Created byFuzzy Cloud

Supreme Court of India

NIRMALA ANANDversusADVENT CORPORATION (P) LTD. AND ORS.

Citation
2002 INSC 414
Decided
30 September 2002
Disposal
Appeal(s) allowed

Holding

Specific performance is warranted, and the purchaser must pay a reasonable additional sum of Rs.6,25,000 to the sellers, balancing the breach and equity.

Summary

The appellant, Nirmala Anand, entered into a 1966 agreement to purchase a flat for Rs.60,000, paying Rs.35,000 before the seller's lease was cancelled, leaving the building incomplete. She sued for specific performance, but the High Court denied it and awarded damages; the Division Bench affirmed. On appeal, the Supreme Court held that the seller breached by failing to deliver possession and that specific performance was appropriate despite the massive increase in property value over three decades. The Court exercised its discretion to impose a reasonable condition, directing the appellant to pay an additional Rs.6,25,000 (instead of the contested Rs.40,00,000) to the sellers, alongside the balance consideration, to balance equities. The appeal was allowed, the decree modified, and a conditional order for specific performance was issued.

Issues considered

  • Whether specific performance of a flat purchase agreement can be granted when the seller has breached and the market value has escalated dramatically.
  • Whether the purchaser must be ordered to pay an additional sum beyond the balance consideration, and if so, what amount is reasonable.
  • Whether the court may impose conditions on the grant of specific performance under its equitable discretion.

Legislation cited

Subjects

specific performancebreach of contractreal estateincrease in market valueequitable reliefconditional decreebalance of equities

Judgment

A                               NIRMALA ANAND
                                         V.

              ADVENT CORPORATION (P) LTD. AND ORS.

                            SEPTEMBER 30, 2002

B     [G .B. PATTANAIK, Y.K. SABHARWAL AND H.K .. SEMA, JJ.]


          Contract Act, 1872:

         Agreement for purchase of flat-Part payment made by purchaser-
C Before completion of constrziction lease of the' land was cancelled by
    Corporation-Seller could not perform his obligation-Suit for specific
    performance-Single Judge rejected prayer for specific performance but
    directed payment of damages-Affirmed by Division Beneh-On appeal, two-
    Judge Bench Held, purchaser entitled to specific performance of agi:eement-
D   Difference of opinion between the Judges on the amount to be paid by the
    purchaser to the seller in .tie11 of unpaid balance-Matter referred to three-
    Judge Bench-Held, purchaser was ready and willing to perform her part of
    the contract and seller committed .breach in not performing his part of
    agreement by denying the possession offlat in question-Purchaser directed
    to pay to seller certain reasonable additional amount.
E
        Appellant-purchaser entered into an a·greement with the sellers
  (Respondent Nos. I and 2) for purchase of a flat. Appellant made part-
  payment of consideration amount. However, before completion of the
  construction, lease of the land was cancelled by the Municipal Corporation.
  Appellant filed a suit against the Respondents for the specific performance
F of the agreement. Single Judge of the High Court found sellers guilty of
  having committed breach in carrying out the terms of the agreement but            -
  did not allow the relief of specific performance, but awarded certain
  amount in lieu of damages. The judgment and decree was affirmed by
  Division Bench of the High Court. Hence this appeal. The Division Bench
G of this Court allowed the appeal by holding that the appellant was entitled
  to the specific performance of the agreement. However, there was a
  difference of opinion among the Judges on the amount to be paid by the
  purchaser to sellers in lieu of unpaid balance. Hence matter was referred
  to three-Judge Bench to determine as to whether the appellant/purchaser
  should be directed to pay any additional sum, and if so, what amount. "·
H                                       7~
              NIRMALA ANAND v. ADVENT CORPORATION (P) LTD.              707
     Allowing the appeal, the Court                                             A
      HELD: I. I. It is evident that the appellant is ready to take
incomplete flat and pay further sum on account of phenomenal increase
in the market price of the flat during the pendency of this litigation for
over three decades. There appears no reason why the appellant cannot
be allowed to have the entire benefit of manifold 'mega increase of the value   B
of real estate property in the locality. It would not be unreasonable and
inequitable to make the appellant the sole beneficiary of the escalation of
real estate prices and the enhanced value of the flat in question. 1710-A-C)

      2. While balancing the equities, one of the consideration to be kept      C
in view is as to who is the defaulting party. It is also to be borne in mind
whether a party is trying to take undue advantage over the other as also
the hardship that may be caused to the defendant by directing the specific
performance. There may be other circumstances on which parties may
not have any control. The totality of the circumstances is required to be
seen. In the instant case, the suit was filed by the plaintiff within a month   D
of the date when the posses~i()n under the agreement was to be delivered
to her. She had already i)aid more than 50% of the sale consideration.
There was no occasion for her to pay the balance consideration to the
seller. The Courts have concurrently found that the appellant has always
been ready and willing to perform her part of the contract and the seller
committed breach in not carrying out the terms of the agreement. While          E
others left, the appellant has been single handedly fighting for her rights
under the agreement. She has agreed to take the flat on as-is-where-is-
basis without claiming any reduction in purchase price and without
making the seller liable for anything incomplete in the building.
                                                         (710-F-H; 711-A-B)     F
      3. For the revival of the building plans, revival of lease and other
such steps, the sellers and/or their assignees may have to take steps as per
agreement between them but to ask the appellant to pay to Respondeot
Nos. 1 and 2, a sum of Rs. 40,00,000 would be too onerous and would
almost amount to denying her specific performance. It would also amount         G
to putting a premium on the breach committed by Respondents I and 2.
Along with the remaining amount of the sale consideration, the appellant
can also be directed to pay to Respondents 1 and 2 a s,ome reasonable
additional amount, they having been deprived of the amount of Rs. 25,000
during all these years. Having regard to the totality of circumstances,         H
    708                    SUPREME COURT REPORTS (2002] SUPP. 2 S.C.R.

A appellant is directed to pay to Respondents I and 2 a sum of Rs. 6,25,000
    instead of Rs. 25,000. The impugned judgment and decree of the High
    Court shall stand modified and altered accordingly and there shall IJe a
    decree in the Suit on the file of the original side of the High Court on the
    above terms. 1711-B-Fl

B           Nirmala Anand v. Advent Corporation (P) ltd and Ors., 120021 5 SCC
    481, referred to.

            CIVIL APPELLATE JURISDICTION              Civil Appeal No. 574 of
    1988.

C        From the Judgment and Order dated 15.7.1987 of the Mumbai High
    Court in A. No. 204 of 1981.

         Gourab Banerji, R.N. Karanjawala, Arunabh Choudhary and Ms. Meghna
    Mishra for Mrs. M. Karanjawala, for the Appellants.

D        .P.P. Tripathi, Ms. Nina Gupta, Ms. Bina Gupta, Ms. A. Mahajan,
    Ms. Shalini Rai, Ms. Neha Misra, V.N. Raghupathy, C. Mukund, G.K. Singh,
    Ms. Sudha Sharma, T.V. Ratnam and D.N. Mishra, for the Respondent.

          The Judgment of the Court was delivered by

E        Y.K. SABHARWAL, J. The appellant, who was plaintiff No. 4 in the
  suit, entered into an agreement dated 6th September, 1966 with Respondent
  Nos. 1and2 for the Purchase offlat No. 71, on the 7th Floor of the building
  known as 'Divya Prabha' situated at 12-A, Foreshore Road, Bombay. The
  sale consideration payable under the agreement is Rs. 60,000. The agreement
  stipulated that the building was to be completed and possession of the flat
F delivered to the appellant by 30th June, 1969 up to which time, the appellant
  had already paid Rs. 35,000 out of the sale consideration leaving a balance
  of Rs 25,000 Just a few days before the date fixed for completion and
  delivery of possession, the lease of the plot of land on which the flats were
  being constructed was cancelled by the Bombay Municipal Corporation. At
G that stage, the building was incomplete. Admittedly, it is incomplete till date.
           Similar agreements in respect of different flats were also entered into
    by the sellers with other flat purchasers, On 30th July, 1969, a suit , out of
    which the present appeal has arisen, was filed seeking specific performance \ .
    of the flat purchase agree!llents. The plaintiffs other than plaintiff Nos. 4 and
H   7 settled their case with sellers during the pendency of the suit and plaintiff
                      NIRMALA ANAND v. ADVENT CORPORATION (P) LTD. [Y K ~MlHARWAL. J J 709

                  No. 7 also settled during pendency of the appea: beforeJhe J;).i.vision Bench      A
                  of the High court. There was, however, no settlement befween the plaintiff-
                  appellant and respondents I and 2. In the decision of the. suit, learned Single
                  Judge of the High Court held that the appellant was always ready and willing

-            "'
                  to performs her part of the contract and it was the sellers who committed
                  breach in not carrying out the terms of the agreement. L'6arned Single Judge
                  was, however, of the view that the grant of specific performance being             B
                  discretionary remedy in equity, taking into account several and serious
                  imponderabilites and further considering that huge sums may be required to
                  complete the building, which amount cannot be properly assessed, the appellant
                  was not entitled to the relief of specific performance and instead it was
                  directed that the seller shall pay to the appellant damages as assessed by the     c
                  Commissioner for taking accounts with interest at 6% per a11num from the
                  date of the decree till the date of payment/realization, in addition to the
                  repayment of Rs. 35,000 with interest thereon at 9% per annum from 4th
                  October, 1967 till the date of decree and for the subsequent period, at 6% per
                  annum till the date of payment/realization. The judgment and decree of the
                  learned Single Judge was affirmed by a Division Bench of the High Court in         D
                  appeal. Aggrieved therefrom, the present appeal was file.i,9Jl~rant of leave.

                        The appeal was heard by a two Judge Bench. The J'eamed Judges have
                  concurred that the appellant is entitled to the specific :performance of the
                  agreement dated 8th September, 1966. There has, however, been difference
                  of opinion between learned Judges on the condition in respect of additional        E
    '·
                  amount that may be paid by the appellant to respondent Nos. I and 2 and,
                  therefore, the matter has been placed before this three Judge Bench. The
J
                  opinions of the learned Judges are reported in Nirma/a Anand v. Advent
                  Corporation (P.) Ltd. and Ors., [2002] 5 SCC 481. In the opinion expressed
                  by brother Justice Doraiswamy Raju, the appellant has been directed to pay         F
                  sum of Rs. 40,00,000 in addition to the sum already paid to respondents I
                  and 2 and in the view of brother Justice Ashok Bhan, it would be unfair to
                  impose the condition of payment of Rs. 40,00,000 and the appellant is entitled
                  to specific perfonnance of agreement to sell on the price mentioned in the
                  agreement.
    ''oj
         '
                                                                                                     G
                        We have heard learned counsel for the parties. The only question to
                  determine is as to whether the appellant shall be directed to pay respondents
                  I and 2 any additional sum and if so what amount.

                        The appellant is prepared and willing to take possession of the incomplete
                  flat without claiming any reduction in th.e purchase price and would not hold      H
    710                     SUPREME COURT REPORTS [2002) SUPP. 2 S.C.R.

A respondent Nos. 1 and 2 responsible for anything incomplete in the building.
    It has been concurrently held that she did not comm it breach of the agreement
    to sell. She has always been ready and willing to perform her pan of the
    agreement. The appellant is ready and willing to pay to respondents I and 2


B
    interest on sum of Rs. 25,000. The breach was committed by respondents 1
    and 2 as noticed hereinbefore. It is evident that the appellant is ready to take
    incomplete flat and pay further sum as noticed, most likely on account of
                                                                                           -
    phenomenal increase in the market price of the flat during the pendency of
    this litigation for over three decades. We see no reason why the appellant
    cannot be allowed to have, for her alone, the entire benefit of manifold mega
    increase of the value of real estate property in the locality. In our view, it
C   would not be unreasonable and inequitable to make the appellant the sole
    beneficiary of the escalation of real estate prices and the enhanced value of
    the flat in question. There is no reason why the appellant, who is not a
    defaulting party, should not be allowed to reap to herself the fruits of increase
    in value.

D         It is true that grant of decree of specific perfonnance lies in the discretion
    of the court and it is also well settled that it is not always necessary to grant
    specific performance simply for the reason that it is legal to do so. It is  .
    further well settled that the court in its discretion can impose any reasonable
    condition including payment of an additional amount by one party to the
E   other while granting or refusing decree or specific performance. Whether the
    purchaser shall be directed to pay an additional amount to the seller or converse
    would depend upon the facts and circumstances of a case. Ordinarily, the
    plaintiff is not to be denied the relief of specific performance only on account
    of the phenomenal increase of price during the pendency of litigation. That
    may be, in a given case, one of the consideration besides many others to be
F   taken into consideration for refusing the decree of specific performance. As
    a general rule, it cannot be held that ordinarily the plaintiff cannot be allowed
    to have, for her alone, the entire benefit of phenomenal increase of the value
    of the property during the pendency of the litigation. While balancing the
    equities, one of the consideration to be kept in view is as to who is the
G   defaulting party. It is also to be borne in mind whether a partly is trying to
    take undue advantage over the other as also the hardship that may be caused
    to the defendant by directing the specific performance. There may be other
    circumstances on which parties may not have any control. The totality of the
    circumstances is required to be seen.

H         In the present case, the suit was filed by the plaintiff within a month
                NJ RM ALA ANAND 1·. ADVENT CORPORA TJON (P) LTD. [Y.K. SABHARWAL, J.J 7 J ]


            of the date when the possession under the agreement was to be delivered to A
            her. By that time, she had already paid more than 50% of::1e saie consideration.
            There was no occasion for her to pay the balance consideration to the seller.
            The courts have concurrently found that the appellant has always been ready
            and willing to perform her part of the contract and the seller committed
      ...   breach in not carrying out the terms of the agreement While others left, the
            appellant has been single handedly fighting for her rights under the agreements. B
            She has agreed to take the flat on as is where is basis without claiming any
            reduction in purchase price and without making the seller liable for anything
            incomplete in the building. Further the building except the flat in question
            has been sold by respondents 1 and 2 to the 7th respondent. For the revival
            of the building plans, revival of lease and other such steps, the sellers and/ C
            or their assignees may have to take steps as per agreement between them but
            to ask the appellant to pay to respondent Nos. I and 2, a sum of Rs. 40,00,000
            would be too onerous and would almost amount to denying her specific
            performance. It would also amount to putting a premium on the breach
            committed by respondents l and 2. Along with the remaining amount of the
            sale consideration, the appellant can also be directed to pay to respondents D
            1 and 2 some reasonable additional amount, they having been deprived of
            that amount of Rs. 25,000 during all these years.

                  Having regard to the totality of circumstances, we would direct the
            appellant to pay to respondents I and 2 a sum of Rs. 6,25,000 instead of Rs.
            25,000. The amount of Rs. 40,00,000, Wherever it appears in the opinion of        E
            Justice Doraiswamy Raju, would be read as Rs. 6,25,000. all other conditions
            will remain.

                  The appeal is accordingly allowed and the impugned judgment and
            decree of the High Court shall stand modified and altered and there shall be      F
            a decree in Suit No. 744 of 1969 on the file of the original side of the High
            Court, Bombay in the following terms:

                   (i)   There shall be conditional decree for specific performance of the
                         agreement dated 8.9.1966 entered into between the 4th plaintiff
...
  \
                         and Defendants 1 and 2 and Defendants 1 and 2 shall execute a        G
                         sale deed as envisaged in the agreement for sale of Flat No. 71
                         on 7th Floor of the building known as "divya Prabha" situated
                         at No. 12-A, Foreshore Road, Bombay, on "as-is-where-is
                         condition".
                   (ii) That the appellant-plaintiff 4, within a period of six weeks, shall   H
    712                   SUPREME COURT REPORTS [2002] SUPP. 2 S.C.R.

A              pay the defendants-respondents I and 2, a sum of Rs. 6,25,000
               (Rupees six lakh and twenty five thousand only) in addition to
               the sum already paid by her. The appellant shall be entitled to
               have the sale deed executed in her favour only on prior
               compliance and satisfaction of this condition.
          (iii) The rights and interest in the land shall be as agreed to between     ,.
B
                parties and as per scheme and arrangement contained in the
                agreement dated 8-9-1996.
          (iv) Defendants I and 2 and/or the 7th respondent in this appeal viz.
               Gaurav Overseas Private Ltd. 92, Maker Chambers, Nariman
                            /



c              Point Bombay 400 020, as and when they secure the necessary
               renewal of the lease and revalidation of the building plan, the
               same shall be for the benefit of the appellant-Plaintiff 4 also,
               subject to the condition that she shall contribute her share of the
               monetary commitments and expenses incurred therefor, on being
               intimated by any of them in writing four weeks from the date of
D              such receipt of the intimation. In case of dispute about the
               quantum, the same shall be got determined and settled before the
               Commissioner for taking accounts, on being moved by either of
               them. The sum so determined shall be a charge on the property
               comprised in Flat No. 71, till it is paid and shall be entitled to
               be recovered, accordingly.
E
          (v) The appellant and the 7th respondent shall be at liberty to mutually
              agree for completion of the incomplete building at such prevailing
              market rates as would be applicable for the work and manner of
              its completion and the mode of payment. If there can be no such
              mutual agreement among the appellant and the 7th respondent in
F             this regard, as and when the sale deed is executed by the I st and
              2nd defendants, as per this decree, the appellant shall be at liberty
              to make her own arrangement to have her flat completed through
              approved and Iicensed architects.
          (vi) The sale/conveyance pursuant to the decree in the suit shall be
G              subject to all such rights and liabilities and obligations of
               respective parties (the appellant, respondents I, 2 and 7) under
               the suit agreement, as are available to each of them against the
               others, had the sale been effected even without the intervention
               of this Court, by mutual agreement of parties.
H         (vii) The appellant falling to comply with the terms of the conditional
    NIRMALAANAND v. ADVENT CORPORATION (P) LTD. [Y.K. SABHARWAL, J.J 713

              decree passed as above, shall stand denied and lose her right and A
              entitlement to get specific performance of the agreement dated
              8-9-1966 in her favour and consequently, the appeal shall stand
              dismissed with the appellant's rights secured as per the judgments
              and decrees dated 23-3-1981 and 15-7-1987 firmly affirmed and
              settled, and the rights to have them executed in the manner known
              to law, alone serving to the appellant.                            B
         (viii) Each party shall bear their respective costs in this Court.
         The appeal is allowed in above terms.

S.K.S.                                                          Appeal allowed.


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "specific performance"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.