Created byFuzzy Cloud

Supreme Court of India

PRIYANKA ESTATES INTERNATIONAL P. LTD. & ORS.versusSTATE OF ASSAM & ORS.

Citation
2009 INSC 1281
Decided
3 December 2009
Disposal
Dismissed

Holding

Construction beyond the sanctioned five‑and‑a‑half floors was unauthorized, non‑compoundable and must be demolished; the SAC order does not constitute a valid sanction.

Summary

The Supreme Court examined whether Priyanka Estates International Ltd. and its directors could lawfully construct six to eight floors in a building for which only a five‑and‑a‑half‑floor plan had been sanctioned by the Guwahati Municipal Corporation (GMC). The Court held that the Standing Appellate Committee's order did not constitute a valid sanction, that the construction beyond the approved plan was unauthorized, non‑compoundable under the building bye‑laws, and therefore liable to demolition under Section 88 of the Guwahati Metropolitan Development Authority Act. The Court also clarified that a public notice suffices as notice to individuals under the Act, and that the authorities may demolish the sixth to eighth floors and any un‑compounded portion of the fifth floor. Consequently, the appeals were dismissed and demolition directions were affirmed.

Issues considered

  • Whether construction beyond the sanctioned five‑and‑a‑half floors without permission under Sections 24 and 25 of the Guwahati Metropolitan Development Authority Act is illegal.
  • Whether the order of the Standing Appellate Committee (SAC) amounts to a valid sanction for the extra floors.
  • Whether the extra floors constitute non‑compoundable items under the building bye‑laws.
  • Whether a public notice under Section 88 of the Development Act satisfies the requirement of notice to individual owners.
  • Whether demolition orders can be issued without a proper show‑cause notice.

Subjects

unauthorised constructiondemolitionbuilding bye‑lawscompoundable vs non‑compoundable itemspublic noticeGuwahati Metropolitan Development Authority ActSection 88standing appellate committeeurban development

Judgment

                    [2009] 16 (ADDL.) S.C.R. 80


A     PRIYANKA ESTATES INTERNATIONAL P. LTD. & ORS.                    '(


                              v.
                 STATE OF ASSAM & ORS.
               (Civil Appeal No. 8026 of 2009)
                       DECEMBNER 3, 2009
B
         [V.S. SIRPURKAR AND DEEPAK VERMA, JJ.]

       Guwahati Metropolitan Development Authority Act, 1985
  - ss. 24 and 25 - Construction of extra floors without sanction
c - Authority concerned directing demolition of the extra floors
  - Writ petition - High Court directing demolition of extra floors
  - On appeal, held: construction of building beyond 5Yi floors
  was illegal, unauthorized and without any sanction or approval
  of plans - However, if half unsanctioned portion of 5th floor,
D is found to be compoundable, the same not to be demolished
  - Authorities at liberty to demolish 6th to 8th floors and half
  of the 5th floor if not cnmpounded ultimately - Urban
  Development.

       s. 88 - Notice to individual - Failure in - Effect of - Held:
E Public notice by authorities cautioning the proposed
  purchasers to enter into agreement of purchase of flats on
  seeing Completion and Occupancy Certificates in favour of
  builders, would be deemed to be notice to the individuals -
  Notice.
F
       Pursuant to permission granted by Guwahati
  Metropolitan Development Authority (GDMA) for sale of the
  land for residential-cum-commercial use, the land was sold
  to appellant No. 1. Thereafter Guwahati Municipal
G Corporation (GMC) granted permission for construction of
  basement, ground and upto 51/2 floors. Thereafter,
  applicant No. 1 applied for grant of permission for
  construction of remaining part of 5th floor and 6th, 7th and
  8th floors. The permission was refused by GMC. Appellant
H                                80
        PRIYANKA ESTATES INTERNATIONAL P. LTD. &                  81
                ORS. v. STATE OF ASSAM
"    preferred appeal against refusal order and the same was            A
     allowed by Standing Appellate Committee (SAC) directinu
     that permission be granted. Despite the order, no formal
     permission was granted by GMC. Appellant moved further
     application, wherein Administrator-cum-Minister reviewed
     the verdict in appeal and granted permission for further           B
     construction, subject to fulfilment of certain conditions.
     Appellants continued with construction of building
     beyond 5% floors, without compliance of the conditions
     and without getting actual sanction for such construction.
     GMDA issued notices to the appellant for demolition of the         c
     construction beyond 5% floors. Appellants filed writ
     petition challenging the order, wherein status quo was
     ordered to the effect that the Municipal Authority shall take no
     steps to pull down the building and operation of notices for
     demolition was stayed.                                             D
         Subsequently GMDA passed order of demolition.
     This order was also challenged in other writ petition, by
     the appellants. Despite the order of status quo, appellants
     continued with the construction. By a further clarificatory
     order, High Court directed that no further construction to         E
     be carried out. Third parties also filed writ petitions
     seeking demolition of extra construction. High Court, by
     the impugned order dismissed the petitions filed by
,.   appellants and allowed that filed by third parties directing
     demolition. Hence the present appeals.                             F

         Dismissing the appeals, the Court

          HELD: 1.1. Rules, regulations and bye-laws are made
     by Corporation or by Development Authorities, taking in
     view the larger public interest of the society and it is a         G
     bounden duty of ~he citizens to obey and follow such
1
     rules which ar~ _.• ade for their benefit. If unauthorised
     constructions are allowed to stand or given a seal of
     approval by court then it is bound to affect the public at
     large. An individual has a right, including a fundamental          H
   82     SUPREME COURT REPORTS (2009] 16 (ADDL.) S.C.R.

                                                                   >(

A right, within a reasonable limit, it inroads the public rights
  leading to public inconvenience, therefore, it is to be
  curtailed to that extent. [Para 74] [108-8-D]

       1.2. In view of the admitted position that the width of
  the road is only 38 feet and under the building bye-laws,
B
  maximum allowable height can be double the width of the
  road, i.e.76 feet, but in the instant case the SAC has
  allowed construction upto 93 feet, which contravenes the
  building bye-laws, therefore, such an order of SAC has
  no legal force and cannot be basis for construction
c beyond   76 feet, allowable under building bye-laws. [Para
  29] [94-H; 95-A-B]

       1.3. The only plan approved was for 5Yz floors by
  GMC. Order passed by SAC also does not give them
D blanket permission to construct upto 8th floor. The
  respondents have come to the conclusion and have
  conceded before this court, plan or sanction approved
  by either of the two authorities, that is, GMC or GMDA will
  hold good and permission from both the authorities
E simultaneously would not be required for the same, if it
  has already been accorded by any one of the authorities.
  Thus, if no permission u/s. 24 and 25 of the Development
  Act was obtained by the appellant, then it would not be
  detrimental to the interest of the appellants, provided          ,,.
F there is sanction and approval of plans by the
  Corporation for remaining 3Yz floors i.e. beyond 51/z floors.
  [Paras 51 and 52] [101-C-D]

       1.4. The order of SAC cannot be construed as an
  order of sanction as it is not a semblance of permission.
G It was not end of the matter because necessary sanction
  or permission could have been granted only by the
  Municipal Commissioner and not by the Appellate
  Authority. Admittedly, even after passing of the order by
  SAC in appeal, there was no further sanction by the
H Municipal Commissioner or by Chief Executive Officer of
              PRIYANKA ESTATES INTERNATIONAL P. LTD. &                 83
                      ORS. v. STATE OF ASSAM
       )<
            the Development Authority granting permission to raise           A
            the height of the building upto 8th floor. [Para 57) [103-
            E-F]

                 1.5. Clause (a) of building bye-law 37 stipulates that
            for the purpose of calculation of building height, existing
                                                                             B
            width of the road shall be taken into account and not the
            proposed width. Even if the proposed width is 40 feet or
            50 feet, it will not make any difference because it clearly
            contemplates that what is to be taken into consideration
            is the existing width of the road. There is nothing on
            record to show that the existing width of the road is more
                                                                             c
            than 38 feet. Thus, at the most, the construction could
            have been only upto the height of 76 feet, provided there
            was sanction granted by either of the two Authorities.
            [Para 54) [101-G-H; 102-A-B]
                                                                             D
                1.6. Construction of the building beyond 5% floors
            was not only illegal, unauthorized and without any
            sanction or approval of plans but was also against the
            spirit of Appellate Order of SAC. Thus, Respondent-
            authorities are directed to demolish 6th, 7th and 8th floor.     E
            [Para 58) [103-G]

                1.7. Addition of extra floor falls in the category of non-
            compoundable items. Thus, in any case anything that
        ~
            has been constructed beyond 5th floor would be non-
            compoundable and same cannot be compounded at all.
                                                                             F
            In other words, minor deviations from the sanctioned
            plan should be confined only to the FAR permissible but
            should not extend to the extra floor. [Para 55) [102-B-D]

                 1.8. Respondent-authorities conceded that on                G
            suitable representations being made by the occupants,
       i    the cases as regards construction of two flats on
            remaining half of 5th floor can be considered afresh to
            find out ;f the same would fall within the category of
            compoundable items or not. If the same are found within          H
---<
    84    SUPREME COURT REPORTS (2009] 16 (ADDL.) S.C.R.

                                                                  >(

A the category of compoundable items then necessary
  order by respondents in this regard would be passed
  otherwise order of demolition would follow for them also.
  [Para 59) (104-A-C]

       1.9. However, it is not acceptable that if cases of two
B
  flat owners on the 5th floor are to be considered so as
  to find out whether the constructions raised by the
  builder in their cases would fall within the compoundable       ~.

  items or not, then the case of the person, whose flat is
  situated on the 6th floor should also be directed to be
c considered on a suitable representation being made by
  her. The construction of an extra floor does not fall within
  the category of compoundable items which is manifest
  from Appendix Ill of the building bye-laws of the
  Corporation. What would ultimately constitute a
D sanctioned and duly approved map would be the one
  approved by the Commissioner as he alone has authority          ..
  to do so. The appellants have failed to produce any such
  duly approved map. [Paras 68, 69 and 72] [106-G-H; 107-
  A, F]
E
         1.10. Respondent-authorities shall be at liberty to
    proceed with demolition of half of the 5th floor, if not
    ultimately compounded; and 6th, 7th and 8th floors. [Para
    82] [110-B]
                                                                  '"
F       M.I Builders Pvt. Ltd. v. Radhey Shyam Sahu and Ors.
  (1999) 6 SCC464; Friends Colony Development Committee
  v. State of Orissa and Ors. (2004) 8 SCC 733; Royal Paradise
  Hotel (P) Ltd. vs. State of Haryana and Ors. (2006) 7 SCC
  597; Mahendra Buburao Mahadik and Ors. v. Subhash
G Kris,hna Kanitkar and Ors. (2005) 4 SCC 99, relied on.

        Corporation of Calcutta v. Mulchand Agarwala AIR 1956
    SC 110; Syed Muzaffar Ali and Ors. v. Municipal Corporation
    of Delhi 1995 Supp. (4) SCC 426; Muni Suvrat-Swamy Jain
    S.M.P. Sangh v. Arun Nathuram Gaikwad and Ors. {2006) 8
H                                                                      ,____
         PRIYANKA ESTATES INTERNATIONAL P. LTD. &               85
                 ORS. v. STATE OF ASSAM
)<

      SCC 590; Municipa/Corporation, Ludhiana v. lnderjit Singh       A
      and Anr. (2008) 13 SCC 506; Olga Tellis and Ors. etc. v.
      Bombay Municipal Corporation and Ors. etc. (1985) 3 SCC
      545; S.L. Kapoor v. Jagmohan and Ors. (1980) 4 SCC 379,
      referred to.
           2. Respondents had also issued a public notice on          B
      02.07.2002, published in local newspaper in vernacular
      giving general warning and information to all proposed
"     purchasers of flats that unless builder is able to show
      Completion Certificate and Occupancy Certificate duty
      issued by authorities, no one should enter into                 c
      agreement to purchase flat/flats from the builder. It is,
      therefore, to be construed that public notice will hold
      good even with regard to adherence to the requirement
      of Section 88 of the Development Act, if individual person
      had not been noticed by the authorities. [Para 53] [101-        D
 ;    E-F]
            3.1. It is a sound policy to punish the wrong-doer and
      it is in that spirit that the courts have moulded the reliefs
      of granting compensation to the victims in exercise of the
      powers conferred on it. In doing so, the courts are             E
      required to take into account not only the interest of the
      petitioners and the respondents but also the interest of
      public as a whole with a view that public bodies or
 ..   officials or builders do not act unlawfully and do perform
      their duties properly. [Para 77] [108-H; 109-A-B]               F
          3.2. The instant case is not a case of breach of
      contract. It is a clear case of breach of the obligation
      undertaken to erect the building in accordance with
      building regulations and failure to truthfully inform the
                                                                      G
      warranty of title and other allied circumstances. [Para 79]
      [109-0]
           3.3. The jurisdiction and power of courts to indemnify
      a citizen for injuries suffered due to such unauthorised
      or illegal construction having been erected by builder/         H
     86     SUPREME COURT REPORTS [2009] 16 (ADDL.) S.C.R.

                                                                  '(


A coloniser is required to be compensated by them. An
  ordinary citizen or· a common man is hardly equipped to
  match the might and power of the builders. This court
  has restrained itself from giving relief under Article 142
  of constitution of India, of compensation to the flat owners
B for variety of reasons and on account of various disputed
  questions that may be posed in the matter. However,
  liberty is granted to those, whose flats are ultimately
                                                                 )I;
  going to be demolished, to exhaust the remedy that may
  be available to them in accordance with law. [Paras 75
  and 80) [108-E-F; 109-F-G]
c
                      Case Law Reference :
          AIR 1956 SC 110       Referred to.         Para 61
          1995 Supp. (4) SCC 426 Referred to.        Para 61
D         (2006) 8 sec 590      Referred to.         Para 62
          (2008) 13 sec 506     Referred to.         Para 62
          (1985) 3 sec 545      Referred to.         Para 63

E         (1980) 4 sec 379      Referred to.         Para 64
          (1999) 6 sec 464      Relied on.           Para 65
          (2004) 8 sec 733      Relied on.           Para 65
          (2006) 1 sec 597      Relied on.           Para 65
F
          (2005) 4 sec 99       Relied on.           Para 65
        CIVIL APPELLATE JURISDICTION : Civil Appeal No.
    8026 of 2009.
      From the Judgment & Order datt:id 28.07.2006 of the
G Gauhati High Court in Writ Petitions. No. 5018, 5146 of 2002
  & 2747 of 2006.
                              WITH
    C.A. No. 8025, 8027, 8028 & 8029-8032 of 2009.
H
            PRIYANKA ESTATES INTERNATIONAL P. LTD. &                87
                    ORS. v. STATE OF ASSAM
               Shekhar Naphade, Mukul Rohtagi, Vijay Hansaria, Anoop A
         Chaudhary, June, Chaudhary, Milly Hazarika, Ramji Srinivasan,
         P.1. Jose, Anupam Mishra, Kajori Roy, Vivek Kafari Ray, Dhruv
         Mehta, Yashraj Singh Deora, Mohit, T.S. Sabarish (for K.L.
         Mehta & Co.), Shankar Divate, Kamal Mohan Gupta, Manish
         Goswami (for Map & Co.), Jagjit Singh Chhabra, H. Baruah, B
         Balbir Dosanjh, Rameshwar Prasad Goyal, Jitendra Kumar,
;I       Ranjan K. Pandey, Galib Kabir, Corporate Law Group (NP),
         Rauf Rahim, for the appearing parties.

             The Judgment of the Court was delivered by
                                                                         c
              DEEPAK VERMA, J. 1. Leave granted.

              2. The principal question that emerges for consideration
         in these appeals is whether to sustain the order of demolition
         as passed by the Gauhati High Court vide impugned judgment D
         and order or to put an imprimatur of this Court to the
         unauthorised constructions raised by M/s. Priyanka Estates
         International (P) Ltd. (Appellant No.1 herein) beyond 5Y:! floors.
         Facts material for deciding the said appeals are mentioned
         hereinbelow.
                                                                         E
              3. For the sake of convenience, the facts appearing in SLP
         (C) No. 14480 of 2006 titled as Mis. Priyanka Estates
     ~   lntemational (P) Ltd. & Others Vs. State of Assam & Others
         are taken into consideration. Appellant No.1 is a company of
         which Appellant Nos.2 & 3 are Directors.                        F

              4. Appellant No.1 herein purchased an open piece of land
         approximately admeasuring 4.62 Kathas from one Smt. Nandita
         Banerjee on 9.8.1999 by registered deed of sale. Prior to
         execution of sale, the vendor of Appellant No.1 applied to G
     ,   Guwahati Metropolitan Development Authority (hereinafter
         referred to as 'GMDA') for grant of 'No Objection Certificate'
         for sale of land. The said permission was accorded on
         17.7.1999 mentioning therein that permission is granted for
         "residential-cum-commercial use" of the said plot and that H 1
    88     SUPREME COURT REPORTS (2009] 16 (ADOL.) S.C.R.


A   proposed width of the road abutted by plot is approximately 50
    feet.

        5. Pursuant to the said permission, Sale Deed was
  executed in favour of Appellant No.1, whereafter it applied to
  Guwahati Municipal Corporation (hereinafter referred to as
8
  'GMC') on 16.11.1999 for according permission for
  construction of basement, ground, mezzanine, first, second,
  third, fourth and half of 5th floors. The permission was accorded       <
  to Mis. Priyanka Estates International (P) Ltd. on 03.02.2000
  by the GMC for construction of basement, ground floor,
C mezzanine upto fourth floor and half on the 5th floor. For 1st floor
  to fourth, the floor area permissible was 7283 sq. ft. but on 5th
  floor, the permissible floor area was fixed at half of it, i.e., 3817
  sq. ft only. It was granted on certain conditions as mentioned
  in the sanction dated 3.2.2000.
D
        6. Thereafter, on 08.02.2000, Appellant No.1 applied for          ~
  grant of permission for construction of remaining part of 5th ,
  6th, 7th and 8th floors. This permission was refused by GMC
  on 27.3.2000 on the following grounds.
E
         "(i) Maximum allowable height of building can be 76'
                and proposed height would be 93'.

          (ii)    The margin on both sides and rear is less than
                  required norms.
F
          (iii)   FAR is exceeded than allowable 300.

          (iv)    The structural certificate is not submitted."

      So, proposal for 5th (part) 6th, 7th and 8th floor building,
G permission was rejected.

       7. Feeling aggrieved by the said rejection by GMC,
  appellants preferred an appeal under Section 438 of the
  Guwahati Municipal Corporation Act, 1971 (hereinafter referred
H to as 'the Act') before the Standing Appellate Committee (in
    PRIYANKA ESTATES INTERNATIONAL P. LTD. &                       89
    ORS. v. STATE OF ASSAM [DEEPAK VERMA, J.]
) short 'SAC').                                                           A

       8. This came to be disposed of on 5.5.2000 with the
  following directions:

            "In view of the above discussion as well as
       observation, in our considered opinion, the appellant's            B
       case deserve consideration. Accordingly, we hold that the
       appellant be accorded permission as sought for. We
       hereby set aside the impugned order, as aforesaid,
       passed by the Commissioner, GMC, the Respondent.
                                                                          c
                In the result, the appeal is allowed."

       9. Since, despite the fact that SAC had allowed the appeal
   of Appellants with regard to construction of 5th (part), 6th, 7th
   and 8th floors, no formal permission was still accorded by             D
   Commissioner GMC to it, they moved further application on
.\ 28.8.2001 before Administrator-cum- Minister, Guwahati
   Development Department, as it appears by that time, GMC had
   been dissolved.

       10. The said appeal was considered by Administrator-               E
  cum-Minister and the appeal verdict was reviewed on
  29.5.2002 with certain conditions as mentioned hereinbelow :

        "(i)     To obtain NOC from State Fire Department;

        (ii)     Submit affidavit regarding the Structural Certificate;   F

        (iii)    Compulsory covered parking and private service
                 system like drainage, sewage, storm drain, water
                 supply etc.;
                                                                          G
        (iv)     No further FAR beyond 487.00;

        (v}      To submit completion certificate and obtain
                 Occupancy Certificate from GMC;

        (vi)     To pay a penal charge to the Corporation amounting       H
    90     SUPREME COURT REPORTS [2009] 16 (ADDL.) S.C.R.


A               to Rs.10,00,000.00 (ten lacs);

          (vii) Your building is liable for instant demolition at your
                own risk and cost in case of non-compliance of the
                above."
B        11. However, it appears that without compliance of the
    aforesaid conditions fully and without getting actual sanction for
    construction of building beyond 5Y2 floors from the
    Commissioner of G.M.C. Appellants continued with the                 t
    construction activities and tried to complete the same.
c
       12. Guwahati Metropolitan Development Authority (As
  already referred to as 'GMDA') now came into picture and
  issued notice to Appellant No.2 on 02.02.2001 to show cause
  and to give explanation as to without grant of proper sanction
D under GMDA Act, how the construction work is progressing.
       · 13. Another notice by GMDA was issued to the Appellant
  No.2 on 5.9.2001 asking to remove/demolish the building/
  construction/ development or the portion erected by them which
  is in violation of the provisions of Guwahati Metropolitan
E Development Authority Act (for short 'the Development Act'). No
  replies to the aforesaid two notices were sent by the Appellants
  herein on the ground that the same were not received.

       14. Last and final notice in this regard was issued by GMDA
F on  18.2.2002    mentioning therein with regard to earlier two
  notices sent on 2.2.2001 and 5.9.2001 and finally asking the
  Appellants to remove the construction within three days from the
  receipt of this last notice failing which, necessary action as per
  provision of the Development Act will be initiated without giving
G further intimation.

        15. Appellants replied to the said last notice on 18.2.2002
  menlioning therein that they had not received the earlier two          •
  letters but mentioned that permission has been granted by
  GMC on 3.2.2000, and is still operative, which clarified the
H position of construction of the building beyond 5Yi floors also
      PRIYANKA ESTATES INTERNATIONAL P. LTD. &                     91
      ORS. v. STATE OF ASSAM [DEEPAK VERMA, J.]
1   but did not actually present any sanctioned or approved plans/       A
    maps beyond 51h floor.

         16. Not being satisfied with the reply to the show cause
    notice, submitted by the Appellants, the Respondents
    proceeded to issue another notice to the Appellant No.2 on
                                                                         B
    3.5.2002, with a categorical statement that construction over
    and above 6th and 7th floor was wholly illegal, without due
    sanction and therefore, the same be removed/demolished.
j               -~~



         17. It appears that, thereafter, some correspondence
    between the parties continued. Finally on 31.7.2002 by two           c
    orders, the Commissioner, GMC informed the Appellant No.1
    that plans submitted by them are insufficient for the following
    reasons and requested it to furnish the required materials as
    under and to forthwith stop the construction :
                                                                         D
          "1.     Affidavit for structural design as per format at the
                  building bye laws.

          2.      NOC from State Fire Department.

          3.     Declaration in affidavit to maintain the FAR within     E
                 487."

          18. The Appellants, therefore, were constrained to move
    the High Court challenging the said order dated 31.7.2002 by
"   filing W.P.(C) No.5018 of 2002 purportedly under Articles 226
                                                                         F
    and 227 of Constitution of India.

         19. Further order of demolition came to be issued to the
    Appellant No.2 by GMDA on 30.5.2006, clearly mentioning
    therein that no sanction was obtained by the Appellants under
    Section 24 & 25 of the Development Act and had actually              G
    violated the provisions of Building Bye-laws of Guwahati
)   Municipal Corporation (for short, 'building bye-laws'), in the
    following manner :

         "1.     FAR of the building is 490 which exceeds allowable      H
    92    SUPREME COURT REPORTS (2009] 16 (ADDL.) S.C.R.


A               FAR 300.

          2.    Maximum floor height 93' exceeds allowable height
                76' in this road.

          3.    Since the building is mixed used with residential at
B               top floors, setback required is 15' side to 20' rear,
                which is not maintained.

          4.    Balcony projection is allowed, maximum X of the
                building length in any side, which is not maintained.
c         5.    Two staircases and lift on opposite direction is
                required which is not available in the building as per
                building plan.

          6.    Construction of building is going on despite our
D               order to stop construction."

         20. The said order further directed demolition of the
    building beyond the sanctioned plan dated 3.2.2000. The
    Appellants, therefore, challenged the said order dated
E   30.5.2006 issued by Chief Executive Officer GMDA by filing
    another W.P.(C)No.2747 of 2006. In W.P.(C) No.5018 of 2002,
    (earlier W.P. filed in the Gauhati High Court) an order of status
    quo came to be passed on 12.8.2002 and it further directed
    that Municipal Authority shall take no steps to pull down the
F   building and the operation of the letter dated 31.7.2002 was
    stayed.

       21. It appears that pursuant to the said order, Appellants
  continued with the construction activities presumably on the
  ground that order of status quo is against the Respondents of
G the Writ Petition and not against the Appellants. Thus, Sanatan
  Dharam Sabha, Guwahati filed an application seeking
  permission to be impleaded in the said petition and also
  bringing to its notice that despite the order of maintenance of
  status quo, Appellants are continuing with the construction.
H Thus, another order clarifying the earlier order came to be
   PRIYANKA ESTATES INTERNATIONAL P. LTD. &                     93
   ORS. v. STATE OF ASSAM [DEEPAK VERMA, J.]
passed by the High Court on 20.9.2002 whereby a categorical           A
direction was issued that no further construction over the said
land shall be made and all construction activities should come
to a standstill immediately. It appears that only after passing
the said order, Appellants stopped the construction work.
                                                                      B
     22. Sanatan Dharam Sabha alongwith three residents of
Panbazar locality of Guwahati city filed W.P.(C) No.5146 of
2002 in the Gauhati High Court against the action of GMC and
GMDA granting permission to the appellant, M/s. Priyanka
Estates for multi-storeyed building in question and prayed for        C
its demolition.

      23. Thus, all the three petitions, i.e. W.P.(C) No.5018/2002,
 W.P.(C) No.2747/2006 and W.P.(C) No.5146/2002 were
 consolidated for the purpose of analogous. hearing and have
 been disposed of by Division Bench of Gauhati High Court vide        D
 impugned judgment and order dated 28.7.2006. Vide
 impugned judgment, the Writ Petitions preferred by Appellants
 herein numbered as 5018/02 and 2747/06 having been found
·devoid of merit and substance were dismissed but W.P.(C) No.
 5146/2002 filed by Sanatan Dharam Sabha has been allowed             E
 to the extent indicated in the impugned order.

     24. Feeling aggrieved and dissatisfied with the aforesaid
judgment and order, civil appeal arising out of
S.L.P.(C)No.14480/06 titled, 'M/s. Priyanka Estates
International (P) Ltd. & Ors. vs. State of Assam & Ors.' has F
been filed by Builder and its Directors; civil appeals arising out
of S.L.P.(C) No.15546/06 titled, 'Vishal Saraf v. State of
Assam & Ors.' and civil appeal arising out of
S.L.P.(C)No.15547/06 titled, 'Suresh Kumar Harlalka v. State
of Assam & Ors.' have been filed by owners of flats on 7th floor G
and civil appeal arising out of S.L.P.(C) No. 16898/06 titled,
'Sarla Devi Lahoty vs. State of Assam & Ors.' has been filed
by owner of one flat on 6th floor. lnsofcr "1S civil appeals arising
out of S.L.P.(C) Nos.28291-28294/2009 titled, 'Shyam Sunder
Agarwala vs. State of Assam & Ors.' are concerned, the same H
    94    SUPREME COURT REPORTS [2009] 16 (ADDL.) S.C.R.


A have been filed by owner of one flat on 5th floor only. Since the
  matters were common and identical challenging primarily the
  order passed by Division Bench of the High Court and
  pertained to the same building claiming identical reliefs, these
  Appeals have been heard together. Perused the records.
B
       25. Mr. Shekhar Naphade, leaned Senior Counsel, Mr.
  Mukul Rohtagi, learned Senior Counsel with Mr. Shankar
  Divate, Mr. Dhruv Mehta, Mr. Yashraj Singh Deora, Advocates,
                                                                      t
  Mr. Vijay Hansaria, learned Senior Counsel with Mr. P.I. Jose
  and Mr. Kamal Mohan Gupta, Advocates appeared for the
c Appellants  in the aforesaid appeals. Mr. L. Nageshwar Rao,
  learned Senior Counsel with Ms. Millie Hazarika and Mr.
  Manish Goswami appeared for the Respondents.

       26. Respondents have contended that for construction of
D any building, permission from GMC is a condition precedent
  and unless such permission is granted no construction can be
  raised.

      27. It has further been submitted that such construction has
  to be as per the sanctioned plan approved by GMC and no
E
  deviation from such approved plan can be made.

       28. According to them, Appellant No.1 was admittedly
  granted permission for construction of 5Y2 storeyed building,
  apart from basement, ground and mezzanine floor vide order              ~

F dated 03.02.2000, thereafter, no further permission has been
                                                                              '
  granted for raising any construction on remaining part of 5th
  floor and upwards. The order of the SAC dated 05.05.2000
  setting aside the order of Commissioner, GMC dated
  27.3.2000 rejecting the permission to raise construction on part
G of the 5th floor up to 8th floor was itself illegal, beyond the
  jurisdiction and competence of SAC as it violated the building
  bye-laws.

        29. In view of the admitted position that the width of the
    road is only 38 feet and under the building bye-laws, maximum
H
      PRIYANKA ESTATES INTERNATIONAL P. LTD. &                     95
      ORS. v. STATE OF ASSAM [DEEPAK VERMA, J.]
    allowable height can be double the width of the road, i.e., 76       A
    feet but in the instant case the SAC has allowed construction
    upto 93 feet, which contravenes the building bye-laws, therefore,
    such an order of SAC has no legal force and cannot be basis
    for construction beyond 76 feet, allowable under building bye-
    laws.                                                                B
          30. It has been submitted by them that the order of the SAC
    dated 05.05.2000 lost its force and sanctity after the
    communication dated 29.05.2002 was issued by GMC by which
    the Appellants were asked to comply with certain conditions
    before granting any permission for construction of a building
                                                                         ·c
    for remaining part of 5th floor and above.

          31. It has also been contended that even though the order
    passed in Appellants' Writ Petition was to maintain status quo
    but taking advantage thereof, they continued with the                D
    construction and only on subsequent order being passed on
1   20.09.2002, the construction activities were stopped but by that
    time Appellants had already raised construction upto 8th floor,
    in flagrant violation of building bye-laws.
                                                                         E
         32. They have also contended that GMDA passed an order
    under Section 88 of the Development Act for demolition of
    construction for remaining part of the 5th floor and above and
    that too after issuance of notices to Appellants and giving
~   reasonable opportunity to them to show cause. Appellants were
    aware that construction beyond 5% floor was without due              F
    sanction and approval, thus, obviously illegal, yet they continued
    with the same.

         33. They further submitted that there was no violation of
    principles of natural justice. It was contended that Appendix Ill    G
    of the. buildin.g bye-laws provides for compoundable and non-
    compoundable items. It is evident therefrom that construction
    of extra floor falls in the category of non-compoundable items
    meaning thereby if extra floor is conz~ructed without due
    sanction/approval, then, it would be beyond the purview of           H
    96    SUPREME COURT REPORTS [2009] 16 (ADDL.) S.C.R.

                                                                          I
A compoundable items. As regards violation of principles of
  natural justice, they have contended that before passing the
  order of demolition, notices were issued to the Appellants to
  show cause, as required under Section 88 of Development Act
  but they did not take any action thereon.
B
         34. Whenever Respondents asked for sanctioned/
    approved plans for construction beyond 5Yi floors, Appellants
    only showed them the plans which were sanctioned and/or
    approved for construction of, only upto 5Yi floors. It was also
    contended by them that even upto that stage Appellants had
c   failed to show any approved sanctioned plans and maps
    allowing them to construct beyond the permissible limit of 5Yi
    floors. Thus, they have contended that the building constructed
    beyond 5Yi floors is absolutely illegal, unauthorized and without
    any sanction plans, thus liable to be demolished.
D
          35. In order to understand the various provisions of the Act,   f
    it is necessary to know the irnport of the relevant sections of
    the Act material for deciding the appeals .

       . 36. Section 327 of the Act prohibits any person from
E
  erecting or re-erecting any building without written permission
  from the Corporation. Section 328 provides for submission of
  an application by a person interested to ereci or re-erect a
  building to the Corporation for approval of the site together with
                                                                          +
  site plan with land title document, elevation and sections of the
F building, specification of the work and also containing such
  particulars as may be required by bye-laws in that behalf.
  Section 329 empowers the Commissioner of the GMC to
  refuse such permission and to disapprove the site on the
  grounds formulated in Section 330. Section 331 provides for
G the grounds on which permission to erect or re-erect the
  building can be refused by GMC. Section 332 empowers the
  Commissioner to direct modification of the sanctioned plan.
  Section 333 stipulates the period within which erection or re-
  erection is to be completed. Section 337 empowers the
H
      PRIYANKA ESTATES INTERNATIONAL P. LTD. &                    97
      ORS. v. STATE OF ASSAM [DEEPAK VERMA, J.]
~

     Commissioner to require the removal or alteration of the work      A
     which may not be in conformity with bye-laws etc. Section 416
     of the Act empowers the GMC to formulate different bye-laws
     including the bye-laws relating to the building. Section 438 of
     the Act provides for appeal from the order passed by the
     Commissioner including the order refusing to grant permission      B
     to construct or re-construct a building to the SAC. Sub-section
     (3) of Section 438 of the Act empowers the State Govt. to call
     for the records of any matter from the Corporation and to pass
     such orders as may be deemed necessary after examination
     of such records.                                                   c
         37. It is necessary to refer to Section 88 of the
     Development Act which reads as under :

          "88. Power of demolition of building. -(1) Where any
          development has been commenced or is being carried on         D
-t        or has been completed in contravention of the Master Plan
          or development scheme or without the permission,
          approval or sanction referred to in Section 25 and Section
          30 of the Act or in contravention of any conditions subject
         to which such permission, approval or sanction has been        E
         granted, the authority may in addition to any prosecution
         that may be instituted under the Act, make an order
         directing that such development shall be removed by
         demolition, filling or otherwise by the owner, occupier,
'        manager or by any person at whose instance the                 F
         development has been commenced or is being carried out
         or has been completed within such period not being less
         than five days and more than thirty days from the date on
         which a copy of the order of removal with brief statement
         of the reasons thereof has been delivered to the owner,        G
         occupier and manager or the rerson at whose instance
         the development has been commenced or is being carried
         out or has been completed as may be specified in the
         order and on his failure to co nply v.ith the order, the
         authority may remove or cause to be removed the
                                                                        H
    98     SUPREME COURT REPORTS [2009] 16 (ADDL.) S.C.R.
                                                                          .!

A        development and the expenses of such removal shall be
         recovered from the owner, occupier, manager or any
         person at whose instance the development was.
         commenced or was being carried out or was completed
         as arrears of land revenue; provided that no such order
B        shall be made unless the owner, occupier, manager or the
         person concerned has been given a reasonable
         opportunity to show cause why the order shall not be made.

         (2) The provisions of this section shall be in addition to and
         not in derogation of any other provision relating to
c        demolition of buildings contained in any other law for the
         time being in force.

         (3) No compensation shall be claimed by any person for
         any damage which he may sustain in consequence of the
D        removal of any development under this section or the
         discontinuance of the development under Section 87 of this
         Act."

       38. Mr. Shekhar Naphade, learned Senior Counsel for
E Appellants firstly strenuously contended before us that NOC
  dated 17.7.1999 granted by GMDA clearly stipulated that the
  plot purchased by Appellants would fall in the category of
  "residential-cum-commercial use" and width of the road abutted
  by the plot is proposed to be 50 feet. Thus, according to him,               +
F the height of the building can be 100 feet, being the double of
  the width of the road. Since the height of the building of the
  Appellants even after construction upto 8th floors is only 93 feet,
  the part of the building beyond 5% floors is not liable to be
  demolished.

G        39. It was also contended by him that initial permission was
    granted by GMC whereas notices of demolition have been
    issued by GMDA which appears to be absolutely contrary and
    against the provisions of law. It was also contended that
    Respondents have failed to prove that any notices were sent
H
            PRIYANKA ESTATES INTERNATIONAL P. LTD. &                       99
            ORS. v. STATE OF ASSAM [DEEPAK VERMA, J.]
          to them on 02.02.2001 or 05.09.2001 by GMDA as it has been             A
          categorically mentioned by the Appellants pursuant to third
          notice·received by them and replied to.

               40. It was also argued that in the light of specific order
          passed by SAC, conscious decision has been taken by the
                                                                                 B
          Government and denial of hearing itself would amount to
          prejudice, consequently, violation of principles of natural justice.
      )
                41. If Commissioner was dissatisfied with the modification
          of his order by the SAC then as provided under sub-section
          (2) of Section 438 of the Act, he was required to make a               c
          reference to the Corporation within 60 days thereof which he
          failed to do. He was, therefore, bound by the Appellate Order
          of SAC and could not have super-imposed his own views or
          conditions.
                                                                                 D
               42. Mr. Mukul Rohtagi, learned Senior Counsel appearing
          for Shyam Sunder Agarwala submitted that he is owner of part
          of the 5th floor which ha$ not been sanctioned.

               43. According to Mr. Mukul Rohtagi half of the 5th floor has
          already been sanctioned and even if the width of the road              E
          abutted to the building is taken as 38 feet, the height allowed
'•
          would be 76 feet. Thus, it will have no height problem. At the
          most, the only objection can be with regard to FAR which
      ~
          objection can be waived as the same falls within compoundable
          items.                                                                 F

                44. Shri Shyam Sunder Agarwala had purchased the said
          flat on 18.04.2005 for a total amount of Rs.9,43,850. It has also
          been contended that after purchase of the said flat his name
"""       has been mutated in the Corporation records. He is paying              G
          property tax, water tax etc., which Corporation is accepting.
          Thus, for this reason also it is not liable to be demolished.

               45. He further contended that two parallel bodies, that is,
          GMC and GMDA cannot take action for demolition of the
          building as the permission was accorded by GMC whereas                 H
    100 SUPREME COURT REPORTS [2009] 16 (ADDL) S.C.R.

                                                                        .•
A notices of demolition have been issued by GMDA. Thus,
  according to him, whole procedure is illegal and void, thus liable
  to be quashed.

       46. In the light of this, it has been contended that Section
B
  88 of the Development Act could not be put into service against            "
  the Appellants as the same amounts to violation of principles
  of natural justice as no notice has been served on the said
                                         \

  Appellant.                              '

        47. Mr. Vijay Hansaria, learned Senior Counsel appearing
c for other Appellants submitted that they are owners of flat
  No.7A/7C and 7D having purchased on 14.06.2004 and
  03.01.2005 for a sum of Rs.17,72,460 and 9,43,850
  respectively. He has reiterated that Section 88 of the
  Development Act has not been complied with inasmuch as no
D opportunity to show cause has been given to these Appellants,
  thus violation of principles of natural justice is writ large from
  the record. Commissioner had no other alternative but to abide
  by the Appellate Order of SAC and in any case it should have
  been treated as deemed sanction.
E
        48. Shri Kamal Mohan Gupta, learned counsel appearing
  for Sarla Devi Lahoty, owner of a flat on 6th floor has also
  reiterated the aforesaid arguments already advanced by M/s.
  Shekhar Naphade, Vijay Hansaria and Mukul Rohtagi.
                                                                        +
  Additionally, he has submitted that Sarla Devi Lahoty purchased
F a flat on 27.12.2004 for Rs. 8,63,010, after making due inquiries
  with regard to sanction of building plans etc. Thus, she would
  be a bonafide purchaser for value and for any acts of omission
  or commission said to have been committed by builder M/s.
  Priyanka Estates International Pvt. Ltd. this Appellant cannot be
G put to any loss.

         49. After having gone through the record carefully, the crux
    of the matter is whether M/s. Priyanka Estates International Pvt.
    Ltd. is in possession of any approved or sanctioned plan
H
                    PRIYANKA ESTATES INTERNATIONAL P. LTD. &                      101
                    ORS. v. STATE OF ASSAM [DEEPAK VERMA, J.]
    '             beyond 5Yz floors, i.e., for the remaining 3Yz floors or not. If not,   A
                  then what is the effect thereof?

                      50. It is clear from the record that the only plan approved
                  was on 03.02.2000 for 5Yz floors by GMC. Order dated
                  05.05.2000 passed by SAC also does not give them blanket
                                                                                          8
                  permission to construct upto 8th floor.

        -.               51. It is also to be seen that respondents have come to
                  the conclusion and have fairly conceded before us that plan or
                  sanction approved by either of the two authorities, that is, GMC
                  or GMDA will hold good and permission from both the                     c
                  authorities simultaneously would not be required for the same,
                  if it has already been accorded by any one of the authorities.

                       52. On the strength of this, we can safely proceed that if
                  no permission under Section 24 and 25 of the Development D
         -;       Act was obtained by Mis. Priyanka Estates International Pvt.
                  Ltd. then it would not be detrimental to the interest of the
                  Appellants, provided there is sanction and approval of plans by
                  the Corporation for remaining 3Yz floors i.e. beyond 5Yz floors.

                        53. Here, it is pertinent to point outthat Respondents had E
'   .             also issued a public notice on 02.07.2002, published in local
                  newspaper in vernacular giving general warning and information
                  to all proposed purchasers of flats that unless builder is able
             ~
                  to show Completion Certificate and Occupancy Certificate duly
                  issued by authorities, no one should enter into agreement to F
                  purchase flat/flats from the builder. It is, therefore, to be
                  construed that public notice will hold good even with regard to
                  adherence to the requirement of Section 88 of the Development
                  Act, if individual person had not been noticed by the authorities.
                                                                                      G
                        54. Clause (a) of building bye-law 37 stipulates that for the
             ,,   purpose of calculation of building height, existing width of the
                  road shall be taken into account and not the proposed width.
                  Even if the proposed width is 40 feet or 50 feet, it will not make
                  any difference because it clearly contemplates that what is to
                                                                                      H
    102     SUPREME COURT REPORTS [2009] 16 (ADDL.) S.C.R.


A be taken into consideration is the existing width of the road.
  There is nothing on record to show that the existing width of
  the road is more than 38 feet. Thus, at the most, the construction
  could have been only upto the height of 76 feet, provided there
  was sanction granted by either of the two Authorities.
B
       55. Appendix Ill of building bye-laws deals with penalties
  to be levied for violation of provisions of Master Plans, Zoning
  Plans Regulations and Bye-laws. Certain items are
  compoundable items but certain items fall in the category of            t
  non-compoundable items. However, addition of extra fleor falls
C in the category of non-compoundable items. Thus, in any case
  anything that has been constructed beyond 5th floor would be
  non-compoundable arid same cannot be compounded at all.
  In other words, minor deviations from the sanctioned plan
  should be confined only to the FAR permissible but should not
D extend to the extra floor.

       56. For better appreciation of the aforesaid provision the
    same is reproduced hereinbelow :-

          "Appendix Ill
E
       PENALTIES TO BE LEVIED FOR VIOLATIONS OF
    PROVISION OF MASTER PLAN/ZONING PLAN
    REGULATIONS AND BYE LAWS.

F         (i) All provisions of Bye-laws except items given below shall
          not be compounded/regularized and shall have to be
          rectified by alteration/demolition at the risk and cust of
          owner.

          Compoundable items:
G
          (1) Coverage              -   maximum of 15%
          (2) F.A.R.                -   maximum of 10%
          (3) Set Back              -   Upto 2'- 6"
H
       PRIYANKA ESTATES INTERNATIONAL P. LTD. &                  103
       ORS. v. STATE OF ASSAM [DEEPAK VERMA, J.]
          (4) Open Space            -   Maximum 10% reduction           A

          (5) Total Height of       -   1.5%
              Building

          Non Compoundable items:
                                                                        B
          (1) Use of building

          (2) Addition of extra floor

          (3) Parking Norms
                                                                        c
          (4) Parking Norms

          (5) Projection/encroachment of public land."

         Critical and analytical perusal of the same would show that
     addition of extra floor falls within the ambit of non-             D
-!   compoundable items.

          57. The order of SAC cannot be construed as an order of
     sanction as it is not a semblance of permission. It was not end
     of the matter because necessary sanction or permission could       E
     have been granted only by the Municipal Commissioner and
     not by the Appellate Authority. Admittedly, even after passing
     of the order by SAC in appeal, there was no further sanction
     by the Municipal Commissioner or by Chief Executive Officer
~
     of the Development Authority granting permission to raise the      F
     height of the building upto 8th floor.

          58. Thus, looking to the matter from all angles, we are of
     the opinion that construction of the building beyond 5% floors
     was not only illegal, unauthorized and without any sanction or
     approval of plans but was also against the spirit of Appellate     G
     Order of SAC. Thus, except for directing the Respondent-
     authorities to demolish 6th, 7th and 8th floor, we are left with
     no alternative.

         59. As regards construction of two flats on remaining half     H
    104 SUPREME COURT REPORTS (2009] 16 (ADDL.) S.C.R.


A of 5th floor, Mr. L. Nageshwar Rao, learned Senior Counsel for        ~

    Respondent-authorities fairly conceded that on suitable
    representations being made by the occupants, their cases can
    be considered afresh to find out if the same would fall within
    the category of compoundable items or not. If the same are
B found within the category of compoundable items then
  . necessary order by respondents in this regard would be passed
    otherwise order of demolition would follow for them also. Thus, .
    on the promise of Sr. Advocate Mr. L. Nageshwar Rao, we
    hope and trust, suitable orders would be passed by the
                                                                        ,
c Authorities as regards two flats on 5th floor are concerned
    within two months from the date of submission of the
    Representations.

       60. Even though various authorities had been placed
  before us by the learned counsel appearing for parties, it is not
D required to deal with them in extenso. However, a cursory
  reference to the same would meet the ends of justice.

       61. Mr. Shekhar Naphade has placed reliance on
  Corporation of Calcutta v. Mulchand Agarwala AIR 1956 SC
E 110 to contend that it should be a last resort to direct demolition
  of a building and if it falls within the compoundable limit then it
  should not be directed to be demolished. To advance
  contentions further in this regard, reliance has been placed on
  para 4 of an order of this Court in the case of Syed Muzaffar
F Ali & Others v. Municipal Corporation of Delhi 1995 Supp. (4)
  sec 426 which is reproduced hereunder :
        "4. However, it is to be pointed out that mere di:>;:,drture
        from the authorized plan or putting up a construction without
        sanction does not ipso facto and without more necessarily
G       and inevitably justify demolition of the structure. There are
        cases and cases of such unauthorized constructions.
        Some are amenable to compounding and some may not
        be. There may be cases of grave and serious breaches
        of the licensing provisions or building regulations that may
H
    PRIYANKA ESTATES INTERNATIONAL P. LTD. &                  105
    ORS. v. STATE OF ASSAM [DEEPAK VERMA, J.]
       call for extreme stage of demolition.                         A

        62. Reliance has also been placed on yet another judgment
  of this Court in the case of Muni Suvrat-Swamy Jain S.M.P.
   Sangh v. Arun Nathuram Gaikwad & Others (2006) 8 SCC
  590, which dealt with Section 351 of the Bombay Municipal 8
  Corporation Act to hold that if execution of work has
  commenced contrary to provisions of the Act. then to give
+ notice to the person carrying on the construction work to show
   cause why it should not be pulled down, is a must. The use of
  the word "shall" would signify that it is mandatory to issue notice C
   and then to pass any order. Lastly, a recent judgment of this
   Court in the case of Municipal Corporation, Ludhiana v.
   lnderjit Singh & Anr. (2008) 13 SCC 506 has been pressed
   into service. This also deals primarily with the requirement of
   issuance of show cause notice to the person who had raised
   construction, so as to enable the said party to show cause, if D
 _.the construction has been made in total violation of the
   sanctioned map or it falls within the category of compoundable
   items.

       63. Mr. Vijay Hansaria has placed reliance on the famous      E
  off-quoted judgment of this Court in the case of Olga Tellis and
  Others etc. v. Bombay Municipal Corporation & Others etc.
  (1985) 3 sec 545 which dealt with plight of the pavement
 ~dwellers, who were in unauthorised possession and were
  sought to be evicted. He sought to contend that the fundamental    F
  rule of principles of natural justice should have been followed
  before passing the order of demolition.

      64. Further with regard to opportunity of hearing he has
  placed reliance on a judgment of this Court in the case of S.L.
  Kapoor v. Jagmohan and Others (1980) 4 SCC 379.                    G

       65. On the other hand, Mr. L. Nageshwar Rao has placed
  reliance on various judgments of this Court, viz., M.I. Builders
  Pvt. Ltd. v. Radhey Shyam Sahu and Others (1999) 6 SCC
                                                                     H
    106 SUPREME COURT REPORTS [2009] 16 (ADDL.) S.C.R.


A 464; Friends Colony Development Committee v. State of
  Orissa and Others (2004) 8 SCC 733; Royal Paradise Hotel
  (P) Ltd. Vs. State of Haryana and Others (2006) 7 SCC 597;
  and Mahendra Buburao Mahadik and Others v. Subhash
  Krishna Kanitkar and Others (2005) 4 SCC 99 to contend that
B where constructions have been made in absolute and flagrant
  violation of the sanctioned plan then the only alternative is to
  direct demolition of the same.
                                                                         t
         66. It is not necessary to deal with the aforesaid judgments
   of this Court in greater detail as the consistent ratio decidendi
C of this Court is that if the constructions are in absolute violation
   of sanctioned or approved plans and are not likely to fall in the
  category of compoundable items, then the necessary
  consequence is to order its demolition and seal of approval for
  such illegal activities is not required to be given by this Court.
D
        67. It is µertinent to mention here that hearing of the
  appeals had commenced on 22.10.2009 and had almost
  concluded on 28.10.2009. But on the said date, Mr. Anoop
  George Chaudhary and Ms. June Chaudhary, learned Senior
E Counsel, appeared with Mr. Kamal Mohan Gupta for Sarla Devi
  Lahoty and submitted that they would be replying to the
  arguments advanced by learned counsel for Respondents.
  Though not approved as a healthy practice, yet we granted
  them permission.
F      68. It was submitted by them that if cases of two flat owners
  on the 5th floor are to be considered so as to find out whether
  the constructions raised by the builder in their cases would fall
  within the compoundable items or not, then the case of Sarla
  Devi Lahoty should also be directed to be considered on a
G suitable representation being made by her, as her flat is
  situated on the 6th floor. It was contended that even after taking
  the height of 6th floor, it would not cross the maximum helght
  of 76 feet looking to the width of the existing road.

H       69. However, the said contention cannot be accepted as
           PRIYANKA ESTATES INTERNATIONAL P. LTD. &                  107
           ORS. v. STATE OF ASSAM [DEEPAK VERMA, J.]
,.
         construction of an extra floor does not fall within the category A
         of compoundable items which is manifest from Appendix Ill of
         the building bye-laws of the Corporation reproduced
         hereinabove.

              70. However, with regard to two flats on 5th floor, a
         direction can be given to the Respondents to consider their         B
         cases if they submit their representations within a period of 30
 ..      days hereof. Respondents would examine whether their cases
         fall within the compoundable items/limit or not. In case,
         Respondents come to the conclusion that these two flats
         constructed on 5th floor fall within the compoundable limit, then   c
         necessary orders be passed in this regard, after charging
         compounding fees as may be applicable to the facts of the
         case, in accordance with law, otherwise, they would also face
         the wrath of demolition.
                                                                          D
 ~             71. Even a conjoint reading of the order dated 05.05.2000
         passed by SAC and the order dated 29.05.2002 of the
         Administrator-cum-Minister makes it clear as noon day that it
         does not clothe the Appellants to continue with the construction
         work beyond 5Y2 floors as these orders were passed subject 'E
         to fulfilling certain conditions contained therein.

              72. It is obvious that what would ultimately constitute a
     1
         sanctioned and duly approved map would be the one approved
         by the Commissioner as he alone has authority to do so. The
         Appellants have failed to produce any such duly approved map.       F

             73. It is- a matter of common knowledge that illegal and
       unauthorised constructions beyond the sanctioned plans are on
       rise, may be due to paucity of land in big cities. Such activities
       are required to be dealt with by firm hands otherwise builders/ G
       colonisers would continue to build or construct beyond the
     ' sanctioned and approved plans and would still go scot-free.
       Ultimately, it is the flat owners who fall prey to such activities
       as the ultimate desire of a common man is to have a shelter of
       his own. Such unlawful constructions are definitely against the H
    108 SUPREME COURT REPORTS [2009] 16 (ADDL.) S.C.R.


A public interest and hazardous to the safety of occupiers and
  residents of multi-storeyed buildings. To some extent both
  parties can be said to be equally responsible for this. Still the
  greater loss would be of those flat owners whose flats are to
  be demolished as compared to the Builder.
B       74. Even though on earlier occasions also, under similar
  circumstances, there have been judgments of this Court which
  should have been a pointer to all the builders that raising
  unauthorised construction never pays and is against the interest      +
  of society at large, but, no heed to it has been given by the
c builders. Rules, regulations and bye-laws are made by
  Corporation or by Development Authorities, taking in view the
  larger public interest of the society and it is a bounden duty of
  the citizens to obey and follow such rules which are made for
  their benefit. If unauthorised constructions are allowed to stand
D or given a sea! nf approval by court then it is bound to affect
  the public at large. An individual has a right, including a
  fundamental right, within a reasonable limit, it inroads the public
  rights leading to public inconvenience, therefore, it is to be
  curtailed to that extent.
E
        75. The jurisdiction and power of courts to indemnify a
  citizen for injuries suffered due to such unauthorised or illegal
  construction having been erected by builder/coloniser is
  required to be compensated by them. An ordinary citizen or a
  common man is hardly equipped to match the might and power
F of the builders.

       76. In the case in hand, it is noted that number of occupiers
  were put in possession of the respective flats by the builder/
  developer constructed unauthorisedly in violation of the laws.
G Thus, looking to the matter from all angles it cannot be disputed
  that ultimately the flat owners are going to be the greater
  sufferers rather than builder who has already pocketed the price
  of the flat.

        77. It is a sound policy to punish the wrong-doer and it is
H
  PRIYANKA ESTATES INTERNATIONAL P. LTD. &                     109
  ORS. v. STATE OF ASSAM [DEEPAK VERMA, J.]
in that spirit that the courts have moulded the reliefs of granting   A
compensation to the victims in exercise of the powers
conferred on it. In doing so, the courts are required to take into
account not only the interest of the petitioners and the
respondents but also the interest of public as a whole with a
view that public bodies or officials or builders do not act           B
unlawfully and do perform their duties properly.

      78. In the case in hand, admittedly, at no point of time
Appellant No.1- M/s. Priyanka Estates International Pvt. Ltd.
was able to show to its prospective purchasers the Occupancy          C
Certificate or Completion Certificate issued by the authorities
concerned. The same could not even be shown to us and
without it, Appellant No.1 could not have embarked into sale
of flats as it was mandatorily required.

     79. The instant case is not a case of breach of contract. It     D
is a clear case of breach of the obligation undertaken to erect
the building in accordance with building regulations and failure
to truthfully inform the warranty of title and other allied
circumstances.
                                                                      E
      80. Even though at the first instance, we thought of invoking
this Court's jurisdiction conferred under Article 142 of the
Constitution of India so as to do complete justice between the
parties and to direct awarding of reasonable/suitable
compensation/interest to the flat owners, whose flats are
ultimately going to be demolished, but, with a very heart, we         F
have restrained ourselves from doing so, for variety of reasons
and on account of various disputed questions that may be
posed in the matter. However, we grant liberty to those, whose
flats are ultimately going to be demolished, to exhaust the
remedy that may be available to them in accordance with law.          G

    81. We also feel it necessary and expedient to direct the
Respondent-authorities that if ultimately flat owners, whose flats
are going to be demolished shall be given at least three
                                                                      H
    110      SUPREME COURT REPORTS [2009] 16 (ADDL.) S.C.R.


A months' time to vacate the same. This would enable them to
  mitigate the losses that may be incurred by them. We
  accordingly direct so.

       82. In the light of the foregoing discussions, these appeals
  are dismissed with the directions contained hereinabove.
8
  Respondent-authorities shall be at liberty to proceed with
  demolition of half of the 5th floor, if not ultimately compounded;
  6th, 7th and 8th floors as mentioned hereinabove.

          83. Counsel's fee Rs. 10,000/- each.
c
    K.K.T.                                    Appeals dismissed.


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "unauthorised construction"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.