of the records
show that the parties had not agreed to the extension of
the mandate of the arbitrator. Further, Subsection (2) of
0
Section 14 of the Act stipulates that if a controversy
remains concerning any of the grounds referred to under
clause (a) of sub-section (1), a party may, unless
otherwise agreed to by the parties, apply to the Court to
decide on the termination of the mandate. Thus the
E respondent rightly applied to the Court for the termination
of the mandate of the arbitrator pursuant to the
provisions of this section, and the Court was within its
jurisdiction to decide accordingly. [Paras 5, 7, 11 and 12)
[121-F-H; 122-A; 125-8-C-F-G-H]
F
Northern Railway Administration, Ministry of Railway v.
Patel Engineering Company Ltd. 2008 (10) SCC 240, relied
on.
G Ace Pipeline Contracts Private Limited v. Bharat
Petroleum Corporation Limited (2007) 5 SCC 304, referred
to.
Case Law Reference:
AIR 2007 SC 1401 held inapplicable Para 6
H
N.B.C.C. LTD. v. J.G. ENGINEERING PVT. LTD. 113
2003 (9) sec 662 held inapplicable Para 6 A
2004 (1) sec 540 held inapplicable Para 6
2oos (10) sec 240 relied on Para 14, 15
(2007) 5 sec 304 referred to Para 14
B
CIVIL APPELLATE JURISDICTION: Civil Appeal No. 8
of 2010.
From the Judgment & Order dated 23.3.2006 of the High
Court at Calcutta in G.A. No. 235 of 2006 in A.P. No. 361 of c
2005.
WITH
C.A. No. 9/2010
D
Ginny Jetley Rautray, Kanchan Kaur Dhodi for the
Appellant.
A.K. Ganguli, Pranab Kumar Mullick for the Respondent.
The Judgment of the Court was delivered by E
TARUN CHATIERJEE, J. 1. Leave granted.
2. These appeals are directed against the final Judgments
and orders dated 23rd of March, 2006, and 21st of September,
2007 passed by the High Court at Calcutta in G.A. No.235 of F
2006 arising out of A.P. No. 361 of 2005, whereby the High
Court had allowed the petition of the respondent and thereby
terminated the mandate of the arbitrator and thus appointed a
new Arbitrator for deciding the dispute bt::tween the parties.
G
3. In order to appreciate the controversy existing between
the parties, it may be important to narrate the facts as emerging
from the case made by the appellant, which are as follows :-
In the month of December 1992, the appellant had issued H
114 SUPREME COURT REPORTS [2010] 1 S.C.R.
A notice inviting tender for construction of terminal buildings and
various ancillary jobs at the Bhubaneshwar Airport at
Bhubaneshwar, Orissa. The respondent submitted its offer,
which was accepted by the appellant.
On 30th of March, 1993, the appellant entered into a
8
contract with the respondent for construction of the aforesaid
work at the Bhubaneshwar Airport for a total consideration of
Rs. 5, 71, 13,541.33/-. The date of commencement of the work
was fixed on 1st of March, 1993 and the stipulated date of
completion was 31st of October, 1994. However, on 20th of
C March, 1996, the appellant terminated the contract of the
respondent alleging that the respondent had failed to fulfill its
part of the obligations required under the contract. On 20th of
May, 1996, the respondent invoked the arbitration clause and
sought for an appointment of an arbitrator for adjudication of
D the disputes between the parties. On 9th of August, 1996, the
Chairman-cum-Managing Director of the appellant appointed
a sole arbitrator to adjudicate upon the claims and counter
claims of the parties. The appellant filed its counter claim on
30th of April, 1997 before the sole arbitrator. The respondent
E submitted its rejoinder and objections to the counter claims on
12th of May, 2001, after about 4 years from the date of reply
by the appellant. During this period, the appellant had virtually
closed its regional office in Calcutta as most of the work done
in its office was completed. This, according to the appellant,
F caused in several transfers of the arbitrators appointed by the
appointing authority. Meanwhile, the appointing authority had
appointed three arbitrators due to the above-mentioned reason
and the arbitration process had come to a stand still due to the
inaction of the respondent and its failure to participate.
G
Thereafter, on 20th of May, 2004, the respondent filed an
application before the Calcutta High Court seeking removal of
the then incumbent arbitrator and the arbitral proceedings were
stayed by the Court. On 20th of September, 2004, the High
Court directed the Chairman-cum-Managing Director of the
H
N.8.C.C. LTD. v. J.G. ENGINEERING PVT. LTD. 115
[TARUN CHATTERJEE, J.]
appellant company to appoint a new arbitrator in terms of the A
arbitration clause within a period of four weeks from the date
of communication of its order. The High Court further directed
the arbitrator so appointed to conclude the arbitration
proceedings within a period of six months from the date of his
appointment. Pursuant to the order of the High Court, the B
Chairman-cum-Managing Director of the appellant company
appointed Shri AK. Gupta, Deputy General Manager of the
appellant as the sole arbitrator. The said arbitrator finally
concluded the proceedings after hearing on 18th of June, 2005.
It is an admitted position that the time to conclude the arbitration c
proceeding in terms of the order of the High Court before Shri
A. K. Gupta, who was appointed as the sole arbitrator by the
Chairman-cum-Managing Director of the company had by then
already expired.
However, both the parties extended the time to conclude D
the arbitration proceeding and to pass an award accordingly,
the time was enlarged for conclusion of the arbitration to 30th
of September, 2005.
It is also an admitted position that the time limit so fixed E
i.e. arbitration must be concluded and award must be passed
within 30th of September, 2005, could not be adhered to by
the arbitrator and he failed to publish the award within this
period. About three months after the expiry of the period of
concluding the proceeding and passing of the award, it was the F
respondent who moved an application before the High Court
for a declaration that the mandate of the arbitrator had already
stood terminated. We may keep it on record that the appellant
had not filed any application for enlargement of time for the
conclusion of the arbitration proceeding or to pass the award G
. after the expiry of the period.
On 22nd of December, 2005, the High Court, vide an
interim order, restrained the arbitrator from making an award
and at the same time, had refused to accept the award
produced by the arbitrator before it which were well beyond the H
116 SUPREME COURT REPORTS [2010) 1 S.C.R.
A period fixed by the High Court. On 23rd of March, 2006, the
High Court, by its impugned order, terminated the mandate of
the arbitrator on the ground of delay in making the award. The
appellant then challenged the above mentioned order of the
Calcutta High Court before this Court vide SLP No.19471 of
B 2007 on 12th of September, 2007. At the same time, the High
Court by the impugned order dated 21st of September, 2007
passed in AP No. 361/2005 appointed Mr. Justice Chittatosh
Mookherji (As His Lordship then was) as the sole arbitrator to
adjudicate the disputes between the parties. The appellant,
C feeling aggrieved by this order as well has filed a special leave
petition which came to be registered as SLP No. 22243 of
2008, which after hearing the learned counsel for the parties
and on grant of leave, was heard in presence of the learned
counsel for the parties.
D 4. We have heard the learned counsel appearing on behalf
of the parties and examined the impugned orders of the High
Court and also other materials on record in depth and in detail.
As noted herein earlier, the respondent had made an
application before the Calcutta High Court under Section 14
E of the Arbitration and Conciliation Act, 1996 (in short the "Act")
for a declaration that the mandate of the arbitrator Shri A.K.
Gupta had already stood terminated. As had already been
mentioned above, the appointing authority had appointed three
arbitrators prior to the appointment of Shri Gupta who were all
F unable to conduct the arbitral proceedings for some reason or
the other. It may be kept on record that the respondent filed an
application before the High Court for a declaration that the
appointment of the arbitrator namely, Shri Amitava Basu, who
was appointed as the sole arbitrator prior to the appointment
G of Shri A. K. Gupta had stood terminated by an order dated
20th of September, 2004, by which the High Court had
terminated the appointment and ordered the appointing
authority of the appellant to appoint a new arbitrator who will
conclude the proceeding and pass an award within six months
H from the date of his appointment. Subsequent to this order of
N.B.C.C. LTD. v. J.G. ENGINEERING PVT. LTD. 117
[TARUN CHATIERJEE, J.]
the High Court, the appellant appointed Mr. AK Gupta as the A
new arbitrator who was to complete his proceedings by 27th
of March, 2005 i.e. six months from the date of his appointment.
It is pertinent to mention that the appellant did not file any appeal
against the above-mentioned order of the High Court.
Therefore, it may be taken that the appellant had accepted the B
aforesaid order of the High Court and thereby accepted its
decision to fix the time of the arbitration proceedings to be
mandatorily concluded within six months from the date of
appointment of the arbitrator. The order, thus having assumed
finality, a time limit was imposed for the conclusion of the c
arbitration proceedings. Thus, the appellant is estopped from
raising any objection against the imposition of the time limit as
had been done by the Court in this respect. From the records
before us, we have noticed that inspite of conducting a number
of proceedings, the arbitrator was unable to conclude the D
proceedings within the time fixed by the High Court. The
arbitration clause in the contract enables the arbitrator to extend
the time for making and publishing the award by mutual
consent of the parties. From a perusal of the documents before
us, we notice that the parties mutually agreed to extend the time E
till 31st August, 2005 for making and publishing the award,
which were further extended by the parties till 30th of
September, 2005 on account of the arbitrator having failed to
conclude the proceedings within.the previous date fixed by the
parties. But the arbitrator having failed to do so by 30th of
September, 2005, the respondent moved the High Court to F
terminate the mandate of the arbitrator as he had failed to
conclude the proceedings within the time limit fixed by the
parties. The High Court accordingly terminated the mandate of
the arbitrator on account of his failure to publish the award within
the time fixed by the parties. We are of the opinion that the High G
Court was perfectly justified in doing so on an application filed
by the respondent before it. Quite interestingly, it has come to
our notice that the arbitrator in question had appeared before
the High Court and submitted that the award was ready but the
same could not be published on account of the interim order H
118 SUPF..L\r1E COURT REPORTS (2010] 1 S.C.R.
A passed by the same restraining him from publishing it. There
was, however, no order of the Court restraining the arbitrator
from publishing the award till almost three months after the
expiry of the time fixed by the mutual consent of the parties to
make and publish the award prior to the interim order passed
B by the High Court.
5. A perusal of the arbitration agreement quite clearly
reveals that the arbitrator has the power 1u enlarge the time to
make and publish the award by mutual consent of the parties.
C Therefore, it is obvious that the arbitrator has no power to further
extend tile time beyond that whic,h is fixed without the consent
of both the parties to the dispute. It is an admitted position that
the respondent did not give any consent for extension of time
of the arbitrator. Thus given the situation, the arbitrator had no
power to further enlarge the time to make and publish the award
D and therefore his mandate had automatically terminated after
the expiry of the time fixed by the parties to conclude the
proceedings. The learned counsel contended that the
arbitration proceedings involved questions of highly technical
and complex issues which would require sufficient amount of
E time to be decided in a just and proper way. However the
records clearly illustrate that even after a passage of over nine
years, the matter which was to be decided between the parties
by way of arbitration, could not be resolved and the process
lingered on. Arbitration is an efficacious and alternative way of
F dispute resolution between the parties. There is no denying the
fact that the method of arbitration has evolved over the period
of time to help the parties to speedily resolve their disputes
through this process and in fact the Act recognizes this aspect
and has elaborate provisions to cater to the needs of speedy
G disposal of disputes. The present case illustrates that inspite
of adopting this efficacious way of resolving the disputes
between the parties through the arbitration process, there was
no outcome and the arbitration process had lingered on for a
considerable length of time which defeats the notion of the
H whole process of resolving the disputes through arbitration. The
N.B.C.C. LTD. v. J.G. ENGINEERING PVT. LTD. 119
. [TARUN CHATTERJEE, J.]
contention of the appellant therefore cannot be justified that A
since the dispute was highly technical in nature, it had to be
dealt with elaborately by the arbitrator and thus, he was justified
in being late. The High Court had thus correctly fixed the time
for the arbitration to be concluded within a period of six months
from the appointment of the fourth arbitrator Shri AK. Gupta 8
considering the time that had been spent for the arbitration
process prior to Mr. Gupta's appointment. That apart, even
assuming that the arbitration process involved highly technical
and complex issues, which was time consuming, even then, it
was open for the arbitrator or for the parties to approach the c
Court for extension of time to conclude the arbitration
proceeding which was not done by either by the arbitrator or
by any of the parties. As had been correctly noted by the High .
Court in its impugned judgment, there was no cogent reason
for the delay in making and publishing the award by the D
arbitrator. He already had the relevant materials at his disposal
and could base his findings on the observations made by the
three arbitrators who were appointed prior to him. The
Arbitrator was bound to make and publish his award, within the
time mutually agreed to by the parties, unless the parties E
consented to further enlargement of time. Therefore, the
condition precedent for enlargement of time would depend only
on the consent of the parties, that is to say, that if the parties
agree for enlargement of time. If consent is not given by the
parties, then the authority of the arbitrator would automatically
cease to exist after the expiry of the time limit fixed. In the F
present case, the arbitrator had failed to publish the award
within the time limit fixed by the parties, and hence, the High
Court was justified in terminating the mandate of the arbitrator.
We therefore do not find any fault with the impugned order of
the High Court in this regard. From a perusal of the records, G
we can see that the respondent had filed an application to
terminate the mandate of the arbitrator before the High Court
almost after three months from the date of expiry of the time to
publish the award although the appellant did not choose to file
any application for enlargement of time for conclusion of the H •
120 SUPREME COURT REPORTS (2010) 1 S.C.R.
A arbitration proceeding. It is obvious that the respondent could
not have possibly known about the outcome of the award. Even
after the expiry of the time as mentioned above, the arbitrator
did not make any effort to publish the award nor was anything
conveyed on behalf of the appellant to the respondent for
B extending the time of the arbitrator to publish his award. It was
a clear lapse on the part of both the arbitrators and the appellant
who was well aware that the mandate of the arbitrator had
already expired and it could only be extended by a mutual
consent of the parties according to the arbitration agreement.
c It has been correctly observed by the High Court that the
arbitrator had become functus officio in the absence of
extension of time beyond 30th of September, 2005 to make
and publish the award. After the said date, the arbitrator had
no authority to continue with the arbitration proceedings. The
D learned counsel appearing on behalf of the appellant argued
that in the absence of any statutory period prescribed under the
Act for rendering an award, the direction of the Court to
conclude the arbitration proceedings within the time prescribed
by it, would not make an award passed beyond the time so
E prescribed, null and void. He further argued that the High Court
was wrong in not extending the time fixed by it in the order
dated 20th of September, 2004, for early conclusion of the
arbitration proceedings and terminating the mandate of the
arbitrator when neither the Act nor the arbitration agreement
F prescribed any time for making and publishing the award.
6. The learned counsel appearing on behalf of the
appellant had drawn our attention to a decision of this Court in
Jatinder Nath Vs. Mis Chopra Land Developers Pvt. Ltd. &
G Anr. [AIR 2007 SC 1401] to satisfy us that the award which was
passed after four months of entering upon reference does not
ipso facto become nonest and the Court has power to extend
time and give life to the vitiated award. So far as this decision
is concerned, we may keep it on record that this decision was
rendered under the Arbitration Act of 1940 and not under the
H"
N.8.C.C. LTD. v. J.G. ENGINEERING PVT. LTD. 121
[TARUN CHATIERJEE, J.]
present act with which we are only concerned. In view of our A
reasonings given hereinafter and in view of the facts involved
in this case, we do not find any ground to rely on this decision
of this Court for the purpose of this case. The other decision
cited by the learned counsel for the appellant is the decision
reported in General Manager, Department of B
Telecommunications, Thiruvananthapuram Vs. Jacob S!o
Kochuvarkey Kalliath (Dead) by LRs. And Others [2003 (9)
sec 662]. The learned counsel particularly relied on para 8 of
the said decision. We have carefully gone through para 8 of
the decision relied on by the learned counsel for the appella_nts. c
We may not forget that we are concerned in this case with the
Arbitration and Conciliation Act, 1996 and not under the Land
Acquisition Act, 1894. Without going into the details of this
decision, we may simply say that this decision cannot have any
manner of application and the principles laid down to the facts D
and circumstances of the present case. The last decision,
which was cited by the learned counsel for the appellant is the
decision reported in National Aluminum Co. Ltd. Vs. Pressteel
& Fabrications (P) Ltd. and Another [2004 (1) SCC 540]. In
our view, this decision also is of no help to the appellant. The E
principles laid down in the said decision cannot have any
application in the present case although the decision rendered
in this case is the decision under the Arbitration and
Conciliation Act, 1996.
7. Taking into consideration the arguments of the appellant, F
it is necessary to mention here that the Court does not have
any power to extend the time under the Act unlike Section 28
of the 1940 Act which had such a provision. The Court has
therefore been denuded 'of the power to enlarge time for
making and publishing an award. It is true that apparently there G
is no provision under the Act for the Court to fix a time limit for
the conclusion of an arbitration proceeding, but the Court can
opt to do so in the exercise of its inherent power on the
application of either party. Where however the Arbitration
agreement itself provides the procedure for enlargement of time H
122 SUPREME COURT REPORTS [2010] 1 S.C.R.
A and the parties have taken recourse to it, and consented to the
enlargement of time by the arbitrator, the Court cannot exercise
its inherent power in extending the time fixed by the parties in
the absence of the consent of either of them.
8 8. The counsel for the appellant further contended that the
High Court could not have terminated the mandate of the
arbitrator on the ground that the award was passed beyond the
time limit fixed by it. It is clear from an apparent perusal of the
judgment of the High Court and the records before us that the
.c High Court had not terminated the mandate of the arbitrator on
the ground that the arbitrator could not pass the award within
the time fixed by it vide its order dated 20th of September,
2004. In fact, the arbitrator had continued to proceed with the
arbitration procedure after the time fixed by the Court had
expired on account of the mutual consent of the parties to
D extend the time limit. Such an action was clearly warranted
under the arbitration agreement in force between the parties.
On the contrary, the arbitrator had ceased to have any authority
only after the time limit fixed by the parties had expired and the
respondent did not give consent to the extension of the time
E for publishing the award. Thus, such a contention of the
appellant cannot be accepted. The High Court had merely
asserted this fact that the mandate of the arbitrator had
automatically expired after the time fixed by the parties to the
effect that it had lapsed.
F
9. The Appellant further argued that the High Court had
failed to appreciate that the parties had undergone the process
of arbitration for a long time and it was not wise to terminate
the mandate of the arbitrator when the award was ready and
G fit to be published, considering the fact that a huge sum of
money had been spent during the proceedings. Therefore, the
High Court should not have ordered the appointment of a new
arbitrator. It is to be noted that the High Court in its impugned
judgment had ordered Shri AK. Gupta to hand over the relevant
H materials relating to the proceedings to the newly appointed
N.B.C.C. LTD. v. J.G. ENGINEERING PVT. LTD. 123
[TARUN CHATIERJEE, J.]
arbitrator. Thus, such an action would inherently make it clear A
for the newly appointed arbitrator to conduct the proceedings
and it is not required from him to start the proceedings from
scratch all over again. Further, if the award was ready as had
been contended by the appellant, it is baffling that even after
three months from the expirY of the period fixed by the parties B
for publication of the award, the arbitrator had not come out with
the award or had notified the respondent that the award was
ready. It was only when the High Court restrained the arbitrator
from coming out with any award in the dispute that the arbitrator
submitted before the Court that the award was ready to be c
published. At the risk of repetition, we may once again note,
that the Court has no inherent power to enlarge the time for
publication of the award once it has not been extended by the
parties to that effect.
10. The appellant further argued that the arbitrator having D
concluded the proceedings couldn't be said to have failed to
act so as to attract the provisions of Section 14 of the Act and
call for termination of the mandate of the arbitration. He had
also contended that under Section 15 (2) of the Act, substitute
arbitrator should be appointed according to the rules that were E
applicable to the appointment of the arbitrator. Accordingly, his
contention was that the High Court had erred in holding that the
appointing authority had not appointed an arbitrator while
terminating the mandate of the arbitrator in the same
proceedings. F
It is necessary to mention here Section 14 ahd Section 15
of the Act for the sake of convenience.
"Section 14: Failure or impossibility to act -
G
(1) The mandate of an arbitrator shall terminate if-
(a) He becomes de jure or de facto unable to perform his
functions or for other reasons fails to act without undue
delay; and H
124 SUPREME COURT REPORTS [2010) 1 S.C.R.
A (b) He withdraws from his office or the parties agree to the
termination of his mandate.
(2) If a controversy remains concerning any of the grounds
referred to in clause (a) of subsection (1 ), a party may,
unless otherwise agreed by the parties, apply to the court
B
to decide on the termination of the mandate.
(3) If, under this section or sub-section (3) of section 13,
an arbitrator withdraws from his office or a party agrees
to the termination of the mandate of an arbitrator, it shall
c not imply acceptance of the validity of any ground referred
to in this section or sub-section (3) of section 12."
"Section 15: Termination of mandate and substitution of
arbitrator-
D (1) In addition to the circumstances referred to in section
13 or section 14, the mandate of an arbitrator shall
terminate-
(a) Where he withdraws from office for any reason; or
E
(b) By or pursuant to agreement of the parties
(2) Where the mandate of an arbitrator terminates, a
substitute arbitrator shall be appointed according to the
rules that were applicable to the appointment of the
F arbitrator being replaced.
(3)Unless otherwise agreed by the parties, where an
arbitrator is replaced under subsection (2), any hearings
previously held may be repeated at the discretion of the
G arbitral tribunal.
(4) Unless otherwise agreed by the parties, an order or
ruling of the arbitral tribunal made prior to the replacement
of an arbitrator under this section shall not be invalid solely
H
N.B.C.C. LTD. v. J.G. ENGINEERING PVT. LTD. 125
[TARUN CHATTERJEE, J.]
because there has been a change in the composition of A
the arbitral tribunal."
11. With reference to the contention made by the appellant
that the arbitrator having concluded the proceedings couldn't
be said to have failed to act so as to attract the provisions of 8
Section 14 of the Act, which will call for termination of the
arbitration proceeding. It is pertinent to mention here that the
arbitrator had not concluded the proceedings as had been
agreed to by the parties within the time fixed for doing so. The
mandate of the arbitrator was terminated only because of the C
fact that the arbitrator having failed to conclude his proceedings
within time did not warrant to be continued as an arbitrator in
the absence of the consent of both the parties. It is clear from
a bare reading of sub section 1 (a) of section 14 of the Act,
the mandate of an arbitrator shall terminate if he fails to act
without undue delay. In the present case, it is clear that the D
arbitrator had extended the time provided to it without any
concrete reasons whatsoever and thus his mandate was liable
to be terminated. Sub section 1(b) further states that the
mandate of an arbitrator shall also stand to be terminated if he
withdraws from his office or the parties agree to the termination E
of his mandate. From the perusal of the records and the
submissions of the parties, we observe that the mandate of the
arbitrator was extended by an agreement between the parties,
which was not extended beyond 30th September, 2005. Thus
it can be construed that the parties had not agreed to the F
extension of the mandate of the arbitrator failing which, the
mandate was automatically terminated.
12. Further, Subsection (2) of Section 14 of the Act
stipulates that if a controversy remains concerning any of the G
grounds referred to under clause (a) of subsection (1), a party
may, unless otherwise agreed to by the parties, apply to the
Court to decide on the termination of the mandate. Thus the
respondent rightly applied to the Court for the termination of the
mandate of the arbitrator pursuant to the provisions of this H
126 SUPREME COURT REPORTS [2010] 1 S.C.R.
A section, and the Court was within its jurisdiction to decide
accordingly.
13. However, the contention of the Appellant that the High
Court had erred in not allowing the appellant to decide upon
the appointment of an arbitrator pursuant to sub-section (2) of
8
Section 15 of the Act must be accepted. Section 15 (2) of the
Act provides that where the mandate of an arbitrator terminates,
a substitute arbitrator shall be appointed according to the rules
that were applicable to the appointment of the arbitrator
C replaced. In this connection, it would be appropriate to refer to
the relevant portion of the impugned judgment of the High Court,
which gives an elaborate observation on the above-mentioned
issue raised by the appellant:
"The question therefore is, whether in view of section 15
D (2) of the 1996 Act, an independent arbitrator can be
appointed by this Court as prayed for by the appellant or
whether the appellant should once again invoke the
Arbitration Clause, call upon the Chairman-cum-Managing
Director of the respondent to appoint an arbitrator, wait for
E a further period of 30 days, to see whether the Chairman-
cum-Manag ing Director acts or not and then make a
request to the Hon'ble Chief Justice or his designate under
Section 11 (6) of the 1996 Act to appoint an arbitrator.
Arbitration is an informal, quick and easy alternative mode
F
of adjudication of disputes by agreement of the parties.
This Court cannot but take judicial notice of the fact that
the Arbitration Clause was invoked way back in May 1996
and almost 10 years have expired since then. The
appointment of successive Arbitrator by the Chairman-
G cum-Managing Director of the respondent has only resulted
in delay.
When the mandate of an arbitrator is terminated on the
ground of delay, the rules applicable to the appointment
H of the arbitrator are to apply to the appointment of a new
N.B.C.C. LTD. v. J.G. ENGINEERING PVT. LTD. 127
[TARUN CHATTERJEE, J.]
arbitrator. It would, however, be a mockery of justice, if A
every time the mandate of an arbitrator was terminated or
the arbitrator resigned or otherwise became unable to
proceed, the parties were to start from scratch, by invoking
the Arbitration Clause.
B
Once the mandate of the arbitrator terminates, the person
required to appoint arbitrator is required to fill up the
vacancy with utmost expedition, failing which the
provisions of section 11 (6) of the 1996 Act would be
attracted. In the instant case, as per the Arbitration C
agreement the Chairman-cum-Managing Director was
required to appoint a new arbitrator in case the arbitrator
became unable to continue, whatever be the reason. Even
thought the time limit for conclusion of arbitration expired
on 3oth September, 2005, the Chairman-cum-Managing
Director of the respondent did not appoint another D
arbitrator."
14. We have carefully examined the aforesaid
observations of the impugned judgment of the High Court. We
are of the view that in view of a three-Judge Bench decision of E
this Court in the case of Northern Railway Administration,
Ministry of Railway vs. Patel Engineering Company Ltd. [2008
(10) SCC 240] in which a decision of this Court in Ace Pipeline
Contracts Private Limited vs. Bharat Petroleum Corporation
Limited [(2007) 5 SCC 304] was also referred to, the F
application for appointment of an Arbitrator under Section 11
of the Act should be referred back to the High Court for fresh
decision. Arijit Pasayat, J (as His Lordship then was), heading
a three-Judge Bench of this Court after considering the scope
and object of the Act particularly Section 11 of the Act G
concluded the following :-
"A bare reading of the scheme of Section 11 shows
that the emphasis is on the terms of the agreement being
adhered to and/or given effect as closely as possible. In
other words, the Court may ask to do what has not been H
128 SUPREME COURT REPORTS [201 OJ 1 S.C.R.
A done. The court must first ensure that the remedies
provided for are exhausted. It is true as contended by Mr.
Desai, that it is not mandatory for the Chief Justice or any
person or institution designated by him to appoint the
named arbitrator or arbitrators. But at the same time, due
B regard has to be given to the qualifications required by the
agreement and other considerations.
xxxxxxxxxxxxxx
In all these cases at hand the High Court does not
C appear to have focused on the requirement to have due
regard to the qualifications required by the agreement or
other considerations necessary to secure the appointment
of an independent and impartial arbitrator. It needs no
reiteration that appointment of the arbitrator or arbitrators
D named in the arbitration agreement is not a must, but while
making the appointment the twin requirements of Sub-
section (8) of Section 11 have to be kept in view,
considered and taken into account. If it is not done, the
appointment becomes vulnerable. In the circumstances, we
E set aside the appointment made in each case, remit the
matters to the High Court to make fresh appointments
keeping in view the parameters indicated above."
In the aforesaid decision in the case of Northern Railway
F Administration (Supra}, Arijit Pasayat, J. (as His Lordship then
was), held that the High Court in the said case did not appear
to have focused on the requirement to have due regard to the
qualifications required by the agreement or other conditions
necessary to secure the appointment of an independent and
impartial arbitrator. In the aforesaid decision, this Court also
G concluded that since the requirement of sub-section (8) of
Section 11 was not at all dealt with by the High Court in its order,
the appointment of an arbitrator without dealing with Sub-
section 8 of Section 11 of the Act became vulnerable and
accordingly, such appointment must be set aside. Similar is the
H position in this case. In this case also, before appointing an
•
N.B.C.C. LTD. v. J.G. ENGINEERING PVT. LTD. 129
[TARUN CHATTERJEE, J.]
arbitrator under Section 11 (6) of the Act, the High Court had A
failed to take into consideration the effect of Section 11 (8) of
the Act as was done in Northern Railway Administration (supra).
15. In view of the discussions made hereinabove and
particularly, in view of the principles laid down by this Court in 8
Northern Railway Administration (supra), we set aside the
impugned order and remand the case back to the High Court
for fresh decision of the application under Section 11 (6) of the
Act and while considering the application afresh, the High Court
is directed to take into consideration the aforesaid decision of C
this Court.
16. The appeals are thus allowed to the extent indicate
above. There will be no order as to costs.
D.G. Appeals partly allowed. o
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.