P.K. SINGHversusM/S. S.N. KANUNGO AND OTHERS
- Citation
- 2010 INSC 110
- Decided
- 18 February 2010
- Disposal
- Disposed off
- Bench
- M PANCHALB S CHAUHAN
Holding
The letters seeking adjustment of the decree are not contempt of court; the High Court judgment finding contempt is set aside.
Summary
The case arose from an arbitration award directing the Andaman and Nicobar Administration to pay a contractor a sum with interest. The Executive Engineer (appellant) wrote letters to the contractor seeking to adjust the award by having the contractor accept only the principal amount and waive interest, invoking Order XXI Rule 2 of the CPC. The contractor filed a contempt petition under Section 14 of the Contempt of Courts Act, alleging willful and deliberate violation of the High Court's judgment. The High Court held the appellant guilty of contempt, accepted an unconditional apology and imposed costs, but failed to decide whether the alleged violation actually amounted to contempt. The Supreme Court held that the letters seeking adjustment constitute a permissible "adjustment" under Order XXI Rule 2 and do not amount to contempt; the High Court erred in presuming contempt and in imposing costs. Consequently, the Supreme Court set aside the High Court judgment and disposed of the appeal without any order as to costs.
Issues considered
- Whether the letters sent by the executive engineer seeking adjustment of the arbitration award constitute contempt of court under Section 14 of the Contempt of Courts Act, 1971.
- Whether a violation of a judgment is willful and deliberate for the purpose of contempt.
- Whether the High Court erred in presuming contempt without first deciding if the alleged violation amounted to contempt.
- Whether costs can be imposed after an unconditional apology in a contempt proceeding.
Legislation cited
- Arbitration and Conciliation Act, 1996s. 34
- Code of Civil Procedure, 1908s. Order XXI Rule 2
- Contempt of Courts Act, 1971s. 14
Subjects
Judgment
[2010] 2 S.C.R. 1040
A P.K. SINGH
v.
M/S. S.N. KANUNGO AND OTHERS
(Civil Appeal No. 6551 of 2002)
FEBRUARY 18, 2010
8
[J.M. PANCHAL AND DR. B.S. CHAUHAN, JJ.]
Contempt of Courts Act, 1971:
s. 14 - Contempt petition alleging wilful and deliberate
C violation of judgment of High Court - In an appeal arising out
of a contract, High Court directing the Department to pay ,
decretal amount to the contractor, along with interest - Officer
concerned writing to contractor for settlement as regart:Js
. ,
· interest component - High Court holding the officer concerned
D · guilty of contempt of court and while accepting unconditional
apology, imposing cost on him - HELD: Order 21, r. 2 CPC
relates to the payment of amount to a decree-holder out of .
court - An agreement, which extinguishes· the decree as sucll
in whole or in part and results in the satisfaction of the decree
E in respect of the particular relief or relieves granted by the
decree, is an 'adjustment' within the meaning of r.2 - It is open
to the parties to enter into a contract or compromise with
reference to their rights under the decree - Adjustment is not
the same as satisfaction of the decree but is some method
F of settling decree which is not provided for in the decree itself
- ·The right of the judgment-debtor to make an attempt to
. adjust the decree is independent and cannot be treated as
contempt of court - Having regard to the interest of the
. department, the officer concerned had addressed letters to the
G . contractor to adjust the award - The letters for adjustment of
award could not have been treated as contempt of court within
the meaning of the provisions of the Act - The tenor of letters
do not indicate that there was any willful disobedience on the
· part of the officer in not complying with the judgment of the
H 1040
P.K. SINGH v. S.N. KANUNGO AND ORS. 1041
High Court - The error of law committed by High Court is that A
· without answering the question whether violation of the
judgment amounts to contempt of court, it presumed that
violation of the judgment amounts to contempt of court, and
proceeded to examine the question whether violation of the
judgment was willful or deliberate - After reaching the B
conclusion that the violation is neither willful nor deliberate,
the High Court should have at once dropped the contempt
proceedings and could not have accepted the unconditional
apology tendered by the officer nor could have imposed cost
on him - Further, the High Court itself came to the conclusion c
that a Jetter being written by the officer would not amount to
willful and deliberate disobedience of the decree of the court
- In any view of the matter, the High Court, after accepting
the unconditional apology tendered by the officer, should not
have imposed cost on him - On the facts and in the D
. circumstances of the case, the judgment impugned cannot
be sustained and is set aside - Code of Civil Procedure, 1908
- Or. 21, r.2. [Para 7 and 10]
CIVIL APPELLATE JURISDICTION : Civil Appeal No.
6551 of 2002. E
From the Judgment & Order dated 9.4.2001 of the High
Court of Calcutta, Circuit Bench at Port Blair in contempt
Application No. 1O of 2001.
Jayasree Singh, Swati Sinha, Fox Mandal & Co., for the
F
Appellant.
Jena Kalyan Das for the Respondents.
The Order of the Court was delivered
ORDER G
The instant appeal is directed against the judgment dated
April 9, 2001 rendered by the High Court at Calcutta in
Contempt Application No. 010 of 2001 by which the appellant
is held guilty of contempt of court and is directed to pay the cost
. of the application to the respondent which is assessed at 200 H
1042 SUPREME COURT REPORTS [2010) 2 S.C.R.
A GMs.
2. From the record of the case it is evident that a contract
was entered into between the respondent-contractor and the
Andaman and Nicobar Administration through Union of India
for execution of the work of extension of runway by 1542 meters
B (5000 ft.) at Port Blair Airport on 29.12.1995. During the course
of the execution of the said contract, dispute arose between
the parties regarding payments of bills. The dispute was
referred to sole arbitration of Mr. O.P. Goel. The arbitrator made
his Award on March 22, 1999 and directed the Andaman and
C Nicobar Administration to pay to the respondent a sum of
· Rs.2,81,83,305/- (Rupees two crores eighty one lacs, eighty
three thousand, three hundred and five only) with 12% interest
per annum from the date of withholding of the amount of
Rs.41,42,000/- (Rupees forty one lacs forty two thousand only)
D till the date of payment.
3. Feeling aggrieved, the Union of India, through the
Exe·cutive Engineer, Andaman and Nicobar Public Works
Department, filed an application under Section 34 of the
Arbitration and Conciliation Act, 1996 on 17th June, 1999 for
E setting aside the Award. By judgment dated 29.9.2000 the
learned District Judge, Andaman and Nicobar Island, Port Blair,
dismissed the application with cost of Rs.500/-. Thereupon,
Union of India, through the Executive Engineer, preferred an
appeal, i.e., FAT No. 4220 of 2001, before the High Court at
F Calcutta. The Division Bench of the High Court dismissed the
appeal by judgment dated 26.2.2001. However, the High Court
clarified that the claim No. 4 of the Award dated 22.3.1999
would stai1d modified and the respondent-contractor would be
entitled to interest @ 12% per annum from the date of reference
G of the dispute to arbitration till the date of payment of the said
amount.
4. Thereafter, the appellant, who is Executive Engineer,
Construction Division II, APWD, South Andaman, addressed
a letter to the Superintending Engineer, Construction Circle No.
H 1, Andaman Public Works Departme,nt, on 5.3.2001 giving
\
P.K. SINGH v. S.N. KANUNGO AND ORS. 1043
details of the financial implication of the Award dated A
22.3.1999. The appellant received a letter dated March 30,
2001 from the Executive Engineer (PLG), CE's Office, APWD,
Port Blair stating that the principal component of the Award
might be released to the agency, i.e., the respondent herein,
immediately. The appellant thereupon wrote a letter dated B
30.3.2001 to the Chief Engineer, APWD requesting that the
acceptance of the Award should be communicated with details
re~rding amount/principal component to be paid. It was also
mentioned in the-said letter that for delay, if any, in payment of
the amount, he would not be responsible. The appellant c. -
thereafter addressed another letter on the same day to the
respondent requesting it to intimate its acceptance of the Award
amount to Rs.2,81,83,305/- in full and final settlement of its
claim. The respondent thereupon replied by a letter dated
30.3.2001 to the appellant that it was not willing to accept the
0
amount statPd in the aforesaid letter. The appellant, therefore,
wrote another letter on 30.3.2001 to the respondent informing
that the principal component of the Award of Rs.2,81,83,305/-
would be released on the same day and requested the
respondent to reconcile with the appellant for mutual
understanding about payment of interest. The respondent wrote E
a letter to the appellant on March 31, 2001 mentioning that it
was willing to accept the principal amount of the Award "at
present" but the remaining amdunt of the interest etc. should
be released within a fortnight. Thereupon, the appellant
addressed a letter dated 2.4.2001 to the Chief Engineer, F
APWD, Port Blair, forwarding a copy of the letter received by
him from the respondent and pointed out that the respondent
was unwilling to accept the amount of the Awa(d without
interest. The appellant addressed another letter dated 2.4.2001
to the Chief Engineer informing him about the changed stand G
of the respondent regarding its willingness to accept the
principal component of the Award and requested him to
communicate the decision regarding payment of interest
without further delay.
5. The respondent filed Contempt Application No. 010 of H
1044 SUPREME COURT REPORTS [2010] 2 S.C.R.
A 2001 in the month of April, 2001 under Section 14 of the
Contempt of Courts Act, 1971 complaining about willful and
deliberate violation of the judgment and decree dated February
26, 2001 passed in First Appeal T. No. 4220 of 2001. The High
Court issued notice to the respondent. On notice being served,
s the appellant filed a reply denying that there was willful and
deliberate breach of the decree passed by the court. By
impugned judgment the Division Bench of the High Court at
Calcutta, Circuit Bench at Port Blair, found the respondent guilty
of contempt of court and while accepting the unconditional
,c apology of the appellant, imposed cost of 200 GMs upc:in him
to be paid within a week. This judgment has given rise to the
instant appeal.
6. This Court has heard the learned counsel for the
appellant and considered the documents forming part of the
D instant appeal.
7. From the facts mentioned above, it is evident that, after
Award of the arbitrator was confirmed by Division Bench of the
Calcutta High Court, the appellant had made an attempt to
adjust the decree in terms of Order XX.I Rule 2 of Code of Civil
E Procedure by requesting the respondent to accept the principal
amount and waive the interest awarded thereon. The contents
of the two letters written by the appellant to the respondent do
not show that any attempt was made by the appellant to sit in
appeal over the judgment of the High Court. Those two letters
F do not indicate that the appellant had criticized the High Court
for awarding interest in favour of the respondent. The record
would indicate that within the framework of law, the appellant
had mctde an attempt to persuade the respondent to forego
claim relating to interest. Order XXI Rule 2 of Code of Civil
G Procedure relates to the payment of amount to a decree holder
out of court and inter alia provides that when any wrong
payment under a decree of any other kind is paid out of court
to the decree holder, the decree holder has to certify payment ·
made as required by the said Rule. An agreement, which
H extinguishes the decree as such in whole or in part and re;:,u:ts
P.K. SINGH v. S.N. KANUNGO AND ORS. 1045
in the satisfaction of the decree in respect of the particular relief A
or reliefs granted by the decree, is an 'adjustment' within the·
meaning of this Rule. It is open to the parties to enter into a
contract or compromise with reference to their rights under the
decree. If the contract or the compromise amounts to an
'adjustment' of the decree, it must be recorded under this Rule B
and unless so recorded cannot be recognized by the executing
court. Adjustment is not the same as satisfaction of the decree
but is some method of settling decree which is not provided
for in the decree itself. The right of the judgment debtor to make
an attempt to adjust the decree is independent and cannot be c
treated as contempt of court. Having regard to the interest of
the department concerned, the appellant had addressed letters
to the ;,respondent to adjust the Award. The letters for
·~djustment of Award could not have been treated as contempt
of cou~f within the meaning of the provisions of the Contempt D
of Courts Act, 1971. The tenor letters do not indicate that there
was any willful disobedience on the part of the appellant ih not
;bomplying with the judgment of the High Court.
, 8. Even if it is assumed for. the sake of argument that
1
writing of the letter dated 30.3.2001 amounts to contempt, this E
Court finds that the two letters dated 30.3.2001 and 2.4:2001
1 addressed by the appellant to the Chief Engineer, APWD, Port
Blair, indicate that the appellant had taken all possible steps
to comply with the Award confirmed by the High Court.
According to the High Court, asking the respondent to accept F
only the principal amount vide letter dated 30.3.2001 amounts
to violation of the judgment of the High Court. Having held so,
the High Court prpceeded to examine the question whether the
violation of judgment of the High Court would amount to the
con1empt of court. The High Court also considered the question G
whether violation of judgment by the appellant was willful and
deliberate. The High Court noticed that after addressing letter
dated 30:3.2001, another letter on the same day was
addressed by ·th.e appellant inviting the respondent for
negotiation with reference to the rate of interest payable to the
H
..>
1046 SUPREME COURT REPORTS (2010] 2 S.C.R.
A respondent and concluded that even if previous letter amounted
to violation of the judgment of the court, the appellant did not
do so willfully and deliberately. Though the High Court ostensibly
proceeded to examine the question whether violation of the
judgment of the High Court would amount to contempt of court,
B the said question is neither determined nor answered one way
or the other. The error of law committed by the High Court is
that without answering the question whether the violation of the
judgment amounts to the contempt of court, the High Court
presumed that the violation of the judgment amounts to
c contempt of court and proceeded to examine the question
whether the violation of judgment was willful or deliberate. After
reaching the conclusion that the violation is neither willful nor
deliberate, the High Court should have at once dropped the
contempt proceedings and could not have accepted the
unconditional apology tendered by the appellant nor could have /
0
imposed cost on the appellant. In any view of the matter, the
High Court, after accepting the unconditional apology tendered
by the appellant, should not have imposed cost on the appellant
for negligence and reckless manner in which it had allegedly
acted in the instant case.
E
9. Further, the High Court itself came to the conclusion that
a letter being written by the Executive Engineer would not
amount to willful and deliberate disobedience of the decree of
the court.
F 10. On the facts and in the circumstances of the case, this
Court is of the opinion that the judgment impugned cannot be
sustained and is liable to be set aside.
11. For the foregoing reasons, the appeal succeeds. The
G impugned judgment is set aside. The cost, if any, recovered
from the appellant be refunded to him. The appeal stands,
accordingly, disposed of.
12. There shall be no order as to costs.
H RP. Appeal disposed of.
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.