SHREE SAI ENGINEERINGversusDAKSHIN GUJARAT VIJ COMPANY LIMITED
- Disposal
- DISPOSED AS INFRUCTUOUS
- Bench
- HEMANT M PRACHCHHAK
Holding
The petition is held to be infructuous as the relief sought has already been granted.
Summary
Shree Sai Engineering filed a special civil application seeking an electricity connection from Dakshin Gujarat Vij Company Limited. The respondent company supplied the connection to the petitioner’s premises at Plot No. 722, GIDC, Ankleshwar. The petitioner’s counsel argued that the grievance remained, but the respondent contended that the relief had already been granted, rendering the petition infructuous. The Court examined whether any further relief could be granted and concluded that the petition no longer had any operative relief. Accordingly, the petition was disposed of as infructuous, and the notice was discharged. The Court left open the possibility for the petitioner to raise any other issues in a separate proceeding.
Issues considered
- Whether the petition becomes infructuous after the respondent supplies the electricity connection sought by the petitioner
Subjects
Judgment
C/SCA/9599/2023 ORDER DATED: 17/03/2026
IN THE HIGH COURT OF GUJARAT AT AHMEDABAD
R/SPECIAL CIVIL APPLICATION NO. 9599 of 2023
================================================================
SHREE SAI ENGINEERING
Versus
DAKSHIN GUJARAT VIJ COMPANY LIMITED & ANR.
================================================================
Appearance:
MR HIMANSHU C DESAI(6832) for the Petitioner(s) No. 1
MR CHINMAY M GANDHI(3979) for the Respondent(s) No. 1
MS RUMI M GANDHI(3472) for the Respondent(s) No. 1
MS NIRALI SARDA, ASST. GOVERNMENT PLEADER for the Respondent(s)
No. 2
================================================================
CORAM:HONOURABLE MR. JUSTICE HEMANT M.
PRACHCHHAK
Date : 17/03/2026
ORDER
When the matter is taken up for hearing, learned counsel Mr.
Chinmay Gandhi, appearing on behalf of the respondent-Company,
has submitted that the grievance raised in the present petition does
not survive any longer, as the respondent-Company has supplied
electricity connection to the petitioner at the premises located at Plot
No. 722 of GIDC, Ankleshwar and therefore, the present petition has
become infructuous.
In view of above, present petition stands disposed of as having
become infructuous. Notice is discharged.
So far as the other issues are concerned, it is open for the
petitioner to agitate the same by way of 'ling appropriate
proceedings in a di(erent petition.
(HEMANT M. PRACHCHHAK,J)
Dolly
Original copy of this order has been signed by the Hon'ble Judge.
Digitally signed by: DOLLYBEN CHETANBHAI VADUKAR(HC01392), PRIVATE SECRETARY, at High Court of Gujarat on 18/03/2026 15:20:33
Page 1 of 1