Created byFuzzy Cloud

Supreme Court of India

PSA SICAL TERMINALS PVT. LTD.versusTHE BOARD OF TRUSTEES OF V.O. CHIDAMBRANAR PORT TRUST TUTICORIN AND OTHERS

Citation
2021 INSC 365
Decided
28 July 2021
Disposal
Dismissed

Holding

The award was set aside because the arbitral tribunal exceeded its jurisdiction by making findings based on no evidence, resulting in patent illegality, and the court may not re‑appreciate evidence or rewrite the contract.

Summary

The dispute arose from a BOT concession for the seventh berth at V.O. Chidambaranar Port, where PSA SICAL Terminals (SICAL) sought to replace a royalty payment model with a revenue‑sharing model, alleging a change in law under Article 14 of its licence agreement. The arbitral tribunal awarded SICAL relief, finding that government policy changes in 2003 and 2005 constituted a change in law that adversely affected SICAL. TPT challenged the award under Section 34 of the Arbitration and Conciliation Act, 1996, arguing that the tribunal exceeded its jurisdiction, ignored vital tariff orders, and substituted contractual terms without consent. The Supreme Court held that courts may only interfere on the limited grounds listed in Section 34, notably patent illegality or violation of public policy, and that the tribunal’s findings were based on no evidence and were perverse, amounting to patent illegality. Consequently, the award was set aside and the appeals dismissed. The Court emphasized that arbitral tribunals cannot re‑appreciate evidence or rewrite contracts, and that the scope of judicial interference is narrowly confined.

Issues considered

  • The arbitral tribunal's finding of a change in law under Article 14.3 was justified.
  • Whether the tribunal was authorized to substitute the royalty payment module with a revenue‑sharing module without the licensor's consent.
  • Whether the award can be set aside on the ground of patent illegality arising on its face.
  • Whether the court may re‑appreciate evidence or interfere with the merits of the award under Section 34/37 of the Arbitration Act.

Legislation cited

Subjects

ArbitrationSection 34Public policy of IndiaPatent illegalityChange in lawRoyalty vs revenue sharingContract amendmentPerverse awardScope of judicial interference

Judgment

408                       [2021]
               SUPREME COURT     5 S.C.R. 408
                              REPORTS                        [2021] 5 S.C.R.


A                    PSA SICAL TERMINALS PVT. LTD.
                                  v.
      THE BOARD OF TRUSTEES OF V.O. CHIDAMBRANAR PORT
                TRUST TUTICORIN AND OTHERS
                (Civil Appeal Nos. 3699-3700 of 2018)
B
                                  JULY 28, 2021
                  [R. F. NARIMAN AND B. R. GAVAI, JJ.]
             Arbitration and Conciliation Act, 1996: s.34 – Application
      for setting aside award – Scope of interference – Held: In an
C     application under s.34, the court is not expected to act as an
      appellate court and re-appreciate the evidence – The scope of
      interference would be limited to grounds provided under s.34 of the
      Arbitration Act – The interference would be so warranted when the
      award is in violation of “public policy of India”, which has been
D     held to mean “the fundamental policy of Indian law” – A judicial
      intervention on account of interfering on the merits of the award
      would not be permissible – However, the principles of natural justice
      as contained in s.18 and 34(2)(a)(iii) of the Arbitration Act would
      continue to be the grounds of challenge of an award – The ground
      for interference on the basis that the award is in conflict with justice
E     or morality is now to be understood as a conflict with the “most
      basic notions of morality or justice” – It is only such arbitral awards
      that shock the conscience of the court, that can be set aside on the
      said ground – An award would be set aside on the ground of patent
      illegality appearing on the face of the award and as such, which
F     goes to the roots of the matter – However, an illegality with regard
      to a mere erroneous application of law would not be a ground for
      interference – Equally, re-appreciation of evidence would not be
      permissible on the ground of patent illegality appearing on the face
      of the award.
            Arbitration and Conciliation Act, 1996: s.34 – Arbitral
G
      Tribunal passed the award in favour of SICAL holding that there
      was a change in law and thereby granting reliefs as prayed for by
      SICAL – It directed conversion of Container Terminal of TPT from
      royalty model to revenue share model – The finding of the Arbitral
      Tribunal was based on a premise that when TPT entered into a
H
                                        408
PSA SICAL TERMINALS PVT. LTD. v. THE BOARD OF TRUSTEES OF V.O.             409
            CHIDAMBRANAR PORT TRUST TUTICORIN


contract with SICAL there was an existing policy, which provided           A
royalty to be factored into the cost while fixation of tariff and that
subsequently, the GoI changed its policy on 29th July, 2003 thereby
providing that royalty payment/revenue sharing will not be factored
into/taken into account as cost for fixation/revision of tariff by TAMP;
and that there was subsequent change in policy on 31st March, 2005
                                                                           B
by which part of royalty was permitted to be factored into the cost –
According to the Arbitral Tribunal, there was a change in policy,
which amounted to change in law, which, in turn, adversely affected
SICAL – Award of Arbitral Tribunal challenged by TPT before the
District Judge – District Judge dismissed the s.34 petition – TPT
successfully challenged before the High Court – Aggrieved SICAL            C
filed instant appeals – Held: When the bid document was notified
and when SICAL submitted its bid and LoI was issued to it, there
were no guidelines in vogue – Even the guidelines of February
1998 do not provide for royalty being factored as cost while fixation
of tariff – On the contrary, the tariff order of 1999 specifically
                                                                           D
clarifies that it has left the royalty issue to be decided by TPT and
the GoI – It has specifically clarified that the approval by TAMP
should not be interpreted to be amounting to any implicit approval
of royalty-related issue – Further, the tariff order issued on 20 th
September, 2002 specifically rejects the claim of SICAL for factoring
any royalty as cost while tariff/price fixation – SICAL has challenged     E
the said order before the High Court by way of writ petition, which
petition has been allowed – It is also not in dispute, that on account
of interim order passed by the High Court dated 8th November, 2002,
SICAL is still continuing to charge at rates notified in the 1999
tariff order – In this scenario, the finding of the Arbitral Tribunal,
                                                                           F
that there was a law when the Agreement was entered into between
the parties, which provided royalty as a pass-through and that the
said law has been changed for the first time in 2003 and
subsequently again changed in 2005, is a finding based on ‘no
evidence’ – Had the Arbitral Tribunal perused the tariff orders of
1999 and 2002, it would have found that in the 1999 tariff order           G
TAMP has specifically observed that its approval of the tariff should
not be construed as its implicit approval of royalty-related issue
and the 2002 tariff order specifically states that royalty was not
permitted to be factored in the cost while determining tariff – The
Arbitral Tribunal has totally failed to take into consideration this
                                                                           H
410            SUPREME COURT REPORTS                        [2021] 5 S.C.R.


A     aspect of the matter – As such, since the finding of the Arbitral
      Tribunal, that there was an existing law to the effect that the royalty
      payable shall be permitted as a pass-through in cost while fixation
      of tariff, is based on ‘no evidence’ and the finding, that there was a
      change in law in 2003 and 2005 is based on without taking into
      consideration the relevant evidence, would come in the realm of
B
      perversity as explained by this Court in paragraph 31 of the Associate
      Builders – The findings are based on ‘no evidence’ and ‘ignorance
      of vital evidence’ in arriving at its decision.
              Arbitration and Conciliation Act, 1996: s.34 – Whether the
      Arbitral Tribunal was justified in passing an award thereby
C     substituting ‘royalty payment module’ to the ‘revenue-sharing
      module’ – A contract duly entered into between the parties cannot
      be substituted unilaterally without the consent of the parties – The
      intention of the parties could be gathered from the documents on
      record – SICAL made representation to TPT seeking a relief under
D     the terms of Article 14.3 of the Agreement – TPT informed SICAL
      that the issues raised by it were under examination – However, TPT
      refused to consider SICAL’s application for relief since, according
      to it, the issue raised by SICAL was pending before the High Court
      – SICAL filed writ petition before High Court – High Court allowed
      the writ petition clarifying that the petition pending before the High
E     Court had nothing to do with the representation under Article 14 of
      the License Agreement and remanded the matter to TPT for
      consideration afresh – TPT rejected the claim of SICAL – TPT has
      specifically observed that any change in the Agreement cannot be
      done without prior approval of the GoI – SICAL wrote to TPT
F     invoking arbitration under Article 15.3 of the License Agreement –
      TPT strenuously contested the claim of SICAL with regard to prayer
      for change from ‘royalty payment mode’ to ‘revenue sharing mode’
      – It could, thus, be seen that SICAL wanted the Agreement to be
      amended so as to change the ‘royalty payment method’ to ‘revenue-
      sharing method’ – TPT was always opposed to it – The intention of
G     TPT is apparent from its various communications and its stand before
      the Arbitral Tribunal, that it was not agreeable for amendment of
      the Agreement from ‘royalty payment method’ to ‘revenue-sharing
      method’ – However, ignoring the stand of TPT, by the impugned
      Award, the Arbitral Tribunal has thrust upon a new term in the
H
PSA SICAL TERMINALS PVT. LTD. v. THE BOARD OF TRUSTEES OF V.O.              411
            CHIDAMBRANAR PORT TRUST TUTICORIN


Agreement between the parties against the wishes of TPT – The               A
‘royalty payment method’ has been totally substituted by the Arbitral
Tribunal, with the ‘revenue-sharing method’ – It is thus clear, that
the Award has created a new contract for the parties by unilateral
intention of SICAL as against the intention of TPT.
       Arbitration: An Arbitral Tribunal is not a Court of law – Its        B
orders are not judicial orders – Its functions are not judicial functions
– It cannot exercise its powers ex debito justitiae.
      Dismissing the appeals, the Court
       HELD : 1. The scope of interference would be limited to
grounds provided under Section 34 of the Arbitration Act. An                C
award would be set aside on the ground of patent illegality
appearing on the face of the award and as such, which goes to the
roots of the matter. However, an illegality with regard to a mere
erroneous application of law would not be a ground for
interference. Equally, re-appreciation of evidence would not be             D
permissible on the ground of patent illegality appearing on the
face of the award. A decision which is perverse, though would not
be a ground for challenge under “public policy of India”, would
certainly amount to a patent illegality appearing on the face of
the award. However, a finding based on no evidence at all or an
award which ignores vital evidence in arriving at its decision would        E
be perverse and liable to be set aside on the ground of patent
illegality. [Paras 42, 43][434-H; 435-C-E]
      2. Article 14 of the bid document deals with ‘change in law’.
Article 14.3 provides for relief under change in law. If, after the
date of Agreement, there is a change in the law which substantially         F
and adversely affects the rights of the Licensee under the
Agreement so as to alter the commercial viability of the project,
the Licensee may, by written notice, request amendments to the
terms of the Agreement. It further provided, that subject to
provisions of Article 14.3, the Licensee shall not be entitled to           G
any compensation whatsoever from the Licensor as a result of
change in law. [Para 55][442-G-H; 443-B-C]
      MMTC Limited v. Vedanta Limited (2019) 4 SCC 163:
      [2019] 3 SCR 1023 – relied on.
                                                                            H
412            SUPREME COURT REPORTS                        [2021] 5 S.C.R.


A            3.1 Neither under Section 34 nor under Section 37 of the
      Arbitration Act, the Court is entitled to reappreciate the evidence.
      The said limitation would be equally applicable to this Court also.
      Admittedly, the bid document was published on 9th April, 1997.
      The technical bid of SICAL was submitted on 24th October, 1997.
      The financial offer of SICAL was submitted on 19th December,
B
      1997. LoI was issued on 29th January, 1998. All this has happened
      prior to the guidelines issued by TAMP in February 1998. As
      such, it is beyond any doubt, that when the bid document was
      notified and when SICAL submitted its bid and LoI was issued to
      it, there were no guidelines in vogue. For the first time, the
C     guidelines were adopted by TAMP in the workshop held in
      Chennai on 26th/27th February, 1998. [Para 60][444-C-F]
            3.2 Even 1998 guidelines do not mention, that the royalty
      could be factored in the cost while determining the tariff. Though
      the said guidelines observed, that the port pricing may continue
D     to be cost-based with an assured rate of return, it further
      observed, that such a concept of an assured rate of return is not
      in consonance with a competitive system. Thus, it is amply clear,
      that when the bids were invited, and SICAL submitted its bid
      and LoI was issued to it, there was no policy at all. Even the 1998
      guidelines do not provide for factoring the royalty in cost while
E     determining the tariff. [Para 63][445-G-H; 446-A]
            4. A conjoint reading of all documents would reveal that
      when the bid document was published in April 1997; SICAL
      tendered its bid in October, 1997 and submitted its financial offer
      in December,1997; and the LoI was issued to SICAL on 29 th
F     January, 1998, there were no guidelines at all. Even the guidelines
      of February 1998 do not provide for royalty being factored as
      cost while fixation of tariff. On the contrary, the tariff order of
      1999 specifically clarifies that it has left the royalty issue to be
      decided by TPT and the GoI. It has specifically clarified that the
G     approval by TAMP should not be interpreted to be amounting to
      any implicit approval of royalty-related issue. Further, the tariff
      order issued on 20th September, 2002specifically rejects the claim
      of SICAL for factoring any royalty as cost while tariff/price fixation.
      SICAL has challenged the said order before the Madras High

H
PSA SICAL TERMINALS PVT. LTD. v. THE BOARD OF TRUSTEES OF V.O.           413
            CHIDAMBRANAR PORT TRUST TUTICORIN


Court by way of writ petition, which petition has been allowed. It       A
is also not in dispute, that on account of interim order passed by
the Madras High Court dated 8th November, 2002, SICAL is still
continuing to charge at rates notified in the 1999 tariff order.
[Para 76][451-A-D]
      5.1 In this scenario, the finding of the Arbitral Tribunal,        B
that there was a law when the Agreement was entered into
between the parties, which provided royalty as a pass-through
and that the said law has been changed for the first time in 2003
and subsequently again changed in 2005, is a finding based on
‘no evidence’. Had the Arbitral Tribunal perused the tariff orders
of 1999 and 2002, it would have found that in the 1999 tariff order      C
TAMP has specifically observed that its approval of the tariff
should not be construed as its implicit approval of royalty-related
issue and the 2002 tariff order specifically states that royalty was
not permitted to be factored in the cost while determining tariff.
The Arbitral Tribunal has totally failed to take into consideration      D
this aspect of the matter. [Para 77][451-D-F]
       6.2 As such, since the finding of the Arbitral Tribunal, that
there was an existing law to the effect that the royalty payable
shall be permitted as a pass-through in cost while fixation of tariff,
is based on ‘no evidence’ and the finding, that there was a change       E
in law in 2003 and 2005 is based on without taking into
consideration the relevant evidence, would come in the realm of
perversity as explained by this Court in paragraph 31 of the
Associate Builders. The findings are based on ‘no evidence’ and
‘ignorance of vital evidence’ in arriving at its decision. [Para
78][451-F-H]                                                             F

      Associate Builders v. Delhi Development Authority
      (2015) 3 SCC 49 : [2014] 13 SCR 895 – relied on.
      7.1 This brings us to the next issue viz., as to whether the
Arbitral Tribunal was justified in passing an award thereby              G
substituting ‘royalty payment module’ to the ‘revenue-sharing
module’. A contract duly entered into between the parties cannot
be substituted unilaterally without the consent of the parties. The
intention of the parties could be gathered from the documents
on record. SICAL, for the first time, made representation to TPT
                                                                         H
414            SUPREME COURT REPORTS                      [2021] 5 S.C.R.


A     on 6th October, 2006 thereby seeking a relief under the terms of
      Article 14.3 of the Agreement. On 14 th October, 2006, TPT
      informed SICAL that the issues raised by it were under
      examination. However, vide order dated 27th October, 2006, TPT
      refused to consider SICAL’s application for relief since, according
B     to it, the issue raised by SICAL was pending before the Madras
      High Court. SICAL therefore filed writ petition being Writ Petition
      No. 4361 of 2006 before the Madras High Court. The Madras
      High Court allowed the said writ petition vide order dated 21st
      August, 2007 clarifying that the petition pending before the High
C     Court had nothing to do with the representation under Article 14
      of the License Agreement and remanded the matter to TPT for
      consideration afresh. Vide a reasoned letter dated 25th April, 2008,
      TPT rejected the claim of SICAL. TPT has specifically observed
      that any change in the Agreement cannot be done without prior
      approval of the GoI. SICAL on 19th November, 2012 addressed a
D
      letter to TPT invoking arbitration under Article 15.3 of the License
      Agreement. TPT strenuously contested the claim of SICAL with
      regard to prayer for change from ‘royalty payment mode’ to
      ‘revenue sharing mode’. [Para 79][452-A-E]

E           7.2 It could thus be seen, that SICAL wanted the Agreement
      to be amended so as to change the ‘royalty payment method’ to
      ‘revenue-sharing method’. TPT was always opposed to it. The
      intention of TPT is apparent from its various communications
      and its stand before the Arbitral Tribunal, that it was not agreeable
F     for amendment of the Agreement from ‘royalty payment method’
      to ‘revenue-sharing method’. [Para 80][453-E-F]

             7.3 However, ignoring the stand of TPT, by the impugned
      Award, the Arbitral Tribunal has thrust upon a new term in the
      Agreement between the parties against the wishes of TPT. The
G     ‘royalty payment method’ has been totally substituted by the
      Arbitral Tribunal, with the ‘revenue-sharing method’. It is thus
      clear, that the Award has created a new contract for the parties
      by unilateral intention of SICAL as against the intention of TPT.
      [Para 81][453-G]
H
PSA SICAL TERMINALS PVT. LTD. v. THE BOARD OF TRUSTEES OF V.O.        415
            CHIDAMBRANAR PORT TRUST TUTICORIN


      Ssangyong Engineering and Construction Company                  A
      Limited v. National Highway Authority of India (NHAI)
      (2019) 15 SCC 131 : [2019] 7 SCR 522 – relied on.
      8. An Arbitral Tribunal is not a Court of law. Its orders are
not judicial orders. Its functions are not judicial functions. It
cannot exercise its powers ex debito justitiae. It has been held      B
that the jurisdiction of the arbitrator being confined to the four
corners of the agreement, he can only pass such an order which
may be the subject-matter of reference.The impugned Award
would come under the realm of ‘patent illegality’ and therefore,
has been rightly set aside by the High Court. [Paras 87, 88]
[456-A-C]                                                             C

      Bharat Coking Coal Ltd. v. Annapurna Construction
      (2003) 8 SCC 154 : [2003] 3 Suppl. SCR 122; Md.
      Army Welfare Housing Organization v. Sumangal
      Services (P) Ltd. (2004) 9 SCC 619 : [2003] 4 Suppl.
      SCR 385 – relied on.                                            D

      State of Jharkhand and Others v. HSS Integrated SDN
      and Another (2019) 9 SCC 798; Sumitomo Heavy
      Industries Limited v. Oil and Natural Gas Corporation
      Limited (2010) 11 SCC 296 : [2010] 9 SCR 176; Kwality
      Manufacturing Corporation v. Central Warehouse                  E
      Corporation (2009) 5 SCC 142; Rashtriya Ispat Nigam
      Limited v. Dewan Chand Ram Saran (2012) 5 SCC 306
      : [2012] 4 SCR 1; Steel Authority of India Limited v.
      Gupta Brother Steel Tubes Limited (2009) 10 SCC 63 :
      [2009] 14 SCR 253; Pure Helium India (P) Limited v.             F
      Oil and Natural Gas Corporation Limited (2003) 8 SCC
      593 : [2003] 4 Suppl. SCR 561; P.V. Subba Naidu and
      Others v. Government of A.P. and Others (1998) 9 SCC
      407; Dhannalal v. Kalawati Bai and Others (2002) 6
      SCC 16 : [2002] 1 Suppl. SCR 19; Swamy Atmananda
      and Others v. Shri Ramakrishna Tapovanam and Others             G
      (2005) 10 SCC 51 : [2005] 3 SCR 556; Transcore v.
      Union of India and Another (2008) 1 SCC 125 : [2006]
      9 Suppl. SCR 785; Sandvik Asia Private Limited v.
      Vardhman Promoters 2007 (94) DRJ 762; Hansalaya
                                                                      H
416          SUPREME COURT REPORTS                      [2021] 5 S.C.R.


A          Properties v. Dalmia Cement (Bharat) Limited 2008
           (106) DRJ 820; Adani Power (Mundra) Limited v.
           Gujarat Electricity Regulatory Commission and Others
           (2019) 19 SCC 9; Raghunathrao Ganpatrao v. Union
           of India (1994) 1 SCC Supp 191 : [1993] 1 SCR 480;
           Nagubai Ammal and Others v. B. Shama and Others
B
           [1956] SCR 451; Suresh Kumar Wadhwa v. State of
           Madhya Pradesh and Others (2017) 16 SCC 757 :
           [2017] 14 SCR 1; All India Power Engineer Federation
           and Others v. Sasan Power Limited and Others (2017)
           1 SCC 487 : [2016] 9 SCR 901; Rashtriya Chemicals
C          and Fertilizers Limited v. Chowgule Brothers and Others
           (2010) 8 SCC 563 : [2010] 7 SCR 962; South East
           Asia Marine Engineering and Constructions Limited v.
           Oil India Limited (2020) 5 SCC 164; J.G. Engineers
           Private Limited v. Union of India and Another (2011) 5
           SCC 758 : [2011] 8 SCR 486; Satyanarayana
D
           Construction Company v. Union of India and Others
           (2011) 15 SCC 101 – referred to.
                           Case Law Reference
      (2019) 9 SCC 798              referred to            Para 26
E     [2010] 9 SCR 176              referred to            Para 26
      (2009) 5 SCC 142              referred to            Para 26
      [2012] 4 SCR 1                referred to            Para 26
      [2009] 14 SCR 253             referred to            Para 26
F
      [2003] 4 Suppl. SCR 561       referred to            Para 26
      (1998) 9 SCC 407              referred to            Para 26
      [2002] 1 Suppl. SCR 19        referred to            Para 26
      [2005] 3 SCR 556              referred to            Para 26
G
      [2006] 9 Suppl. SCR 785       referred to            Para 26
      (2019) 19 SCC 9               referred to            Para 29
      [1993] 1 SCR 480              referred to            Para 33
      [1956] SCR 451                referred to            Para 33
H
PSA SICAL TERMINALS PVT. LTD. v. THE BOARD OF TRUSTEES OF V.O.              417
            CHIDAMBRANAR PORT TRUST TUTICORIN


[2017] 14 SCR 1                  referred to               Para 33          A
[2016] 9 SCR 901                 referred to               Para 33
[2010] 7 SCR 962                 referred to               Para 33
(2020) 5 SCC 164                 referred to               Para 33
[2011] 8 SCR 486                 referred to               Para 33          B
(2011) 15 SCC 101                referred to               Para 33
[2019] 7 SCR 522                 relied on                 Para 33
[2019] 3 SCR 1023                relied on                 Para 58
                                                                            C
[2014] 13 SCR 895                relied on                 Para 78
[2003] 3 Suppl. SCR 122          relied on                 Para 84
[2003] 4 Suppl. SCR 385          relied on                 Para 86
      CIVIL APPELLATE JURISDICTION : Civil Appeal No. 3699-
3700 of 2018.                                                               D
     From the Judgment and Order dated 01.11.2017 of the High Court
of Madras at Madurai Bench in CMA(MD) No. 345 of 2016 and C.M.P.
(MD) No. 4867 of 2016.
     Dr. A.M. Singhvi, Gopal Jain, Sr. Advs., Sonal Jain, Zerick Dastur,
                                                                            E
Ms. Sneha Sheth, Ishkaran Singh, Ms. Archana Uppuluri, Ms. Kajal
Sharma, Advs. for the appellant.
      Mrs. Madhvi Dewan, ASG, Keshav Thakur, Ayush Puri, Mahesh
Prasad, Shikhar Sardana, Ajay Singh, Babu Malayil, Rajesh Singh
Chauhan, Advs. for the respondents.
                                                                            F
      The Judgment of the Court was delivered by
      B. R. GAVAI, J.
       1. The appellant has approached this Court being aggrieved by
the judgment and order dated 1st November 2017, passed by the Division
Bench of the Madras High Court in C.M.A. (MD) No. 345 of 2016 and           G
C.M.P. (MD) No. 4867 of 2016, thereby allowing the appeal of the
respondent No.1 herein under Section 37(1)(c) of the Arbitration and
Conciliation Act, 1996 (hereinafter referred to as ‘the Arbitration Act’)
vide which the High Court set aside the award dated 14th February 2014,
passed by the Arbitral Tribunal and the order passed by the District        H
418             SUPREME COURT REPORTS                            [2021] 5 S.C.R.


A     Judge dated 25th February 2016, rejecting the application filed by the
      respondent No.1 herein under Section 34 of the Arbitration Act.
            2. The facts necessary for adjudication of the present appeals are
      as under:-
               The respondent No.1-The Board of Trustees of V.O.
B     Chidambranar Port Trust, Tuticorin (hereinafter referred to as ‘TPT’)
      issued a global tender on 9th April 1997, inviting bids for development of
      the Seventh Berth at V.O. Chidambranar Port, Tuticorin as a Container
      Terminal and for operating and maintaining the same for 30 years on a
      Build, Operate and Transfer (hereinafter referred to as ‘BOT’) basis.
C     In response to the tender, the appellant-PSA Sical Terminals Pvt. Ltd.
      (hereinafter referred to as ‘SICAL’) submitted its bid on 24th October
      1997. The financial offer was submitted by SICAL on 19th December
      1997. Since SICAL’s offer was the highest, the same was accepted and
      a Letter of Intent (hereinafter referred to as ‘LoI’) was issued to it on
      29th January 1998 and the same was followed by a License Agreement
D     dated 15th July 1998.
              3. In the meantime, the Tariff Authority for Major Ports (hereinafter
      referred to as ‘TAMP’) which is an authority constituted under the Major
      Port Trusts Act, 1963 adopted guidelines on 26th/27th February 1998.
      SICAL submitted its tariff proposal with regard to the Container Terminal
E     on 28th September 1999. A revised proposal came to be submitted by
      SICAL on 8th October 1999, thereby including royalty as an element of
      cost. The said proposal was approved by TAMP’s order dated 8 th
      December 1999. TAMP notified its order of 8th December 1999 vide
      gazette notification dated 28th December 1999, thereby approving the
F     tariff as proposed by SICAL vide proposal dated 8th October 1999.
      SICAL submitted a further proposal on 8th February 2002 for review in
      tariff, again including therein an increase in royalty to be paid as an
      element of cost and proposed for an increase in the tariff. TPT vide
      communication dated 10th April 2002, objected to the proposal of SICAL
      for increase in tariff. TAMP vide its order dated 20th September 2002,
G     rejected the proposal of SICAL for increase in tariff.
            4. SICAL filed Writ Petition Nos. 40637-40639 of 2002 before
      the Madras High Court for quashing of the TAMP order dated 20 th
      September 2002. In the said proceedings, the Madras High Court passed
      an order dated 8th November 2002 granting interim relief in favour of
H
PSA SICAL TERMINALS PVT. LTD. v. THE BOARD OF TRUSTEES OF V.O.                   419
     CHIDAMBRANAR PORT TRUST TUTICORIN [B. R. GAVAI, J.]


SICAL, thereby staying the TAMP order dated 20th September 2002.                 A
Vide the said order, SICAL was permitted to charge tariff at the rate
prevailing prior to the TAMP order impugned in those petitions.
        5. Ministry of Shipping, Government of India (hereinafter referred
to as ‘GoI’) vide notification dated 29th July 2003, clarified that revenue
sharing/royalty payment shall not be factored into as cost for fixation/         B
revision of tariff by TAMP and further directed that the same shall be
clearly indicated in subsequent bid documents. On 31st March 2005,
TAMP notified the revised guidelines thereby disallowing royalty as an
element of cost. However, it also provided that in BOT cases where
bidding processes were finalized before 29 th July 2003, the tariff
computation will take into account royalty/revenue share as cost for             C
tariff fixation in such a manner as to avoid likely loss to the operator on
account of the royalty/revenue share not being taken into account. This
was subject to a maximum of the amount quoted by the next lowest
bidder. This was also to be allowed only for the period up to which such
likely loss would arise. It further provided that this would not be applicable   D
if there is a provision in the concession agreement on treatment of royalty/
revenue share.
        6. On 17 th August 2005, a Memorandum of Compromise
(hereinafter referred to as the ‘MoC’) came to be filed before the Madras
High Court between SICAL, GoI and TAMP who were parties to the                   E
Writ Petition Nos. 40637-40639 of 2002. As per the said MoC, SICAL
was to submit a proposal to the Ministry of Shipping and Transport, GoI
in the matter of permitting royalty to be allowed to be factored into cost
while fixation of tariff for the period prior to 31st March 2005. It was
also clarified that for the period thereafter, new guidelines provide the
manner and mode in which this has to be done. The MoC provided that              F
on receipt of the proposal, the Central Government would consider the
same and pass appropriate orders consistent with the policy decision of
the Government of India (hereinafter referred to as the ‘GoI’) in the
matter of Chennai Container Terminal Limited (hereinafter referred
to as the ‘CCTL’) dated 5th August 2003 and accordingly issue a directive        G
under Section 111 of the Major Port Trusts Act, 1963. Vide the said
MoC, it was further provided that SICAL would continue to charge the
1999 Tariff which was permitted as per the interim orders passed by the
High Court till new tariff was gazetted. It further provided that
advantages/ gains, if any, that SICAL has enjoyed by virtue of not
                                                                                 H
420            SUPREME COURT REPORTS                           [2021] 5 S.C.R.


A     implementing the 2002 Tariff, will be quantified by TAMP and such
      advantages/gains will be adjusted/set-off in the proposed new tariff and
      such set-off will be spread over a period of three years.
             7. In pursuance of the aforesaid MoC, GoI issued a directive/
      order to TAMP in case of SICAL on 17th April 2006. Vide the said
B     directive/order, the request of SICAL for claiming a part of royalty as
      pass through came to be rejected. SICAL thereafter submitted its proposal
      for fixation of tariff on 18th April 2006. TAMP passed a tariff order on
      23rd August 2006, which came to be notified on 15th September 2006,
      vide which SICAL’s proposal for increase in tariff was rejected.
C            8. SICAL made a written representation to TPT on 6th October
      2006, thereby seeking relief under the terms of Article 14.3 of the License
      Agreement. Vide the said representation, SICAL requested for amending
      the License Agreement so as to incorporate the revenue sharing method
      and incidental changes.

D            9. SICAL also filed Writ Petition Nos. 38845 and 38846 of 2006
      before the Madras High Court on 9th October 2006, thereby challenging
      the GoI directive dated 17th April 2006 and the TAMP order dated 23rd
      August 2006. On 27th October 2006, TPT refused to consider SICAL’s
      application for amendment of the License Agreement on the ground that
      the issues raised were pending consideration before the Madras High
E     Court. The said communication dated 27th October 2006 came to be
      challenged by SICAL before the Madras High Court vide Writ Petition
      No.43461 of 2006. The Madras High Court passed an order dated 21 st
      August 2007, in Writ Petition No. 43461 of 2006 filed by SICAL, observing
      therein that the representation dated 6th October 2006, had nothing to do
F     with the pendency of said writ petition and quashed the communication
      dated 27th October 2006. It directed TPT to consider and decide the
      representation of SICAL on its own merits.
            10. Vide subsequent order dated 22nd August 2007, Writ Petition
      Nos. 38845 and 38846 of 2006 were allowed by setting aside the TAMP
G     order dated 23rd August 2006 and the GoI directive dated 17th April
      2006. The said order was passed on the ground that SICAL was not
      given sufficient opportunity of being heard by TAMP and GoI and
      therefore, directed TAMP and GoI to pass fresh order after giving
      opportunity of hearing to the SICAL.

H
PSA SICAL TERMINALS PVT. LTD. v. THE BOARD OF TRUSTEES OF V.O.                   421
     CHIDAMBRANAR PORT TRUST TUTICORIN [B. R. GAVAI, J.]


      11. In pursuance of the order passed by the High Court, the GoI            A
issued a directive on 20th February 2008, therein considering the
contentions raised on behalf of SICAL. The said directive provided that
TAMP, while fixing the tariff in case of SICAL, should take into
consideration the benefit given in the case of CCTL.
       12. TAMP vide notification dated 26th February 2008, notified the         B
guidelines for upfront tariff fixation for Public Private Partnership projects
at Major Ports.
       13. In pursuance of the order passed by the High Court dated 21 st
August 2007, the Chairman, TPT passed an order on 25th April 2008,
observing therein that any change in the bidding parameter is a matter of        C
policy regarding which a decision can be taken only by the GoI and in
effect, rejected the proposal of SICAL for amending the License
Agreement, so as to incorporate the revenue sharing method.
        14. SICAL thereafter submitted its proposal for fixation of tariff
thereby proposing an increase in tariff on 3rd October 2008. TAMP                D
passed tariff order dated 17th December 2008, which came to be notified
on 30th December 2008, rejecting SICAL’s proposal for increase in tariff.
SICAL thereafter again on 6th January 2009, made a representation to
TPT for amendment of the License Agreement in view of Article 14.3.
SICAL also filed Writ Petition Nos. 1350 and 1351 of 2009, challenging
the tariff order dated 17th December 2008 and the policy direction issued        E
by GoI dated 20th February 2008. The Madras High Court vide order
dated 15th October 2009 allowed those petitions by setting aside the
tariff order of 2008 and the GoI directive of 20th February 2008. Vide
the said order, the Madras High Court directed TAMP to issue fresh
tariff order after obtaining necessary proposal from SICAL and after             F
according sufficient opportunity including personal hearing to SICAL.
The GoI directive of 2008 also came to be set aside with a direction to
the GoI to consider the matter afresh after giving an opportunity of hearing
to SICAL. The said orders have been challenged by TAMP by filing
Writ Appeal No. 1845 of 2009 which is pending. It also appears that an
appeal has also been filed by SICAL which is also pending before the             G
Division Bench of the Madras High Court.
      15. SICAL thereafter addressed a letter to TPT dated 1 st
December 2009, raising therein the ground of change in law and therefore
again praying for shifting to revenue sharing model. A meeting was held
                                                                                 H
422            SUPREME COURT REPORTS                           [2021] 5 S.C.R.


A     by the Secretary, Ministry of Shipping, GoI on 28th February 2011, wherein
      the representatives of TPT and SICAL were present. It was decided in
      the said meeting that two proposals each should be submitted by SICAL
      as well as TPT. These proposals were to be considered by the Expert
      Committee.
B             16. SICAL thereafter on 28th June 2011, moved a petition under
      Section 9 of the Arbitration Act before the District Judge, Tuticorin with
      a grievance that the royalty payable for each Twenty-foot Equivalent
      Unit (hereinafter referred to as “TEU”) was scheduled to exceed the
      tariff. On 30th June 2011, District Judge, Tuticorin passed an order
      granting ad-interim stay in the Section 9 petition, thereby restraining TPT
C     from demanding or recovering any royalty at an escalated rate. In July
      2011, SICAL addressed a letter to the Chairman, TPT requesting for
      referring the dispute for arbitration under Article 15.3 of the License
      Agreement. The said request came to be rejected by the Chairman,
      TPT vide communication dated 28th September 2011.
D            17. In the meanwhile, the proposals submitted by SICAL as well
      as TPT were being considered by the Expert Committee. On 30th April
      2012, District Judge, Tuticorin passed an order thereby allowing the
      Section 9 petition filed by SICAL and made absolute the ad-interim
      injunction granted in its favour. Thereafter, there was exchange of certain
E     communications between SICAL and TPT with regard to the submission
      of performance bank guarantee at an escalated rate. In the meantime,
      TPT challenged the order of injunction granted by the District Judge by
      filing an appeal being C.M.A.(MD) No. 1131 of 2012 and the same is
      pending consideration before the Madurai Bench of the Madras High
      Court. SICAL addressed a letter dated 19th November 2012, invoking
F     arbitration clause under Article 15.3 of the License Agreement. In the
      meantime, on 8 th August 2013, TAMP issued 2013 Guidelines for
      determination of tariff for projects at Major Ports.
             18. On 5th April 2013, SICAL filed its Statement of Claim in the
      arbitration proceedings. TAMP filed its counter statement in June 2013
G     to which a statement in rejoinder came to be filed by SICAL on 28th
      June 2013. TPT filed its reply to the rejoinder in August 2013. Vide
      award dated 14th February 2014, the Arbitral Tribunal passed the award
      in favour of SICAL holding that there was a change in law and thereby
      granting reliefs as prayed for by SICAL. It directed conversion of
H     Container Terminal of TPT from royalty model to revenue share model.
PSA SICAL TERMINALS PVT. LTD. v. THE BOARD OF TRUSTEES OF V.O.                    423
     CHIDAMBRANAR PORT TRUST TUTICORIN [B. R. GAVAI, J.]


        19. The award of Arbitral Tribunal dated 14th February, 2014 came         A
to be challenged by TPT by filing a petition under Section 34 of the
Arbitration Act being OP No. 389 of 2014 before the Madras High Court.
SICAL challenged the jurisdiction of the Madras High Court to adjudicate
the petition filed under Section 34 of the Arbitration Act. There were
certain interlocutory proceedings to which reference would not be
                                                                                  B
necessary. By order dated 9th June 2015, the Madras High Court held
that the petition filed by TPT under Section 34 of the Arbitration Act
was not tenable on the ground of jurisdiction. As such TPT re-presented
its Section 34 petition on 30th June 2015, before the District Judge, Tuticorin
being Ar.O.P. No. 260 of 2015. The District Judge, Tuticorin vide order
dated 25th February 2016, dismissed the Section 34 petition filed by TPT.         C
Being aggrieved thereby, TPT filed an appeal before the Madras High
Court which came to be allowed by the order dated 1st November 2017,
vide which the award of the Arbitral Tribunal dated 14th February 2014
and the order passed by the District Court dated 25th February 2016,
came to be set aside. Being aggrieved thereby, SICAL has approached
                                                                                  D
this Court by way of the present appeals.
      20. We have heard Dr. A.M. Singhvi and Shri Gopal Jain, learned
Senior Counsel on behalf of the appellant-SICAL, Smt. Madhavi Divan,
learned Additional Solicitor General of India and Shri Keshav Thakur,
learned counsel on behalf of TPT.
                                                                                  E
        21. Dr. Singhvi submitted that Article 14 of the License Agreement
specifically provides that if after the date of the agreement, there is a
change in law which substantially and adversely affects the rights of the
Licensee under the said agreement, so as to alter the commercial viability
of the project, the Licensee may, by written notice, request amendments
to the terms of the agreement. He submitted that the definition of law in         F
Article 14 is wide enough and includes any valid act, ordinance, rule,
regulation, notification, directive, orders, policy, bye-laws, administrative
guidelines, ruling or instruction having the force of law, enacted or issued
by Government Authority. The learned Senior Counsel submitted that
Article 14.3 also provides that subject to the provisions of Article 15.3,        G
the Licensee shall not be entitled to any compensation whatsoever from
the Licensor as a result of change in law. He submitted that if Article
14.3 is read in the correct perspective, it will be clear that compensation
is not provided to the Licensee on account of any change in law inasmuch
as a relief could be provided to the Licensee by suitably amending the
                                                                                  H
424             SUPREME COURT REPORTS                            [2021] 5 S.C.R.


A     terms of the agreement when such a change substantially and adversely
      affects the rights of the Licensee. He submitted that the said Article is a
      unique one.
             22. Dr. Singhvi submitted that the Nhava Sheva Container Terminal
      Limited (hereinafter referred to as the ‘NSCT’) was the first project
B     which was built on BOT basis. The second one being the Seventh Berth
      of TPT. He submitted that these are the only projects wherein royalty
      method has been adopted. He submitted that all subsequent projects
      provide for revenue sharing model. He submitted that it will be clear
      from the stand of TPT, when the proposal was moved by SICAL for
      increase in tariff in 1999, that it also understood that the royalty was also
C     to be factored in while finalizing the tariff. He submitted that perusal of
      the tariff order dated 8th December 1999, would reveal that even TAMP
      has allowed royalty as a pass through. He submitted that the guidelines
      of 1998 would also clarify that it was a policy of TAMP that the port
      pricing was to continue to be cost based with an assured rate of return.
D     He submitted that the said guidelines provide for an assured rate of
      return. He submitted that TPT, as a matter of fact, vide communication
      dated 3rd November 1999 addressed to TAMP, had opposed any reduction
      of tariff as proposed by SICAL.
             23. Dr. Singhvi submitted that the first change in law was effected
E     vide order of the GoI dated 29th July 2003, by which no percentage of
      royalty was permitted as a pass through. The second change in law was
      effected on 31st March 2005, by which the royalty was permitted as a
      pass through, however, restricting the same to the maximum of the amount
      quoted by the next lowest bidder. He therefore submitted that on account
      of these changes in law, SICAL was entitled to get a relief of amendment
F     of the License Agreement and on failure of TPT to provide the relief,
      SICAL was entitled to invoke arbitration. He submitted that though several
      representations were made to TPT, the same had not been responded to
      and as such, SICAL was left with no alternative than to invoke the
      arbitration clause. He submitted that this has been rightly construed by
G     the Arbitral Tribunal. However, the Division Bench of the High Court
      has erroneously interfered with the finding of fact recorded by the Arbitral
      Tribunal which was upheld by the District Judge.
            24. Dr. Singhvi further submitted that SICAL has been put in a
      very precarious situation. He submitted that on one hand it is required to
H     pay royalty to TPT on the basis of annual increment, however the tariff
PSA SICAL TERMINALS PVT. LTD. v. THE BOARD OF TRUSTEES OF V.O.                     425
     CHIDAMBRANAR PORT TRUST TUTICORIN [B. R. GAVAI, J.]


which it can charge, has been so fixed so as not to allow royalty as a             A
pass through. He submitted that at one point of time in 2011, the tariff
has been so fixed that it surpasses the amount of royalty per TEU, SICAL
would be required to pay to TPT. He submitted that if the same is
permitted, SICAL would not be in a position to continue its operations.
He submitted that SICAL has provided a minimum guarantee to lift a
                                                                                   B
minimum of 4.5 lakh tons of cargo. He submitted that this has been
rightly appreciated by the Arbitral Tribunal wherein it has observed that
if such a position is permitted to continue, it will substantially and adversely
affect SICAL. He submitted that a chart at Page No. 1132 shows that
SICAL would incur a gross loss of Rs. 2250 crores. He further submitted
that TAMP and the GoI have acted in a discriminatory manner. He                    C
submitted that when in case of NSCT, a complete pass through so far as
royalty is concerned, is permitted, the same is denied in case of SICAL.
        25. Dr. Singhvi further submitted that the High Court has grossly
erred in referring to the writ petitions and the MoC filed in one of the
writ petitions, while setting aside the award. He submitted that the writ          D
petitions filed by SICAL were basically against TAMP and with regard
to the fixation of tariff. However, the arbitration proceedings were about
the change in law which changed the policy of permitting pass through
of royalty to denial of pass through of royalty. Whereas the proceedings
before TAMP are pertaining to fixation of tariff. He further submits that
the proceedings before the High Court pertain to the period prior to               E
2013, whereas the present proceedings pertain to the relief to which
SICAL is entitled under Article 14 of the agreement on account of change
in law. He submitted that SICAL was compelled to approach the
arbitrator since in 2011-12, the royalty payable to TPT crossed the tariff.
He submitted that the contention considered by the High Court with                 F
regard to the MoC was only an oral argument made by TPT and not
part of the pleadings.
       26. Dr. Singhvi submitted that the scope of interference in an
application under Section 34 and in an appeal filed under Section 37 is
very limited. He submitted that unless a finding recorded by the arbitrator        G
amounts to perversity, an interference would not be warranted either
under Section 34 or Section 37. He submitted that the District Judge had
rightly rejected the Section 34 Application. He further submitted that it
was erroneous on part of the High Court in exercise of its jurisdiction
under Section 37 to interfere with a well-reasoned award of the Arbitral
                                                                                   H
426             SUPREME COURT REPORTS                          [2021] 5 S.C.R.


A     Tribunal. He relies on the following judgments in support of his
      submissions:-
            MMTC Limited v. Vedanta Limited 1, Associate Builders v.
      Delhi Development Authority2, State of Jharkhand and Others v.
      HSS Integrated SDN and Another3, Sumitomo Heavy Industries
B     Limited v. Oil and Natural Gas Corporation Limited 4, Kwality
      Manufacturing Corporation v. Central Warehouse Corporation5,
      Rashtriya Ispat Nigam Limited v. Dewan Chand Ram Saran6, Steel
      Authority of India Limited v. Gupta Brother Steel Tubes Limited 7,
      Pure Helium India (P) Limited v. Oil and Natural Gas Corporation
      Limited8, P.V. Subba Naidu and Others v. Government of A.P. and
C     Others 9 , Dhannalal v. Kalawati Bai and Others 10 , Swamy
      Atmananda and Others v. Shri Ramakrishna Tapovanam and
      Others11 and Transcore v. Union of India and Another12.
              27. Dr. Singhvi submitted that the UNIDROIT Principles of
      International Commercial Contracts provide the rules of interpretation
D     of contracts. He submitted that the said principles provide that a contract
      shall be interpreted according to the common intention of the parties. It
      is only when the intention cannot be established that the contract shall
      be interpreted according to the meaning that a reasonable person of the
      same kind as a party, would give it in the same circumstances. He
E     submitted that from the perusal of Article 14 as well as the conduct of
      the parties, it is clear that the parties intended that if there was any
      change in lawto the detriment of the Licensee, the Licensee was entitled
      to relief from the Licensor by amendment of the contract. He submitted
      that such intention is clarified from the fact that in such an event, the
      Licensee was not entitled to claim any compensation. The learned Senior
F     Counsel in this respect relies on the judgments of the Delhi High Court
      1
        (2019) 4 SCC 163
      2
        (2015) 3 SCC 49
      3
        (2019) 9 SCC 798
      4
        (2010) 11 SCC 296
      5
        (2009) 5 SCC 142
G     6
        (2012) 5 SCC 306
      7
        (2009) 10 SCC 63
      8
        (2003) 8 SCC 593
      9
        (1998) 9 SCC 407
      10
         (2002) 6 SCC 16
      11
         (2005) 10 SCC 51
      12
H        (2008) 1 SCC 125
PSA SICAL TERMINALS PVT. LTD. v. THE BOARD OF TRUSTEES OF V.O.                 427
     CHIDAMBRANAR PORT TRUST TUTICORIN [B. R. GAVAI, J.]


in Sandvik Asia Private Limited v. Vardhman Promoters 13and                    A
Hansalaya Properties v. Dalmia Cement (Bharat) Limited14.
        28. Dr. Singhvi further submitted that the agreement has to be
read as a whole. In his submission, whereas Articles 10.8, 13.4.7 and
13.4.8 make the Licensor’s decision binding, Article 14 does not provide
it. He submitted that Article 14 is unique in the sense that it provides for   B
restoration of equilibrium. He submitted that the Tribunal had two choices
either to grant a pass through or revenue sharing. If it has chosen one of
them, then even if it is considered to be a possible view, an interference
therein was not warranted.
       29. Shri Gopal Jain, learned Senior Counsel submitted that economic     C
viability for long term contracts has to be provided. He submitted that
Article 14 was provided as an in-built safeguard for the said purpose.
Relying on the judgment of this Court in Adani Power (Mundra) Limited
v. Gujarat Electricity Regulatory Commission and Others 15, he
submitted that while construing business contracts, business efficacy is
a relevant consideration which has been considered by the Arbitral             D
Tribunal and as such, an interference would not be warranted.
       30. Smt. Divan, the learned ASG submitted that the financial offer
made by SICAL was made on 19th December 1997 i.e. much before the
1998 Guidelines came to be published. She submitted that it is unthinkable
that the rates quoted by SICAL in 1997 were on the basis of the guidelines     E
which were for the first time published in the year 1998. She submitted
that even the said guidelines do not provide for permitting royalty as a
pass through. It is further submitted that while submitting the bid, SICAL
has submitted the bid on the basis of royalty payable to TPT during the
concession period.                                                             F
       31. Smt. Divan further submitted that SICAL has indulged into
the conduct of approbate and reprobate. She submitted that whereas in
the writ petitions filed by it, SICAL has taken a specific stand that the
guidelines do not have the force of law, it has now turned around and
taken a stand in the arbitration proceedings that it amounts to change of      G
law. She further submitted that on the date on which the arbitration
proceedings were commenced, the tariff orders were already quashed
in the writ proceedings in favour of SICAL and only with a view to take
13
   2007 (94) DRJ 762
14
   2008 (106) DRJ 820
15
   (2019) 19 SCC 9                                                             H
428             SUPREME COURT REPORTS                            [2021] 5 S.C.R.


A     double advantage, SICAL has initiated arbitration proceedings. She
      further submitted that because of the interim order passed by the High
      Court, the 1999 tariff order is still holding the field,thereby giving a huge
      undue benefit to SICAL. She submitted that even the conduct of SICAL
      needs to be taken into consideration. Though as per MoC which was
      filed way back in 2005, SICAL was required to compensate TPT, it has
B
      not done so. She therefore submitted that on one hand, SICAL is taking
      advantage of orders of the Court and on the other hand not complying
      with the obligations set out in the MoC, on the basis of which the High
      Court has disposed of writ petition.
             32. Smt. Divan submitted that even the third tariff order passed in
C     case of SICAL had been quashed by the Madras High Court, challenge
      to which is pending before the Division Bench. She further submitted
      that on account of an order passed in Section 9 proceedings, TPT is
      getting a very meagre amount from SICAL.
             33. Smt. Divan further submitted that by the award, the Tribunal
D     has provided for entire substitution of the terms of the contract between
      the parties. She submitted that when the agreement between the parties
      was based on royalty method, the Tribunal, by a substitution, has provided
      for revenue sharing method. She submitted that this is not permissible at
      all in law. A party cannot be thrusted with a new contract against its
E     wishes. Smt. Divan further submitted that SICAL having elected/availed
      the remedies of filing of the writ petition, cannot for the same relief
      under the bogey of so-called change in law, invoke arbitration proceedings.
      She therefore submitted that the High Court has rightly considered the
      same and set aside the award. Smt. Divan relied on the following
      judgments of this Court in support of her submissions.
F
           Raghunathrao Ganpatrao v. Union of India 16, Nagubai
      Ammal and Others v. B. Shama and Others 17, Suresh Kumar
      Wadhwa v. State of Madhya Pradesh and Others18, All India Power
      Engineer Federation and Others v. Sasan Power Limited and
      Others19, Rashtriya Chemicals and Fertilizers Limited v. Chowgule
G     Brothers and Others20, South East Asia Marine Engineering and
      16
         (1994) 1 SCC Supp 191
      17
         [1956] SCR 451
      18
         (2017) 16 SCC 757
      19
         (2017) 1 SCC 487
      20
H        (2010) 8 SCC 563
PSA SICAL TERMINALS PVT. LTD. v. THE BOARD OF TRUSTEES OF V.O.                429
     CHIDAMBRANAR PORT TRUST TUTICORIN [B. R. GAVAI, J.]


Constructions Limited v. Oil India Limited21, J.G. Engineers Private          A
Limited v. Union of India and Another 22 , Satyanarayana
Construction Company v. Union of India and Others23, Ssangyong
Engineering and Construction Company Limited v. National
Highway Authority of India (NHAI)24
       34. Dr. Singhvi, in rejoinder, submitted that a stray statement made   B
by SICAL that the guidelines do not have the force of law, would not be
relevant. Inasmuch as in the counter filed by TPT as well as TAMP,
they have themselves stated before the High Court that the said guidelines
will have the force of law. He therefore submitted that SICAL was
entitled in law to invoke Article 14 since there was a change in law
which adversely affects the Licensee.                                         C

       35. Dr. Singhvi further submitted that the contention of Smt. Divan
that reliance has been placed by SICAL on change of law for the first
time in 2013, is factually incorrect inasmuch as right from 2006, SICAL
has been making representations to TPT for giving relief under Article
14. To counter the submission of Smt. Divan that the bid of SICAL was         D
tendered in December 1997, he submitted that though the bid was tendered
in December 1997, the agreement was entered into in July 1998, when
the guidelines had already come into effect from February 1998. He
submitted that the perusal of the proposals submitted by TPT in pursuance
of the meeting held by Secretary, Ministry of Shipping and Transport,         E
GoI, would show that TPT as well as its consultant had agreed for
revenue share model. He reiterated that the proceedings before the High
Court were restricted only to TAMP orders and had nothing to do with
change of law. He submitted that none of the case laws cited by Smt.
Divan considers a clause analogous to Article 14 and therefore, the said
cases would not be applicable to the facts of the present case. He further    F
submitted that the argument with regard to doctrine of election is also
without substance.
       36. With the assistance of the learned counsel for the parties, we
have gone through the documents placed on record. Though various
judgments of this Court as well as some of the High Courts have been          G
cited by counsel of both the parties, we do not find it necessary to refer
21
   (2020) 5 SCC 164
22
   (2011) 5 SCC 758
23
   (2011) 15 SCC 101
24
   (2019) 15 SCC 131                                                          H
430                SUPREME COURT REPORTS                          [2021] 5 S.C.R.


A     to all of them. In our view, a reference to few recent judgments of this
      Court will be sufficient.
              37. A bench of this Court, of which one of us (R.F. Nariman, J.)
      was a party, has considered various judgments of this Court in the case
      of Associate Builders (supra).
B             38. Another bench of this Court, again to which one of us (R.F.
      Nariman, J.) was a party, has considered various judgments of this Court
      including the judgment in Associate Builders (supra)and the effect of
      the Arbitration and Conciliation (Amendment) Act, 2015 in the case of
      Ssangyong Engineering and Construction Company Limited v.
      National Highways Authority of India (NHAI)25, to which we will
C     refer shortly.
              39. Before that, it will be apposite to refer to judgment of this
      Court in the case of MMTC Limited (supra),wherein this Court has
      revisited the position of law with regard to scope of interference with an
      arbitral award in India.
D             40. It will be relevant to refer to the following observations of this
      Court in the case of MMTC Limited (supra):
              “11. As far as Section 34 is concerned, the position is well-settled
              by now that the Court does not sit in appeal over the arbitral
              award and may interfere on merits on the limited ground provided
E             under Section 34(2)(b)(ii) i.e., if the award is against the public
              policy of India. As per the legal position clarified through decisions
              of this Court prior to the amendments to the 1996 Act in 2015, a
              violation of Indian public policy, in turn, includes a violation of the
              fundamental policy of Indian law, a violation of the interest of
              India, conflict with justice or morality, and the existence of patent
F
              illegality in the arbitral award. Additionally, the concept of the
              “fundamental policy of Indian law” would cover compliance with
              statutes and judicial precedents, adopting a judicial approach,
              compliance with the principles of natural justice,
              and Wednesbury [Associated                  Provincial        Picture
G             Houses v. Wednesbury Corpn., (1948) 1 KB 223 (CA)]
              reasonableness. Furthermore, “patent illegality” itself has been
              held to mean contravention of the substantive law of India,
              contravention of the 1996 Act, and contravention of the terms of
              the contract.
      25
H          (2019) 15 SCC 131
PSA SICAL TERMINALS PVT. LTD. v. THE BOARD OF TRUSTEES OF V.O.                  431
     CHIDAMBRANAR PORT TRUST TUTICORIN [B. R. GAVAI, J.]


     12. It is only if one of these conditions is met that the Court may        A
     interfere with an arbitral award in terms of Section 34(2)(b)(ii),
     but such interference does not entail a review of the merits of the
     dispute, and is limited to situations where the findings of the
     arbitrator are arbitrary, capricious or perverse, or when the
     conscience of the Court is shocked, or when the illegality is not
                                                                                B
     trivial but goes to the root of the matter. An arbitral award may
     not be interfered with if the view taken by the arbitrator is a possible
     view based on facts. (See Associate Builders v. DDA [Associate
     Builders v. DDA, (2015) 3 SCC 49 : (2015) 2 SCC (Civ) 204] .
     Also see ONGC Ltd. v. Saw Pipes Ltd. [ONGC Ltd. v. Saw Pipes
     Ltd., (2003) 5 SCC 705] ; Hindustan Zinc Ltd. v. Friends Coal              C
     Carbonisation [Hindustan Zinc Ltd. v. Friends Coal
     Carbonisation, (2006) 4 SCC 445] ; and McDermott
     International Inc. v. Burn Standard Co. Ltd. [McDermott
     International Inc. v. Burn Standard Co. Ltd., (2006) 11 SCC
     181] )
                                                                                D
     13. It is relevant to note that after the 2015 Amendment to Section
     34, the above position stands somewhat modified. Pursuant to the
     insertion of Explanation 1 to Section 34(2), the scope of
     contravention of Indian public policy has been modified to the
     extent that it now means fraud or corruption in the making of the
     award, violation of Section 75 or Section 81 of the Act,                   E
     contravention of the fundamental policy of Indian law, and conflict
     with the most basic notions of justice or morality. Additionally,
     sub-section (2-A) has been inserted in Section 34, which provides
     that in case of domestic arbitrations, violation of Indian public
     policy also includes patent illegality appearing on the face of the        F
     award. The proviso to the same states that an award shall not be
     set aside merely on the ground of an erroneous application of the
     law or by reappreciation of evidence.
     14. As far as interference with an order made under Section 34,
     as per Section 37, is concerned, it cannot be disputed that such           G
     interference under Section 37 cannot travel beyond the restrictions
     laid down under Section 34. In other words, the court cannot
     undertake an independent assessment of the merits of the award,
     and must only ascertain that the exercise of power by the court
     under Section 34 has not exceeded the scope of the provision.
                                                                                H
432            SUPREME COURT REPORTS                            [2021] 5 S.C.R.


A           Thus, it is evident that in case an arbitral award has been confirmed
            by the court under Section 34 and by the court in an appeal under
            Section 37, this Court must be extremely cautious and slow to
            disturb such concurrent findings.”
             41. In Ssangyong Engineering and Construction Company
B     Limited (supra), this Court after considering various judgments including
      the judgment in Associate Builders (supra) observed thus:
            “34. What is clear, therefore, is that the expression “public policy
            of India”, whether contained in Section 34 or in Section 48, would
            now mean the “fundamental policy of Indian law” as explained in
C           paras 18 and 27 of Associate Builders [Associate
            Builders v. DDA, (2015) 3 SCC 49 : (2015) 2 SCC (Civ) 204] i.e.
            the fundamental policy of Indian law would be relegated to
            “Renusagar” understanding of this expression. This would
            necessarily mean that Western Geco [ONGC v. Western Geco
            International Ltd., (2014) 9 SCC 263 : (2014) 5 SCC (Civ) 12]
D
            expansion has been done away with. In short, Western
            Geco [ONGC v. Western Geco International Ltd., (2014) 9 SCC
            263 : (2014) 5 SCC (Civ) 12] , as explained in paras 28 and 29
            of Associate Builders [Associate Builders v. DDA, (2015) 3 SCC
            49 : (2015) 2 SCC (Civ) 204] , would no longer obtain, as under
E           the guise of interfering with an award on the ground that the
            arbitrator has not adopted a judicial approach, the Court’s
            intervention would be on the merits of the award, which cannot
            be permitted post amendment. However, insofar as principles of
            natural justice are concerned, as contained in Sections 18 and
            34(2)(a)(iii) of the 1996 Act, these continue to be grounds of
F
            challenge of an award, as is contained in para 30 of Associate
            Builders [Associate Builders v. DDA, (2015) 3 SCC 49 : (2015)
            2 SCC (Civ) 204] .
            35. It is important to notice that the ground for interference insofar
            as it concerns “interest of India” has since been deleted, and
G           therefore, no longer obtains. Equally, the ground for interference
            on the basis that the award is in conflict with justice or morality is
            now to be understood as a conflict with the “most basic notions of
            morality or justice”. This again would be in line with paras 36 to
            39 of Associate Builders [Associate Builders v. DDA, (2015) 3
H           SCC 49 : (2015) 2 SCC (Civ) 204] , as it is only such arbitral
PSA SICAL TERMINALS PVT. LTD. v. THE BOARD OF TRUSTEES OF V.O.                  433
     CHIDAMBRANAR PORT TRUST TUTICORIN [B. R. GAVAI, J.]


     awards that shock the conscience of the court that can be set              A
     aside on this ground.
     36. Thus, it is clear that public policy of India is now constricted
     to mean firstly, that a domestic award is contrary to the
     fundamental policy of Indian law, as understood in paras 18 and
     27 of Associate Builders [Associate Builders v. DDA, (2015) 3              B
     SCC 49: (2015) 2 SCC (Civ) 204], or secondly, that such award is
     against basic notions of justice or morality as understood in paras
     36 to 39 of Associate Builders [Associate Builders v. DDA,
     (2015) 3 SCC 49 : (2015) 2 SCC (Civ) 204] . Explanation 2 to
     Section 34(2)(b)(ii) and Explanation 2 to Section 48(2)(b)(ii) was
     added by the Amendment Act only so that Western                            C
     Geco [ONGC v. Western Geco International Ltd., (2014) 9 SCC
     263: (2014) 5 SCC (Civ) 12], as understood in Associate
     Builders [Associate Builders v. DDA, (2015) 3 SCC 49: (2015)
     2 SCC (Civ) 204], and paras 28 and 29 in particular, is now done
     away with.                                                                 D
     37. Insofar as domestic awards made in India are concerned, an
     additional ground is now available under sub-section (2-A), added
     by the Amendment Act, 2015, to Section 34. Here, there must be
     patent illegality appearing on the face of the award, which refers
     to such illegality as goes to the root of the matter but which does        E
     not amount to mere erroneous application of the law. In short,
     what is not subsumed within “the fundamental policy of Indian
     law”, namely, the contravention of a statute not linked to public
     policy or public interest, cannot be brought in by the backdoor
     when it comes to setting aside an award on the ground of patent
     illegality.                                                                F

     40. The change made in Section 28(3) by the Amendment Act
     really follows what is stated in paras 42.3 to 45 in Associate
     Builders [Associate Builders v. DDA, (2015) 3 SCC 49: (2015)
     2 SCC (Civ) 204], namely, that the construction of the terms of a
     contract is primarily for an arbitrator to decide, unless the arbitrator   G
     construes the contract in a manner that no fair-minded or
     reasonable person would; in short, that the arbitrator’s view is not
     even a possible view to take. Also, if the arbitrator wanders outside
     the contract and deals with matters not allotted to him, he commits
                                                                                H
434             SUPREME COURT REPORTS                            [2021] 5 S.C.R.


A           an error of jurisdiction. This ground of challenge will now fall
            within the new ground added under Section 34(2-A).
            38. Secondly, it is also made clear that reappreciation of evidence,
            which is what an appellate court is permitted to do, cannot be
            permitted under the ground of patent illegality appearing on the
B           face of the award.
            39. To elucidate, para 42.1 of Associate Builders [Associate
            Builders v. DDA, (2015) 3 SCC 49: (2015) 2 SCC (Civ) 204],
            namely, a mere contravention of the substantive law of India, by
            itself, is no longer a ground available to set aside an arbitral award.
C           Para 42.2 of Associate Builders [Associate Builders v. DDA,
            (2015) 3 SCC 49: (2015) 2 SCC (Civ) 204], however, would remain,
            for if an arbitrator gives no reasons for an award and contravenes
            Section 31(3) of the 1996 Act, that would certainly amount to a
            patent illegality on the face of the award.

D           41. What is important to note is that a decision which is perverse,
            as understood in paras 31 and 32 of Associate
            Builders [Associate Builders v. DDA, (2015) 3 SCC 49: (2015)
            2 SCC (Civ) 204], while no longer being a ground for challenge
            under “public policy of India”, would certainly amount to a patent
            illegality appearing on the face of the award. Thus, a finding based
E           on no evidence at all or an award which ignores vital evidence in
            arriving at its decision would be perverse and liable to be set aside
            on the ground of patent illegality. Additionally, a finding based on
            documents taken behind the back of the parties by the arbitrator
            would also qualify as a decision based on no evidence inasmuch
F           as such decision is not based on evidence led by the parties, and
            therefore, would also have to be characterised as perverse.
            42. Given the fact that the amended Act will now apply, and that
            the “patent illegality” ground for setting aside arbitral awards in
            international commercial arbitrations will not apply, it is necessary
G           to advert to the grounds contained in Sections 34(2)(a)(iii) and
            (iv) as applicable to the facts of the present case.”
             42. It will thus appear to be a more than settled legal position, that
      in an application under Section 34, the court is not expected to act as an
      appellate court and reappreciate the evidence. The scope of interference
      would be limited to grounds provided under Section 34 of the Arbitration
H
PSA SICAL TERMINALS PVT. LTD. v. THE BOARD OF TRUSTEES OF V.O.                   435
     CHIDAMBRANAR PORT TRUST TUTICORIN [B. R. GAVAI, J.]


Act. The interference would be so warranted when the award is in                 A
violation of “public policy of India”, which has been held to mean “the
fundamental policy of Indian law”. A judicial intervention on account of
interfering on the merits of the award would not be permissible. However,
the principles of natural justice as contained in Section 18 and 34(2)(a)(iii)
of the Arbitration Act would continue to be the grounds of challenge of
                                                                                 B
an award. The ground for interference on the basis that the award is in
conflict with justice or morality is now to be understood as a conflict
with the “most basic notions of morality or justice”. It is only such arbitral
awards that shock the conscience of the court, that can be set aside on
the said ground. An award would be set aside on the ground of patent
illegality appearing on the face of the award and as such, which goes to         C
the roots of the matter. However, an illegality with regard to a mere
erroneous application of law would not be a ground for interference.
Equally, reappreciation of evidence would not be permissible on the ground
of patent illegality appearing on the face of the award.
       43. A decision which is perverse, though would not be a ground            D
for challenge under “public policy of India”, would certainly amount to a
patent illegality appearing on the face of the award. However, a finding
based on no evidence at all or an award which ignores vital evidence in
arriving at its decision would be perverse and liable to be set aside on the
ground of patent illegality.
                                                                                 E
       44. To understand the test of perversity, it will also be appropriate
to refer to paragraph 31 and 32 from the judgment of this Court in
Associate Builders (supra), which read thus:
       “31. The third juristic principle is that a decision which is perverse
       or so irrational that no reasonable person would have arrived at          F
       the same is important and requires some degree of explanation. It
       is settled law that where:
       (i) a finding is based on no evidence, or
       (ii) an Arbitral Tribunal takes into account something irrelevant to
       the decision which it arrives at; or                                      G
       (iii) ignores vital evidence in arriving at its decision,
       such decision would necessarily be perverse.
       32. A good working test of perversity is contained in two
       judgments. In Excise and Taxation Officer-cum-Assessing                   H
436            SUPREME COURT REPORTS                            [2021] 5 S.C.R.


A           Authority v. Gopi Nath & Sons [1992 Supp (2) SCC 312], it was
            held: (SCC p. 317, para 7)
            “7. … It is, no doubt, true that if a finding of fact is arrived at by
            ignoring or excluding relevant material or by taking into
            consideration irrelevant material or if the finding so outrageously
B           defies logic as to suffer from the vice of irrationality incurring the
            blame of being perverse, then, the finding is rendered infirm in
            law.”
            In Kuldeep Singh v. Commr. of Police [(1999) 2 SCC 10: 1999
            SCC (L&S) 429], it was held: (SCC p. 14, para 10)
C           “10. A broad distinction has, therefore, to be maintained between
            the decisions which are perverse and those which are not. If a
            decision is arrived at on no evidence or evidence which is
            thoroughly unreliable and no reasonable person would act upon it,
            the order would be perverse. But if there is some evidence on
D           record which is acceptable and which could be relied upon,
            howsoever compendious it may be, the conclusions would not be
            treated as perverse and the findings would not be interfered with.”
            45. Keeping these principles in mind, we will have to examine the
      present case.
E            46. The facts in the present case are not in much dispute. It will
      be relevant to refer to clause 5.6 of the bid document, which was published
      by TPT on 9th April, 1997, which reads thus:
            “5.6 TERMS OF THE FINANCIAL OFFER
            The license to develop the seventh berth as a full-fledged container
F
            terminal with ship to shore and shore to ship handling facility,
            manage, operate and maintain the terminal shall be given for a
            period of 30 years inclusive of construction period.
            The bidder shall state his financial offer to the TPT as the sum of
            the following components:
G
            a) Quantum of initial payment at the time of executing the contract
            in order to secure the agreement;
            b) Royalty fee payable (before the day of each calendar month)
            after the commissioning of the terminal for each TEU handled at
H           the terminal in the preceding calendar month. In case actual
PSA SICAL TERMINALS PVT. LTD. v. THE BOARD OF TRUSTEES OF V.O.                437
     CHIDAMBRANAR PORT TRUST TUTICORIN [B. R. GAVAI, J.]


      throughput falls below the minimum throughput guaranteed by             A
      the Licensee in his bid, then the Licensee shall pay royalty as per
      his minimum guaranteed throughput.
      (The operator shall pay to the port royalty fee in the same currency
      in which charges are realised from users. The exchange rate to
      be used would be notified rate on the date of realisation).             B
      c) Guaranteed minimum TEU throughput that will be handled in
      each year of the contract.
      The offer shall be in the format shown in Attachment 4.1.”
       47. Perusal of the bid document would reveal, that the bid was for     C
a license to develop the seventh berth as a full-fledged container terminal
with ship-to-shore and shore-to-ship handling facility and also to manage,
operate and maintain the same for a period of 30 years inclusive of
construction period. The bidder was to state his financial offer to TPT
comprising of three aspects:
                                                                              D
      (a)    quantum of initial payment at the time of executing the
             contract in order to secure the agreement;
      (b)    royalty fee payable (before the day of each calendar month)
             after the commissioning of the terminal for each TEU
             handled at the terminal in the preceding calendar month. It
                                                                              E
             is also clear, that in case actual throughput falls below the
             minimum throughput guaranteed by the Licensee in his bid,
             then the Licensee shall pay royalty as per his minimum
             guaranteed throughput. It also clarifies, that royalty was to
             be paid in the same currency in which the Licensee realizes
             the charges from users; and                                      F
      (c)    guaranteed minimum TEU throughput that will be handled
             in each year of the contract.
       48. It will also be necessary to refer to clause 4.7.1 and 4.7.2 of
the bid document, which reads thus:
                                                                              G
      “4.7.1 SETTING OF PRICES
      The prescribed rates and charges to be collected by the LICENSEE
      from users shall not exceed the maximum rates as approved by
      the Government/Tariff Regulatory Authority. The proposed rates
      for handling are given in Annexure II.                                  H
438             SUPREME COURT REPORTS                           [2021] 5 S.C.R.


A           The LICENSEE shall bill the users of the container terminal for
            services including terminal charges, wharfage on cargo
            containerised, container box and cargo related charges to be
            collected by the LICENSEE. These revenues shall be collected
            from cargo interests and the owners or agents of the vessels and
            shall accrue to and be payable to the LICENSEE. Charges on
B
            account of Berth Hire, Port Dues, Pilotage etc shall be raised and
            recovered directly by TPT from the users.
            4.7.2 REGULATION & REVIEW
            Normally the tariff will be revised by the Government/Tariff
C           Regulatory Authority once in 3 years.
            For any increase from prevailing scales, the LICENSEE may apply
            for revision of tariff to the Licensor. The Licensor may recommend
            it for approval of the Committee constituted by the Government/
            Tariff Regulatory Authority.”
D            It would thus be clear, that the bid document itself provides, that
      the prescribed rates and charges to be collected by the Licensee from
      users shall not exceed the maximum rates as approved by the
      Government/Tariff Regulatory Authority. The proposed rates for handling
      were prescribed in Annexure-II of the bid document. It is also provided,
E     that the tariff will be revised by the Government/Tariff Regulatory
      Authority once in three years. It is further provided, that for any increase
      from prevailing scales, the Licensee may apply for revision of tariff to
      the Licensor and that the Licensor may recommend it for approval of
      the Committee constituted by the Government/Tariff Regulatory Authority.

F            49. It will be relevant to note that the offer was required to be in
      the format shown in Attachment 4.1 (Bidders Financial Offer),which
      requires to give details in three columns. The first one being ‘Traffic
      guaranteed from the Seventh Berth (in TEUS)’. The second being ‘Rate
      of royalty/TEU’; and the third being ‘Amount (Rupees)’. These details
      were to be provided for all 30 years. It will also be relevant to refer to
G     Attachment 4.4, which reads thus:
            “All Responsive Bids which meet the Qualification criteria laid
            down for the technical evaluation will be ranked based on the
            present value of the expected payments to the TPT by the Bidder
            (discounted @ 16% per annum) according to the payment schedule
H           presented in the financial proposal in Attachment 4.1. The
PSA SICAL TERMINALS PVT. LTD. v. THE BOARD OF TRUSTEES OF V.O.                    439
     CHIDAMBRANAR PORT TRUST TUTICORIN [B. R. GAVAI, J.]


      calculation of the royalty fees will be based on the Licensee’s             A
      minimum guaranteed volume of traffic.
      If, in the opinion of TPT, the prices quoted in a bid including royalties
      and schedule of royalties are found to be unrealistic, then such bid
      will be rejected and not considered for ranking.”
      50. Attachment 4.4 makes it amply clear, that all responsive bids           B
which meet the qualification criteria for technical evaluation will be ranked
on the basis of the royalty fees quoted by the bidder.
      51. It will also be relevant to refer to Article 7.3.1 and 7.3.5.1 of
the Agreement, which read thus:
                                                                                  C
      “7.3.1     Setting Prices
      The Licensee shall be entitled to recover from the owners/
      consignees or vessel owners/agents rates and/or charges due and
      payable by them for use of the Container Terminal services
      including terminal charges, wharfage on cargo containerised,                D
      container box and cargo related charges in respect of cargo and
      other services provided by the Licensee provided however that
      the rates and/or charges to be collected by the Licensee shall not
      exceed the rates fixed by Licensor in respect of similar services
      and duly notified by the GoI in official gazette or to be fixed by the
      Tariff Authority for Major Ports constituted under Article 47A of           E
      the Major Port Trusts Act, 1963, as applicable, from time to time.
      For the purpose of fixing or revising existing Tariff, the GoI has
      set up an independent Tariff Authority for Major Ports constituted
      under Article 47A of the Major Port Trusts Act, 1963. The Tariff
      to be fixed by such authority would be the maximum rate of tariff           F
      and the Licensee would be free to fix the tariff at a rate lower
      than that fixed by such authority. Regarding fixation of tariff and
      setting prices, the Licensee shall follow the rules and regulations
      stipulated by TAMP for fixing/review of tariff.
      These charges shall be collected from cargo interests and the
                                                                                  G
      owners or agents of the vessels and shall accrue to and be payable
      to the Licensee. The rates prevailing at the time of signing this
      Agreement are contained in Appendix 15 to this Agreement.
      Charges on account of Berth Hire, Port Dues and Pilotage shall
      be raised and recovered directly by the Licensor from the users.
                                                                                  H
440      SUPREME COURT REPORTS                         [2021] 5 S.C.R.


A     The Licensee shall be free to give discounts in tariff. However,
      such discounts shall be given by the Licensee only in respect to
      the charges due and payable by the consignees/owners or vessel
      owners/agents to the Licensee and not in respect of the charges
      payable by such persons directly to the Licensor.
B     xxx xxx xxx
      7.3.5 Payment and Payment Terms
      7.3.5.1 Initial Payment
      In consideration of the grant of this License, the Licensee shall
C     pay to the Licensor an initial amount of Rs.45 million (Rupees
      Forty Five Millions only) simultaneously on the Date of Award of
      License.
      The Licensee shall pay to the Licensor, royalty calculated on the
      basis of Minimum guaranteed traffic royalty rates, as set out in
D     Appendix 12 irrespective of discounts in tariffs, if any, that may
      be granted by the Licensee. Royalty shall be paid every Month on
      the basis of annual minimum guaranteed traffic as set out in
      Appendix 12. Monthly royalty shall be initially calculated
      proportionately to the yearly royalty based on the annual minimum
      guaranteed traffic as per the Appendix 12 and shall be paid latest
E     by the 7th Day of the subsequent Month. At the end of each 3
      Month period the total royalty payable shall be computed and the
      difference, if any, between the amount of royalty actually payable,
      calculated on the basis of actual TEUs handled and the
      corresponding amount as set out in the Appendix 12, and the amount
F     of royalty already remitted, shall be paid by the Licensee to the
      Licensor within fifteen Days of expiry of the relevant 3 Months
      period.
      In case the actual traffic falls below the annual minimum
      guaranteed traffic as guaranteed by the Licensee and as set out
      in the Appendix l2, then the Licensee shall pay the amount of
G
      royalty as per its annual minimum guaranteed traffic.
      It is to be noted that the minimum guaranteed traffic royalty rate
      as set out in Appendix 12 will be adjusted upwards or downwards
      as a one time measure on fixation of tariff for containers by the
      TAMP for the first time. This adjustment will be carried out by
H
PSA SICAL TERMINALS PVT. LTD. v. THE BOARD OF TRUSTEES OF V.O.                441
     CHIDAMBRANAR PORT TRUST TUTICORIN [B. R. GAVAI, J.]


      the Port based on a single percentage (plus or minus) to be applied     A
      to all the figures quoted as royalty vide Appendix 12. This single
      percentage shall be decided on the basis of sum of weighted
      average of variations to the rates in respect of tariff or containers
      in the following manner...”
        52. Perusal of Article 7.3.1 would reveal, that the Licensee was      B
entitled to recover from owners/consignees or vessel owners/agents,
rates and/or charges due and payable by them for use of Container
Terminal services including terminal charges, wharfage on cargo
containerized, container box and cargo related charges in respect of
cargo and other services provided by the Licensee. However, it was
provided, that the rates and/or charges to be collected by the Licensee       C
shall not exceed the rates fixed by Licensor in respect of similar services
and duly notified by the GoI in official gazette or to be fixed by TAMP
constituted under Section 47A of the Major Port Trusts Act, 1963. The
Agreement itself clarifies, that the tariff to be fixed by TAMP should be
the maximum rate of tariff and the Licensee would be free to fix the          D
tariff at a rate lower than that fixed by such authority. It is also clear,
that the Licensee was to follow the rules and regulations stipulated by
TAMP regarding fixation of tariff. Appendix-15 to the Agreement also
details out the rates prevailing at the time of signing of the Agreement.
The Article specifies that the Licensee was free to give discounts on
tariffs. However, such discount would be given only in respect of the         E
charges payable to the Licensee and not payable to the Licensor.
        53. Article 7.3.5.1 provides for initial payment of Rs.45 million
simultaneously on the date of award of license. The Agreement further
clarifies, that the Licensee shall pay to the Licensor royalty calculated
on the basis of minimum guaranteed traffic royalty as set out in Appendix-    F
12. It is also provided, that minimum guaranteed traffic royalty rate as
set out in Appendix-12 will be adjusted upwards or downwards as a
one-time measure on fixation of tariff for containers by TAMP for the
first time.
      54. It will be relevant to refer to Article 14, which is the bone of    G
contention between the parties, which reads thus:
                            “ARTICLE 14
                          CHANGE IN LAW
                                                                              H
442            SUPREME COURT REPORTS                           [2021] 5 S.C.R.


A           14. Change in Law
            14.1 Definition of Law
            For the purposes of this Agreement, “Law” means any valid act,
            ordinance, rule, regulation, notification, directive, order policy,
            bylaw, administrative guideline, ruling or instruction having the
B           force of law enacted or issued by a Government authority.
            14.2 Definition of Change in Law
            For the purposes of this Agreement “Change in Law” means any
            amendment, alteration, modification or repeal of any existing law
C           by Government Authority or through any interpretation thereof by
            the court of law or enactment or any new law coming into effect
            after the date of this Agreement, provision for which has not been
            made elsewhere in this Agreement.
            14.3 Relief under Change in Law
D           If, after the date of this Agreement, there is a ‘Change in the Law
            which substantially and adversely affects the rights of the Licensee
            under this Agreement so as to alter the commercial viability of the
            project, the Licensee may, by written notice request amendments
            to the terms of this Agreement.
E           Subject to provisions of Article 14.3, the Licensee shall not be
            entitled to any compensation whatsoever from the Licensor as a
            result of Change in Law.
            14.4 Changes in Tax Laws and Regulations
            The Licensee is not entitled to any compensation for any increase
F           in direct and/or indirect tax which the Licensee is liable to pay in
            respect of the Project.”
            55. Article 14 deals with ‘change in law’. Article 14.1, which
      defines ‘law’, states, that law means any valid act, ordinance, rule,
      regulation, notification, directive, order policy, bylaw, administrative
G     guideline, ruling or instruction having the force of law enacted or issued
      by a Government Authority.
             Article 14.2, which deals with ‘change in law’, states, that ‘change
      in law’ would mean any amendment, alteration, modification or repeal of
      any existing law by Government Authority or through any interpretation
H
PSA SICAL TERMINALS PVT. LTD. v. THE BOARD OF TRUSTEES OF V.O.               443
     CHIDAMBRANAR PORT TRUST TUTICORIN [B. R. GAVAI, J.]


thereof by a court of law or enactment of any new law coming into            A
effect after the date of this Agreement, provision for which has not been
made elsewhere in the said Agreement.
       Article 14.3 provides for relief under change in law. If, after the
date of Agreement, there is a change in the law which substantially and
adversely affects the rights of the Licensee under the Agreement so as       B
to alter the commercial viability of the project, the Licensee may, by
written notice, request amendments to the terms of the Agreement. It
further provided, that subject to provisions of Article 14.3, the Licensee
shall not be entitled to any compensation whatsoever from the Licensor
as a result of change in law.
                                                                             C
      56. The questions therefore that we will have to answer are:
      (i) As to whether the Arbitral Tribunal was justified in finding a
      change in law, which entitled the Licensee to invoke Article 14.3
      of the Agreement; and
      (ii) As to whether the Arbitral Tribunal was justified in converting   D
      the contract from royalty payment module to revenue-sharing
      module of Berth No. VII with the claimant’s liability to the revenue
      share being fixed at 55.19%.
       57. For answering the aforesaid questions, we will have to consider
the documents placed on record. Apart from that, we will also have to        E
take into consideration the conduct of the parties and their intention as
could be gathered from the said material.
      58. In this respect, it will be relevant to refer to paragraph 16 in
the case of MMTC Limited (supra), which reads thus:
                                                                             F
      “16. It is equally important to observe at this juncture that while
      interpreting the terms of a contract, the conduct of parties and
      correspondences exchanged would also be relevant factors and it
      is within the arbitrator’s jurisdiction to consider the same.
      [See McDermott International Inc. v. Burn Standard Co.
      Ltd. [McDermott International Inc. v. Burn Standard Co. Ltd.,          G
      (2006) 11 SCC 181]; Pure Helium India (P) Ltd. v. ONGC [Pure
      Helium India (P) Ltd. v. ONGC, (2003) 8 SCC 593] and D.D.
      Sharma v. Union of India [D.D. Sharma v. Union of India,
      (2004) 5 SCC 325].]”
                                                                             H
444             SUPREME COURT REPORTS                           [2021] 5 S.C.R.


A            59. The entire finding of the Arbitral Tribunal is based on a premise
      that when TPT entered into a contract with SICAL there was an existing
      policy, which provided royalty to be factored into the cost while fixation
      of tariff and that subsequently, the GoI changed its policy on 29th July,
      2003 thereby providing that royalty payment/revenue sharing will not be
      factored into/taken into account as cost for fixation/revision of tariff by
B
      TAMP; and that there was subsequent change in policy on 31st March,
      2005 vide which part of royalty was permitted to be factored into the
      cost. However, it being subjected to a maximum amount of the bid of the
      second lowest bidder. According to the Arbitral Tribunal, there was a
      change in policy, which amounted to change in law, which, in turn,
C     adversely affected SICAL.
             60. Let us examine the correctness of this finding. We are fully
      aware, that neither under Section 34 nor under Section 37 of the
      Arbitration Act, the Court is entitled to reappreciate the evidence. The
      said limitation would be equally applicable to this Court also. Admittedly,
D     the bid document was published on 9th April, 1997. The technical bid of
      SICAL was submitted on 24th October, 1997. The financial offer of
      SICAL was submitted on 19th December, 1997. LoI was issued on 29th
      January, 1998. All this has happened prior to the guidelines issued by
      TAMP in February 1998. As such, it is beyond any doubt, that when the
      bid document was notified and when SICAL submitted its bid and LoI
E     was issued to it, there were no guidelines in vogue. For the first time, the
      guidelines were adopted by TAMP in the workshop held in Chennai on
      26th/27th February, 1998.
            61. Let us examine what do these guidelines provide.

F           “The TAMP must adhere to established costing systems and
            pricing principals, its overall objective shall be to move towards
            competitive pricing.
            There are various approaches to tariff fixation. Until more
            information/knowledge becomes available. Attempts may be made
G           to smoothen the system within the existing framework.
            During the Interregnum, port pricing may continue to be cost-
            based with an assured rate of return. Although the concept of
            an assured rate of return is not consonant with a completive
            system. It will be advisable to maintain it for the time being
            so as not to destabilize the system with abrupt changes. At
H
PSA SICAL TERMINALS PVT. LTD. v. THE BOARD OF TRUSTEES OF V.O.                  445
     CHIDAMBRANAR PORT TRUST TUTICORIN [B. R. GAVAI, J.]


      the same time, to militate the full impact of its continuance,            A
      the reasonableness of the existing base and the absolute
      total costs may have to be examined to ensure that costs of
      inefficiencies, uneconomic user /practices or excess are not
      passed on to users. Even if the TAMP is not equipped at present
      to cope with the load of work relating to such scrutiny, it must at
                                                                                B
      least start pressuring against such costs being built into tariffs.
      An assured rate of return can be achieved either by increasing
      the surplus through a rationalized tariff structure and/or reducing
      the cost of services; or by reducing the capital base by eliminating
      unproductive and obsolete assets.”
                                                                                C
                                                       [emphasis supplied]
       62. It could thus be clearly seen that what is provided is that
TAMP must adhere to established costing systems and pricing principals
and its overall objective should be to move towards competitive pricing.
It further provides that until more information/knowledge becomes               D
available, attempts should be made to smoothen the system within the
existing framework. It further provides that during the interregnum, port
pricing is to be continued to be cost-based with an assured rate of return.
It however specifically observes that the concept of an assured rate of
return is not consonant with a competitive system. It provides that
however, it will be advisable to maintain it for the time being so as not to    E
destabilize the system with abrupt changes. It further provides that to
militate the full impact of its continuance, the reasonableness of the
existing base and the absolute total costs may have to be examined to
ensure that costs of inefficiencies, uneconomic user/practices or excess
are not passed on to users. It further observed, that an assured rate of        F
return can be achieved either by increasing the surplus through a
rationalized tariff structure and/or reducing the capital base by eliminating
unproductive and obsolete assets.
       63. It could thus clearly be seen, that even 1998 guidelines do not
mention, that the royalty could be factored in the cost while determining       G
the tariff. Though the said guidelines observed, that the port pricing may
continue to be cost-based with an assured rate of return, it further
observed, that such a concept of an assured rate of return is not in
consonance with a competitive system. Thus, it is amply clear, that when
the bids were invited, and SICAL submitted its bid and LoI was issued
                                                                                H
446             SUPREME COURT REPORTS                             [2021] 5 S.C.R.


A     to it, there was no policy at all. Even the 1998 guidelines do not provide
      for factoring the royalty in cost while determining the tariff.
            64. No doubt that when the first proposal for revision of tariff
      was submitted by SICAL, in its comments submitted to TAMP, TPT has
      supported the proposal submitted by SICAL. It is also undisputed, that
B     TAMP vide order dated 08th December, 1999(notified on 28th December,
      1999)has approved the proposal with regard to fixation of tariff insofar
      as SICAL is concerned. It will be relevant to refer to sub-para (iv) of
      paragraph 7 of the TAMP order, which reads thus:
             “(iv) It will be necessary at this point to refer to the royalty issue.
C            Even though some considerations relating to royalty have
             tariff- implications, we have not so far chosen to interfere
             in this regard; the royalty issue has been left to be settled
             by the Port Trust and the Government. That being so, in
             the light of the TPT’s conditional support to the request
             for dollar-denomination, it will be necessary for us to clarify
D            that our approval of the tariffs cannot be interpreted to
             amount to any implicit approval of royalty-related issues.
             Specifically, in the context of the TPT’s condition about dollar-
             denomination of royalty, the method of conversion adopted by the
             Applicant for the purpose of financial statements based on tariffs
E            denominated in dollar terms cannot be deemed to have been
             approved by us.”
                                                              [emphasis supplied]
              65. It could thus be clear, that TAMP has observed, that though
      some considerations relating to royalty have tariff-implications, it had
F     not so far chosen to interfere in that regard. The royalty issue has been
      left to be settled by TPT and the GoI. It has been clarified that its approval
      to the tariff cannot be interpreted to be amounting to any implicit approval
      of royalty-related issues. It is thus clear, that even the 1999 TAMP order
      made it clear, that the said order should not be interpreted to amount to
G     any implicit approval of royalty related issues. It is thus clear, that royalty
      was permitted to be factored in cost only on account of TPT’s conditional
      support to the proposal submitted by SICAL. It will also be relevant to
      note that TAMP order of 1999 is much after the TAMP guidelines, which
      were issued in February 1998. Undisputedly, the said order has been
      accepted by SICAL including the aforesaid observations in sub-para
H     (iv) of paragraph 7.
PSA SICAL TERMINALS PVT. LTD. v. THE BOARD OF TRUSTEES OF V.O.                 447
     CHIDAMBRANAR PORT TRUST TUTICORIN [B. R. GAVAI, J.]


       66. The second tariff order in case of SICAL came to be passed          A
on 20th September, 2002 (notified on 4th October, 2002). It will be relevant
to refer to sub-para (xi) of paragraph 15.
      “(xi) One of the main items of expenditure considered by the
      PSA SICAL is the royalty payment it has to make to the TPT as
      per the Concession Agreement. This liability accounts for about          B
      11.4%, 15.4% and 19.2% of the operating income estimated on
      the basis of the existing tariffs for the years 2002, 2003 and 2004
      respectively. As has been mentioned earlier, the existing tariffs
      were allowed to the PSA SICAL by accepting its proposal to
      adopt the (then) existing CHPT rates. That being so, there was
      no detailed cost analysis carried out then.                              C

      It is admitted that the issue of admissibility of ‘royalty’ as a
      cost item has come under a focused scrutiny only in the
      case relating to the CCTL which was disposed of in March,
      2002. In that case, this Authority decided not to allow
      ‘revenue share’ as a cost element for computation of tariffs             D
      at the CCTL. This Authority held that allowing royalty in
      tariff would mean that the CCTL (Private Terminal
      Operator) and the CHPT (the Licensor) both of whom
      enjoyed a dominant position, could enter into any
      commercial arrangement between themselves and pass on                    E
      the consequential cost to customers. This Authority also
      observed that there had been no commitment from anywhere about
      consequential tariff adjustments and the CA also did not give any
      assurance to the Licensee about tariff adjustments corresponding
      to the royalty quoted.
                                                                               F
      In view of the principle set out in the CCTL case, it is
      necessary to accord a similar treatment in the case of the
      PSA SICAL also. It is noteworthy that no extraordinary
      circumstances appear to emerge in this case warranting
      any exceptional consideration. That being so, royalty has
      not been considered as an admissible item of cost for this               G
      tariff exercise.”
                                                      [emphasis supplied]
      67. Perusal of the aforesaid sub-para would clearly reveal that
one of the main items of expenditure considered by SICAL was the
                                                                               H
448             SUPREME COURT REPORTS                           [2021] 5 S.C.R.


A     royalty payment it has to make to TPT as per the Concession Agreement.
      It states that the existing tariffs were allowed to SICAL by accepting its
      proposal to adopt the then existing Chennai Port Trust (hereinafter
      referred to as “CHPT”) rates. It clarifies that there was no detailed cost
      analysis carried out then. It further states that the issue of admissibility
      of royalty as a cost item came under a focused scrutiny only in the case
B
      relating to CCTL, which was disposed of in March 2002. It states, that
      in that case, the Authority decided not to allow ‘revenue share’ as a cost
      element for computation of tariffs for CCTL. It observes, that allowing
      royalty in tariff would mean that CCTL (Private Terminal Operator) and
      CHPT (the Licensor), both of whom enjoyed a dominant position, could
C     enter into any commercial arrangement between themselves and pass
      on the consequential cost to customers. It further specifies, that the
      Authority had observed, that there had been no commitment from
      anywhere about consequential tariff adjustments corresponding to the
      royalty quoted. It further observed that no extraordinary circumstances
      appear to emerge in the case of SICAL warranting any exceptional
D
      consideration. As such, royalty had not been considered as an admissible
      item of cost in the tariff.
             68. The said order is passed when the 1998 guidelines were still
      holding the field. In this factual background, it is difficult to appreciate
      as to how it could be said that the 1998 guidelines issued by TAMP
E     permitted royalty to be factored in cost while fixation of tariff.
            69. The 2002 tariff order has been challenged by SICAL by filing
      Writ Petitions being Writ Petition Nos 40637-40639 of 2002 before the
      Madras High Court. The Madras High Court has also passed interim
      order on 8th November, 2002 thereby staying the 2002 notification and
F     permitting SICAL to charge tariff on the basis of the 1999 tariff order.
            70. Then comes the notification dated 29th July, 2003 issued by
      the GoI, which is in the following terms:
            “In a few cases recently a question arose as to what treatment to
G           be given to revenue sharing/royalty payment made by private
            terminal operators to the concerned major ports for the purpose
            of fixation/revision of tariff. TAMP has also requested for
            guidelines from Ministry in the matter. The matter has been
            discussed with Chairman, TAMP and considered in this Ministry
            and it has been decided to clarify as a matter of policy that
H
PSA SICAL TERMINALS PVT. LTD. v. THE BOARD OF TRUSTEES OF V.O.                 449
     CHIDAMBRANAR PORT TRUST TUTICORIN [B. R. GAVAI, J.]


      the revenue sharing/royalty payment shall not be factored                A
      into/taken into account as cost for fixation/revision of tariff
      by TAMP for the following reasons:-
      (i) The benefit of higher efficiency on account of private
      participation in ports should also be passed on to shippers or the
      users which will not be so if royalty is allowed to be factored in       B
      the cost of private operators.
      (ii) If royalty is allowed as cost, the private bidder can offer any
      high percentage which he will recover from the shippers/users in
      the shape or royalty cost lectured in fixing of higher rates.
      It has also been decoded that the position in this regard may be         C
      clearly indicated in the bid documents itself while inviting bids for
      private sector participation at major ports.”
                                                      [emphasis supplied]
       71. Perusal of the said notification would clearly show that the        D
GoI has decided to clarify, as a matter of policy, that the revenue-sharing/
royalty payment shall not be factored into/taken into account as cost for
fixation/revision of tariff by TAMP. The said notification specifically
provides that the benefit of higher efficiency on account of private
participation in ports should also be passed on to shippers or the users
which will not be so if royalty is allowed to be factored in the cost of       E
private operators. It further provides that if royalty is allowed as cost,
the private bidder can offer any high percentage which he will recover
from the shippers/users in the shape of royalty cost factored in fixing of
higher rates.
       72. Then comes a notification dated 31st March, 2005 issued by          F
TAMP. It willbe relevant to note that these guidelines have been issued
subsequent to the consultation meetings held with the stake-holders at
Kolkata, Chennai and Mumbai. It will be relevant to refer to clause
1.4.2, which reads thus:
      “1.4.2. The earlier guidelines adopted in Feb. 1998 stand                G
      superseded. The principles evolved through various tariff orders
      will, however, continue to apply to the extent they are consistent
      with and not specifically superseded by these guidelines. A
      compendium or digest of principles evolved will be published
      periodically.”
                                                                               H
450             SUPREME COURT REPORTS                              [2021] 5 S.C.R.


A            73. It is thus clear, that the 31st March, 2005 notification specifically
      states that the guidelines adopted in February 1998 stand superseded.
      However, it provides, that the principles evolved through various tariff
      orders would continue to apply to the extent they are consistent with and
      not specifically superseded by the 2005 guidelines.
B            74. It will also be relevant to refer to paragraph 2.8.1 of the 2005
      guidelines.
             “2.8.1. ‘Royalty/Revenue share’ payable to the landlord port
             by the private operator will not be allowed as an admissible
             cost for tariff computation as decided by the Govt. in the
C            Ministry of Shipping vide its Order No. PR-14019/6/2002-
             PG dt. 29th July, 2003. In those BOT cases where bidding
             process was finalized before 29 July, 2003, the tariff
             computation will take into account royalty / revenue sharing
             as cost for tariff fixation in such a manner as to avoid likely
             loss to the operator on account of royalty / revenue share
D            not being taken into account, subject to maximum of the
             amount quoted by the next lowest bidder. This would,
             however, be allowed for the period upto which such likely
             loss will arise. This would not be applicable if there is provision
             in the concession agreement on treatment of ‘Royalty/Revenue
E            Share’.”
                                                               [emphasis supplied]
              75. The said guidelines specifically provide that ‘royalty/revenue
      share’ payable to the landlord port by the private operator will not be
      allowed as an admissible cost for tariff computation as decided by the
F     Government in the Ministry of Shipping vide its Order No.PR-14019/6/
      2002-PG dated 29th July, 2003. It further provided, that in those BOT
      cases where bidding process was finalized before 29th July, 2003, tariff
      computation will take into account royalty/revenue sharing as cost for
      tariff fixation in such a manner as to avoid likely loss to the operator on
G     account of the royalty/revenue share not being taken into account.
      However, this was subjected only to a maximum of the amount quoted
      by the next lowest bidder. This was further subjected to be allowed for
      the period upto which such likely loss would arise. It further provided
      that this would not be applicable if there is provision in the concession
      agreement on treatment of royalty/revenue share.
H
PSA SICAL TERMINALS PVT. LTD. v. THE BOARD OF TRUSTEES OF V.O.                   451
     CHIDAMBRANAR PORT TRUST TUTICORIN [B. R. GAVAI, J.]


       76. A conjoint reading of all these documents would reveal that           A
when the bid document was published in April 1997; SICAL tendered its
bid in October, 1997 and submitted its financial offer in December,1997;
and the LoI was issued to SICAL on 29th January, 1998, there were no
guidelines at all. Even the guidelines of February 1998 do not provide for
royalty being factored as cost while fixation of tariff. On the contrary,
                                                                                 B
the tariff order of 1999 specifically clarifies that it has left the royalty
issue to be decided by TPT and the GoI. It has specifically clarified that
the approval by TAMP should not be interpreted to be amounting to any
implicit approval of royalty-related issue. Further, the tariff order issued
on 20th September, 2002 specifically rejects the claim of SICAL for
factoring any royalty as cost while tariff/price fixation. As already stated     C
herein above, SICAL has challenged the said order before the Madras
High Court by way of writ petition, which petition has been allowed. It is
also not in dispute, that on account of interim order passed by the Madras
High Court dated 8th November, 2002, SICAL is still continuing to charge
at rates notified in the 1999 tariff order.
                                                                                 D
        77. In this scenario, the finding of the Arbitral Tribunal, that there
was a law when the Agreement was entered into between the parties,
which provided royalty as a pass-through and that the said law has been
changed for the first time in 2003 and subsequently again changed in
2005, in our view, is a finding based on ‘no evidence’. Had the Arbitral
Tribunal perused the tariff orders of 1999 and 2002, it would have found         E
that in the 1999 tariff order TAMP has specifically observed that its
approval of the tariff should not be construed as its implicit approval of
royalty-related issue and the 2002 tariff order specifically states that
royalty was not permitted to be factored in the cost while determining
tariff. The Arbitral Tribunal has totally failed to take into consideration      F
this aspect of the matter.
       78. As such, we are of the view, that since the finding of the
Arbitral Tribunal, that there was an existing law to the effect that the
royalty payable shall be permitted as a pass-through in cost while fixation
of tariff, is based on ‘no evidence’ and the finding, that there was a           G
change in law in 2003 and 2005 is based on without taking into
consideration the relevant evidence, would come in the realm of perversity
as explained by this Court in paragraph 31 of the Associate Builders
(supra). The findings are based on ‘no evidence’ and ‘ignorance of vital
evidence’ in arriving at its decision.
                                                                                 H
452             SUPREME COURT REPORTS                           [2021] 5 S.C.R.


A            79. This brings us to the next issue viz., as to whether the Arbitral
      Tribunal was justified in passing an award thereby substituting ‘royalty
      payment module’ to the ‘revenue-sharing module’. A contract duly
      entered into between the parties cannot be substituted unilaterally without
      the consent of the parties. The intention of the parties could be gathered
      from the documents on record. SICAL, for the first time, made
B
      representation to TPT on 6th October, 2006thereby seeking a relief under
      the terms of Article 14.3 of the Agreement. On 14th October, 2006, TPT
      informed SICAL that the issues raised by it were under examination.
      However, vide order dated 27th October, 2006, TPT refused to consider
      SICAL’s application for relief since, according to it, the issue raised by
C     SICAL was pending before the Madras High Court. SICAL therefore
      filed writ petition being Writ Petition No. 4361 of 2006 before the Madras
      High Court. The Madras High Court allowed the said writ petition vide
      order dated 21st August, 2007 clarifying that the petition pending before
      the High Court had nothing to do with the representation under Article
      14 of the License Agreement and remanded the matter to TPT for
D
      consideration afresh. Vide a reasoned letter dated 25th April, 2008, TPT
      rejected the claim of SICAL. TPT has specifically observed that any
      change in the Agreement cannot be done without prior approval of the
      GoI. SICAL on 19th November, 2012 addressed a letter to TPT invoking
      arbitration under Article 15.3 of the License Agreement. TPT strenuously
E     contested the claim of SICAL with regard to prayer for change from
      ‘royalty payment mode’ to ‘revenue sharing mode’. The stand of TPT
      has been crystalized by the Arbitral Tribunal in paragraph 5 of the Award,
      which reads thus:
            “5. Sum and substance of the defence is as follows:
F               “There is no dispute at all. The grievance of the SICAL is that
                there is an error committed by TAMP in fixing the tariff. That
                grievance had been repeatedly taken before the High Court of
                Madras by SICAL and at all stages orders have been passed
                by setting aside the orders challenged. Therefore, the real
G               grievance of SICAL is only against TAMP and not against
                PORT. Since the issue regarding fixing of tariff is pending
                finality, SICAL cannot maintain any claim legally or factually
                against PORT. PORT is bound by the order of TAMP.
                Whatever order TAMP passes, the PORT is bound to obey.
                The PORT has no right to interfere with the tariff fixing power
H
PSA SICAL TERMINALS PVT. LTD. v. THE BOARD OF TRUSTEES OF V.O.                 453
     CHIDAMBRANAR PORT TRUST TUTICORIN [B. R. GAVAI, J.]


          of TAMP which is their exclusive domain and jurisdiction. The        A
          Contract is not entered into on the basis of any guidelines.
          There was no guideline, as contended by SICAL, on the date
          of the contract. By the present dispute, SICAL is trying to
          change the entire nature of the contract, namely, from the
          royalty module to the revenue sharing module. It is
                                                                               B
          impermissible for a court or this Tribunal to compel any party
          to enter into a new contract. Contract is always by consent of
          parties. All the grievance put forward before the Tribunal by
          SICAL is their grievance in sum and substances before TAMP
          and High Court of Madras in all challenges made against the
          order of TAMP. Neither a Court nor the Tribunal can rewrite          C
          the Contract. The contract is an enforceable one and simply
          because SICAL is stated to be losing monetarily, the relief
          sought for in this dispute cannot be granted. If the case of
          SICAL is true, it is open to them to put an end to the contract
          and seek appropriate relief. If such a termination of the contract
                                                                               D
          takes place at the instance of SICAL, then the PORT will take
          steps to get appropriate relief. Section 56 of the Contract Act
          is applicable to this case”
      A number of case laws have been cited by the learned Senior
Counsel for the PORT and we will refer to them at the appropriate
stage.”                                                                        E

      80. It could thus be seen, that SICAL wanted the Agreement to
be amended so as to change the ‘royalty payment method’ to ‘revenue-
sharing method’. TPT was always opposed to it. The intention of TPT is
apparent from its various communications and its stand before the Arbitral
Tribunal, that it was not agreeable for amendment of the Agreement             F
from ‘royalty payment method’ to ‘revenue-sharing method’.
       81. However, ignoring the stand of TPT, by the impugned Award,
the Arbitral Tribunal has thrust upon a new term in the Agreement
between the parties against the wishes of TPT. The ‘royalty payment
method’ has been totally substituted by the Arbitral Tribunal, with the        G
‘revenue-sharing method’. It is thus clear, that the Award has created a
new contract for the parties by unilateral intention of SICAL as against
the intention of TPT.
     82. After referring to various international treaties on arbitration
and judgments of other jurisdictions, this Court in Ssangyong                  H
454            SUPREME COURT REPORTS                           [2021] 5 S.C.R.


A     Engineering and Construction Company Limited (supra), observed
      thus:
            “76. However, when it comes to the public policy of India,
            argument based upon “most basic notions of justice”, it is clear
            that this ground can be attracted only in very exceptional
            circumstances when the conscience of the Court is shocked by
B
            infraction of fundamental notions or principles of justice. It can be
            seen that the formula that was applied by the agreement continued
            to be applied till February 2013 — in short, it is not correct to say
            that the formula under the agreement could not be applied in view
            of the Ministry’s change in the base indices from 1993-1994 to
C           2004-2005. Further, in order to apply a linking factor, a Circular,
            unilaterally issued by one party, cannot possibly bind the other
            party to the agreement without that other party’s consent. Indeed,
            the Circular itself expressly stipulates that it cannot apply unless
            the contractors furnish an undertaking/affidavit that the price
            adjustment under the Circular is acceptable to them. We have
D           seen how the appellant gave such undertaking only conditionally
            and without prejudice to its argument that the Circular does not
            and cannot apply. This being the case, it is clear that the
            majority award has created a new contract for the parties
            by applying the said unilateral Circular and by substituting
            a workable formula under the agreement by another formula
E
            dehors the agreement. This being the case, a fundamental
            principle of justice has been breached, namely, that a
            unilateral addition or alteration of a contract can never be
            foisted upon an unwilling party, nor can a party to the
            agreement be liable to perform a bargain not entered into
F           with the other party. Clearly, such a course of conduct would
            be contrary to fundamental principles of justice as followed
            in this country, and shocks the conscience of this Court.
            However, we repeat that this ground is available only in
            very exceptional circumstances, such as the fact situation
            in the present case. Under no circumstance can any court
G           interfere with an arbitral award on the ground that justice has not
            been done in the opinion of the Court. That would be an entry into
            the merits of the dispute which, as we have seen, is contrary to
            the ethos of Section 34 of the 1996 Act, as has been noted earlier
            in this judgment.”
H                                                           [emphasis supplied]
PSA SICAL TERMINALS PVT. LTD. v. THE BOARD OF TRUSTEES OF V.O.                   455
     CHIDAMBRANAR PORT TRUST TUTICORIN [B. R. GAVAI, J.]


        83. As such, as held by this Court in Ssangyong Engineering              A
and Construction Company Limited (supra), the fundamental principle
of justice has been breached, namely, that a unilateral addition or alteration
of a contract has been foisted upon an unwilling party. This Court has
further held that a party to the Agreement cannot be made liable to
perform something for which it has not entered into a contract. In our
                                                                                 B
view, re-writing a contract for the parties would be breach of fundamental
principles of justice entitling a Court to interfere since such case would
be one which shocks the conscience of the Court and as such, would fall
in the exceptional category.
      84. We may gainfully refer to the following observations of this
Court in Bharat Coking Coal Ltd. v. Annapurna Construction26.                    C

          “22. There lies a clear distinction between an error within the
          jurisdiction and error in excess of jurisdiction. Thus, the role of
          the arbitrator is to arbitrate within the terms of the contract. He
          has no power apart from what the parties have given him under
          the contract. If he has travelled beyond the contract, he would be     D
          acting without jurisdiction, whereas if he has remained inside the
          parameters of the contract, his award cannot be questioned on
          the ground that it contains an error apparent on the face of the
          record.”
       85. It has been held that the role of the Arbitrator is to arbitrate      E
within the terms of the contract. He has no power apart from what the
parties have given him under the contract. If he has travelled beyond the
contract, he would be acting without jurisdiction.
       86. It will also be apposite to refer to the following observations
of this Court in the case of Md. Army Welfare Housing Organization               F
v.Sumangal Services (P) Ltd.27
          “43. An Arbitral Tribunal is not a court of law. Its orders are not
          judicial orders. Its functions are not judicial functions. It cannot
          exercise its power ex debito justitiae. The jurisdiction of the
          arbitrator being confined to the four corners of the agreement, he     G
          can only pass such an order which may be the subject-matter of
          reference.”

26
     (2003) 8 SCC 154
27
     (2004) 9 SCC 619                                                            H
456             SUPREME COURT REPORTS                            [2021] 5 S.C.R.


A            87. It has been held that an Arbitral Tribunal is not a Court of law.
      Its orders are not judicial orders. Its functions are not judicial functions.
      It cannot exercise its powers ex debito justitiae. It has been held that
      the jurisdiction of the arbitrator being confined to the four corners of the
      agreement, he can only pass such an order which may be the subject-
      matter of reference.
B
            88. In that view of the matter, we are of the considered view, that
      the impugned Award would come under the realm of ‘patent illegality’
      and therefore, has been rightly set aside by the High Court.
             89. The High Court has gone into various other aspects of the
C     matter. Arguments have also been advanced before us with regard to
      NSCT being given a discriminatory treatment as against SICAL. The
      arguments have also been advanced on the ground of approbate and
      reprobate and doctrine of election. It has also been argued on behalf of
      SICAL that it is incurring huge losses. Per contra, it is submitted on
      behalf of TPT, that it is incurring huge losses on account of various
D     interim orders passed by the High Court and the District Judge in Section
      9 applications.
             90. We do not propose to go into those aspects of the matter.
      TAMP has issued various notifications with regard to fixation of tariff so
      also various orders have been passed by the GoI with regard to the
E     aspect of grant or refusal of pass through of royalty payable. Various
      petitions have been filed by SICAL challenging the said orders and
      notifications. All the petitions were allowed thereby remanding the matters
      to TAMP and GoI. However, it is not in dispute, that SICAL, by virtue of
      the interim order passed dated 8th November, 2002 in Miscellaneous
F     Petition No. 60240 of 2002 in Writ Petition No.40638 of 2002 is continuing
      to levy charges on the basis of 1999 tariff order (dated 8th December,
      1999) passed by TAMP.
              91. The last notification issued by TAMP with regard to price/
      tariff fixation dated 17th December, 2008, gazetted vide notification dated
G     30th December, 2008 was challenged by SICAL by way of Writ Petition
      No.1350 of 2009. The last direction issued by the GoI dated 20th February,
      2008 was also challenged by SICAL by way of Writ Petition No.1351 of
      2009. By an order dated 15th October, 2009, the High Court has allowed
      these writ petitions by setting aside the order of the GoI dated 20th
      February, 2008 and the notification dated 17th December, 2008 issued by
H
PSA SICAL TERMINALS PVT. LTD. v. THE BOARD OF TRUSTEES OF V.O.                 457
     CHIDAMBRANAR PORT TRUST TUTICORIN [B. R. GAVAI, J.]


TAMP and has directed the GoI as well as TAMP to consider the issue            A
afresh.
      92. It is informed at the Bar, that the said order has been carried
in appeal before the Division Bench of the High Court both by SICAL
as well as TAMP, which are still pending before the High Court.
       93. We are of the considered view, that if we make any observation      B
on merits of the issue with regard to aforesaid submissions made before
us, it may prejudicially affect the rights of either of the parties. We
therefore refrain from making any observation with regard to the
aforesaid arguments, though heavily contested before us.
       94. We therefore, confine ourselves with the issue as regards the       C
validity of the Award. We also clarify that any observations made by the
High Court with regard to other aspects of the matter except the validity
of the Award, would not come in the way of either of the parties raising
their grievances in either the proceedings which are pending before the
Division Bench of the High Court or any other proceedings to which             D
either of it would be entitled to take recourse in law.
      95. In the result, with these observations, we dismiss the appeals.
However, in the facts and circumstances of the case, there shall be no
order as to costs. Pending applications, if any, shall stand disposed of
accordingly.                                                                   E

Devika Gujral                                             Appeals dismissed.




                                                                               F




                                                                               G




                                                                               H


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Arbitration"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.

PSA SICAL TERMINALS PVT. LTD. versus THE BOARD OF TRUSTEES OF V.O. CHIDAMBRANAR PORT TRUST TUTICORIN AND OTHERS — 2021 INSC 365 - Legal Desk AI