Created byFuzzy Cloud

Supreme Court of India

POORAN CHAND NANGIAversusNATIONAL FERTILIZERS LTD.

Citation
2003 INSC 535
Decided
8 October 2003
Disposal
Dismissed

Holding

A party who has accepted an arbitral award without reservation cannot later challenge it on jurisdictional grounds, and the Deputy General Manager (Materials) was competent to enter into arbitration under the contract clause.

Summary

The appellant, a contractor, entered into a work contract with National Fertilizers Ltd. that required any dispute to be referred to the sole arbitration of the General Manager, or, if unavailable, to a Deputy Manager of not lower than Dy. Manager rank. When a dispute arose, the Deputy General Manager (Materials) acted as arbitrator and awarded the contractor Rs. 69,52,404, which the contractor accepted and received. The contractor later challenged the award, claiming the Deputy General Manager lacked jurisdiction because the contract named the General Manager as the sole arbitrator. The Supreme Court held that the contractor’s unequivocal acceptance of the award barred any subsequent challenge on jurisdictional grounds, and that the contract clause expressly permitted a Deputy Manager to act as arbitrator when the General Manager was unavailable, making the Deputy General Manager competent. Consequently, the appeal was dismissed.

Issues considered

  • Whether a party who has unequivocally accepted an arbitral award can later challenge the award on the ground of lack of jurisdiction.
  • Whether the Deputy General Manager (Materials) was authorized under the contract to act as the arbitrator in place of the General Manager.

Subjects

ArbitrationJurisdictionArbitral award acceptanceContract clauseDeputy General ManagerChallenge of awardWork contract

Judgment

                       POORAN CHAND NANGIA                              A
                                   v.
                      NATIONAL FERTILIZERS LTD.

                           OCTOBER 8, 2003
                                                                        B
               [V.N. KHARE, CJ., AND S.B. SINHA, J.]

      Arbitration :

        Arbitrator-Appointment of-Award challenged as withoutjurisdiction C
  after accepting awarded sum-Maintainability-Work contract-Contract
  providing for reference of any dispute to sole arbitration of General
  Manager or Dy. Manager, in case former is not available-On a dispute
  having arisen between ihe parties Dy. General Manager entered into
  arbitration and awarded a certain amount to contractor who accepted the D
· same-Later, the contractor challenged the award as without
  jurisdiction and a nullity inasmuch as instead of General Manager,
  the Dy. General Manager entered into the reference-Held, contractor
  having submitted unequivocally to the jurisdiction of the arbitrator
  and also having accepted the awarded amount without any reservation,
  cannot challenge the award-General Manager was appointed as sole E
  arbitrator, but since contractor expressed an apprehension of getting
  justice from him, Dy. General Manager entered into reference-Since the
   reference was made in terms ofthe contract and the General Manager was
   not available, the Dy. General Manager was competent to enter into the
   arbitration.                                                           F

      CIVIL APPELLATE JURISDICTION : Civil Appeal No. 1996 of
 1998.

     From the Judgment and Order dated 29.4.97 of the Madhya Pradesh G
 High Court in Misc. A. No.116 of 1996.

      Vijay Kumar for Ms. Sangeeta Kumar' for the Appellant.

      K.N. Bhat and Ghanshyam Joshi for the Respondent.                 H
                                  531
    532                SUPREME COURT REPORTS (2003] SUPP. 4 S.C.R.
A         The following Order of the Court was delivered :

          The appellant herein entered into an agreement with the respondent-
    National Fertilizers Limited, for construction of roads, bridges/culverts,
    pedestrain roads and sewerage etc. The agreement was a written one. It
B   appears that the dispute has arisen between the appellant and the respondent,
    as a result of which the appellant moved to the Court for appointment of
    an Arbitrator. The Court appointed a sole Arbitrator in terms of clause 59
    of the contract, which provided resolution of the dispute by an Arbitrator.
    It appears that the Deputy General Manager (Materials), Vijaypur entered
C   into the reference and submitted his award on 9th November, 1992 to the
    District Judge, Guna. The appellant herein accepted the award and received
    a sum of Rs. 69,524,04. He, however, filed an objection before the Court
    of the District Judge, Guna, that t3e award is without jurisdiction, inasmuch.
    as instead of the General Manager, who was appointed as . the sole
D   Arbitrator, the Deputy General Manager (Materials) entered into the
    reference and, therefore, the award given by the Deputy General Manager
    (Materials) was without any jurisdiction and is a nullity. The said objection
    was rejected by the Court on the ground that the appellant having accepted
    the award, it was not open to him to challenge the same on the ground that
    the Arbitrator had no jurisdiction. The appellant thereafter preferred an
                                                                                     ·t
E   appeal before the High Court. The High Court also agreed with·the view            )
    taken by the Civil Court and dismissed the appeal. It is against the said
    judgment of the High Court, the appellant is in appeal before us.

          We have heard learned counsel for the parties. Only two questions
F which arise for our consideration are : (I) whether once the appellant
    having accepted the award, is it open to him to challenge the same on the
    ground that the Arbitrator had no jurisdiction and, (2) whether the Deputy
    General Manager (Materials) was competent or has jurisdiction to enter
    into an Arbitration.
G
         So far as the first question is concerned, it is not disputed that the
    appellant had received the money which was due to him under the award
    and once the appellant had submitted to· the award unequivocally and
    without reservation, it is not open to him to challenge the award. We have ..
H   looked ~to the record and find that the appellant had submitted unequivocally
          P.C. NANGIA v. NATIONALFERTILIZERSLTD.                     533

to the jurisdiction of the Arbitrator. He also accepted the awarded amount A
without any reservation. Had the appellant desired to challenge the award,
he could have reserved his right to do so, but no such reservation was made
in the letters sent by him. In this view of the matter, there remains no
manner of doubt about the fact that the appellant had submitted to the
award and it does not lie in the mouth of the appellant to challenge the B
award. For these reasons, we reject the first argument of the learned counsel
for the appellant.

     So far as the second question is concerned, we may refer to clause
59 of the contract, which runs as under :
                                                                           c
             "59.l(a) Except where otherwise provided for in the contract,
        all questions and disputes relating to the meaning of the
        specifications, designs drawings and instructions herein before
        mentioned and as to the quality of workmanship and materials
        used on the work or as to any other question, claim right, matter D
        or thing, whatsoever, in any way arising out or of relating to the
        contract, designs, drawings, specifications, estimates, instructions,
        orders or these conditions of otherwise concerning the works, or
        the execution or failure to execute the same whether arising during
        the progress of the work or after the completion or abandonment E
        thereof shall be referred to the sole arbitration of the General
        Manager of the NEL and if the General Manager is unable or
        unwilling to act, then to the sole arbitration of the some other
        person in the employment ofNEL and not below the rank of Dy.
        Manager appointed by the General Manager, willing to act as .mch F
        arbitrator."

      The District Judge, Guna of the Civil Court appointed the General
Manager of the Corporation subject to clause 59 aforementioned. It is not
in dispute that an apprehension was expressed by the appellant that if the
General Manager was appointed as an Arbitrator, he would not get justice. G
Presumably, on the aforementioned ground the Deputy General Manager
(Materials) entered into the reference. Having regard to the fact that the
reference was made in terms of clause 59 of the contract, we do not find
any illegality in the matter of entering into the reference of the Deputy
General Manager (Materials) as once the General Manager was not H
    534                SUPREME COURT REPORTS (2003] SUPP. 4 S:C.R.

A   available, the Deputy General Manager (Materials) was totally competent
    to enter into the arbitration and, thus, the objection taken by the appellant
    that the Deputy General Manager (Materials) had no jurisdiction must be
    rejected.

B        For all these reasons, we do not find any merit in the appeal. It fails
    and is, accordingly dismissed. There shall be no order as to costs.

    R.P.                                                     Appeal dismissed.


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Arbitration"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.