UNION OF INDIA ETC. ETC.versusNATIONAL HYDROELECTRIC POWER CORPN. LTD. AND ORS. ETC. ETC.

Citation
2001 INSC 311
Decided
25 July 2001
Disposal
Dismissed

Holding

The levy of cess on the hydro‑electric power generating industry was invalid because the amendment of Schedule I under Section 16 of the Water (Prevention and Control of Pollution) Cess Act, 1977 was not lawfully effected as Parliament never passed the required resolution.

Summary

The Union of India sought to levy a cess on the National Hydroelectric Power Corporation under the Water (Prevention and Control of Pollution) Cess Act, 1977. Hydro‑electric plants were not originally listed in Schedule I, and a notification (GSR 377(E), 16 April 1993) was issued to add them. The respondents challenged the levy, arguing that the amendment of Schedule I was invalid because the procedure in Section 16(2) – laying the notification before Parliament and obtaining a parliamentary resolution – was not complied with. The High Court held that no resolution was ever moved, so the amendment was ineffective and the cess could not be collected. The Supreme Court affirmed this view, stating that without a parliamentary resolution the amendment of Schedule I was unlawful, and therefore the levy was not in accordance with law. Consequently, the appeals were dismissed without any order as to costs.

Issues considered

  • Whether the addition of hydro‑electric power generating industry to Schedule I of the Water (Prevention and Control of Pollution) Cess Act, 1977 was valid under Section 16.
  • Whether a cess can be lawfully levied on the hydro‑electric power industry in the absence of a valid parliamentary resolution approving the amendment.

Legislation cited

Subjects

Water pollution cessSchedule I amendmentParliamentary approvalEnvironmental lawHydroelectric powerStatutory interpretation

Judgment

A                        UNION OF INDIA ETC. ETC.
                                    v.
               NA TJONAL HYDROELECTRIC POWER CORPN. LTD.
                            AND ORS. ETC. ETC.

                                    JULY 25, '.LOO I
B
     [B.N. KIRPAL, N. SANTOSH HEGDE AND K.G. BALAKRISHNAN, JJ.)



            Water (Prevention and Control of Pollution) Cess Act, 1977 :

c         S. I 6(2)-Amendment of Schedule I-Units causing pollution--Levy and
    collection of cess from industries specified in Schedule I-Initially hydro-
    power generating industry not included in Schedule I-Notification No. GSR
     377(£) dated 16.4.1998 issued imposing cess on hydro-power generating
     industry-Challenged-High Court holding that provisions of Section 16 had
D   not been complied with while purporting to amend Schedule I-Held, High
    Court was right in holding that levy of cess was not in accordance with law--
     Though the Notification was laid before the Parliament, steps leading to passing
    of resolution were not even commenced, and as such it cannot be said that
    there was a valid amendment ofSchedule I to the Act-Legislation-Amendment
    of an Act-Environmental law.
E
            CIVIL APPELLATE JURISDICTION : Civil Appeal No. 2885 of
    2000.

         From the Judgment and Order dated 11.10.99 of the HimachaI Pradesh
    High Court in C.W.P. No. 403 of 1997.
F
                                         AND

            C.A. Nos. 4659-4668 of 2000 With C.A. No. 4516/2000 and 4517 I
    2000.

G         D.S. Mehra, K.K. Venugopal, Ms. B. Sunita Rao, Ms. Sushma Suri,               ·- -
    Satish K. Agnihotri, Ms. Yogmaya Agnihotri, Anil K. Pandey, Naresh K.
    Sharma, Dhruv Mehta, N.S. Bawa, N.D. Kalra, Ms. Karan Nehra, Ms. Shobha,
    Anil Nag, Ashok Kumar Gupta, Ajit Pudussery, Sushi! Kr. Ja!n, Ms. Jayshree
    Anand, Jagjit S. Ch'.~ura, V.K. Shailendra, Krishnan Venugopal, R.S. Suri,
H   Mahabir Singh, S.B. Upadhyay and Rajiv Nanda for the appearing parties.
                                        14
        U.0.1. v. NATIONAL HYDROELECTRIC POWER CORPN. LTD.                   15
      The following Order of the Court was delivered :                             A
      Civil Appeal Nos. 2885/2000 and 4659-4668/2000

     The short question which arises for consideration in these cases is :
Whether there can be a valid levy under the provisions of the Water (Prevention
and Control of Pollution) Cess Act, I977 (hereinafter referred to as "the said     B
Act") on the hydro power generating industry?

      The aforesaid Act was promulgated with a view to levy and collect cess
from the units which were thought to cause pollution and the funds so realised
were to be entrusted to appropriate authorities, inter a/ia, for remedial
measures.                                                                          c
      According to Section 3 of the side Act, the cess was payable by every
person carrying on any specified industry and by every local authority. The
expression 'specified industry' is defined in Section 2(c) to mean any industry
specified in Schedule I.
                                                                                   D
      When the Act was promulgated, hydel power generating industry was
not included in Schedule I. In order to be able to impose cess on this industry,
a notification No. GSR 377(E) dated 16th April, 1993 was purported to be
issued under Section 16 of the Act.

      The respondent filed writ petitions challenging the imposition of cess       E
on the hydro power generating industry. Amongst other grounds which were
raised, it was contended on behalf of the respondents that there had' been no
valid amendment of Schedule I of the Act and, therefore, no cess could be
imposed. This was one of the contentions which was accepted by the High
Court which came to the conclusion that the provisions of Section 16 had not       F
been complied with while purporting to amend Schedule I of the Act.

      In these appeals, it has been contended by the learned Additional
Solicitor General that a notification had been issued as contemplated by
Section I 6 and the matter had been referred to a Parliamentary Committee
and this shows that there had been sufficient compliance with the provisions       G
of Section 16 and the amendment should be regarded as having been duly
incorporated in Schedule I.

     Section 16 reads as follows :

           "16. Power to amend Schedule I. - ( 1) The Central Government           H
     16                         SUPREME COURT REPORTS [2001] SUPP. I S.C.R.

A           may, by notification in the Official Gazette add to Schedule I any
            industry having regard to the consumption of water in the carrying on
            of such industry and the consequent discharge thereof resulting in
            pollution of any stream and thereupon Schedule I shall, subject to the
            provisions of sub-section (2), be deemed to be amended accordingly.

B               (2) Every such notification shall be laid before each House of
            Parliament, if it is sitting, as soon as may be after the issue of the
            notification, and if it is not sitting, within seven days of its re-assembly
            and the Central Government shall seek the approval of Parliament to
            the notification by a resolution moved within a period of fifteen days
            beginning with the day on which the notification is so laid before ~he
c           House of the People, and if Parliament makes any modification in the
            notification or directs that the notification should cease to have effect,
            the notification shall thereafter have effect only in such modified
            form or be of no effect, as the case may be, but without prejudice to
            the validity of anything previously done thereunder."
D
           Sub-section (I) gives power to the Central Government to add to
     Schedule I any industry, but the procedure which is to be followed is provided
     by sub-section (2). When a notification is issued with a view to making an
     addition to Schedule I, the same is required to be laid before each House of
     Parliament if it is sitting and if the Parliament is not in session then a time
E    limit of seven days is prescribed from the re-assembly of the Parliament
     within which the notification must be so place. Sub-section (2) further requires
    that after the notification has been so place, then within fifteen days of the
    placing of the notification, the Central Government has to seek approval of
    the Parliament to the issuance of the notification. Mere perusal of sub-section
F   (2) shows that there has to be a positive act of approval by the Parliament
    to the issuance of the notification before it can be held that Schedule I has
    been amended. Merely laying the notification before each House of Parliament
    is not sufficient compliance within the provisions of Section 16(2). There is
    of course no time limit within which the Houses of Parliament are required
    to pass a resolution once the Central Government has sought approval as
G   contemplated by sub-section (2), but in the present case the pleadings disclose
    that no such approval was in fact sought for.

          During the hearing of the writ petitions before the Himachal Pradesh
    High Court, an affidavit dated 19th July, 1999 was filed by one Dr. Jag Ram
    Additional Director in the Ministry of Environment & Forests, Government
H   of India. In paragraph 4 of the said affidavit, he states as follows :
                   U.0.1 v. NATIONAL HYDROELECTRIC POWER CORPN. LTD.                  17

                       "4. That during the course of hearing on 5-7 July, I999 before       A
                   this Hon'ble Court reference was made to the averments made in
                   paragraph 5 of the aforementioned affidavit (dated 9.12.98) by this
                   respondent. In this connection, this respondent submits that the
                   requisite records and bulletins of the Parliament have been further
                   exam in ed. It was found that no resolution relating to the above        B
                   notification dated 16.4.93, had been moved."

                We see no reason to disbelieve the correctness of the averment so made
          in the said affidavit. The averment made is categorical and unequivocal,
          namely, that no resolution relating to the notification dated 16.4.1993 had
          been moved in the Parliament. If no resolution had been moved, the question       C
          of the Parliament giving approval does not arise. Though the first step of
          placing the notification in each House of Parliament had been taken, subsequent
          steps leading to passing of the resolution were not even commenced with the
          moving of the resolution. It is not necessary for us to consider what is the
          effect of not moving the resolution within the time frame of 15 days as
          prescribed by sub-section (2) as the present case is not where there has been     D
          a delay in moving the resolution. There has been in fact a non-compliance
          with the said requirement. With resolution not having been moved at all, it
          cannot be held that there was a valid amendment of Schedule I to the Act.
          The High Court,. in our opinion, was, therefore, right in coming to the
          conclusion that this levy and the purported realisation of the cess was not in    E
          accordance with law.

                 The appeals are, accordingly, dismissed, but with no order as to costs.

                 Civil Appeal Nos. 4516 and 4517 of 2000.

               In view of the above order, these appeals are also dismissed, but with       F
          no order as to costs.

          R.P.                                                      Appeals dismissed.

_..-->·


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Water pollution cess"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.