Created byFuzzy Cloud

Supreme Court of India

STATE OF MADHYA PRADESH & ANRversusMEDHA PATKAR & ORS.

Citation
2011 INSC 531
Decided
2 August 2011
Disposal
Disposed off

Holding

Canal‑affected persons cannot be treated on par with oustees of submergence; they are not covered by the definition of "oustee" and therefore are not entitled to the same R&R package, though they may receive supplementary compensation as per the Land Acquisition Act, 1894.

Summary

After the completion of the Indira Sagar and Omkareshwar dams, the Madhya Pradesh government initiated land acquisition for canal construction under the Land Acquisition Act, 1894. Medha Patkar and other petitioners challenged the acquisition, arguing that the Command Area Development (CAD) plans had not been submitted to or approved by the Ministry of Environment and Forests, that the PESA Act required prior Panchayat consultation, and that canal‑affected persons should receive the same rehabilitation and resettlement benefits as those displaced by submergence. The High Court held that canal‑affected persons were entitled to the same benefits, a view the State appealed. The Supreme Court held that the definition of "oustee" under the Narmada Water Dispute Tribunal award does not include canal‑affected persons and that they cannot be placed on par with submergence‑affected persons, but allowed the State to make supplementary awards by treating the Section‑4 notification date as the date of the judgment and recomputing market value under the Land Acquisition Act. The Court also clarified that any further canal work must obtain MoEF clearance. The appeal was disposed of, with the State directed to award the supplementary compensation and to seek environmental clearance for future work.

Issues considered

  • The adequacy of CAD plans and their approval by the Ministry of Environment and Forests before land acquisition for canals
  • Whether canal‑affected persons are entitled to the same rehabilitation and resettlement benefits as oustees of submergence under the Narmada Water Dispute Tribunal award and the R&R Policy
  • Compliance with the PESA Act in land acquisition within scheduled areas

Legislation cited

Subjects

land acquisitioncanal affected personsrehabilitation and resettlementNarmada Valley projectsenvironmental clearancePESA Actcommand area development planscompensationsupplementary awardSupreme Court

Judgment

                         [2011] 9 S.C.R. 664


A             STATE OF MADHYA PRADESH & ANR
                                  v.
                      MEDHA PATKAR & ORS.
                   (Civil Appeal No. 6229 of 2011)

                          AUGUST 2, 2011
                                                                          •
B
             [J.M. PANCHAL, DEEPAK VERMA AND
                    DR. B.S. CHAUHAN, JJ.]

         LAND ACQUISITION:
c
        Acquisition of land to set up canals - Compensation -
   'Canal affected persons' - After construction of Indira Sagar
   Project and Omkareshwar Dam, land acquired for setting up
   canals - Writ petition claiming full benefits of Rehabilitation
                                                                     ..
0 and Resettlement Policy framed for Narmada Valley Projects,
   for canal affected persons also - Held: This Court in Narmada
   Bachao Ando/an-I has held that 'canal affected persons'
   cannot be put at par with 'submergence affected persons' - It
   was not permissible for the High Court to take a contrary view
E - The definition of 'oustee' under the Narmada Water Dispute
   Tribunal Award does not take within its ambit the 'canal
  affected person' nor does the said award apply to the projects
  in the instant case - However, in the interim order, Supreme
  Court has taken care of 'hardship cases' - Further, as
  suggested by the State Government, the date of s. 4
F notification shifted to the date of the instant judgment in
  relation to the canal affected persons and the Land Acquisition
  Collector directed to reconsider the market value of the land
  in question accordingly and make supplementary awards in
  accordance with the provisions of the Land Acquisition Act -
G It is clarified that the further canal work would be subject to
  clearance which may be given by MoEF - Land Acquisition
  Act, 1894 - Public Interest litigation - Precedent.

        On completion of Indira Sagar Project and
H                                664
 STATE OF MADHYA PRADESH & ANR. v. MEDHA 665
              PATKAR & ORS.
Omkareshwar dam, in order to set up canals, land A
acquisition proceedings under the provisions of the Land
Acquisition Act, 18994 were initiated. The respondents
filed a writ petition before the High Court challenging the
acquisition of land for construction of canals on the
grounds, inter-a/ia, that Command Area Development B
plans (CAD Plans) had not been submitted by the State
nor had it been approved by the Ministry of Environment
and Forest (MoEF); that there had been no compliance
of Panchayats (Extension of Scheduled Areas) Act, 1996
(PESA Act) which required consultation with office c
bearers of Panchayats before initiation of land
acquisition proceedings; that the canal affected persons
were also entitled for the full benefit of Rehabilitation and
Resettlement Policy (R&R Policy) framed for the Narmada
Valley Projects, including the allotment of land in lieu of · D
the land acquired as per R & R policy.

    The High Court held, inter a/ia, that though there was
an intelligible differentia in making the classification
between the oustees of submerged areas of dam and
canals, but the same has no rational nexus with the             E
object to achieve so far as the rehabilitation was
concerned and, therefore, the persons affected by canal
work were entitled to the same benefit as that of
submergence affected persons. Aggrieved, the State
Government filed the appeal.                                    F

    Disposing of the appeal, the Court
    HELD: 1.1 It is evident from the Narmada Water
Disputes Tribunal Award, 1997 that the definition of
'oustee' does not take within its ambit the "canal affected     G
person". However, the said award does not apply to the
projects in the instant case, as it was meant only for Inter-
state projects like Sardar Sarovar Project. [para 13] [676-
E-F; 677-C]
                                                                H
    666    SUPREME COURT REPORTS              [2011] 9 S.C.R.
                                                                  ~



A      1.2 So far as the Indira ·Sagar Project is concerned,
  it was given clearance on 24.6.1987 and did not have any
  specific direction for r~habilitation. Similarly, for
  Omkareshwar Project, clearance was granted on
  13.10.1993 and part (vii) thereof provided that the                         ~

B rehabilitation programme would be extended to landless
  labourers and people affected due to canal by identifying       •
  and allocating suitable land "as permissible". The words
  "as permissible" have been interpreted by this Court* and
  there is no reason to reconsider the issue afresh. [para
c 14) [677-D·F]

        *Narmada Bachao Ando/an v. State of M.P., AIR 2011
    SC 1989 - relied on.
       1.3 This Court in Narmada Bachao Andolan-r* has                    '
D taken a view that the canal affected persons cannot be
  put at par with the submergence affected persons. In
  view of the fact-situation, it was not permissible for the
  High Court to take a view contrary to the view taken by
  this Court, particularly, when the High Court came to the
E conclusion that there was a reasonable differentia
  between the two. However, this Court by an interim order
  dated 5.5.2010 has also taken care of "hardship cases"
  in canal affected areas. [paras 18-19) [678-G-H; 679-A-B]
                                                                      r
      ** Narmada Bachao Ando/an v. Union of India & Ors.
F 2000 (4) Suppl. SCR 94 = (2000) 10 SCC 664 - relied on.

       1.4 The State has graciously agreed that in order to
  give more benefit to canal affected persons, the Court
  may award some more benefits. The State has suggested
G that in order to achieve the purpose, the date of s. 4                  •
                                                                      1
  Notification, irrespective of its actual date, in relation to
  all canal affected persons be shifted (postponed) to the
  date of this judgment and the market value of the land be .
  re-determined according to the provisions of the Act 1894
H making the supplementary awards and giving the
     · STATE OF MADHYA PRADESH & ANR. v. MEDHA               667
                    PATKAR & ORS.

     opportunity to such oustees further for filing reference u/    A
     s 18 of the Act 1894. In this view of the matter, the Land
     Acquisition Collector is directed to reconsider the market
     value of the land of the canal affected persons as if s.4
     Notification in respect of the same has been issued on
     date, i.e. 2.8.2011, and make the supplementary awards         B
     in accordance with the provisions of the Act 1894. Such
     concession extended by the State would be over and
     above the relief granted by this Court by order dated
     5.5.2010 as clarified/modified subsequently and it is
     further clarified that further canal work would be subject     c
     to clearance/direction which may be given by MoEF. [para
     20) (679-B-F]

                         Case Law Reference:
         2000 (4) Suppl. SCR 94     relied on           para 5      D
         AIR 2011 SC 1989           relied on           para 14
         CIVIL APPELLATE JURISDICTION : Civil Appeal No.
     6229 of 2011.
                                                                    E
         From the Judgment & Order dated 11.11.2009 of the High
     Court of Madhya Pradesh at Jabalpur in W.P. (C) No. 6056 of
     2009.
/"      T.R. Andhyarujina, C.D. Singh, Sunny Chaudhary, Shomick
     Ghosh, Abhimanyu Singh for the Appellants.                     F

          Mohan Jain, ASG, D.K. Thakur, Prabhat Kumar, Rekha
     Pandey, Shreekant N. Terdal, Sanjay Parikh, Mamta Saxena,
     Anitha Shenoy, Syed Naqvi, N.K. Sharma, lina, Rajesh Kumar,
     Medha Patkar (Respondent In Person) for the Respondents.       G
•)
         The Judgment of the Court was delivered by

         DR. B. S. CHAUHAN, J. 1. Leave granted.

         2. This appeal has been preferred by the State of Madhya   H
    668        SUPREME COURT REPORTS                [2011] 9 S.C.R.
                                                                       .... ,

A Pradesh and instrumentality of the State against the judgment
  and order dated 11.11.2009 in Writ Petition (C) No.6056 of
  2009 of the High Court of Madhya Pradesh at Jabalpur,
  whereby the High Court has restrained the State of Madhya
  Pradesh or any other statutory authority of further acquisition                    '
B of land or for any excavation or any construction of the canal
  network for the command areas of the Indira Sagar and
  Omkareshwar projects till the Command Area Development
  plans (hereinafter called CAD Plans) submitted to the
  Government of India, Ministry of Environment and Forest
c (hereinafter called MoEF) are scrutinized by the committee of
  experts and clearance is granted by the said Ministry. The
  appellant-State Government has further been directed to
  provide rehabilitation and resettlement benefits under the
  Rehabilitation and Resettlement Policy (hereinafter called R&R                ..
  Policy) for Narmada Valley Projects to the canal affected
D
  persons/families of Indira Sagar and Omkareshwar projects
  and the Narmada Control Authority (hereinafter called NCA) has
  been directed to ensure implementation of the aforesaid
  directions.

E          3. The facts and circumstances giving rise to this appeal
    are:

       A. That after completing the procedure prescribed for
                                                                       .r
  establishment of dams and irrigation projects, the project
F reports for Indira Sagar and Omkareshwar projects were
  prepared and submitted for clearance. The environmental
  clearance for Indira Sagar project was granted by MoEF on
  24.6.1987 by an administrative order. The Planning
  Commission also approved investment to be made in Indira
  Sagar project on 6.9.1989.
G
        B. The R & R Policy of 1989 was introduced by the State
  of Madhya Pradesh for the oustees of submerged area in
  Narmada Valley projects. Land acquisition proceedings were
  initiated in year 1991 for canal construction under Indira Sagar
H project. A comprehensive CAD plans for Omkareshwar project

                                                                                     -
                    STATE OF MADHYA PRADESH & ANR. v. MEDHA 669
         " ....         PATKAR & ORS. [DR. S.S. CHAUHAN, J.]

                  were sent to MoEF for clearance. Environment Impact                     A
                  Assessment and Environment Management Plan reports were
                  also submitted for Omkareshwar project to MoEF which also
                  contained the R & R plan for lhe affected persons of the
~                 Omkareshwar project. It provided that the persons whose land
            ~     was to be acquired for establishment of canals were not to be           B
                  included in R & R plans.

                       C. The Ministry of Welfare, Government of India accorded
                  clearance to the R & R plan of Omkareshwar project on
                  8.10.1993. Similarly, by an. administrative order environmental
                  clearance for Omkareshwar project was granted by MoEF on                c
                  13.10.1993.

    'I
                       D. The MoEF ·issued statutory notification under Section
                  3(2) of Environment (Protection) Act, 1986 (hereinafter called
          •       the Act 1986) read with Rule 5(3) of the Environment                    D
                  (Protection) Rules 1986 requiring environmental clearance for
                  development of project on 27.1.1994. The canal construction
                  in Indira Sagar project started on 30.5.1999. The NVDD vide
                  order dated 14.8.2000 amended the definition of "Displaced
                  person" adding in clause 1(a) the following words:                      E
                       "..... or is required for the project-related canal construction
                       and construction of the Government Project Colony."
     /'>
                       The Planning Commission granted approval in respect of
                  Omkareshwar project on 15.5.2001. The R & R policy stood                F
                  materially changed vide amendment dated 1.9.2003 as from
                  the definition of "displaced person" the words ·''which is required
                  for project related construction of canals or the Government
                  project colony" stood deleted .
          •••

                                                                                          G
                      The Amendment to the Rehabilitation Policy was made by
                  the Narmada Control Board (NCB) on the recommendation of
                  the NVDA on 2.7.2003 as per Business Rules of Narmada
                  Control Board Part II Special Procedure for Emergency
                                                                                          H
    670     SUPREME COURT REPORTS                  [2011] 9 S.C.R.
                                                                        ••
A Sanction and not under the Government of Madhya Pradeh
  Business Rules.

        E. The dam construction of Indira Sagar project stood
  completed in year 2005 and the High Court, in a pending
  litigation, permitted the State of Madhya Pradesh to raise water
8 level of Indira Sagar Dam upto 260 meter against the full
  reservoir level of 262.13 meters vide order dated 8.9.2006. The
  High Court further clarified that NCA had no role to play
  regarding the Indira Sagar project i.e. intra-State project as its
  role was confined to inter-State Project, i.e. Sardar Sarovar
C Project.

          F. The Omkareshwar dam stood completed in year 2007.
    In order to set up canals, land acquisition proceedings were
    initiated in year 2009 and in some cases after conclusion of
o   the proceedings, compensation under the provisions of Land
    Acquisition Act, 1894 (hereinafter called the Act 1894) has
    been paid. However, in some cases acquisition proceedings
    are still in progress.

       G. The respondents preferred Writ Petition (C) No.6056
E of 2009 before the High Court of Madhya Pradesh at Jabalpur
  on 18.6.2009 challenging the acquisition of land for excavation
  of canals; execution, excavation and construction of canal on
  various grounds, inter-a/ia; the CAD Plans had not been
  submitted by the State and not approved by the MoEF; there
                                                                        .. '
F had been no compliance of Panchayats (Extension of
  Scheduled Areas) Act, 1996 (hereinafter called PESA Act)
  which required consultation with office bearers of Panchayats
  before initiation of land acquisition proceedings; the canal
  affected persons were also entitled for the full benefit of R & R
G Policy including the allotment of land in lieu of the land acquired
  as per R & R policy, which had not been provided for.

       H. The State of M.P., appellant herein contested the case
  contending that land acquisition proceedings could not be
H challenged at a belated stage i.e. after dispossession of the

                                                                               .
               STATE OF MADHYA PRADESH & ANR. v. MEDHA                   671
                   PATKAR & ORS. [DR. B.S. CHAUHAN, J.]
    ......    tenure holders; authorities had submitted the CAD Plans and A
              acted on the same after being approved by the MoEF. Canal
              affected person could not be treated at par with an oustee of
              the submerged area of the dam, rather he would be given
              benefit as per the policy prescribed for such a class of persons.
t                                                                               B
                   4. The High Court after considering the rival submissions
          •   held as under:

                   (I) The CAD Plans of Indira Sagar and Omkareshwar
              projects were required to be prepared and submitted to the
                                                                               c
              authority entrusted with the responsibility of monitoring, planning
              and implementation of environmental safeguards and this was
              to be done before the commencement of the canals so that
              such authority could ensure that the environmental safeguards
              and mitigative measures had been properly planned and could
    •         be implemented pari passu with the construction of the ·canal D
     .,       project.

                   (II) If land is acquired and excavated before preparation
              and submission of CAD Plans to such monitoring authority,
              environmental safeguards could not be implemented pari passu E
              with the construction of canal project. Rather, if the main canals
              and branch canals are constructed without keeping in mind the
              environmental requirements then there may be immense
              problem of water logging and salinity disturbing the
    /':>      environmental plans and the authority entrusted to ensure the
                                                                                 F
              environmental safeguards may not be able to reverse the
              acquisition of land.

                   (Ill) There was an intelligible differentia in making the
              classifieation between the oustees of submerged areas of dam
              and canals but have no rationale nexus with the object to G
     J
         ..   achieve so far as the rehabilitation was concerned. Thus, the
              person·s affected by canal work were entitled to the same
              benefit as that of submergence affected persons.

                   (IV) In view of the provisions of Sections 3 and 4{i) of H
    672      SUPREME COURT REPORTS                  [2011] 9 S.C.R.


A   PESA Act, the State Legislature was not competent to make
    any law under Part IX of the Constitution of India inconsistent
    with the basic features of the Gram Sabha or Panchayats at
    the appropriate level requiring consultation for land acquisition
    in the scheduled area for the development projects. Therefore,
s   it was not permissible for the court to issue direction to the
    authorities to consult Gram Sabha before acquisition of land.

         (V) Challenge to the acquisition of land could not be
    entertained at a belated stage as the possession of the land
C   had been taken long back.

        (VI) The clearance from MoEF requires the agents to
    monitor the environmental protection measures.

         In view of the above, the High Court issued directions as
D   explained in para 2 hereinabove. Hence, this appeal.

        5. Shri T.R. Andhyarujina, learned senior counsel
   appearing for the appellants has submitted that CAD Plans
   have been submitted by the authorities from time to time to the
   ministries of the Central Government and have got the
E clearances and the work had been executed giving strict
   adherence to those clearances. Even at present, the revised
   CAD Plans have been submitted and are being considered by
  the Expert Committee of the MoEF, wherein the respondent-
   Ms. Medha Patkar has also been heard. As voluminous
F documents have been submitted by her and this Court had
  been issuinu directions from time to time, the MoEF has yet to
  take the final decision. The State authorities are bound to
  proceed in accordance with the final decision taken by the
   MoEF and in case the CAD Plans are not found to be
G appropriate or complete and the MoEF issues certain
  directions or asks for some variations etc. the State
  Government would proceed accordingly. Therefore, according
  to Mr. Andhyarujina, the issue of submission and clearance of
  CAD Plans should not be decided at this stage by the court. It
H is further submitted by Mr. Andhyarujina that in case a party is
                     STATE OF MADHYA PRADESH & ANR. v. MEDHA 673.
                         PATKAR & ORS. [DR. B.S. CHAUHAN, J.]
         ...        aggrieved by the order to be passed by MoEF, it would be            A
                    open to it to challenge the said order before the appropriate
                    forum.

                         So far as the issue of rehabilitation is concerned, it has
..                  been canvassed on behalf of the State that question of putting
                                                                                        B
                    the canal affected persons at par with submergence affected
                •   persons does not arise. This Court in Narmada Bachao
                    Ando/an v. Union of India & Ors., (2000) 10 SCC 664,
                    (hereinafter called "Narmada Bachao Ando/an /'') has
                    categorically held that both classes are different and cannot be
                    put on equal footings. The canal affected people may rather be
                                                                                        c
                    benefited because of the canals while the submergence
                    affected persons may suffer permanently or temporarily.
                    Therefore, to that effect, the High Court was not justified in
     y              issuing direction to treat both the classes at par.
                                                                                        D
           'r            6. On the other hand, Ms. Medha Patkar, respondent-in-
                    person and Mr. Sanjay Parikh, learned counsel for the
                    respondents have submitted that there is no difference in the
                    sufferings of the persons, whether they are submergence
                    affected persons or canal affected persons. No rationale nexus      E
                    can be found to treat them differently. Therefore, the High
                    Court's finding to that extent does not require any interference.
                    The CAD Plans submitted by the State authorities are not
                    complete and are being examined by the Expert Committee
         ,/"'),
                    of the MoEF. Therefore, the High Court has rightly directed the     F
                    authority not to proceed with excavation or establishment of
                    canals etc. The facts of the case do not warrant any interference
                    by this Court. Appeal lacks merit and is liable to be dismissed.

                         7. We have considered the rival submissions made by
                    learned counsel for the parties and perused the record .            G
          • ~

                        8. Though, a large nu'mber of issues have been agitated .
                    before the High Court and dealt with, some of them have not
                    been agitated before us. The issue of consultation with the
                    Gram Sabha or Panchayats before acquisition of land and H
    674       SUPREME COURT REPORTS                [2011) 9 S.C.R.


A validity of the acquisition proceedings had been dealt with by
                                                                       ....
  the High Court against the writ petitioners and the same has
  not been challenged before us. Thus, only two issues survive,
  i.e. submission of CAD Plans before the MoEF and
  requirements of its clearance; and entitlement of the canal
                                                                                ;
8 affected persons.
                                                                       •
         9. So far as the first issue is concerned, this Court vide
    order dated 25.2.201 Oafter taking note of the directions issued
    by the High Court and in view of the fact that the CAD Plans
    etc. were being considered by the Expert Committee of the
c   MoEF and for many years excavation and construction of canal
    work and acquisition of land for that purpose had been done
    to a great extent and the High Court order brought the same to
    a standstill, passed the following order:
                                                                                •
D               "In the above circumstances, excavation or
          construction of the canal work and acquisition of land may
          go on for the time being, however, it would be subject to
          approval of the MoEF of the revised plans submitted on
          16th October, 2009. The State would be at liberty to file
E         further details regarding the Command Area Development
          Plans to the MoEF and if such details regarding the
          Command Area Development Plans are filed, the same
          may be referred to the Expert Committee for consideration.
          The Expert Committee to take a decision within a period       r

F         of six weeks and as soon as the Report is available to
          MoEF, the MoEF to take decision within a further period
          of four weeks thereafter."
       10. Mr. Mohan. Jain, learned Additional Solicitor General
  appearing for the MoEF has supported the case of the State
G contending that the State authorities had always been submitting          )

  the CAD Plans from time to time and the same had also been               •
  cleared by the statutory authorities. References have been
  made to the decision dated 10.2.2011 taken by Dr. Pandey's
  Committee on CAD Plans and all other subsequent decisions
H taken on 29th/30th April, 2011 on the CAD Plans submitted by


                                                                                    2
                    STATE OF MADHYA PRADESH & ANR. v. MEDHA 675
                       PATKAR & ORS. [DR. S.S. CHAUHAN, J.]
         ......   the State Government. Mr. Jain assured the Court that the A
                  decisions would be taken by the MoEF strictly in accordance
                  with law considering the report of the Expert Committee. Time
                  is being taken in view of the order dated 11.5.2011 passed by
                  this Court directing MoEF to proceed with the draft minutes
~                 prepared by the Environment Appraisal Committee after B
             ~
                  providing the opportunity of personal hearing to the writ
                  petitioner- Ms. Medha Patkar. Though the hearing stood
                  concluded, a large number of documents submitted by Ms.
                  Patkar yet require to be considered. The final decision shall be
                  taken within 4 weeks.                                            c
                       11. While considering the reliefs, which could be given to
                  the canal affected persons, this court on 5.5.2010 passed the
                  following order :
    ,.                       "The State of Madhya Pradesh shall_ consider the         D
                      "hardship cases"; those cases wherein land of a Khatedar
         "            is in excess of 60% or above is acquired for canal, those
                      affected parties may be given land as far as possible in
                      the near vicinity or in the canal command area of the project
                      and if it is not possible, the land may be given from the       E
                      Land Bank. The Khatedars who have already received
                      compensation, should return the Government 50% of the
                      compensation amount already taken by them as land value
                      and the remaining amount may be refunded -to the
    ,,-.              Government in 20 interest free annual installments. If the      F
                      Khatedars are not willing to take land from the land bank,
                      they may be given the compensation as per the present
                      market value plus 30% solatium thereof. Those who are
                      not coming in the category of hardship cases,
                      compensation is to be paid under the Land Acquisition Act       G
                      with 30% solatium .
     •_:.
                            Any grievance in respect of these affected parties
                      may be placed before the Grievance Redressal Authority
                      for Narmada Water Basin Project which has been set up
                      by the State Government.. Land Bank should, as far as H
     676       SUPREME COURT REPORTS                   [2011] 9 S.C.R


A          possible, give cultivable land and also basic infrastructure
           such as school, primary health centre, communication
           facilities etc. shall be provided."

          12. While entertaining I.A. No.9 of 2011, on 21.7.2011 the
     aforesaid order was modified as under:
8
           "50% of the cash compensation already received by the
           Khatedars have to be refunded to the Government as land
           value of land allotted and the remaining cost of the land
           will be paid in 20 interest free annual installments."
c
        While hearing the matter, this court further clarified the
    order dated 5.5.2010 to the extent that 30% solatium as
  . mentioned in the order dated 5.5.2010 meant as provided
    under the Act 1894 and not over and above the same to make
D it 60%.                                                                        •
           Therefore, the question remains as what are the other            ,.
     reliefs that can be granted to the canal affected persons and
     as to whether they can be put at oar with the oustees of
     submergence area.
E
          13. The Narmada Water Dispute Tribunal Award 1979
     defined 'oustee' as well as provided for rehabilitation:

           "Oustee- An "Oustee shall mean any person who since at
           least one year prior to the date of publication of the
F
           notification under section 4 of the Act, has been ordinarily
           residing or cultivating land or carrying on any trade,
           occupation or calling or working for gain in the area likely
           to be submerged permanently or temporarily."
G          Provision for Rehabilitation: According to the present
           estimates the number of oustee families would be 7,366
           spread over 173.villages in Madhya Pradesh, 467 families         ••
           spread over 27 villages in Maharashtra. Gujarat shall
           establish rehabilitation villages in Gujarat in the irrigation
'H         command of the Sardar Sarovar Project on the norms
                    STATE OF MADH'(A PRADESH & ANR. v. MEDHA 677
                        PATKAR & ORS. [DR. S.S. CHAUHAN, J.]
         ~:..          hereinafter mentioned for rehabilitation of the families who    A
                       are willing to migrate to Gujarat. For oustee families who
                       are unwilling to migrate to Gujarat, Gujarat shall pay to
                       Madhya Pradesh and Maharashtra the cost, charges and
                       expenses for establishment of such villages in their
~
                       respective territories on the norms as hereinafter              B
                       provided."
              •
                       Thus, it is evident from the above that the definition of
                  'oustee' does not take within its ambit the "canal affected
                  person". However, the said award does not apply to the present
                  projects as it was meant only for Inter-State projects like Sardar
                                                                                       c
                  Sarovar Project.

                       14. So far as the Indira Sagar Project is concerned, it was
    .,            given clearance on 24.6.1987 and did not have any specific
                  direction for rehabilitation. Similarly, for Omkareshwar Project,    D
         ~        clearance was granted on 13.10.1993 and part (vii) thereof,
                  provided that the rehabilitation programme would be extended
                  to landless labourers and people affected due to canal by
                  identifying and allocating suitable land "as permissible".
                                                                                       E
                       The words "as permissible" have been interpreted by this
                  Court in Narmada Bachao Ando/an v. State of M.P., AIR 2011
                  SC 1989, that addition of such terms while granting clearance
                  did not create a right in favour of such persons as the
    _,;''         rehabilitation is to be made in accordance with the terms of R
                                                                                       F
                  & R Policy. Thus, we do not see any reason to reconsider the
                  issue afresh.
                       15. The general R & R Policy of the State of Madhya
                  Pradesh defines 'displaced person' in para 1.1 as a person in
                  an area likely to come under submergence because of project          G
     (            or which is required by the project. The R & R Policy was
         .A
                  amended by the State of Madhya Pradesh on 14.8.2000 which
                  included the persons whose land was likely to come under
                  submergence or was required for the project related canal
                  construction.                                                        H
    678       SUPREME COURT REPORTS                   [2011] 9 S.C.R.

A        16. This Court in Narmada Bachao Ando/an I (supra)                 ....
    considered a similar issue, but made the distinction between
    canal affected persons and persons affected by submergence
    in para 169 which reads as under:

B         "Dealing with the contention of the petitioners that there will
          be 23,500 canal-affected families and they should be                          <

          treated on a par with the oustees in the submergence              •
          area, the respondents have broadly submitted that there
          is a basic difference in the impacts of the projects in the
          upstream submergence area and its impacts in the
c         beneficiary zone of the command area. While people, who
          were oustees from the submergence zone, required
          resettlement and rehabilitation, on the other hand, most
          of the people falling under the command area were in
          fact beneficiaries of the projects and their remaining land
D          would now get relocated with the construction of the canal               ~




          leading to greater agricultural output. We agree with this            ~



           view and that is why, in the award of the Tribunal, the State
           of Gujarat was not required to give to the canal-affected
           people the same relief which W«S required to be given to
E          the oustees of the submergence area." (Emphasis added)

       17. In view of the above, the State of Madhya Pradesh
  amended R & R Policy on 1.9.2003 deleting the words "which
  is required for project related constructions of canal or
F government project colony." Thus, in view of the above, the State                     •
  of M.P. does not give the same R & R package to the canal
  affected persons as those affected by submergence.
       18. This Court has taken a view that the canal affected
  persons cannot be put at par with the submergence affected
G persons, thus, it is not possible for the court to put the canal
  affected persons at par with the submergence affected persons.                    )
                                                                                ~




      In view of the fact-situation, it was not permissible for the
  High Court to take a view contrary to the view taken by this
H Court, particularly, when the High Court came to the conclusion
                       STATE OF MADHYA PRADESH & ANR. v. MEDHA                       679
    • >
                           PATKAR & ORS. [DR. B.S. CHAUHAN, J.]

                      that there was a reasonable differentia between the two.              A

                            19. Be that as it may, this Court vide an interim order dated
                     . 5.5.2010 has also taken care of "hardship cases" in canal
~
                       affected areas.
             II

                            Mr. Andhyarujina, learned senior counsel appearing for the      B
                      State has graciously agreed that in order to give more benefit
                      to canal affected persons, the court may award some more
                      benefits. The State has suggested that in order to achieve the
                      purpose, date of Section 4 Notification in all the cases,
                      irrespective of the actual date of Section 4 Notification in          c
                      relation to all canal affected persons be shifted (postponed) to
                      the date of this judgment and direct to re-determine the market
    ~
                      value according to the provisions of the Act 1894 as early as
                      possible making the supplementary awards and giving the
          "           opportunity to such oustees further for filing reference under        D
                      Section 18 of the Act 1894.

                             20. The State has come forward with most appropriate
                      and valuable suggestion, thus, we accept the same. In view of
                      the above, Land Acquisition Collector is directed to reconsider
                                                                                            E
                      the market value of canal affected person.s as if Section 4
                      Notification in respect of the same has been issued on date,
        ,' .......    i.e. 2.8.2011 and make the supplementary Awards in
                      accordance with the provisions of the Act 1894. Such
                      concession extended by the State would be over and above
                                                                                            F
                      the relief granted by this Court vide order dated 5.5.2010 as
                      clarified/modified subsequently, as explained hereinabove and
                      it is further clarified that further canal work would be subject to
                      clearance/direction which may be given by MoEF.
           •.-4
                          21. In view of the above, appeal stands disposed of.. No          G
                      order as to costs.

                      R.P.                                        Appeal disposed of.


                                                                                            H


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "land acquisition"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.