Created byFuzzy Cloud

Supreme Court of India

THE BLUE DREAMZ ADVERTISING PVT. LTD. & ANR.versusKOLKATA MUNICIPAL CORPORATION & ORS.

Citation
2024 INSC 589
Decided
7 August 2024
Disposal
Appeal(s) allowed

Holding

Blacklisting/debarment is not justified where there is a bona fide contractual dispute; the debarment order is set aside as a disproportionate penalty.

Summary

The Kolkata Municipal Corporation awarded a tender to Blue Dreamz Advertising for advertising on street hoardings, but disputes arose over reciprocal obligations such as work orders, bank guarantees, and the number of hoardings installed. The Corporation issued a show‑cause notice and subsequently debarred the company for five years, alleging non‑payment and breach of contract. The company challenged the debarment, invoking an arbitration clause, and the arbitrator later awarded a set‑off amount, indicating a bona fide contractual dispute. The Single Judge of the Calcutta High Court set aside the debarment on the ground of a genuine dispute, but the Division Bench reversed that decision. The Supreme Court held that blacklisting is a drastic remedy and cannot be imposed where a bona fide dispute exists, deeming the penalty disproportionate, and restored the Single Judge’s order. Consequently, the debarment order was set aside and the appeal was allowed.

Issues considered

  • Whether the Corporation’s order dated 02.03.2016 debaring the appellant for five years is valid and justified under law
  • What relief, if any, the appellant is entitled to in view of the debarment

Subjects

TenderTender conditionsBreach of contractBlacklistingDebarmentBid documentBona fide contractual disputeAdvertisement on street hoardingsFulfilment of reciprocal obligationsDisproportionate penalty

Judgment

                 [2024] 8 S.C.R. 189 : 2024 INSC 589

           The Blue Dreamz Advertising Pvt. Ltd. & Anr.
                               v.
              Kolkata Municipal Corporation & Ors.
                       (Civil Appeal No. 8516 of 2024)
                                07 August 2024
     [B.R. Gavai, Sanjay Karol and K.V. Viswanathan,* JJ.]

                            Issue for Consideration
       Where the case is of an ordinary breach of contract and the
       explanation offered by the person concerned raises a bona fide
       dispute, whether blacklisting/debarment can resorted to as a penalty.

                                  Headnotes†
       Tender – Tender conditions – Breach of contract – Blacklisting/
       debarment – Respondent no.1-Corporation invited bids for
       allotment of contract for display of advertisement on street
       hoardings (including V shaped), Bus passenger shelter
       and kiosks – Appellant was the successful bidder – There
       were issues between the appellant and the Corporation with
       regard to the fulfilment of the reciprocal obligations in the bid
       document – Following which appellant was blacklisted – By
       an order of 02.03.2016, the Corporation debarred the appellant
       from participating in any tender for a period of five years –
       The Single Judge of the High Court set aside the order of
       debarment on the ground that there was a bona fide civil
       dispute between the parties – However, the Division Bench
       of the High Court set aside the judgment of the Single Judge
       of the High Court – Justified or not:
       Held: The appellant, after the award of the tender, has admittedly
       paid an amount of Rs. 3,71,96,265/-, though, according to the
       Corporation, the outstanding amount as on the date of the
       debarment was Rs. 14,63,24,727/- – However, as would be
       clear from the facts, right from the inception there have been
       issues between the appellant and the Corporation with regard to
       the fulfilment of the reciprocal obligations in the bid document –
       There was exchange of correspondence between the parties with
       each side blaming the other for not performing the reciprocal
       obligations – While the appellant had a case with regard to the

* Author
190                                                            [2024] 8 S.C.R.

                       Digital Supreme Court Reports


       non-issuance of work orders; non-receipt of formal format of
       bank guarantee; refusal of No Objection Certificate for obtaining
       connection from the Calcutta Electric Supply Corporation Ltd.;
       existence of only 200 out of 250 allotted street hoardings and
       so on demonstrating breach of obligations by the Corporation –
       The Corporation had a case that Bank Guarantee was not the
       mode of payment and as such there was no reason to insist on
       Bank Guarantee; that in the joint inspection the appellant’s men
       failed to cover all the areas and thereafter when appellant was
       asked to submit a list of allotted location, the appellant failed to
       furnish the same and further there was huge default on the part
       of the appellant – All these reasons fall far short of rendering
       the conduct of the appellant in the present case, so abhorrent
       as to justify the invocation of the drastic remedy of blacklisting/
       debarment – The appellant very clearly has been subjected to
       a disproportionate penalty – The exchange of correspondence
       resulted in invocation of the arbitration and it is undisputed that
       by an award of 26.04.2024, the appellant has been awarded after
       due set off Rs. 2,23,14,565/- with 8% interest per annum under
       the very same dispute – It does signify is that there was a bona
       fide contractual dispute between the parties – The Single Judge
       was right in setting aside the order of debarment on the ground
       that there was a bona fide civil dispute between the parties –
       Therefore, the judgment of the Division Bench of the High Court
       is set aside and the judgment of the Single Judge of the High
       Court is restored. [Paras 28, 30, 31, 42]

                                Case Law Cited
       Erusian Equipment & Chemicals Ltd. v. State of West Bengal &
       Anr. [1975] 2 SCR 674 : (1975) 1 SCC 70; B.S.N. Joshi & Sons
       Ltd. v. Nair Coal Services Ltd. & Ors. [2006] Supp. 8 SCR 11 :
       (2006) 11 SCC 548; Kulja Industries Ltd. v. Chief General Manager
       Western Telecom Project BSNL & Ors. [2013] 14 SCR 430 :
       (2014) 14 SCC 731; Patel Engineering Limited v. Union of India
       and Another (2012) 11 SCC 257 – relied on.

                               List of Keywords
       Tender; Tender conditions; Breach of contract; Blacklisting;
       Debarment; Bid document; Bona fide contractual dispute;
       Advertisement on street hoardings; Fulfilment of the reciprocal
       obligations; Breach of obligations; Disproportionate penalty.
[2024] 8 S.C.R.                                                         191

             The Blue Dreamz Advertising Pvt. Ltd. & Anr. v.
                 Kolkata Municipal Corporation & Ors.

                           Case Arising From
     CIVIL APPELLATE JURISDICTION: Civil Appeal No.8516 of 2024
     From the Judgment and Order dated 21.06.2017 of the High Court
     at Calcutta in MAT No.277 of 2017.
                        Appearances for Parties
     P. S. Datta, Sr. Adv., Ms. Anwesha Saha, Salim Ansari, Advs. for
     the Appellants.
     L. C. Agrawala, Pankaj Agarwal, Sujoy Mondal, Advs. for the
     Respondents.
                Judgment / Order of the Supreme Court

                                Judgment
     K.V. Viswanathan, J.
1.   Leave granted.
2.   The present Appeal is filed against the judgment and order dated
     21.06.2017 passed by the Division Bench of the High Court at Calcutta
     in M.A.T. No. 277 of 2017. By the said judgment, the High Court
     allowed the Appeal of the respondents and set aside the judgment
     of the learned Single Judge. Consequently, the Writ Petition filed by
     the appellant stood dismissed.
     Brief Facts:
3.   The respondent no. 1-Kolkata Municipal Corporation (hereinafter
     referred to as the ‘Corporation’) invited bids for allotment of contract
     for display of advertisement on Street Hoardings (including V Shaped),
     Bus Passenger shelter and Kiosks within its jurisdiction. Under the
     tender conditions, the contract was to be awarded for a period of
     one year, subject to extension of two more years. By an award of
     28.05.2014, the appellant who had participated in the tender and
     quoted the highest rate at Rs. 3,70,00,000/- each for cluster no.
     I, II, III, VI and VIII was notified as a successful bidder and was
     requested to confirm the acceptance. On 29.05.2014, the appellant
     conveyed its acceptance.
4.   Thereafter, a series of correspondence ensued with the appellant
     on matters like, alleged non-receipt of any formal work order (on
192                                                            [2024] 8 S.C.R.

                       Digital Supreme Court Reports


       11.06.2014); non-receipt of any format of the Bank Guarantee (on
       13.06.2014); request for a ‘No Objection Certificate’ for obtaining
       new connection from Calcutta Electric Supply Corporation Ltd. (on
       26.06.2014); problems with the execution like, non-matching of
       the unit code numbers with the hoardings or the non-matching of
       locations; existence of same unit code for different locations, rendering
       the commencement of work incapable (letter of 26.06.2014) and
       existence of lesser hoardings out of the 250 street hoardings (letter
       of 07.07.2014).
5.     The Corporation, by its letter dated 08.07.2014, demanded payment
       for the month of June. Thereafter, the appellant wrote a letter of
       19.07.2014 stating that till date they have identified 200 numbers
       of street hoardings out of the 250 allotted and sought for a joint
       inspection to identify the rest of them. At this stage, the Corporation
       issued a letter of 10.09.2014 stating that there was no reason why
       the appellant was insisting for the Bank Guarantee Format since
       Bank Guarantee was not the mode of payment. According to the
       Corporation, the bills for 5 clusters of Rs. 4,62,67,500/- (for only
       July to September, 2014) had not been paid in spite of service of
       the bill on 08.07.2014. The Corporation also mentioned that in the
       joint inspection the appellant’s men failed to cover all the areas and
       thereafter, the appellant was asked to submit a list of allotted locations
       which, according to the Corporation, the appellant had not furnished.
       The appellant was warned that in case the payment as demanded
       was not paid, steps as per the tender clauses would be taken.
6.     When the matter stood thus, the appellant wrote a letter on 14.11.2014
       setting out all the earlier correspondence and the grievances raised by
       them and ultimately praying that they be granted diminution, reduction
       and/or adjustment of the license fee. They prayed that their demand
       for 174 hoardings be confirmed so that they could make the payment.
       The Corporation served a memo dated 06.12.2014 setting out that
       already a notice of 20.11.2014 was served demanding payment of
       8,16,15,870/- up to December, 2014 but the same has not been
       cleared. The appellant was asked to appear on 12.12.2014 to show
       cause why the allotment of hoarding shall not be cancelled. On
       28.02.2015, a Show Cause Notice was issued asking the appellant to
       show cause why the appellant’s allotment be not terminated as dues
       to the tune of Rs. 10,28,52,918/- plus interest had not been cleared.
[2024] 8 S.C.R.                                                            193

             The Blue Dreamz Advertising Pvt. Ltd. & Anr. v.
                 Kolkata Municipal Corporation & Ors.

7.   In this scenario, on 29.07.2015, a notice was published in English
     Daily “The Times of India” Kolkata stating that the appellant had
     been blacklisted from participating in any advertisement in the city
     of Kolkata. However, on a challenge made in Writ Petition No. 960
     of 2015, on 04.08.2015, a submission was made to the Court by the
     learned senior counsel for the Corporation that the decision of the
     blacklisting of appellant was to be withdrawn and that the Corporation
     would proceed with the matter in accordance with law after providing
     opportunity of hearing. The Writ Petition was disposed of.
8.   The appellant had earlier filed Writ Petition No. 261 of 2015
     challenging the Show Cause Notice of 28.02.2015. The learned
     Single Judge dismissed the Writ Petition on 04.03.2015. An appeal
     bearing APOT No. 89 of 2015 was preferred along with GA No. 782
     of 2015. The Appeal and G.A. were disposed of by an order of 24th
     August 2015 recording the submissions of the Learned Additional
     Advocate General appearing for the Corporation and disposing of
     the matter in the following terms:-
           “Due to typographical errors in the show cause notice
           dated 28th February, 2015, the learned Additional Advocate
           General very fairly submitted he is not pressing this show
           cause notice but the appropriate proceedings shall be
           taken before the Arbitrator.”
9.   Thereafter, the Corporation issued a Show Cause Notice dated
     27.08.2015 to the appellant, stating that as on the said date Rs.
     16,84,34,431/- along with interest is due and payable towards
     license fee/advertisement tax. The Show Cause Notice also alleged
     that the appellant had failed to execute the agreement for street
     hoardings, which was issued on 29.11.2014 and failed to submit the
     bank guarantee which was issued on 27.09.2014 and it also alleged
     that the appellant had illegally shifted several hoardings without
     the consent of the authority. The show cause notice asserted that
     in spite of repeated requests and/or reminders, the appellant had
     failed to make payment and refused and/or neglected to perform the
     obligations as per the terms and conditions of the tender. The Show
     Cause Notice further clearly alleged as under:
           “In view of the aforesaid breach of the terms and conditions
           of the tender, you are requested to file a show cause as
           to why befitting action to blacklist you from participating in
194                                                         [2024] 8 S.C.R.

                     Digital Supreme Court Reports


           any tender process should not be taken all (sic.) you make
           the outstanding payment and comply with the terms and
           conditions of the tender. You are required to submit your
           reply within 15 days from the date of Receipt of this letter,
           failing which the authority will take appropriate decision in
           accordance with law.”
10. By its reply of 15.09.2015, the appellant responded to the Show
    Cause Notice. The appellant mentioned therein that the tender
    document did not empower the Corporation to determine the alleged
    breach on the part of the company arising out of the contract; that in
    view of the submission made by the Corporation before the Division
    Bench, it is only the arbitrator in terms of Clause 18 who can decide
    the dispute mentioned in the Show Cause Notice of 27.08.2015;
    that Corporation is a party to the proposed arbitration proceeding
    and it cannot usurp the power of the arbitrator; that the decision to
    blacklist the appellant without recourse to arbitration proceeding is
    illegal and that any decision to blacklist before the decision of the
    arbitrator would be prejudging the alleged guilt without deciding the
    issue. The appellant prayed that the Show Cause Notice be not given
    effect to till the disposal of the arbitration proceeding.
11. It further appears that by notice dated 05.10.2015, the appellant
    invoked clause 18 of the tender document and sought reference to
    the Joint Municipal Commissioner as arbitrator.
       Debarment Order:
12. By an order of 02.03.2016, the Corporation debarred the appellant
    from participating in any tender for a period of five years or till the
    date of exoneration of the company from the allegation of negligent
    performance/action and also of nonpayment of huge amount or till
    the date of payment of entire dues with interest under the direction
    of any authority/forum/court, whichever is later. The order, after
    recording the history of the dispute and after noticing the fact that
    at the hearing given, the company took the same plea as stated by
    them in their reply, observed as under:-
           “… …. The company had alleged that it could find only 174
           hoarding out of 250 hoardings but the company in their letter
           dated 14th November, 2014 stated, inter alia, that they were
           able to find 200 street hoarding including 26-V-shaped.
[2024] 8 S.C.R.                                                            195

             The Blue Dreamz Advertising Pvt. Ltd. & Anr. v.
                 Kolkata Municipal Corporation & Ors.

           The company cannot take such plea particularly when the
           display sites/hoardings were specified in the lists under
           annexure-I, Il & III to the tender notice. The description of
           works under clause-2 of the tender notice clearly stated that
           the street hoarding in the annexure would be allotted in “As
           in where is basis”. The company after having understood
           the scope and effect of the terms and condition of the
           notice the offers which were accepted by the authorities.
           The bills for 5 clusters amounting to Rs.4,58,97,360/- had
           already been served. The company was informed of its
           failure to pay the sum of Rs.4,58,97,360/- for the period
           from July 2014 to September 2014. The company paid
           part amount for 55 nos. of hoarding as against the said
           demand for the said quarter.
           The company failed to mention the unit code on the allotted
           street hoarding and the company did not adhere to the
           instruction as made in this respect by writing letters on
           repeated occasions.
           Clause-2.1 as incorporated in the tender notice is redundant
           in respect of the hoardings already in-existence since such
           hoardings remain fitted with the provision for supply of
           electricity. In fact, no objection certificate is not required
           from the KMC in respect of the existing hoardings. All
           that is necessary is for confirmation of the change of the
           name of the user/agency. It is on record that the company
           continued to display the advertisement in the hoardings
           without requiring the no objection certificate from the
           KMC until 3rd March 2015 when a letter was issued in this
           respect. There is no document to show that the company
           applied to the CESC for electric connection and the CESC
           required no objection certificate from the KMC. It is on
           record that the contract period commenced from 1st June
           2014 and hence there was no cogent reason to write the
           letter for No Objection Certificate after about 8 months. No
           application to the CESC in the name of the petitioners for
           the purpose illuminated street hoarding was submitted to
           the concerned authorities. The company used the supply of
           Electricity without requiring to inform the KMC AND EACH
           AND EVERY HOARDING was found illuminated during
196                                                      [2024] 8 S.C.R.

                  Digital Supreme Court Reports


       inspection failed to obtain the interim order as prayed for
       preferred the appeal being APOT No. 290 of 2015 and
       an application being G.A. No. 2374 of 2015 was filed in
       connection with the said appeal. The Hon’ble appeal court
       while dismissing the appeal and also the application by an
       order dated 3rd August 2015 was pleased to observe that
       there was no urgency in the matter in view of pendency of
       the writ petition. It was also observed that if the appellants
       were aggrieved in any manner with respect to the contract
       it was necessary for them to invoke arbitration clause.
       The company earlier filed the writ petition being W.P.
       No.261 of 2015 relating to the notice to show cause dated
       28th February 2015. The company was asked to show
       cause why the allotment should not be terminated for not
       clearing the dues amounting to Rs. 10,28,52,918/- as then
       calculated plus interest to take defense upon certain facts
       in the written argument. I am not fully convinced and/or
       satisfied with the stand and/or explanation for several
       reasons and/or ground as stated hereinbefore. It appears
       to me that the company did not have the financial capacity
       to have the display of advertisement rights in 5 clusters
       and as such the company started creating problems on
       one plea to another since after obtaining the allotment
       of Sites. The company in one hand stopped the KMC to
       allot the said site to others and on the other hand itself
       stopped the due payment for 5 clusters. The KMC has
       thus suffered in both counts. Moreover the company has
       made an attempt to set up a bad example to others having
       interest to enjoy the advertisement rights.
       That being the position the KMC has no alternative but
       to blacklist the company for gross negligent action. The
       company is therefore debarred from participating in any
       tender to have the award of contract for a period of 5
       years or till the date of exoneration of the company from
       the allegation of negligent, performance/action and also
       of nonpayment of huge amount or till the date of payment
       of entire dues with interest under the direction of any
       authority/forum/court whichever is later.”
[2024] 8 S.C.R.                                                              197

             The Blue Dreamz Advertising Pvt. Ltd. & Anr. v.
                 Kolkata Municipal Corporation & Ors.

13. In the meantime, it appears that in August, 2016, the appellant
    also filed a claim before the arbitrator claiming an award for Rs.
    19,81,60,400/-. At the hearing before us, it was submitted that the
    arbitrator Justice (Retd.) Narayan Chandra Sil, who ultimately heard
    the matter, passed an award on 26.04.2024 awarding the claimant
    a sum of Rs. 2,23,14,565/- after excluding the set off amount of Rs.
    78,03,435/- along with interest of 8% per annum from the date of
    the award till realization. This statement is reiterated in the written
    submissions. We were also given a copy of the award. The respondent
    has not disputed the said fact.
     Proceedings in the High Court:
14. The appellant also filed a Writ Petition, namely, Writ Petition No.
    6616(W) of 2016 challenging the order of 02.03.2016. The learned
    Single Judge of the High Court while setting aside the order of
    02.03.2016 held as under:
           “It is well settled by the above authorities that blacklisting
           is a civil consequence. The rules of natural justice have
           to be scrupulously followed. This denotes that proper
           reasons have to be given. The reasons, should have
           suggested that public interest would be affected if the writ
           petitioner was continued to be awarded contracts by the
           respondent Corporation. Or it was to be established that
           the writ petitioner was a dishonest business organisation,
           or irresponsible or wholly lacking in business integrity. The
           government or a government agency like the respondent-
           Corporation could not blacklist the writ petitioner without
           assigning these reasons or reasons akin thereto. There is
           a civil dispute between the parties. The matter has gone
           to arbitration. At best, the writ petitioner can be accused of
           taking the contract, not fully paying for it and not performing
           it. The respondent Corporation has a monetary claim against
           the writ petitioner. It does not appear that the writ petitioner
           has made payment of any significant part of the contract
           price. It is astonishing that the respondent Corporation did
           not terminate the contract within the contract period and
           award hoardings to another party when the writ petitioner
           made a breach of the payment condition to pay the quarterly
           licence fee in advance. It waited till after the expiry of
198                                                         [2024] 8 S.C.R.

                      Digital Supreme Court Reports


           the contract period on 30th June, 2015. Thereafter, they
           proceeded to show cause the writ petitioner. This shows
           considerable fault on the part of the respondent Corporation.
           It also goes to indicate that expressly or impliedly the
           respondent Corporation had accepted the alleged breach
           of contract made by the petitioner.
           Moreover, the defence of the writ petitioner in their written
           notes of argument is that 174 hoardings which were
           awarded to them were “non-lucrative”. As the respondent
           Corporation did not issue a no objection certificate, CESC
           Limited could not give permission to light the hoardings.
           The writ petitioner could not put them to any use. If this
           is the defence raised by the writ petitioner it could not be
           cast aside as one totally devoid of any merit. Therefore,
           following the ratio laid down by Mr. Justice Sinha in the
           case of B.S.N. Joshi & Sons Ltd. v. Nair Coal Services Ltd
           and another reported in (2006) 11 SCC 548 blacklisting
           proceeding should not have proceeded with because the
           writ petitioner in my opinion raised a bona fide dispute.
           Furthermore, blacklisting ought not to have been made
           until and unless this dispute was resolved.
           For all the above reasons, the impugned order dated 2nd
           March, 2016 is set aside. Only the issue of blacklisting is
           decided by this order. Any observation regarding any other
           dispute between the parties is to be taken as tentative.”
15. The matter was carried in Appeal by the Corporation and by the
    impugned order, the High Court has allowed the same by holding
    that since the appellant was given a hearing and since the order
    of 02.03.2016 cannot be held to be unreasonable or unfair or
    disproportionate, there existed sufficient reasons for debarring
    the appellant. So holding, the Appeal was allowed. The appellant
    aggrieved is before us in Appeal. This Court while issuing notice in
    the matter by its order of 27.04.2018 stayed the operation of the
    impugned judgment.
       Contentions:
16. We have heard Mr. P.S. Datta, learned senior counsel for the appellant
    and Mr. Sujoy Mondal, learned counsel for the respondent. We have
[2024] 8 S.C.R.                                                       199

             The Blue Dreamz Advertising Pvt. Ltd. & Anr. v.
                 Kolkata Municipal Corporation & Ors.

     also perused the written submissions filed by the appellant. The
     respondent has not filed any written submissions.
17. The learned senior counsel for the appellant contends that the
    Corporation could at best have imposed only a ‘penalty’ for making
    late payments or in the case of default of payments under clause 9
    and there could not have been blacklisting; that blacklisting can be
    only made when there was deviation of clauses 2.8, 11 & 14 and
    that the Show Cause Notice precisely setting out why the blacklisting
    was to be imposed need to have been given; that the grounds of
    blacklisting are not the one stated in clauses 2.8, 11 & 14; that the
    order of blacklisting was passed during the pendency of the arbitration
    proceedings; that the issues relating to blacklisting were akin to the
    facts in issue before the arbitration; that the Corporation has failed
    to prove gross misconduct or irregularities or fraud involving of any
    element of public interest; that the learned Single Judge was right
    in setting aside the order of blacklisting; that the Corporation is
    guilty of having not acted fairly and reasonably by not facilitating
    the appellant to perform his contractual right; that the Corporation
    despite the repeated undertaking before the High Court for taking
    resort to arbitration has deliberately issued the order of blacklisting
    and that any and every act of alleged breach of contract would not
    ensue blacklisting.
18. In support of their submission, the appellant relied on B.S.N. Joshi
    & Sons Ltd. vs Nair Coal Services Ltd. & Ors. (2006) 11 SCC
    548. The appellant also assailed the judgment of the Division Bench
    by contending that the Division Bench failed to consider that there
    was no element of violation of public interest involved in the conduct
    of the appellant and in fact the Corporation was guilty of having
    not acted fairly and reasonably and that the Division Bench has
    completely overlooked this aspect. The appellant further contended
    that the order of blacklisting was disproportionate and contrary to
    the judgment in Kulja Industries Ltd. vs Chief General Manager
    Western Telecom Project BSNL & Ors. (2014) 14 SCC 731.
19. The learned counsel for the Corporation defended the order of
    blacklisting as well as the judgment of the Division Bench and prayed
    that there was no case for interference by this Court.
20. We have considered the submissions of the learned counsels and
    perused the record.
200                                                            [2024] 8 S.C.R.

                       Digital Supreme Court Reports


       Questions for consideration:
21. The following questions arise for consideration:
       a.   Whether in the facts and circumstances of the case, the order of
            the Corporation dated 02.03.2016, debarring the appellant for a
            period of five years is valid and justified in the eye of the law?
       b.   If so, what reliefs is the appellant entitled to?
       Reasons and conclusions:
22. Blacklisting has always been viewed by this Court as a drastic remedy
    and the orders passed have been subjected to rigorous scrutiny. In
    Erusian Equipment & Chemicals Ltd. vs State of West Bengal
    & Anr. (1975) 1 SCC 70, this Court observed that
            “20. Blacklisting has the effect of preventing a person
            from the privilege and advantage of entering into lawful
            relationship with the Government for purposes of gains. The
            fact that a disability is created by the order of blacklisting
            indicates that the relevant authority is to have an objective
            satisfaction….”
23. In Mr. B.S.N. Joshi (supra), this Court held that
            “41. … When a contractor is blacklisted by a department
            he is debarred from obtaining a contract, but in terms of
            the notice inviting tender when a tenderer is declared to
            be a defaulter, he may not get any contract at all. It may
            have to wind up its business. The same would, thus, have
            a disastrous effect on him. Whether a person defaults in
            making payment or not would depend upon the context
            in which the allegations are made as also the relevant
            statute operating in the field. When a demand is made, if
            the person concerned raises a bona fidedispute in regard
            to the claim, so long as the dispute is not resolved, he
            may not be declared to be defaulter.”
                                                   (Emphasis supplied)
24. This Court in Kulja Industries Ltd. (supra) after setting out the legal
    position governing blacklisting/debarment in USA and UK held that:
            “25. Suffice it to say that “debarment” is recognised
            and often used as an effective method for disciplining
[2024] 8 S.C.R.                                                          201

             The Blue Dreamz Advertising Pvt. Ltd. & Anr. v.
                 Kolkata Municipal Corporation & Ors.

           deviant suppliers/contractors who may have committed
           acts of omission and commission or frauds including
           misrepresentations, falsification of records and other
           breaches of the regulations under which such contracts
           were allotted. What is notable is that the “debarment”
           is never permanent and the period of debarment would
           invariably depend upon the nature of the offence committed
           by the erring contractor.
           26. In the case at hand according to the respondent BSNL,
           the appellant had fraudulently withdrawn a huge amount of
           money which was not due to it in collusion and conspiracy
           with the officials of the respondent Corporation. Even so
           permanent debarment from future contracts for all times
           to come may sound too harsh and heavy a punishment
           to be considered reasonable especially when (a) the
           appellant is supplying bulk of its manufactured products to
           the respondent BSNL, and (b) the excess amount received
           by it has already been paid back.”
25. What is significant is that while setting out the guidelines prescribed in
    USA, the Court noticed that comprehensive guidelines for debarment
    were issued there for protecting public interest from those contractors
    and recipients who are non-responsible, lack business integrity or
    engage in dishonest or illegal conduct or are otherwise unable to
    perform satisfactorily. The illustrative cases set out also demonstrate
    that debarment as a remedy is to be invoked in cases where there is
    harm or potential harm for public interest particularly in cases where
    the person’s conduct has demonstrated that debarment as a penalty
    alone will protect public interest and deter the person from repeating
    his actions which have a tendency to put public interest in jeopardy.
    In fact, it is common knowledge that in notice inviting tenders, any
    person blacklisted is rendered ineligible. Hence, blacklisting will not
    only debar the person concerned from dealing with the concerned
    employer, but because of the disqualification, their dealings with
    other entities also is proscribed. Even in the terms and conditions
    of tender in the present case, one of the conditions of eligibility is
    that the agency should not be blacklisted from anywhere.
26. In other words, where the case is of an ordinary breach of contract
    and the explanation offered by the person concerned raises a
202                                                        [2024] 8 S.C.R.

                      Digital Supreme Court Reports


       bona fide dispute, blacklisting/debarment as a penalty ought not
       to be resorted to. Debarring a person albeit for a certain number
       of years tantamounts to civil death inasmuch as the said person is
       commercially ostracized resulting in serious consequences for the
       person and those who are employed by him.
27. Too readily invoking the debarment for ordinary cases of breach of
    contract where there is a bona fide dispute, is not permissible. Each
    case, no doubt, would turn on the facts and circumstances thereto.
28. Examining the facts of this case from that perspective, we find that
    the appellant, after the award of the tender, has admittedly paid an
    amount of Rs. 3,71,96,265/-, though, according to the Corporation,
    the outstanding amount as on the date of the debarment was Rs.
    14,63,24,727/-. However, as would be clear from the facts discussed
    hereinabove, right from the inception there have been issues between
    the appellant and the Corporation with regard to the fulfilment of
    the reciprocal obligations in the bid document. There has been
    exchange of correspondence between the parties with each side
    blaming the other for not performing the reciprocal obligations.
    While the appellant had a case with regard to the non-issuance
    of work orders; non-receipt of formal format of bank guarantee;
    refusal of No Objection Certificate for obtaining connection from
    the Calcutta Electric Supply Corporation Ltd.; existence of only
    200 out of 250 allotted street hoardings and so on demonstrating
    breach of obligations by the Corporation, the Corporation had a
    case that Bank Guarantee was not the mode of payment and as
    such there was no reason to insist on Bank Guarantee; that in the
    joint inspection the appellant’s men failed to cover all the areas
    and thereafter when appellant was asked to submit a list of allotted
    location, the appellant failed to furnish the same and further there
    was huge default on the part of the appellant.
29. Even in the order dated 02.03.2016 by which the appellant was
    debarred for a period of five years, the reason given is that the
    tender notice had clearly stated that the street hoardings in the
    annexures would be allotted on ‘as is where is’ basis; that the
    company having understood the scope and effect of the terms and
    conditions of the notice accepted the award; that, ‘No Objection
    Certificate’, is not required in respect of the existing hoardings; that
    there was no document to show that the company had applied to
[2024] 8 S.C.R.                                                          203

             The Blue Dreamz Advertising Pvt. Ltd. & Anr. v.
                 Kolkata Municipal Corporation & Ors.

     the Calcutta Electric Supply Corporation Ltd. for connection and
     that it appeared to the Corporation that the company did not have
     the financial capacity to pay and as such the company was creating
     problems on one pretext or the other since obtaining the allotment
     of sites. The order also stated that the appellant had set up a bad
     example to others having interest to enjoy the advertisement rights.
30. All these reasons fall far short of rendering the conduct of the appellant
    in the present case, so abhorrent as to justify the invocation of the
    drastic remedy of blacklisting/debarment. The appellant very clearly
    has been subjected to a disproportionate penalty. The Corporation
    has lifted a sledgehammer to crack a nut. We disapprove of the said
    course of action on the facts of this case.
31. The exchange of correspondence resulted in invocation of the
    arbitration and today it is undisputed that by an award of 26.04.2024,
    the appellant has been awarded after due set off Rs. 2,23,14,565/-
    with 8% interest per annum under the very same dispute. We are
    not here concerned with the correctness of the award. What it does
    signify is that there was a bona fide contractual dispute between
    the parties and we hold that the learned Single Judge was right in
    setting aside the order of debarment on the ground that there was
    a bona fide civil dispute between the parties.
32. What renders the matter a fortiori is that when APOT No. 89 of 2015
    along with GA 782 of 2015 filed against the order of the learned
    Single Judge dismissing Writ Petition No. 261 of 2015, the counsel
    for the Corporation had submitted to the Court that the Show Cause
    Notice was being withdrawn at that stage and appropriate proceeding
    was to be taken before the arbitrator. In spite of the statement, the
    Corporation did not invoke arbitration.
33. The appellant invoked arbitration and no doubt a counter claim was
    filed by the Corporation before the arbitrator. Ultimately, the counter
    claim was decreed for Rs. 78,03,435/- and the claim was decreed
    for Rs. 3,01,18,000/- and after ordering set off, an award has been
    passed for Rs. 2,23,14,565/-.
34. The issues framed by the arbitrator also indicate that the assertions
    and counter assertions of the appellant and the Corporation were
    clearly in the nature of a bona fide civil dispute only to demonstrate
    that aspect, the issues are extracted herein below:
204                                                          [2024] 8 S.C.R.

                     Digital Supreme Court Reports


          “1.   Is the arbitral proceeding barred by reasons of accord
                and satisfaction?
          2.    Did the respondents fail to allot 250 street hoardings
                in terms of tender document?
          3.    Did the respondents fail and neglect to provide clear
                sites to the claimants by intervening and removing
                illegal hoardings for obstructions at the allotted sites?
          4.    Did the respondents issue ‘no objection certificate’
                to the claimants for getting new connections from
                the CESCP?
          5.    Was there any mis-match of unit code and the location
                hoardings?
          6.    Was it established and accepted in joint inspection
                by the KMC that only 200 street hoardings out of
                250 could be located?
          7.    Did the claimants fail to deposit the requisite amount
                in advance under the contract for which the KMC,
                the respondent, suffered substantial loss in revenue?
          8.    Was there any obligation of the respondents to identify
                the location of the street hoardings as the agreement
                was on ‘as is where is basis’?
          9.    Did the parties discharge their respective liabilities
                under the contract and if so to what extent?
          10. Is the claimant entitled to the claim amount as
              claimed?
          11. Are the respondents entitled to the amount of counter-
              claim as claimed in their statement of counter-claim?
          12. To what other relief or reliefs the parties are entitled?”
35. The Division Bench has, in our opinion, not appreciated the case in its
    proper perspective. Merely saying that the blacklisting order carried
    reasons is not good enough. Do the reasons justify the invocation
    of the penalty of blacklisting and is the penalty proportionate, was
    the real question.
[2024] 8 S.C.R.                                                              205

             The Blue Dreamz Advertising Pvt. Ltd. & Anr. v.
                 Kolkata Municipal Corporation & Ors.

36. The Division Bench has observed that blacklisting is a business
    decision by which the party affected by the breach decides not to
    enter into any contractual relationship with the party committing the
    breach. It also observed that between two private parties the right
    to take any such decision is absolute and untrammeled by any
    constraints whatsoever. The observations are too sweeping in their
    ambit and wholly overlook the fact that the respondent-Corporation
    is a statutory body vested with the duty to discharge public functions.
    It is not a private party. Any decision to blacklist should be strictly
    within the parameters of law and has to comport with the principle
    of proportionality.
37. The Division Bench having noticed the fact that any decision to
    blacklist will be open to scrutiny on the anvil of the doctrine of
    proportionality has failed to apply the principle to the facts of the
    case in the correct perspective. The Division Bench has also failed to
    correctly appreciate the ratio of the decision in B.S.N. Joshi (supra).
38. There has been no enquiry by the Division Bench as to whether
    the conduct of the appellant was part of the normal vicissitudes in
    business and common place hazards in commerce or whether the
    appellant had crossed the rubicon warranting a banishment order,
    albeit for a temporary period in larger public interest.
39. One such case where this Court found the Lakshman Rekha to be
    breached by the party blacklisted was Patel Engineering Limited vs.
    Union of India and Another, (2012) 11 SCC 257. In that case, while
    upholding the order of blacklisting, this Court recorded the following:
           “33. From the impugned order it appears that the second
           respondent came to the conclusion that: (1) the petitioner is
           not reliable and trustworthy in the context of a commercial
           transaction; (2) by virtue of the dereliction of the petitioner,
           the second respondent suffered a huge financial loss; and
           (3) the dereliction on the part of the petitioner warrants
           exemplary action to “curb any practice of ‘pooling’ and
           ‘mala fide’ in future”.
           34. We do not find any illegality or irrationality in the
           conclusion reached by the second respondent that the
           petitioner is not (commercially) reliable and trustworthy in
           the light of its conduct in the context of the transaction in
           question. We cannot find fault with the second respondent’s
206                                                              [2024] 8 S.C.R.

                          Digital Supreme Court Reports


               conclusion because the petitioner chose to go back on its
               offer of paying a premium of Rs 190.53 crores per annum,
               after realising that the next bidder quoted a much lower
               amount. Whether the decision of the petitioner is bona fide
               or mala fide, requires a further probe into the matter, but,
               the explanation offered by the petitioner does not appear
               to be a rational explanation.
               36. …. The dereliction, such as the one indulged in by
               the petitioner, if not handled firmly, is likely to result in
               recurrence of such activity not only on the part of the
               petitioner, but others also, who deal with public bodies, such
               as the second respondent giving scope for unwholesome
               practices…..”
40. Equally so in Kulja Industries (supra), the party blacklisted was
    alleged to have fraudulently withdrawn a huge amount of money
    which was not due to it in collusion and conspiracy with officials of
    the respondent Corporation.
41. Patel Engineering (supra) and Kulja Industries (supra) bring
    out the contrast between cases of that ilk and others, like the case
    in question. It is this distinction the Division Bench has grossly
    overlooked which, however, the learned Single Judge had rightly
    brought to the fore.
42. For all the reasons set out hereinabove, we set aside the impugned
    judgment of the Division Bench dated 21.06.2017 passed in M.A.T.
    No. 277 of 2017 and restore the judgment of the learned Single
    Judge. The result will be that the Writ Petition No. 6616(W) of 2016
    filed by the appellant before the High Court at Calcutta would stand
    allowed and the order of blacklisting dated 02.03.2016 would stand
    set aside. The Appeal is, accordingly, allowed. No order as to costs.

       Result of the case: Appeal allowed.



       †
           Headnotes prepared by: Ankit Gyan


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Tender"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.