Created byFuzzy Cloud

Supreme Court of India

SURESH JINDALversusBSES RAJDHANI POWER LIMITED AND ORS.

Citation
2007 INSC 1046
Decided
11 October 2007
Disposal
Dismissed

Holding

The licensee lawfully exercised the power conferred by Section 20 of the Indian Electricity Act, 1910 to replace the meter, and the replacement was not illegal.

Summary

The consumer, Suresh Jindal, challenged the replacement of his electromechanical electricity meter with an electronic one by BSES Rajdhani Power Ltd, alleging the new meter ran fast (+1.79%) and was illegal. He sought a writ of mandamus to quash the replacement and the testing report. The Delhi High Court dismissed the petition and the subsequent letters patent appeal. On appeal, the Supreme Court held that the licensee was authorized under Section 20 of the Indian Electricity Act, 1910 to enter premises and replace or alter meters, and that this power is not limited by Section 26. The Court found no statutory prohibition on the replacement, noted that the consumer had not objected to the change, and emphasized the policy decision to replace old meters with electronic ones. Consequently, the appeal was dismissed.

Issues considered

  • The scope of Section 20 of the Indian Electricity Act, 1910 and whether it authorises meter replacement without being controlled by Section 26.
  • Whether the licensee's replacement of the meter was ultra vires or illegal.
  • The applicability of Rule 57 of the Indian Electricity Rules, 1956 to the replacement.
  • The effect of the Delhi Electricity Reforms Act, 2000 and related regulations on the licensee's authority.
  • Whether the consumer was entitled to a writ of mandamus to prevent the use of the electronic meter.

Legislation cited

Subjects

meter replacementelectronic meterIndian Electricity ActSection 20Section 26consumer rightsmandamusstatutory interpretationDelhi Electricity Reforms Actregulatory authority

Judgment

     l
                                    SURESH JINDAL                                 A
                                             v.
                    BSES RAJDHANI POWER LIMITED AND ORS.

                                   OCTOBER 11, 2007
                                                                                  B
                    [S.B. SINHA AND HARJIT SINGH BEDI, JJ.]


                 Indian Electricity Act, 191 O; Ss. 35 and 26/Delhi Electricity
           Reforms Act, 2000; Ss. 14, 15, 61, 63 and 64/Delhi Electricity
           Regulatory Commission (Pe1formance and Standards-Metering and          c
           Billing) Regulations, 2002:
                 Electric energy recording meter-Replacement by an electronic
            meter by Licensee-Electric meter so replaced allegedly running
           faster-Challenge to-Dismissed by High Court-Letters Patent
                                                                                    D
           Appeal also dismissed by High Court-On appeal, Held: Appellant-
           consumer did not object to change ofmeter and allowed respondent-
           Licensee to change his correct meter by another one which he admitted
    - -I
            ·was also correct-He, later, cannot contend that the meter does not
            record correct consumption of electricity-A policy decision for
            replacement ofold electric meters with the new electronic meters issued
                                                                                    E
            by Electricity Regulatory Commission in terms ofprovisions under
            1948 Act to meet the requirement ofannual reserve fund-S. 20 confers
i          power on Licensee to alter a meter which includes replacement of a
           meter-There exists no power in any of the Statutes connected with
           electricity supply which prohibits the Licensee to replace one meter F
     y
           by another-Creative interpretation of the provisions of the Statute
           demands that with advancement in science and technology, the Court
           should read the provision ofthe Statute in a manner so as to give effect
           thereto-Hence, Licensee had necessary authority to replace the meter
           in terms of provision u/s. 20 of 1910 Act-General Clauses Act- G
           Statutory power--Exercise of-Jnte1pretation of Statutes.
    ~
                Words & Phrases:

                                            53                                     H
                                                                           t
    54           SUPREME COURT REPORTS                [2007] 11 S.C.R.
                                                                               'r'
A        'Licensee '-Meaning of in the context of Section 2(e) of the
    Electricity Act,, 1910.
         'Board '-Meaning of in the context ofDelhi Electricity Reform
    (Transfer Scheme) Rules, 2001.
B      A meter for the purpose of recording of consumption of
  electrical energy was installed at the premises of the appellant-
  consumer. It was replaced by an electronic meter by respondent-
  Licensee. The electronic meter when tested by the officials of the            y


  respondent, it was found that the same was running fast by about
c +1.79% which is said to be beyond the BIS standard, as the meter
  installed in the premises was of Class-I category. He filed a writ
  petition before the High Court praying for order/direction in the
  nature of a writ of mandamus, thereby declaring the acts of the
  officials of the respondents as illegal and malafide in replacing the
D correct and working electricity meter of the petitioner by an
  electronic meter at his residence. The writ petition was dismissed
  by the Single Judge of the High Court. A letters patent appeal
  preferred thereagainst by the consumer was also dismissed by the             >-
  High Court. Hence the present appeal.
E      Appellant-consumer contended that in the facts and under the
  circumstances of the case, since Indian Electricity Act, 2003 being
  not applicable, the High Court committed a serious error in passing
  the impugned judgment; that Rule 57 of the Indian Electricity Rules,                 ~
  1956 whereupon reliance was placed by the respondents in their
F counter affidavit is clearly inapplicable and thus reliance so placed
  by the High Court was wholly unwarranted; that the tariff framed             y
  by Delhi Vidyut Board also did not confer any jurisdiction upon the
  respondents to remove the correct meter and replace the same by
  another meter; that the only provision which could have been taken
                                                                                       [
                                                                                       )

G recourse to for replacement of a meter being Section 26 of the 1910                  '
                                                                                       ~
  Act and the same was not applicable in this case; that margin of error
  in the meter being 1.79% in one case and 3.79% in the other which                ¥
                                                                                       •
                                                                                       ~




  is in excess of 1 per cent of error provided for in the proviso
  appended to Rule 57 of the Indian Electricity Rules, the appellant
H had a legal right to obtain a writ in the nature of mandamus directing
                                                                                       t
        SURESHJINDALv. BSESRAJDHANIPOWERLIMITED                          55


      the respondents not to rely thereupon for the purpose of calculating A
      the amount of consumption of electrical energy recorded therein;
      and that in any view of the matter, replacement of the meter having
      taken place prior to coming into force of the 2003 Act and the
      regulations framed thereunder, the High Court was wholly incorrect
      in arriving at its findings.                                         B
           Respondents-Licensee submitted that in terms of Section 20
      of the 1910 Act, a general power has been conferred on the licensee
'I'   to remove a correct meter and replace the same by another meter
      which records more accurately the actual consumption of electrical
      energy having regard to the development of technology and thus          c
      such an action, being de-hors provisions of Section 26 of the Act,
      would not be controlled thereby.
           Dismissing the appeal, the Court
           HELD: 1.1. Appellant did not object to the change of the meter. D
      It proceeded on the basis that the change of the meter is permissible
      in law. He being allegedly unaware of his rights allowed the
      respondent to enter into his premises and change a correct meter
      by another one which according to him is also correct. It, therefore,
      does not lie in the mouth of the appellant now to turn round and E
      contend that electronic meters do not record correct consumption
      of electrical energy. It is one thing to say that electronic meters when
      tested do not register the actual consumption, as a result whereof,
      the consumer would have to pay the energy charges more than he
      is othenvise liable but it is another thing to say that it was legally F
      impermissible. It is not, however denied or disputed that whether
 y    meter is installed by the licensee or by the consumer himself, the
      same must have the requisite certificate granted in terms of the
      regulations, the provisions wherefor have been made in the
      regulations made under the Delhi Electricity Act, 2000.
                                                                               G
                                                            (Para 38) [68-B-D]
~          1.2. If Section 20 of the Indian Electricity Act, 1910 conferred
      a power which is not othenvise controlled by Section 26 thereof, the
      question of the respondent acting wholly without jurisdiction or
      arbitrarily would not arise. [Para 39) [68-E]                         H
                                                                           )..--
                                                                           \

    56           SUPREME COURT REPORTS                [2007] 11 S.C.R.
                                                                                   v!
A      2.1. Regulations made in the year 2002 provided for detailed
  guidelines in regard to the procedures required to be followed by
  the utilities for providing new connections, replacement of defective
  meters etc. The said regulations admittedly were amended in 2003
  providing for payment of compensation to consumers in case of
B repeated levy of arrears for bills already paid. If there had been any
  violation of the meter and billing regulation, the utilities could be
  imposed with penalties. It is at that stage, a policy decision was
  taken by the electricity Regulatory Commission for replacement of
  old electromechanical meters with new electronic meters as a part
c of the Scheme. The Commission in its Order on Annual Revenue
  Requirement issued directions with regard to replacement of meters
  which were carried out pursuant thereto or in furtherance thereof.
                                              [Para 40] [68-H; 69-A-C]
       2.2. Under the Electricity Supply Act, 1948, the State had a role
D to play. Its directions in relation to the policy matters were binding
  on the State Electricity Boards. Such a power continued to be
  operative. If, therefore, the Electricity Regulatory Commission
  which was an independent body could make tariff and for that                     .}-

  purpose had the statutory authority to issue certain directions, no
E exception thereto can be taken. [Para 41] [69-F]
       3.1. Section 26 of the 1910 Act operates in different fields. It
  comes into being only when there exists a dispute. The dispute may
  be in regard to the'quantum of the amount required to be expended
  for removing the meter or the correctness of the meter. The dispute
F may also be, in the event, the meter is held to be not recording the
  consumption of electrical energy correctly, the amount to which the
                                                                                   '(
  consumer would be liable to pay, in relation thereto.
                                                      [Para 44) [70-E]

G      3.2. Section 20 of 1910 Act operates in one field namely
  conferring a power of entry on the licensee. The provision empowers
  the licensee inter alia to alter a meter which would include                      ).._
  replacement of a meter. It is an independent general provision. In
  absence of any statutory provision, there exists no reason to put a
H restrictive meaning thereto. [Para 43) [70-A-B)
   SURESHJINDAL v. BSES RAJDHANIPOWERLIMITED                         57
                     [SINHA,J.]
     3.3. Even under the General Clauses Act, a statutory authority A
while exercising statutory power may do all things which are
necessary for giving effect thereto. There does not exist any
provision in any of the statutes as referred to which precludes or
prohibits the licensee to replace one set of meter by another. If such
a provision is read into the statute, the same would come in the way B
of giving effect to the benefits of new technological development.
Creative interpretation of the provisions of the statute demands that
with the advance in science and technology, the Court should read
the provisions of a statute in such a manner so as to give effect
thereto. (Para 43] [70-B-D]                                            c
     State ofMaharashtra & Anr. v. Dr. Praful B. Desai & Anr., (2003]
4 sec 601, relied on.
     3.4. It is correct that the matter at the relevant point of time
was not covered by any statutory regulations, but even otherwise, D
the respondent had the said authority under Section 20 of the 1910
Act. [Para 46) [70-G-H]
    Belwal Spinning Mills Ltd And Ors. v. UP. State Electricity Board
And Anr., [1997] 6 SCC 740, held inapplicable.
                                                                           E
    CIVIL APPELLATE WRISDICTION: Civil Appeal No. 4789 of
2007.                                       .
     From the Judgment and Order dated 20.2.2006 of the High Comt
of Delhi at New Delhi in L.P .A. No. 256 of 2006.
                                                                           F
     Sanjay Parikh, Lalit Kumar, Anitha Shenoy, Nitin R, Jatin Sahni and
A.N. Singh for the Appellant.
     A. Sharan, A.S.G., Arnn Jaitely, R. Srivastava, Amit Kapur,
Mansoor Ali, Vibha Datta Makhija, Sadhna Sandhu, D.S. Mahra and
Suresh Chandra Tripathy for the Respondents.                    G
     The Judgment of the Court was delivered by
     S.B. SINHA, J. I. Leave granted.
     2. Appellant is a consumer of electrical energy. Respondent is a H
                                                                                     \r
                                                                                     (

                                                                                         \

    58             SUPREME COURT REPORTS                     [2007] 11 S.C.R.
                                                                                             y
A licensee. A meter for the purpose of recording consumption of electrical
  energy was installed at his premise. It was replaced by an electronic meter.
        3. The electronic meter was tested by the officials of the respondent
  and it was found that the same was running fast by about +1. 79% which
B is said to be beyond the BIS standard, as the meter installed in the premises
  was of Class-I category. He filed a writ petition before the High Court
  inter alia contending;
           "4. That the meter installed in the premises of the Petitioner was                ''I'
               intact and OK and was recording the consumption as per
c              Section 57 of the Electricity Supply Rules, 1956 and there was
               no percentage error in the recording of the consumption in the
               meter earlier installed by the agents of the Respondent in the
               premises of the Petitioner.
           5.   That the Petitioner believing the intention of the Respondent
D               has permitted the Respondent to install the meter of their own
                choice believing that the meter which was installed in the
                premises of the Petitioner is of approved design and
                specification ofISI and also in accordance with the rules and                \.-
                regulations under the Electricity Act, 2003."
E
         In the writ petition, the following prayers were made by him:
           a.   A writ, order or direction in the nature of a writ of mandamus,
                thereby declaring the acts of the officials of the Respondents
                as illegal and malafide in replacing the correct and working
F               meter of the Petitioner by another meter in respect of electricity
                connection bearing K.No.2540F320018 installed for 134, First
                Floor, Sunder Nagar, Delhi.                                                  'r

          b.    A writ, order or direction in the nature of a writ of mandamus,
                thereby quashing the meter testing report prepared on 03/03/
G               2005 ·in respect of electricity connection bearing K.No.
                2540F320018 installed for 134, First Floor, Sunder Nagar,
                Delhi.                                                                        -•
          c.    A writ, order or direction in the nature of a writ of mandamus
H               thereby directing the Respondent to get the meter of the
/



       SURESHJINDALv. BSESRAJDHANIPOWERLIMITED                               59
                        [SINHA,J.]
                Petitioner tested as per rule 57 of the Electricity Supply Rules A
                1956 through an independent agency or in any other manner
                a'5 this Hon'ble Court deems fit in the facts and circumstances
                of the case.
           d.   A writ order or direction thereby directing the Respondent to
                calibrate, seal and install at the premises of the Petitioner, the B
                electro mechanical energy meter oflSI make procured by the
                Petitioner in respect of electricity connection bearing K.No.
                2540F320018 for 134, First Floor, Sunder Nagar, Delhi after
                replacing the existing meter."
                                                                                  c
         4. The writ petition was dismissed by a learned Single Judge of the
    Delhi High Court by a judgment and Order dated 14.12.2005. A letters
    patent appeal was preferred thereagainst and by reason of the impugned
    judgment, the same has been dismissed. Appellant is, thus, before us.
         5. Mr. Sanjay Parikh, learned counsel appearing on behalf of the D
    appellant in support of the appeal, inter alia, would submit;
          (i) Respondent being a licensee governed by the Indian Electricity
    Act, 19 IO (hereinafter referred as "19 IO Act"); the provisions of
    Electricity (Supply) Act, 1948 (hereinafter referred as "1948 Act") or the E
    subsequent Acts namely Delhi Electricity Refonns Act, 2000 (hereinafter
    referred to as "2000 Act") or Indian Electricity Act, 2003 being not
    applicable, the High Court committed a serious eiTor in passing the
    impugned judgment.
         (ii) Rule 57 of the Indian Electricity Rules, 1956 whereupon reliance F
    was placed by the respondents in their counter affidavit is clearly
    inapplicable and thus reliance placed thereupon by the High Court in this
    behalf was wholly w1warranted.
          (iii) The tariff framed by Delhi Vidyut Board also did not confer any G
    jurisdiction upon the respondents to remove the correct meter and replace
    the same by another correct meter.
          (iv) The only provision which could have been taken recourse to
    for replacement of a meter being Section 26 of the 1910 Act and the
    same being not applicable in this case, the impugned Judgment cannot be H
                                                                                  ~-
                                                                                  \
    60            SUPREME COURT REPORTS                    [2007] 11 S.C.R.
                                                                                       '<"
                                                                                         I

A sustained.

        (v) Margin of error in the meter being 1. 79% in one case and 3.79%
  in the other which is in excess of 1 per cent of error provided for in the
  proviso appended to Rule 57 of the Indian Electricity Rules, the appellant
B had a legal right to obtain a writ of or in the nature of mandamus directing
  the respondents not to rely thereupon for the purpose of calculating the
  amount of consumption of electrical energy recorded therein.
          (vi) In any view of the matter, replacement of the meter having taken
    place prior to coming into force of the 2003 Act and the regulations
c   framed thereunder, the High Court was wholly incorrect in arriving at its
    findings.
        6. Mr. Arun Jaitley, the learned senior counsel appearing on behalf
  of the respondents, on the other hand, would principally rely upon Section
  20 of the 1910 Act to submit that by reason thereof a general power has
D
  been conferred on the licensee to remove a correct meter and replace
  the same by another meter which records more accurately the actual
  consumption of electrical energy having regard to the development of
  technology and thus such an action, being de-hors provisions of Section              )..


  26 of the Act, would not be controlled thereby. Appellant being a
E
  consumer of electrical energy from Delhi Vidyut Board which was a State
  Electricity Board within the meaning of 1948 Act and the respondent being
  its successor in terms of 2000 Act and 2003 Act, the impugned judgment
  is unassailable.

F        7. The 1910 Act was enacted on 18th March, 1910.
         8. The said Act regulated the terms and conditions of supply of
                                                                                       "(
  electrical energy to the consumers. Licensees in those days used to be
  private companies. Actual terms of the contract for supply of electrical
  energy by the licensees to its consumers were governed by the terms and
G conditions of contract entered into by and between the parties thereto.
  The said Act provide for powers and obligations of the licensee on the
                                                                                        _,,
  one hand as also the rights and obligations on the part of the consumers
  on the other. By reason thereof, licensees under the said Act being public
  utility concerns were bound thereby. It could exercise the statutory powers
H
           SURESH JINDAL v. BSES RAJDHANI POWER LIMITED                        61
    ,,                        [SINHA,J.]

           conferred upon it, which was otherwise not available under the common A
           law or the terms of the contract entered into by and between the parties.
                  9. Section 20 of the Act confers power on the licensee to enter
            into the premises, inter alia, for the purpose of inspecting, testing,
           repairing or altering meters instituted in the premises of the consumers. B
           The said provision ex-fade is not controlled by any other provision
'    -;    thereto. Section 21 of the Act empowers a licensee to prescribe any
           form of appliance in utilising energy supplied by him. All kind of
           utilisation of appliances is governed by the said provisions. The said
           provision has nothing to do with installation or testing or replacing any
           meter. Section 26 ensures installation of correct meter so that the
                                                                                     c
           consumption of electrical energy may be recorded. A meter can be
           installed either by the licensee or by the consumer. An obligation, thus,
           to keep the meter correct will be either on the licensee or the consumer,
           as the case may be. Sub-section (4) of Section 26 empowers the
           licensee to have access for the purpose of inspecting and testing the D
      ~-   meters and for the said purpose the same could be taken off or
           removed.
     -'
                 10. In case however of any dispute or difference and in the event
           the meter installed in the premises of the consumer is found to be not E
           correct, in regard to the quantum amount of reasonable expenses for
           the purpose of taking off or removal of the meter, the Electrical Inspector
           would be the sole authority to determine the same. The Electrical
           Inspector as a statutory authority was also empowered to enter into
           and determine the disputes and differences between the parties not only F
           in regard to the correctness of the meter but also quantify the amount
      y    payable by the consumer to the licensee ifhe comes to the opinion
           that the meter has ceased to be correct subject of course to the
           condition that the same would not exceed the period of six months.
                 11. The principal question which arises for our consideration is G
           as to whether the power conferred upon the licensee under Section
    ;.     20 of the Act is controlled by Section 26 thereof We would deal with
           the said question a little later.
                12. We may now have a quick look at the provisions of the other H
    62           - SUPREME COURT REPORTS                     [2007] 11 S.C.R.


A statutes. The provisions'of 1948 Ad, which is a post-independence Act,
  cast a duty on the State to constitute a Board for the purpose of
  generation, transmission, distribution and supply of electrical energy. It is
  a body corporate and can sue and be sued in its own name. Section 26
  of the 1948 Act provides for conferment of powers and obligations of
B the licensees in the Board as provided for under the 1910 Act wherefor
  a legal fiction has been raised. The proviso appended to Section 26 of
  1948 Act reads as under:-
           "Provided that nothing in sections 3 to 11, sub-sections (2) and
           (3) of section 21 and section 22, sub-section (2) of Section 22A
c          and sections 23 and 27 of that Act or in clauses 1 to V, clause
           VII and clauses IX to XII of the Schedule to that Act relating to
           the duties and obligations of a licensee shall apply to the Board:"


D        13. Section 20 of the 1910 Act was, therefore, made operative
    under the 1948 Act so far as the Board is concerned and thus the said
    power was exercisable by it. Rules were made in terms of Section 37 of
    the 1910 Act only in the year 1957. Rule 57(1) of the Rules reads as
    under:-
E          "57(1) Any meter or maximum demand indicator or other
           apparatus placed upon a consrnner' s premises in accordance with
           section 26 shall be of appropriate capacity and shall be deemed
           to be correct if its limits of error are within the limits specified in
           the relevant Indian Standard Specification and where no such
F          specification exists, the limits of error do not exceed 3 per cent
           above or below absolute accuracy at all loads in e~cess of one
           tenth of full load and up to full load:"
       14. Although reliance has been placed by the respondents in their
G counter affidavit on the said rule, ex-facie the same is not very relevant
  for our purpose. We would, however, deal with the contention of Mr.
  Parikh with regard to the construction of the said provision at a later stage.
          15. The Parliament enacted Electricity Regulatory Commission Act
    in the year 1998 wherewith we are not concerned. It may however be
H
    -{

           SURESHJINDAL v. BSES RAJDHANIPOWERLIMITED                                63
                             [SINHA,J.]
         noticed that the National Capital Territory of Delhi enacted the Delhi A
         Electricity Reforms Act, 2000 (hereinafter referred to as "2000 Act'').
              16. Section 2(e) thereof defines "licence" to mean a licence granted
         under the Indian Electricity Act, 1910.
              17. Section 14 provides for re-organisation of electricity industries; B
         sub-section (1) whereof reads as under:-
                  "Sec. 14(1) The Government may, as soon as may be after the
                  commencement of this Act, cause one or more companies to be
                  incorporated and set up under the provisions of the Companies
                  Act, 1956 (1 of 1956) for the purpose of generation, transmissiQn C
                  or distribution of electricity, including companies engaged in more
                  than one of the said activities, in the National Capital Territory of
                  Delhi and may transfer the existing generating stations or the
                  transmission system or distribution system, or any part of the
                  transmission system or distribution system, to such company or D
                  companies."
                 Sub-sec:tions (3) and (6) of Section 14 of the said Act read as under:
                  Sec. 14(3) The companies incorporated and set up under sub-
                  section ( 1) shall undertake the functions specified in this section E
                  and such other functions as may be assigned to them by the
                  Government.
             1
                  Sec. 14(6) The Government may convert the companies set up
                  under this Act to joint venture companies through a process of F
                  disinvestment, in accordance with the transfer scheme prepared
y                 under the provisions of this Act.

                18. Section 15 provides for reorganisation of Delhi Vidyut Board
         and. transfer of properties, functions and duties thereof.
                                                                                          G
               19. Delhi Vidyut Board was constituted by the National Capital
         Territory of Delhi in terms of the provisions of 1948 Act.

              20. By reason of sub-section (1) of Section 15 all the powers
         conferred upon the Companies as had been existing in the Boards under
                                                                                          H
                                                                                     }--
                                                                                     \

    64            SUPREME COURT REPORTS                     [2007] 11 S.C.R.

A Section 26 of the 1948 Act were saved.
       21. By reason of Section 63, the provisions thereof were to prevail
  over the provisions of 1910 Act and 1948 Act in regard to the matters
  which were inconsistent therewith or contrary thereto. Sub-section (3) of
  Section 63 provides that upon establishment of the Commission, the
B provisions of the 1910 Act and 1948 Act were to be read subject to the
  modifications and reservations contained therein, the relevant clauses
  whereof are as under:-
          "(i) All references to State Electricity Board in the Indian Electricity
c         Act, 1910 (9of1910) in so far as the National Capital Territory
          of Delhi is concerned shall be read as references to the Delhi
          Electricity Regulatory Commission or the companies established
          under section 14 or other licensees or wherever it relates to general
          policy matters, to the Government.
D         (ii) In respect of matters provided in sections 3 to 11, 28, 36(2),
          49A, 50 and 51 of the Indian Electricity Act, 1910 (9of1910),
          to the extent this Act has made specific provisions, the provisions
          of the Indian Electricity Act, 1910 (9 of 1910) shall not apply in               ).
          the National Capital Teni.tory of Delhi."
E
         So far as 1948 Act is concerned, it is provided :
          "(v) All references to State Electricity Board in the Electricity
          (Supply) Act, 1948 (54of1948) in so far as the National Capital
          Territory of Delhi is concerned shall be read as references to the
F         Delhi Electricity Regulatory Commission or the companies
          established under section 14 or other licensees or where it relates
          to general policy matters, to the Government.
          (vi) In respect of matters provided in sections 5 to 18, 19, 20, 23
          to 27, 37, 40 to 45, 46 to 54, 56 to 69, 72 and 75 to 83 of the
G         Electricity (Supply) Act, 1948 (54 of 1948), to the extent this Act
          has made specific provisions, the provisions of the Electricity
          (Supply) Act, 1948 (54of1948) shall not apply in the National
          Capital Territory of Delhi."
H        22. Section 26 of the 1948 Act therefore, would not apply only
         SURESHJINDAL v. BSES RAJDHANI POWER LIMITED                          65
                           [SINHA, J.]
r
      when there exist any corresponding provision in the 2000 Act. It is not A
      disputed that no such provision is in existence. If there does not exist any
      provision contrary to or inconsistent with Section 26 of the Act, the same
      would, indisputably, continue to apply.
           23. St::ction 64 of the said Act provides for the saving clause.        B
            24. We may now notice constitution of various entities in terms of
"">
      the 2000 Act and the Rules framed thereunder. The National Capital
      Territory of Delhi in exercise of its power conferred by Section 60 read
      with Sections 15 and 16 of 2000 Act made Rules known as Delhi
      Electricity Reform (Transfer Scheme) Rules, 2001. The said Rules are         c
      statutory in nature. They provide for transfer and vesting of assets,
      liabilities, proceedings and personnel of Delhi Vidyut Board in the
      successor entities and for detennining the terms and conditions on which
      such transfer or vesting shall take effect.
                                                                                D
,.          25. In the said Rules, "Board" has been defined to mean Delhi
      Vidyut Board constituted under Section 5 of the Electricity (Supply) Act,
      1948. Rule 2(f) defines "DISCOM 2" to mean "South-West Delhi
J>,
      Electricity Distribution Company Limited", a company incorporated under
      the Companies Act, 1956 (1 of 1956) with the principal object of engagfug
      in the business of distribution and supply .of electricity in the area as E
      specified in P&1 II of Schedule 'H'.
            26. The term "transferee" has been defined in Rule 2(r) to mean
      'GENCO', 'TRANSCO', 'DISCOMS' and 'PPCL', as the case may
      be, in whom the undertaking or undertakings or the assets, liabilities,      p
      proceedings and personnel of the Board, as the case may be, are vested
      in terms of these rules and shall include the holding company;
            27. Rule 4(1) provides that assets, liabilities and proceedings
      transferred to the government under sub-rule ( 1) of rule 3 shall stand
      classified as under:                                                    G
          (a) Rights and interests in Pragati Power Project as set out in
      Schedule 'A'
          (b) Generation Undertaking as set out in Schedule 'B'.
                                                                                   H
    66              SUPREME COURT REPORTS                    [2007] 11 S.C.R.


A          (c) Transmission Undertaking as set out in Schedule 'C'
                                                                       ·I

           (d) Distribution Undertaking as set out in Schedule 'D~
           (e) Distribution Undertaking as set out in Schedule 'E'.
B          (t) Distribution Undertaking as set out in Schedule 'F'.

           (g) Holding Company with assets and liabilities as set out in Schedule    }-
    'G'.
           28. Rule 5(1 )(d) of the Rules provides that the undertaking forming
c part of the Distribution Undertaking as set out in Schedule 'D', shall stand
    transferred to and vest in the DISCOM 1, on and from the date of the
    transfer appointed for the said purpose.
          29. Sub-Rule (2) of Rule 5 provides for the consequences of such
    transfers in the following terms :
D
            "Rule 5(2) On such transfer and vesting of the undertakings in terms
            of sub-rule (1 ), the respective transferee shall be responsible for
            all contracts, rights, deeds, schemes, bonds, agreements and other
            instrume~ts of whatever nature, relating to the respective

E
            undertaking and assets and liabilities transferred to it, to which the
            Board was a party, subsisting or having effect on the date of the
            transfer, in the same manner as the Board was liable immediately
            before the date of the transfer, and the same shall be in force and
            effect against or in favour of the respective transferee and may be
            enforced effectively as if the respective transferee had been a party
F
            thereto instead of the Board."
         30. Rule 10 provides for the rights and powers of the transferees,
    sub-Rule (2) whereof reads as under :
            "Rule 10(2) Within sixty days of the effective date of transfer, the
G
            DISCOMS shall apply to the Commission for the grant oflicence
            under the Act to undertake the business of distribution and retail
            supply of electricity in the.respective areas of supply as specified
            in Schedule 'H' :"

H          31. Indisputably, pursuant thereto and/or in furtherance thereof,
        ~)

               SURESH JINDAL v. BSES RAJDHANI POWER LIMITED                        67
                                  [SINHA,J.]
-r
             applications were made for grant of license by the first respondent herein A
             and such license have since been granted in its favour by the
             Commissioner.
                  32. We may also notice that regulations have been framed in terms
             of Section 61 of the 2000 Act known as The Delhi Electricity Regulatory
                                                                                     B
             Commission (Performance Standards- Metering and Billing) Regulations,
 ..,         2002 .

.,                33. Chapter 5 of the said Regulations provide for metering, laying
             down that all installations subject to exemption shall be serviced with a
             meter and all the requirements as laid down in Section 26 of the 2000       c
             Act shall be complied with.
                   34. To complete the narration of the statutory Scheme, we may also
             notice that Delhi Electricity Supply Company undertaking framed
             conditions of supply whereupon strong reliance has been placed by the
             High Court in arriving at its finding. But, we may ignore the same inasmuch D
 )-          as the same are not statutory in nature.
                   35. Before embarking on other questions raised at the Bar, we would
             like to place on record that the High Court had placed strong reliance on
             the rationale of replacing the existing meters with electronic meters, but, E
             we are of the opinion that the same is not at all relevant as in the event it
             is held that the respondent had no authority to replace the existing meters
             with electronic meters, rationale or other justifications in support thereof
             would not legalise an illegal act.
                 [See Hindustan Times and Ors. v. State of UP. and Anr., [2003] F
 1           1 sec 591 Para 30].
 .,.,
                   36. We have referred to at some details the statutory scheme only
             for the purpose of showing that there had all along been a continuity in
             the matter of supply of electrical energy in the National Capital Territory G
             of Delhi either by a private company or by a State Electricity Board, as
             the case may be. We, at this stage, make it clear that we do not intend to
             go into the question of applicability of the provisions of the 2003 Act and
             the regulations made thereunder, for the reason that regulations made
             under Section 50 of the 2003 Act came into force on and from 8.4.2007 H
    68             SUPREME COURT REPORTS                    [2007] 11 S.C.R.

A and Section 55 thereof came into force on 10.3.2006 and, thus, the said
  Act was not in force at the relevant time.
         37. Our attention has also been drawn to Section 49 of the 1948
    Act and the regulations and the tariff framed by the Delhi Vidyut Board.
B       38. At the outset we have noticed that the appellant did not object
  to the change of the meter. It proceeded on the basis that the change of
                                                                                   ;i..
  the meter is permissible in law. He being allegedly unaware of his rights
  allowed the respondent to enter into his premises and change a correct               "1
  meter by another one which according to him is also correct. It, therefore,
c in our opinion does not lie in the mouth of the appellant now to tum round
  and contend that electronic meters do not record correct consumption of
  electrical energy. It is one thing to say that electronic meters when tested
  do not register the actual consumption, as a result whereof, the consumer
  would have to pay the energy charges more than he is otherwise liable
D but it is another thing to say that it was legally impem1issible. It is not,
  however denied or disputed that whether meter is installed by the licensee
                                                                                   --{
  or by the consumer himself, the same must have the requisite ce11ificate
  granted in te1ms of the regulations, the provisions wherefor have been           }.

  made in the regulations made under the 2000 Act.
E        39. If Section 20 of the 1910 Act conferred a power which is not
  otherwise controlled by Section 26 thereof, the question of the respondent
  acting wholly without jurisdiction or arbitrarily would not arise.
  Indisputably, after the Electricity Regulatory Commission came into being,
  it issued certain directions. It had to make tariff. For the purpose of making
F tariff, certain checks and balances were required to be made. The
  loopholes then existing in the matter of transmission of electrical energy       '(
                                                                                   ..,,
                                                                                   .
  which resulted in a huge transmission loss was to be taken care of.
  Therefore, a direction was issued by the Commission that all the existing
  meters should be replaced by electronic meters. We do not see any
G illegality therein.
         40. Various steps had been taken by the respondent No. 2 to resolve
    the grievances of the consumers. Grievance Redressal Forum was
    established in terms of Section 42(5) of the 2003 Act. Regulations made
    in the year 2002 provided for detailed guidelines in regard to the
H
                SURESHJINDALv. BSESRAJDHANIPOWERLIMITED                                69
                                 [SINHA,J.]
    r
              procedures required to be followed by the utilities for providing new A
              connections, replacement of defective meters etc. The said regulations
              admittedly were amended in 2003 providing for payment of compensation
              to consumers in case of repeated levy of arrears for bills already paid. If
              there had been any violation of the meter and billing regulation, the utilities
              could be imposed with penalties. It is at that stage, a policy decision was B
              taken for replacement of old electromechanical meters with new electronic
        ..,   meters as a part of the Scheme. The Commission in its Order on Annual
    y
              Revenue Requirement issued directions with regard to replacement of
              meters which were carried out pursuant thereto or in furtherance thereof,
              which reads as under:                                                           c
                     "Replacement of meters is the responsibility ofthe DISCOMs and
                     the DISCO Ms have submitted details of the meter replacement
                     programme to the Commission, the Commission would like to
                     infom1 the objector that the old electromechanical meters are
                     subject to mechanical wear and tear and tend to record lower D
        /            conswnption over a period of time. Moreover, these meters ar~
                     also more susceptible to tamper. The replacement of such meters
        -"           with electronic meters will enable the utility to record the
                     consumption more accurately as well as reduce the chances of
                     tampe1ing. The DISCOMs have submitted that the existing meters E
                     are being replaced by the electronic meters which is a good step."
                    41. Under the 1948 Act, the State had a role to play. Its directions
              in relation to the policy matters were binding on the State Electricity
              Boards. Such a power continued to be operative. If, therefore, the F
    'f
              Electricity Regulatory Commission which was an independent body could
        r     make tariff and for that purpose had the statutory authority to issue certain
              directions, no exception thereto can be taken.
                    42. We, therefore, are required to consider as to whether the
              authority to make such replacement of meter by the licensee is contained G

(
    ._        in Section 20 of the 1910 Act or not. Even if a harmonious construction
              is given to the Scheme of the Indian Electricity Act as was submitted by
              Mr. Parikh, we do not see as to how Section 26 would govern Section
              20 of the 1910 Act.
                                                                                       H
    70              SUPREME COURT REPORTS                    [2007] 11 S.C.R.

A       43. Section 20 operate in one field namely conferring a power of
  entry on the licensee. The said provision empowers the licensee inter alia
  to alter a meter which would include replacement of a meter. It is an
  independent general provision. In absence of any statutory provision, we
  do not see any reason to put a restrictive meaning thereto. Even under
B the General Clauses Act, a statutory authority while exercising statutory
  power may do all things ~hich are necessary for giving effect thereto.
  There does not exist any provision in any of the statutes referred to
  hereinbefore which precludes or prohibits the licensee to replace one set
  of meter by another. If such a provision is read into the statute, the same
c would come in the way of giving effect to the benefits of new technological
  development. Creative interpretation of the provisions of the statute
  demands that with the advance in science and technology, the Court
  should read the provisions of a statute in such a manner so as to give
  effect thereto.
D        [See State ofMaharashtra & Anr. v. Dr. Praful B. Desai & Anr.,
    [2003] 4 sec 6011
        44. Section 26 of the Act operates in different fields. It comes into
  being only when there exists a dispute. The dispute may be in regard to
E the quantum ofthe amount required to be expended for removing the meter
  or the correctness of the meter. The dispute may also be, in the event,
  the meter is held to be not recording the consumption of electrical energy
  correctly, the amount to which the consumer would be liable to pay, in
  relation thereo.
F       45. Electrical Inspector acts as a statutory authority. He has been
  conferred with a quasi-judicial power to determine the disputes of
  particular kinds. His decision thereupon is final and conclusive. The
  correctness of such decision can be questioned only before a superior
  court of law. Subject of course to a decision of a superior court, the
G decision of the Electrical Inspector is final and binding on the parties.
         '46. It is correct that the matter at the relevant point of time was not
    covered by any statutory regulations, but even otherwise, the respondent
    had the said authority under Section 20 of the 1910 Act.
H         47. Construction of Section 20 vis-a-vis Section 26 of the 1910
    1
    j
          SURESH JINDAL v. BSES RAJDHANI POWER LIMITED                          71
                             [SINHA,J.]
        Act came up for consideration before this Court in Belwal Spinning Mills A
        Ltd And Ors. v. UP. State Electricity Board And Anr., [1997] 6 SCC
        740, wherein a Division Bench of this Court clearly opined;
               "37. After giving our careful consideration to the facts and
               circumstances of the cases in these appeals and the submissions       a
               made by Mr. Gupta, Mr. Sen and Mr. Andhyarujina, the learned
               Solicitor General, it appears to us that Section 20 of the Electricity
               Act authorises the licensee to enter the premises of the consumer
               to remove fittings and other apparatus installed by the licensee.
y              Clause (a) of sub-section (1) of Section 20 authorises the licensee C
               to enter the premises of the consumer for "inspecting, testing,
              repairing or altering the electric supply lines, meters, fittings, works
              and apparatus for the supply of energy belonging to the licensee".
               The licensee, therefore, cannot only enter the premises of the
               consumer for inspecting, testing etc. but the licensee can also alter
               the meter whenever such alteration is needed. Such power under D
               Section 20 does not depend on the adjudication of correctness of
               the meter and other apparatus by the Electrical Inspector on a
              reference under Section 26(6) of the Electricity Act. But such
              power flows from the statutory duties and functions of the licensee
               to maintain the correct meter for recording the quantum of electricity E
              supplied to the consumer. Such duty to ensure maintenance of
              correct meter in the premises of the consumer has been indicated
               in sub-section (1) and sub-section (2) of Section 26. The power
              of removing the meter under Section 20, however, is circumscribed
              by the proviso to sub-section (4) of Section 26 only when the F
              dispute as to the functioning of the meter has been referred to the
              Electrical Inspector under sub-section (6) of Section 26. A licensee
              is authorised under sub-section (7) of Section 26 to place, in
              addition to the meter installed in the premises of the consumer as
              referred to in sub-section (I) of Section 26, other meter or 0
              apparatus as the licensee deems fit for the purpose of recording
              or regulating the amount of energy supplied to the consumer. Such
              power also does not depend on the existence of any dispute as to
              the correctness of the meter installed."
                                                                                       H
                                                                                   \


    72             SUPREME COURT REPORTS                   [2007] 11 S.C.R.
                                                                                   t
A      48. Reliance on the said decision has also been placed by the High
  Court. Mr. Parikh, however, would submit that the High Court failed to
  notice paragraph 48 of the said decision wherein it was laid down that
  Section 26(6) would apply where the meter is not correct and the power
  to remove the meter could be exercised only in such a situation and not
B otherwise.
        49. We may, howeve:r, notice that the observations made in
  paragraph 48 were made while considering the question as to whether
  the decision in terms of sub-section (6) of Section 26 should be limited
  to a statutory period or not. Observations in paragraph 48 of the said
C decision having been made in the aforementioned context, the same cannot
  be said to have any application whatsoever in the instant case.
        50. For the reasons stated hereinbefore, we are of the opinion that
  there is no merit in this appeal. It is dismissed accordingly. 'There shall be
D no order as to costs.
    S.K.S.                                                 Appeal dismissed.
                                                                                       --\.


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "meter replacement"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.