PRASHANT KUMAR SHARIversusGHAZIABAD DEVELOPMENT AUTHORITY
- Citation
- 2000 INSC 183
- Decided
- 3 April 2000
- Disposal
- Dismissed
- Bench
- S SAGHIR AHMAD
Holding
The Development Authority’s demand for the balance amount with penal interest was justified and no unfair trade practice was established.
Summary
The appellant had been allotted a plot by the Ghaziabad Development Authority (GDA) after paying registration, reservation and the first two instalments. He delayed further payments, alleging that the Authority had not completed development and therefore possession was delayed. The GDA issued a letter on 28‑Feb‑1995 demanding payment of the balance amount by 30‑May‑1995, with penal interest if not paid. The appellant paid only part of the balance, the Authority withheld possession and demanded interest. The appellant filed a complaint before the MRTP Commission under Sections 36‑A, 36‑B(a) and 36‑D of the Monopolies and Restrictive Trade Practices Act, claiming unfair trade practice. The Commission dismissed the complaint and the appellant appealed. The Supreme Court held that the Authority’s demand for the balance amount with penal interest was justified, that the appellant’s failure to pay instalments barred him from claiming the Authority’s alleged delay as a defence, and that no unfair trade practice was established. Consequently, the appeal was dismissed.
Issues considered
- Whether the GDA’s demand for payment of the balance amount with penal interest amounts to an unfair trade practice under the MRTP Act.
- Whether the delay in delivery of possession by the GDA relieves the allottee from liability to pay interest on the outstanding amount.
- Whether the MRTP Commission’s order dismissing the complaint can be set aside.
Legislation cited
- Monopolies and Restrictive Trade Practices Act, 1969s. 36-A, s. 36-B(a), s. 36-D
Subjects
Judgment
A PRASHANT KUMAR SHARI
v.
GHAZIABAD DEVELOPMENT AUTHORITY
APRIL 3, 2000
B [S. SAGHIRAHMAD AND R.P. SETHI, JJ.]
Monopolies and Restrictive Trade Practices Act, 1969:
Section 36-A-Unfair Trade Practice-Plot of land-Allotment of-
Allottee failed to pay timely instalments in respect ofa plot ofland-Allottee did
c not deny his liability to pay balance amount with interest-Development Au-
thority therefore, demanded amount with penal interest handing over posses-
sion ofplot-Validity of-Held: Development Authority's demandjustified-
No case of unfair trade practice made out against Development Authority-
Allottee 's complaint rightly dismissed-Urban Development.
D
Allotment of plot of land-Delay in delivery of possession-Balance
amount-Interest on-Held: If the Development Autliority is responsible for
the delay, the allottee cannot be burdened with the interest on the balance
amount.
E The. respondent-Authority allotted a plot of land to the appellant
after he had paid the registration and reservation amounts. Subsequently,
the appellant paid the first and second instalments. Five instalments be-
came due thereafter. The respondent-Authority, by a letter dated 28.2.1995,
called upon the appellant to pay the balance amount together with other
charges latest by 30.5.1885. It was also stated in the said latter that if
F
payment was not made within the due date penal interest would be charged.
The appellant himself, through his letter, admitted the delay in pay-
ments and requested not to cancel the allotment and also indicated his
willingness to pay the entire amount outstanding against him. However,
G the appellant paid only a part of the balance amount due. The respondent-
Authority, therefore, did not not hand over possession of the plot and
demanded penal interest as per its letter dated 28.2.1995.
Being aggrieved the appellant filed a complaint of unfair trade prac-
tice before the MRTP Commission under Sections 36-A, 36-B(a) and 36-D
H of the. Monopolies and Restrictive Trade Practices Act, 1969. The MRTP
896
P.K. SHAHI v. G.D.A. [SETHI, J.] 897
Commission dismissed the complaint. Hence this appeal. A
On behalf of the appellant it was contended that the respondent-
Authority was responsible for the delay in delivery of possession of the
plot and, therefore, the appellant was not liable to pay penal interest for
the period prior to 30.5.1995.
B
Dismissing the appeal, this Court
HELD : 1.1. It is true that if the Authority is found to be responsible
for the delay in delivery of possession of the plot in terms of the agreement
arrived at or according to the assurance given in the brochure, the allottee
cannot be burdened with the interest on the balance amount not paid by c
him. However, it has to be found on facts as to whether the Authority or
the allottee was responsible for the alleged delay. [900-F-G]
2. Having failed to perform his part of the contract, the appellant
cannot be permitted to urge that he is not liable to pay the balance
amount along with interest as according to him the respondent-Authority D
had failed to deliver possession as per the terms of the brochure. The
Authority was not expected to deliver possession in the absence of pay-
ment of the agreed amount. Having failed to perform his part of the
agreement, the appellant cannot be permitted to urge, at this stage, that
he was not liable to pay the interest as agreed to by him at the time of E
accepting the allotment of the plot in his favour. By the letter dated
28.2.1995 the appellant was given further opportunity to make the pay-
ment of the balance amount along with other charges mentioned therein
by a specified date, failing which interest was to be charged from him. The
letter did not envisage that such interest was to be charged from a date
F
subsequent to 30.5.1995 and not prior to it. The mention of the date was
only to intimate the appellant of the concession given to him and upon his
failure to avail ·of the benefit by the specified date, he was liab!e to pay the
interest as agreed upon. [901-F-H; 902-A-BJ
Bihar State Housing Board v. La/it Ram, [1997] 10 SCC 339, held G
inapplicable.
CIVIL APPELLATE JURISDICTION: Civil Appeal No. 5875 of 1999.
From the Judgment and Order dated 29.6.99 of the M.R.T.P. Commis-
sioner, New Delhi in U.T.P.E. No. 92 of 1997. H
898 SUPREME COURT REPORTS [2000) 2 S.C.R.
A Vikas Singh, Yunus Malik, Reetesh Singh, Ms. Richa Kachhwaha and
Lakshmi Raman Singh for the Appellant.
Raju Ramachandran and Rakesh Uttamchandra Upadhyay for the Re-
spondent.
B The Judgment of the Court was delivered by
SETHI, J. The appellant applied for the allotment of a plot measuring
350 sq.mtrs. under the Scheme of "Indrapuram" and paid registration amount
of Rs.42,000 on 28th July, 1989. A further sum of Rs.63,000 being the
reservation amount was paid and plot allotted to him vide letter of the
c
respondent-authority dated 5th November, 1989. The first instalment of
Rs.76,125 was paid by him on 16th August, 1990. Further instalments during
1990-95 were not paid allegedly on the ground that the respondent-authority
had not made any development at the site. The appellant further stated that
he was made to believe that the possession of the plot would be handed over
D to him by the year 1991. Vide letter dated 28th February, 1995, the appellant
was informed that if the balance amount is not paid by him_ by 30th
November, 1995, interest would be charged on the balance amount due: The
appellant's contention is that in terms of the aforesaid letter the interest, if
any, can be charged for the period commencing from 30th November, 1995
E and not earlier to it. He had already paid a total sum of Rs.5,74,993 but the
respondents were allegedly wrongly insisting for the payment of an addi-
tional amowit of Rs.2,34, 127 before delivery of possession of the plot. As
the plot was not delivered to him, the appellant filed a complaint under
Sections 36A, 36B(a) and 360 of the Monopolies & Restrictive Trade
F Practices Act (hereinafter referred to as "the MRTP Act") before the
Monopolies and Restrictive Trade Practices Commission (herein3.fter referred
to as "the Commission") which was registered as Unfair Trade Practice
Enquiry No.92197.
Notice of enquiry under the provisions of the MRTP Act was issued
G to the respondent who appeared before the Commission and contended that
the appellant himself through his letter dated 13th December, 1996 admitted
the delay in payments and indicated his willingness to pay the entire amount
outstanding against him with the request not to cancel the allotment due to
delayed payments. The amount liable to be paid by the appellant was stated
H to have been calculated strictly in accordance with the terms and conditions
P.K. SHAHI v. G.D.A. [SETHI, J.] 899
of the brochure circulated. The respondents could have cancelled the A
allotment in terms of the regulations contained in the brochure but it was not
done to facilitate the appellant to make the payment of the balance amount.
It was contended that the necessary facilities of sewerage, drainage, water
supply and electricity connections were made available to the plot-holders
including the appellant in Indrapuram Scheme. Regarding delivery of pos- B
session, it was contended on behalf of the respondent-authority, that in the
brochure only estimated time of completion of scheme was indicated and
delay in completion had occurred due to various factors including the
constraints of funds. It was further pleaded that the paucity of financial
resources had been caused due to delay or default in payment by the allottees
like the appellant.
c
On the basis of the pleadings of the parties, the Commission framed the
following issues:
"I. Whether .the respondent has been indulging in unfair trade
practices as afleged in the NOE? D
2. Whether these unfair trade practices are prejudicial to the interest
of the complainant/ other members of the public?
3. Whether he is entitled to relief/compensation claimed made by him
in the compensation application? E
4. Relief, if any?"
After referring to the pleadings and the evidence produced, the Commission
concluded:
F
"It transpires that the applicant/complainant has of his own accord,
approached the respondent and indicated his willingness to pay the
amount due from him. Not only has he shown his desire to clear the
dues, he has also acknowledged that there has been delay on his part
in making the payment. Perusal of the allotment letter reveals that
there is a stipulation with regard to payment of interest and penal
G
interest if the payment is not made within the prescribed time limit.
As both the applicant/complainant as well as the respondent are
relying on the allotment letter, it stands to reason that the outstanding
amount including interest should be calculated in the light of this
letter of 5.11.1989. It ~ppears from the affidavit of evidence filed on H
900 SUPREME COURT REPORTS [2000] 2 S.C.R.
A behalf of the respondent that the calculations have been made on the
basis of fu,at letter and the respondent has accordingly, indicated the
amount to the applicant/complainant. In that view of the matter, the
applicant/complainant's contention that interest should be charged
after 30th May, 1995 is not tenable. It is also quite apparent that there
has been delay in the completion of the project but delay seems to
B
have been caused by circumstances beyond the control of the
respondent. It is also common knowledge that there has been cost
escalation and cost etimates of 1989 need revision and the revised
estimate is bound to be much higher than the original estimate. It
appears that development of infrastructure and provision of utilities
c like water supply and electricity connection have also contributed to
the hike in the estimated cost and demand for additional charges for
sewerage, lease rent, etc., cannot be construed or considered to be an
unfair trade practice on the part of the respondent. It also transpires
that the respondent is charged with the responsibility of developing
D land for plots/flats and making the same available to the allottees like
the applicant/complainant on actual cost value basis and the total cost
incurred by it is required to be recovered from the allottees. Iii that·
view of the matter, there is no escape from the conclusion that no case
of unfair trade practices by and on behalf of the respondent has been
made out and no prejudice seems to have been caused to the applicant/
E complainant as a consequence thereof."
Learned counsel appearing for the appellant relying upon a judgment of
this Court in Bihar State Housing Board and Ors. v. Lalit Ram, [1997] 10
sec 339 submitted that as the respondent-authority has been proved to be
F responsible for the delay in delivering possession of the plot, the appellant
could not be burdened to pay the penal interest for the period anterior to 30th
.May, 1995. It is true that if the authority is found to be responsible for the
delay in delivery of the possession of the plot in terms of the agreement
arrived at or according to the assurance given in the brochure, the allottee
cannot be burdened with the interest on the balance amount not paid by him.
G However, it has to be found on facts as to whether the authority or the allottee
was responsible for the alleged delay. According to the available records and
the submissions made on behalf of the appellant it transpires that the schedule
for payment of the total estimated cost of the plot being Rs.4,29,000 and
registration amount of Rs.42,000 was to be paid in the following instalments:
H
P.K. SHAID v. G.D.A. [SETHI, J.J 901
"S.No. Instalment Description Due date of payment A
1. Reservation Amount 4.12.1989
2. Instalment No.1 4.5.1990
3. Instalment No.2 4.11.1990
4. Instalment No.3 4.5.1991 B
5. Instalment No.4 4.11.1991
6. Instlament No.5 4.5.1992
7. Instalment No.6 4.11.1992"
It further transpires that after paying the initial amount of Rs. 42,000 the C
appellant paid the first instalment of Rs. 63,000 on 3.1.1990 and second
instalment of Rs.76,125 on 16th August, 1990 total being Rs.1,81,125.
Amounts of instalment due on 4.11.1990, 4.5.1991, 4.11.1991, 4.5.1992 and
4.11.1992 were, admittedly, not paid on the due dates. The respondent-
authority vide its letter dated 28th February, 1995 called upon the appellant D·
to make upto date payments and 10% of premium of his plot as lease rent and
Rs.4800 as sewer connection and water connection charges latest by 30th
May, 1995. It was pointed out that "if the payment is not made within the due_
date interest shall be charged @ 18% & chokidata fee Rs.5 per day shall be
charged after 30.5.95". Admittedly, till 16.10.1996 no amount was paid. Even
' on that date a sum of Rs.72,188, the amount of instalment payable on E
4.11.1990 was actually paid. The appellant thereafter paid a sum ofRs.2 lakhs
on 7.1.1997 and Rs),29,600 on 13.1.1997 before filing his complaint in the
Commission on 28th February, 1997. Having failed to perform his part of the
contract, the appellant cannot be permitted to urge that he is not liable to pay
the balance amount along with interest as according to him the respondent- F
authority had failed to deliver possession as per terms of the brochure. The
authority was not expected to deliver possession in the absence of the
payment of the agreed amount. Having failed to perform his part of the
agreement, the appellant cannot be permitted to urge, at this stage, that he was
not liable to pay the interest as agreed to by him at the time of accepting the
allotment of the plot in his favour. The reliance of the learned counsel on the G ,
letter dated 28th February, 1995 is also misplaced inasmuch as by that letter
he was given further opportunity to make the payment of the balance amount
alongwith charges mentioned therein by a specified date, failing which
interest and chokidata was to be charged from him. The letter did not envisage
that such interest and chokidata was to be charged from a date subsequent to H
902 SUPREME COURT REPORTS [2000] 2 S.C.R.
A 30th May, 1995 and not prior to it. The mention of the date was only to
intimate the appellant of the concession given to him and upon his failure to
avail of the benefit by the specified date, he was liable to pay the interest as
agreed upon. The judgment of this Court in Bihar State Housing Board and
Ors. v. Lalit Ram (supra) is also of no help to him. In that case the allottee was
found to have been intimating the Board time and againfor completion of the
B construction of the plot but despite his request the same was not completed
and it was held that without completion of the construction, tlie :.foresaid
allottee could not be asked to execute the agreement and upon his failure to
execute the agreement, charged with the liability of paying the interest. The
facts of the .present case are altogether different and distinguishable.
c
After going through the whole record produced before us, we find that
no ground is made out to interfere with the order of the Commission in this
appeal. The appeal is, therefore, dismissed. The appellant is held liable to pay
the amount demanded from him before the delivery of the possession of the
plot. No costs.
D
v.s.s. Appeal dismissed.
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.