Created byFuzzy Cloud

Supreme Court of India

R. KOLANDAIVELU & ORS .versusTHE GOVT. OF TAMIL NADU & ANR.

Citation
2009 INSC 1299
Decided
11 December 2009
Disposal
Dismissed

Holding

The two‑year period under Section 11A is to be computed after excluding the period during which the acquisition proceedings were stayed by a court, and therefore the award was within time and the acquisition did not lapse.

Summary

The appellants owned land that was acquired by the Government of Tamil Nadu under the Land Acquisition Act, 1894. A notification (Sec. 4) was issued on 24‑12‑1986 and a declaration (Sec. 6) on 23‑12‑1987. The appellants filed writ petitions in 1988 challenging the acquisition; the High Court granted an interim stay of four weeks on 11‑Feb‑1988, which effectively continued until a stay of dispossession was ordered on 3‑July‑1991. The award was finally made on 23‑Aug‑1993. The appellants argued that the award was beyond the two‑year period prescribed by Sec. 11A, and thus the acquisition proceedings should have lapsed. The Supreme Court held that the two‑year period must be computed after excluding the time during which the acquisition was stayed by a court order, i.e., from 11‑Feb‑1988 to 3‑July‑1991. Excluding this period, the award was within the statutory limit, so the acquisition did not lapse. The appeal was dismissed, upholding the High Court’s order.

Issues considered

  • Whether the two‑year period for making an award under Section 11A of the Land Acquisition Act, 1894, is to be computed excluding the period during which the acquisition proceedings are stayed by a court order.
  • Whether the interim stay granted on 11‑Feb‑1988 was operative only for four weeks or continued until the order of 3‑July‑1991, and how that affects the computation of the limitation period.
  • Whether the award passed on 23‑Aug‑1993 is barred as being beyond the two‑year limit, causing the acquisition proceedings to lapse.

Legislation cited

Subjects

Land acquisitionSection 11Astay ordercomputation of limitation periodacquisition awardstatutory lapseinterim injunctioncompensation

Judgment

                                   [2009) 16 (ADDL.) S.C.R. 381


-        ...                       R. KOLANDAIVELU & ORS .
                                                v.
                               THE GOVT. OF TAMIL NADU & ANR.
                                                                                        A



                                 (Civil Appeal No. 8235 of 2009)

                                       DECEMBER 11, 2009
                                                                                        B
                        [TARUN CHATTERJEE AND SURINDER SINGH
                                     NIJJAR, JJ.]
    • "
                        Land Acquisition Act, 1894:
                                                                                        c
                        s.11A - Object and legislative intent - Discussed.

                         s. 11A - Award - Limitation - Land acquisition
                   proceedings - s. 6 declaration issued on 23. 12. 1987 - Writ
                   petition by land owners - Interim order - Stay for four weeks
                                                                                        D
                   granted on 11.2.1988 - Order of stay of dispossession on
         _,...     3.7.1991-Award passed on 23.8.1993 - Writ petition finally
L
                   dismissed - Appeal on the ground that acquisition
                   proceedings lapsed due to expiry of two years from date of
                   publication of s.6 declaration - Held: Acquisition proceedings
                   did not lapse and award was well within time - Two years from        E
                   the date of declaration is to be computed after excluding the
                   period when parties approached the court and obtained
                   interim stay of such acquisition notices - Both the parties
                   proceeded on the basis that the interim order of stay passed
          -    "   initially for four weeks continued till the final order of interim   F
                   stay passed by the High Court on application for vacating
                   interim order of stay.
    ..                  Appellants were owners of land under acquisition .
                   They filed writ petitions questioning the validity of                G
                   notification under Section 4 of Land Acquisition Act and
                   Section 6 declaration issued on 23rd December 1987
         ..-*      before the High Court. In the pending writ petitions, by
                   interim order dated 11th Febru:iry, 1988 stay for four
                                                 381                                    H
...
    382    SUPREME COURT REPORTS [2009] 16 (ADDL.) S.C.R.


A weeks was granted. State-respondent filed application to
    vacate the stay order. An order of stay of dispossession
                                                                          ~   -
    was passed on 3rd July 1991. The award was passed on
    23rd August 1993. Writ petitions were finally dismissed.

B
         In appeal to this Court, the appellants contended that
    the interim order of stay was operative only for a period
                                                                              -·
    of four weeks from 11th February, 1988 to 11th March,
    1988, High Court fell into error in dismissing writ petitions
    in as much as the award passed on 23rd August 1993was
    clearly beyond the period of two years from the date of
                                                                      I       •
c   issuance of declaration under s.6 on 23rd December,
    1997.

          Dismissing ihe appeal, the Court

        HELD: 1.1. Perusal of the relevant provisions of the
D
  Land Acquisition Act, ~SS4 namely, Sections 6 and 11A
  with its explanation show that the two years from the date        ).-   .
  of declaration must be computed after excluding the
  period when parties had approached the court and
  obtained interim stay of such acquisition notices. At the
E instance of the appellants, the notification issued under
  Section 4 of the Act and the declaration under Section 6
  initially were stayed for four weeks on 11th of February,
  1988, but the Interlocutory Applications remained
  pending for final disposal and finally on the applications        ,.
F to vacate the stay order at the instance of the State/
  respondents, the applications to vacate the stay were
  disposed of, by an order which clearly shows that the
  order of stay granted initially for four weeks would
  continue pending further orders. Perusal of interim order
G of the High Court show that there was an order of
  prohibition from dispossessing the appellants from the
  acquired lands pending further orders. [Paras 7 and 10]
                                                                    ,. '
  (389-G-H; 390-A-B; 391-G-H; 392-A-B]

H         1.2. Considering the nature of interim order of stay
                   R. KOLANDAIVELU & ORS. v. GOVT. OF TAMIL             383
                                 NADU &.ANR.
·~     -i       passed by the High Court finally on 3rd of July, 1991, it       A
                is abundantly clear that both the parties proceeded on
                the basis that the interim order of stay had been
                continuing and the respondents were prohibited from
                dispossessing the appellants from the acquired lands
                pending further orders. If that was not the case, the           B
                question of filing an application for vacating the order of
                stay granted in favour of the appellants could not arise
 ..         ~
                at all and there was no occasion for the appellants to
                contest the application for vacating the stay order on the
                basis that the interim order of stay was continuing and         c
                should be allowed to continue. That apart, it may be
                stated that although initially the interim order was passed
                for four weeks, the same interim order which was granted
                initially was made final until further orders on 3rd of July,
                1991. From the above narration of facts, it must be held        D
                that no steps could be taken in view of the pending
       . .;     appli<:ations for grant of interim order and in view of the
                interim order granted pending further orders. Therefore,
                it cannot be said that the acquisition proceedings had
                lapsed due to expiry of two years from the date of
                                                                                E
                publication of the declaration under Section 6 of the Act
                relating to the acquired lands. [Para 11) [391-G-H;
                392-A-C]
                    2. The explanation to Section 11 A of the Act is
        -'      intended to confer a benefit on the land holder, whose F
                land is acquired after .the declaration under Section 6 is
                made. By the provision of Section 11A, the State
 '              authorities are required to pass a final award within two
                years from the date of publication of declaration under
                Section 6 of the Act failing which, the acquisition G
                proceedings would lapse, and it would clearly show the
      .,. _).   intention of the legislature that the benefit of this
                provision would be in favour of the land owner if the
                award could not be passed within two years from the
                date of declaration when no order was obtained by the H
    384   SUPREME COURT REPORTS [2009] 16 (ADDL.) S.C.R.

                                                                    1--   ••
A land owner from the Court staying the acquisition and the
    land would revert back to the land owner because of
    expiry of the period of two years from the date of
    declaration or notification within the meaning of Section
    11A of the Act. [Para 13) [393-C-F]
B
       3. There is another aspect of the matter. The purpose
  for which the Land Acquisition Act was amended and
  Section 11Awas enacted, was to prevent inordinate delay
  being caused by the Land Acquisition Officer in making        ~         •
  an award which deprived the land owners of their
c enjoyment of their land or dealt with the land whose
  possession was already taken. The delay in making the
  award subjected the owner of the land to untold
  hardship. The objects and reasons for introducing
  Section 11A into the Act were that "the pendency of
D acquisition proceedings for long periods often causes
  hardship to the affected parties and renders unrealistic      ••
  the scale of compar.sation offered to them" and "it is
  proposed to provide for a period of two years from the
  date of publication of the declaration under Section 6 of
E the Act within which the Collector should make his award
  under the Act". By the introduction of this explanation
  and Section 11A of the Act, the Legislature intended to
  emphasize that the Collector shall make his award under
  the Act within two years from the date of publication of      ,-
F declaration under Section 6 of the Act, failing which the
  acquisition proceeding itself shall lapse. [Para 15] [394-
  C-F]
       4. The appellants having taken advantage of an order
  passed by the High Court during the pendency of the writ
G petition which was sought to be vacated by the State/
  respondents by filing an application for vacating the stay
  order, it must be concluded that the award was passed         ".
  within two years from the date of publication of the
  declaration under Section 6 of the Act and the
                                    '
H respondents were entitled to exclude     the period from
          R. KOLANDAIVELU & ORS. v. GOVT. OF TAMIL                385
                        NADU & ANR.

-· ~   11th of February, 1988 to 3rd of July, 1991 and, therefore,       A
       if this period is excluded as enshrined in the explanation
I      to Section 11A of the Act, the award was within time and,
       therefore, the question of holding that the acquisition
       proceeding must lapse because of expiry of the said
       period, cannot arise at all. [Para 17] [396-H; 397-A-C]           B

           Ashok Kumar and Ors. v. State of Haryana and Another
       2007 (3) sec 470, distinguished.

            Bai/amma (Smt.) Alias Doddabailamma and others v.
       Poornaprajna House Building Cooperative Society and               C
       others 2006 (2) SCC 416 and Yusufbhai Noormohamed
       Nendo/iya v. State of Gujarat and another 1991 (4) SCC 531,
       relied on.

                             Case Law Reference:                         D
            2001 (3) sec 470          distinguished        Para 5
            2006 (2) sec 416          relied on            Para 6
            1991 (4) sec 531          relied on            Para 6
                                                                         E
           CIVIL APPELLATE JURISDICTION : Civil Appeal No.
       8235 of 2009.

           From the Judgment & Order dated 23.1.2007 of the High
       Court of Madras in Writ Appea No. 1735 of 2001.
                                                                         F
           V. Krishnamurhty, R. Viduthalai, Prashanth P., Prachi
       Bajpai, K.V. Bharathi Upadhyaya, R. Nedumaran, Promila,
       Jegadeesh, Indira, S. Thananjayan for the appearing parties.

           The Judgment of the Court was delivered by                    G
           TARUN CHATIERJEE, J. 1. Leave granted.

           2. The appellants are the owners of lands situated in
       Salem Taluk No. 151, Ayothiapatnam in the district of Salem,
       Tamil Nadu (hereinafter referred to as "the acquired lands"). A   H
•
    386 SUPREME COURT REPORTS [2009] 16 (ADDL.) S.C.R.


A notification under Section 4( 1) of the Land Acquisition Act, 1894          ~       ....   ,


  (in short "the Act") was issued on 24th of December, 1986 for
  acquisition of the said lands. A declaration under Section 6 of
  the Act was issued on 23rd of December, 1987. Two writ
  petitions being W.P.Nos.835 and 836 of 1988 were filed
B questioning   the validity and legality of the aforesaid notification
  and the declaration before the High Court of Madras. In the
  pending writ petitions, on 11th of February, 1988, the following
  interim order was passed :-                                                     I
                                                                          '
         "Interim stay for four weeks. Notice returnable in four
c        weeks."

        The aforesaid two writ petitions finally came up for hearing
  before a learned Judge of the High Court who by an order
  dated 23rd of August, 2001 rejected the writ petitions and
D feeling aggrieved, the appeals were filed before the Division
  Bench which by the impugned order had dismissed the
  appeals of the appellants. The appellants, feeling aggrieved,
                                                                          ••
  had filed two special leave petitions which on grant of leave,
  were heard in the presence of the learned counsel for the
E parties.
       Having heard the learned senior counsel for the parties
  and after careful examination of the relevant provisions of the
  Act, we are of the view that these appeals have no merit. The
  submission of Mr.Krishnamurthy, learned senior counsel                  '-
F appearing on behalf of the appellants, was that having regard
  to the fact that the interim order of stay was operative only for
  a period of four weeks from 11th of February, 1988 to 11th of
  March, 1988, the High Court had fallen into a grave error in
  dismissing the writ petitions filed by the appellants inasmuch
G as the award passed on 23rd of August, 1993 was clearly
  beyond the period of two years from the date of issuance of
  declaration under Section 6 of the Act on 23rd of December,             ....
  1987. Mr.Viduthalai, learned senior counsel appearing for the
  respondents contested the submissions advanced by
H Mr.Krishnamurthy, learned senior counsel appearing for the
                     R. KOLANDAIVELU & ORS. v. GOVT. OF TAMIL                 387
                        NADU & ANR. [TARUN CHATTERJEE, J.}
,..
        "'         appellants. He submitted that the High Court was fully justified A
                   in dismissing the writ petitions having regard to the nature of
                   the interim order of stay granted by the High Court in the
                   pending writ petitions and, therefore, it must be held that the
                   question of holding that entire proceedings had lapsed and that
                   the acquired lands must be restored to the appellants could not B
                   arise at all. Before we proceed to consider the issue as posed
                   before us, it would be necessary to deal with some of the
  •          \   ; provisions of the Act. First of such provisions is Section 6 of
                   the Act which deals with intended acquisition. The explanation
                   to Section 6 of the Act says that "In computing any of the         c
                   periods referred to in the first proviso, the period during which
                   any action or proceeding to be taken in pursuance of the
                   notification issued under Section 4(1), is stayed by an order
                   of a Court shall be excluded."

                       3. Section 11 of the Act deals with enquiry and award by       D
       • -i
                  Collector. It says that -

                       "On the day so fixed, or any other day to which the enquiry
                       has been adjourned, the Collector shall proceed to enquire
                       into the objections (if any) which any person interested has   E
                       stated pursuant to a notice given under section 9 to the
                       measurements made under section 8, and into the value
                       of the land and at the date of the publication of the
                       notification under Section 4, sub-section (1) and into the
       -·              respective interests of the persons claiming the
                       compensation and shall make an award under his
                                                                                      F

                       hand ................................. "

                       4. Next comes the most relevant provision of the Act for
                  the purpose of this case i.e. Section 11A of the Act which deals
                  with the period within which an award shall be made. It says G
                  that "The Collector shall make an award under Section 11
      •-"         within a period of two years from the date of the publication of
                  the declaration and if no award is made within that period, the
                  entire proceedings for the acquisition of the land shall lapse,
                  provided that in a case where the said declaration has been H
    388    SUPREME COURT REPORTS [2009] 16 (ADDL.) S.C.R.


A published before the commencement of the Land Acquisition                   ~       ...
  (Amendment) Act, 1984 (68of1984), the award shall be made
  within a period of two years from such commencement.
  Explanation - In computing the period of two years referred
  to in this section, the period during which any action or                           ,
B proceeding  to be taken in pursuance of the said declaration
  is stayed by an order of a Court shall be excluded."

          5. As noted herein earlier, Mr.V.Krishnamurthy, learned
                                                                          !       t
    senior counsel appearing on behalf of the appellants urged that
    in view of the admitted fact that the limited order of stay granted
c   by the High Court in the two writ petitions was not extended by
    it, the award which was passed had lapsed after the expiry of
    period of two years from the date o{ publication of the
    declaration, therefore, it must be held that the entire
    proceedings for the acquisition of the acquired lands had
D   lapsed and, accordingly, the acquired lands of the appellants
    must be restored to them. In this connection, Mr.Krishnamurthy        ••
    had drawn our attention to the admitted fact that the notification
    under Section 6 of the Act was published in the official gazette
    on 23rd of December, 1987 and the limited interim order of stay
E   was granted by the High Court on 11th of February, 1988 and
    on 3rd of July, 1991, an order of stay of dispossession was
    passed in favour of the appellants and thereafter finally the
    award was passed on 23rd of August, 1993. From the above

F
    facts, according to Mr.Krishnamurthy, it would be clear that
    admittedly the period of 2 years from the date of publication of
                                                                          ..
    the declaration under Section 6 of the Act i.e. 23rd of
    December, 1987 had lapsed before the date of award i.e. 23rd
    of August, 1993 although a limited order of stay for four weeks
    was granted which was not extended by any order of extension.
G   In support of this contention, Mr.Krishnamurthy placed strong
    reliance on a decision of this Court in the case of Ashok Kumar
    and Ors. Vs. State of Haryana and Another2007 (3) SCC 470.            . ...
        6. As noted herein earlier, Mr.Viduthalai, the learned
    senior counsel appearing for the respondents submitted that
H
                  R. KOLANDAIVELU & ORS. v. GOVT. OF TAMIL                 389
                     NADU & ANR. [TARUN CHATTERJEE, J.]
->   ~
               on a perusal of the orders passed by the High Court on the A
               question of grant of order of stay, it would be evident that the
               parties had proceeded all along on the basis that the interim
               order of stay granted for a limited period had continued upto
               the stage when the interim order of stay was made absolute
               on the same terms and further in view of the findings of the High B
               Court that both the parties proceeded on the basis that the
               interim order of stay was continuing all through, it must be held
... •          that the time during which the interim order of stay was
               continuing i.e. from 11th of February, 1988 to 3rd of July, 1991
               must be excluded from the calculation of the period within the      c
               meaning of explanation to Section 11A of the Act and if this
               time is excluded, the award which was passed on 23rd of
               August, 1993 was well within time and, therefore, the High Court
               was fully justified in concluding that the question of holding that
               since the award was passed beyond the period of 2 years from D
     •    A    the date of declaration, the entire acquisition proceedings must
               be held to have lapsed, does not arise at all. In support of this
               submission, the learned senior counsel appearing for the
               respondents has relied on two decisions of this Court namely
               Bailamma (Smt.) Alias Doddabailamma and others Vs. E
               Poornaprajna House Building Cooperative Society and
               others 2006 (2) SCC 416 and Yusufbhai Noormohamed
               Nendoliya Vs. State of Gujarat and another 1991 (4) SCC
         _.,   531. Accordingly, Mr.Viduthalai, learned senior counsel for the
               respondents has submitted that there is no reason to interfere
                                                                                   F
               with the orders of the High Court holding that the respondents
               were entitled to exclude the period in terms of the explanation
               to Section 11 A of the Act.

                    7. We have carefully examined the rival submissions of the
               learned senior counsel for the parties. We have also examined       G
               the impugned order of the High Court as well as the relevant
     ~"        provisions of the Act, namely, Sections 6 and 11A with its
               explanation, as noted herein earlier. From a perusal of the
               aforesaid provisions, it would be evident that the two years from
               the date of declaration must be computed after excluding the        H
    390 SUPREME COURT REPORTS (2009] 16 (ADDL.) S.C.R.

                                                                               ~    ~


A period when parties had approached the court and obtained
  interim stay of such acquisition notices. As noted herein earlier,
  at the time of admission of the writ petitions, the following
  interim order was passed on 11th of February 1988 :-

         "Interim stay for four weeks. Notice returnable in four
B
         weeks"

          8. Subsequent to the passing of this interim order, it is true
    that the interim order was not extended by any further order of
                                                                           ;       ...
    the Court. However, the parties thought that the interim order
c   was continuing. Keeping that in mind, the State/respondents
    filed an application for vacating the interim order dated 11th of
    February, 1988 granted by the Court.
       9. On 3rd of July, 1991, on the said application for vacating
D the interim order filed at the instance of the State/respondents,
  the High Court passed the following order:-                              ~   .
        "These petitions coming on for hearing upon perusing the
        petitions and the respective affidavits filed in support of
        W.P. Nos. 835 and 836/88 on the file of the High Court
E       and the order of this Court dated 11.02.88 and made in
        W. M.P. Nos. 1248 and 1249 of 1988 and the counter
        affidavits filed herein and upon hearing the arguments of
        Mr. N. Chinnu, Advocate for the petitioners in W.M.P. Nos.
        1248 and 1249/88 and for the respective respondents in             )c.


F       W. M. P. Nos. 11986 and 11987/90 and Mrs. M. Gomathi,
        Govt. Advocate (Writs) on behalf of the respondents in
        W.M.P. Nos. 1248 and 1249/90 and for the petit:oners in
        W.M.P. Nos. 11986 and 11987of1990, it is 0~...iered; that
         the dispossession of the petitionsers (in W.M.P. Nos.
G        1248 and 1249190) of tfieir lands alone in (1) Survey No.
         99/3A, an extent of 1.34 acres of Ayothipatnam Village,
         Sa/em Ta/uk, Salem District (in W.M.P. Nos. 1248188)              1.,
         and (2) 1-37 acres in Survey Nos. 9813 and 9814,
         Ayothiapatnam Village, Sa/em District in W.M.P. No.
H        1249188 respectively pursuant to the Section 4(1)
             R. KOLANDAIVELU & ORS. v. GOVT. OF TAMIL                    391
                NADU & ANR. [TARUN CHATIERJEE, J.]

               Notification in G. 0. Ms. No. 3320, Social Welfare, dated A
               24.12.1986, on the file of the first respondent in both the
               petitions, and published at page 21 of the Parl-11 Section
               - 2 Supplement to Tamil Nadu Govt. Gazette Issue No.
               1C, dated 07.01.1987, and Section-6 Declaration in G.O.
               Ns. No. 2532, Social Welfare, dated 08.12.1987, and B
               published at pages 23 and 24 of part-fl Section 2
:,.            Supplement to Tamil Nadu Govt. Gazette issue No. 49-
               C, dated 23.12.1987, in so far as they relate to the lands
               of the petitioners in each of the petitions be and hereby
               are stayed pending further orders on this petition." C
               (Emphasis supplied)

                10. As noted herein earlier, c:t the instance of the
           appellants, the notification issued under Section 4 of the Act
           and the declaration under Section 6 initially were stayed for four    0
      • A weeks on 11th of February, 1988, but the Interlocutory
           Applications remained pending for final disposal and finally on
           the applications to vacate the stay order at the instance of the
           State/respondents, the applications to vacate the stay were
           disposed of, as noted herein earlier by an order which clearly        E
           shows that the order of stay granted initially for four weeks would
           continue pending further orders. From a perusal of the
           aforesaid interim order of the High Court passed on 3rd of July,
           1991, it is, therefore, evident that there was an order of
       - ~ prohibition from dispossessing the appellants from the acquired
           lands pending further orders.                                         F

             11. In view of our discussions made herein above and
        considering the nature of interim order of stay passed by the
        High Court finally on 3rd of July, 1991, it is abundantly clear that
        both the parties proceeded on the basis that the interim order           G
• ~     of stay had been continuing and the respondents were
  .._ i prohibited from dispossessing the appellants from the acquired
        lands pending .further orders. If that was not the case, the
        question of filing an application for vacating the order of stay
        granted in favour of the appellants could not arise at all and           H
    392 SUPREME COURT REPORTS [2009) 16 (ADDL.) S.C.R.


A there was no occasion for the appellants to contest the
  application for vacating the stay order on the basis that the
  interim order of stay was continuing and should be allowed to
  continue. That apart, it may be stated that although initially the
  interim order was passed for four weeks, the same interim
a order which was granted initially was made final until further
  orders on 3rd of July, 1991. From the above narration of facts,
  it must be held that no steps could be taken in view of the
  pending applications for grant of interim order and in view of '
  the interim order granted pending further orders. Therefore, it
C cannot be said that the acquisition proceedings had lapsed due
  to expiry of two years from the date of publication of the
  declaration under Section 6 of the Act relating to the acquired
  lands.

       12. In Yusufbhai Noormohamed's case (supra) at para 8,
D this Court observed as under:-

        "The said Explanation is in the widest possible terms and,
        in our opinion, there is no warrant for limiting the action or
        proceeding referred to in the Explanation to actions or
E       proceedings preceding the making of the award under
        Section 11 of the said Act. In the first place, as held by
        the learned Single Judge himself where the case is
        covered by Section17, the possession can be taken

F
        before an award is made and we see no reason why the
        aforesaid expression in the Explanation should be given
                                                                         .-
        a different meaning depending upon whether the case is
        covered by Section17 or otherwise. On the other hand, it
        appears to us that Section11-A is intended to 1i!'n1t the
        benefit conferred on a land holder whose land is acquired
        after the declaration under Section 6 is made to in cases
G
        covered by the Explanation. The benefit is that the award
        must be made within a period of two years of the                 ~ ~
        declaration, failing which the acquisition proceedings
        would lapse and the land would revert to the /and-holder.
        In order to get the benefit of the said provision what is
H
                      R. KOLANDAIVELU & ORS. v. GOVT. OF TAMIL                   393
                         NADU & ANR. [TARUN CHATIERJEE, J.]

-.                     required, is that the /and-holder who seeks the benefit A
                       must not have obtained any order from a court restraining
                       any action or proceeding in pursuance of the declaration
                       under Section 6 of the said Act so that the Explanation
                       covers only the cases of those /and-holders who do not
                       obtain any order from a court which would delay or B
                       prevent the making of the award or taking possession of
                       the land acquired.
  ->
              •                                                (emphasis supplied)

                         13. From the above observations of this Court, it is clear      c
                   that the explanation to Section 11A of the Act is intended to
                   confer a benefit on the land holder, whose land is acquired after
                   the declaration under Section 6 is made. By the provision of
                   Section 11A, the State authorities are required to pass a final
                   award within two years from the date of publication of                D
       .      ~
                   declaration under Section 6 of the Act failing which, the
                   acquisition proceedings would lapse, and it would clearly show
                   the intention of the legislature that the benefit of this provision
                  would be in favour of the land owner if the award could not be
                  passed within two years from the date of declaration when no           E
                  order was obtained by the land owner from the Court staying
                  the acquisition and the land would revert back to the land owner
                  because of expiry of the period of two years from the date of
                  declaration or notification within the meaning of Section 11A
       -,.        of the Act. As noted herein earlier, initially the interim order of    F
                  stay was granted staying the notifications for four weeks, but
                  from the record and the conduct of both the parties and after
                  considering the fact that the State/respondents had to file an
                  application for vacating the stay order thinking that stay order
                  was continuing and the appellants having contested the said            G
                  application for stay till the disposal of the same, there cannot
                  be any doubt in our mind that both the parties proceeded on
........ -t       the basis that the interim order of stay passed initially for four
                  weeks continued till the final order of interim stay passed by
                  the High Court on the application for vaca_ting the interim order
                                                                                         H
    394 SUPREME COURT REPORTS [2009] 16 (ADDL.) S.C.R.


A   of stay.

       14. Such being the stand taken by us, we are, therefore,
                                                                       t
                                                                               -
  of the view that the award was passed in accordance with
  Section 11A of the Act, that is to say, the award was passed
  within two years from the date of publication of declaration under
B
  Section 6 of the Act.

        15. There is another aspect of the matter. The purpose for
  which the Land Acquisition Act was amended and Section 11A
                                                                               -< "
  was enacted, was to prevent inordinate delay being caused by
c the Land Acquisition Officer in making an award which deprived
  the land owners of their enjoyment of their land or dealt with the
  land whose possession was already taken. The delay in making
  the award subjected the owner of the land to untold hardship.
  The objects and reasons for introducing Section 11A into the
D Act were that "the pendency of acquisition proceedings for long
  periods often causes hardship to the affected parties and
  renders unrealistic the scale of compensation offered to them"
  and "it is proposed to provide for a period of two years from
                                                                       .   ~




  the date of publication of the declaration under Section 6 of the
E Act within which the Collector should make his award under the
  Act". By the introduction of this explanation and Section 11 A
  of the Act, the Legislature intended to emphasize that the
  Collector shall make his award under the Act within two years
  from the date of publication of declaration under Section 6 of
F the Act, failing which the acquisition proceeding itself shall       .. -
   lapse. In this connection, reliance can be made to a decision
   of this Court in Bailamma (supra) as noted herein earlier. In
  this decision, this Court had considered the effect of the
   amendment of the Act introducing Section 11A with explanation
   and observed in this connection as follows :
G
         "This Court emphasized the fact that Section 11-A was
         enacted with a view to prevent inordinate delay being
         made by Land Acquisition Officer in making the award          I; .. ~

         which deprived owners of the enjoyment of the property or
H        to deal with the land whose possession has already been
               R. KOLANDAIVELU & ORS. v. GOVT. OF TAMIL              395
                  NADU & ANR. [TARUN CHATIERJEE, J.]


-     +
                taken Delay in making the award subjected the owner of A·
                the land to untold hardship. The objects and reasons for
                introducing Section 11-A into the Act were that "the
                pendency of acquisition proceedings for long periods often
                causes hardship to the affected parties and renders
                unrealistic the scale of compensation offered to them" and B
                "it is proposed to provide for a period of two years from
                the date of publication of the declaration under Section 6
                of the Act within which the Collector should make his
..,        •    award under the Act". The emphasis, therefore, was on the
                Collector making his award within the period prescribed. c
                However, the legislature was also aware of the reality of
                the situation and was not oblivious of the fact that in many
                cases acquisition proceedings were stalled by stay orders
                obtained from courts of law by interested parties. It,
                therefore, became imperative that in computing the period
                                                                               D
                of two years, the period during which an order of stay
      ...       operated, which prevented the authorities from taking any
                action or proceeding in pursuance of the declaration, must
                be excluded. If such a provision was not made, an
                acquisition proceeding could be easily defeated by
                obtaining an order of stay and prolonging the litigation E
                thereafter. Explanation to Section 11-A was meant to deal
                with situations of this kind. The explanation is in the widest
                possible terms which do not limit its operation to cases

      --   .    where an order of stay is obtained by a land-owner alone.
                One can conceive of cases where apart from land- owners F
                others may be interested in stalling the land acquisition
                proceeding. It is no doubt true that in most of the reported
                decisions the party that obtained the stay order happened
                to be the owner of the land acquired. But that will not lead
                us to the conclusion that the explanation applied only to G
                cases where stay had been obtained by the owners of the
.......
~
                land. There may be others who may be interested in
                obtaining an order of stay being aggrieved by the
                acquisition proceeding. It may be that on account of
                development of that area some persons in the vicinity may H
    396 SUPREME COURT REPORTS [2009] 16 (ADDL.) S.C.R.


A       be adversely affected, or it may be for any other reason
        that persons in the locality are adversely affected by the
        project for which acquisition is being made. One can
                                                                         +
                                                                                 -
        imagine many instances in which a person other than the
        owner may be interested in defeating the acquisition
B       proceeding. Once an order of stay is obtained and the
        Government and the Collector are prevented from taking
        any further action pursuant to the declaration, they cannot



c
        be faulted for the delay, and therefore, the period during
        which the order of stay operates must be excluded. In a
        sense, operation of the order of stay provides a justification
        for the delay in taking further steps in the acquisition
                                                                                 -
        proceeding for which the authorities are not to blame."

       16. Following the principles laid down and the observations
  made by this Court in the aforesaid decision, with which we are
D in respectful agreement, we are, therefore, of the view that the
  State/respondent was entitled to exclude the period mentioned
  herein earlier and that it must also be held that if such period
                                                                         .   ~




  is excluded the period of two years from the date of declaration
  under Section 6 of the Act before the award is passed would
E not expire and accordingly, the question of holding that the
  entire acquisition proceeding shall lapse, cannot arise at all.
       17. Before we part with this judgment, we may deal with
  the decision of this Court as relied on by the learned senior
F counsel for the appellants in Ashok Kumar's case (supra). In           ~~-


  our view, this decision stands on a different footing. In that
  decision, it is true that the interim order of injunction was
  passed but not extended whereas in the present case
  admittedly the interim order which was granted by the court for
  a limited period was extended till further orders by an order
G
  dated 3rd of July, 1991 which was passed on the application·
  for vacating the order of stay filed by the State/respondents .
  Such being the position and in view of our discussions made
                                                                           .......
                                                                         ........
  herein above, therefore, the appellants having taken advantage
  of an order passed by the High Court during the pendency of
H
          R. KOLANDAIVELU & ORS. v. GOVT. OF TAMIL               397
             NADU & ANR. [TARUN CHATIERJEE, J.]
       the writ petition which was sought to be vacated by the State/ A
       respondents by filing an application for vacating the stay order,
       it must be concluded that the award was passed within two
       years from the date of publication of the declaration under
       Section 6 of the Act and the respondents were entitled to
       exclude the period from 11th of February, 1988 to 3rd of July, B
       1991 and, therefore, if this period is excluded as enshrined in
       the explanation to Section 11A of the Act, the award was within
       time and, therefore, the question of holding that the acquisition
       proceeding must lapse because of expiry of the said period,
       cannot arise at all. No other submissions were advanced by c
       the learned counsel for the parties.

             18. For the reasons aforesaid, we do not find any reason
       to interfere with the impugned order passed by the High Court
       and accordingly the appeal is dismissed. There will be no order
       as to costs.                                                      D

·- '   D.G.                                       Appeal dismissed.


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Land acquisition"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.