Created byFuzzy Cloud

Supreme Court of India

UNION OF !NOIA & ANR.versusHBL NIFE POWER SYSTEMS LTD.

Citation
2016 INSC 73
Decided
20 January 2016
Disposal
Appeal(s) allowed

Holding

Open advertisement for procurement of critical defence spare parts like submarine batteries is impermissible; such items must be procured only after a development indent and registration with DGQA as per Government policy.

Summary

The case concerned the procurement of submarine batteries, a mission‑critical defence spare part. The respondent sought an open advertisement and request for proposal (RFP) for supply, arguing a vested right after developing prototype cells. The Union of India contended that defence policy requires such critical items to be developed under the supervision of the Director General of Quality Assurance (DGQA) and that only vendors registered with DGQA after a development indent may be considered. The Supreme Court examined the Government's policy, the stringent DGQA procedures, and the distinction between common‑use items and mission‑critical defence supplies. It held that the High Court erred in directing an open tender for submarine batteries, as the policy mandating development indent and DGQA registration is valid and must be followed. Consequently, the appeal was allowed and the High Court order set aside.

Issues considered

  • Whether the High Court was correct in directing the issuance of an open advertisement for procurement of submarine batteries, which are classified as critical defence spare parts.
  • Whether procurement of mission‑critical defence items can be undertaken through open tender or must adhere to the DGQA development‑indent and registration procedure.
  • Whether the respondent has a vested right to obtain an RFP without complying with the DGQA development process.
  • Whether the Defence Ministry/DGQA policy for procurement of critical defence supplies is legally valid and enforceable.

Subjects

defence procurementcritical spare partssubmarine batteriesDGQAdevelopment indentopen tendergovernment policystrategic defence

Judgment

                            [2016] l S.C.R. 576



A                       UNION OF !NOIA & ANR.
                                     v.
                   HBL NIFE POWER SYSTEMS LTD.
                      (Civil Appeal No. 3193 OF 2006)
B                           JANUARY 20, 2016
           [T. S. THAKUR, CJI. AND R. BANUMATHI, J.]
           lender - In respect of purchase of essential defence supplies/
    critical spare parts - Permissibility - Held: In respect of highly
    critical spare parts, the Government has a policy for issuance of
c   the development indent, developing the source and registration with
    DGQA (Director General of Quality Assessment) - DGQA has a
    very stringent procedure before any vendor is registered with DGQA
    for supplying the product - An open advertisement inviting tenders
    can be issued only for purchase of common use items and not for
D   purchase of defence critical spare parts like submarine batteries -
    The High Court erred in directing issuing advertisement inviting
    tender without keeping in view the policy of the Government.
          Allowing the appeal, the Court
           HELD: 1. Defence Ministry/ DGQA (Director General
E
    Quality Assurance) has a very stringent procedure before any
    vendor is registered with DGQA for supplying the 'mission
    critical' strategic defence product. The product, though is
    manufac:tured by a private supplier, it is not as if the Government
    is totally associated with the production process of the product.
F   Prior to grant of registration, the Government pays the vendor
    to 'develop' the product under its supervision for over a period
    of time. Officials of the DGQA are posted at the factory of the
    supplier to ensure that the goods so produced are absolutely in
    order. The inspectors of DGQA inspect every stage of production.
    Development of such products would require upto a maximum of
G   three years, as the development process involves drawing up of
    detailed technical specifications and performance criteria based
    on which the firm has to prepare a detailed design for each and
    every component to meet the stringent military standards. [Para
    9] [581-H; 582-A-C]
H
                                    576
    UNION OF INDIA v. HBL NIFE POWER SYSTEMS LTD.                       577


         2. The subject-matter of the present case is submarine         A
  batteries. The importance of submarine batteries to a submarine
  cannot be underestimated as it is strategically a vital equipment
  for submarines. DGQA therefore ensures that it is associated
  during the production of the batteries by the approved vendor
  and only those batteries which pass the thirteen tests are
                                                                        B
  purchased by the Navy. Ministry of Defence/Navy authorities
  cannot accept the final product without being fully associated with
  the development of the product right from the stage of
  procurement of raw material to the stage of final product. As per
  the policy, RFP (Request for Proposal) could be issued only to a
  firm which is duly registered with DGQA for supply of the product     c
  after development of the product under the aegis of DGQA.
  Having regard to the requirements of a highly critical spare part
  like submarine batteries, the Government has framed the policy
  for issuance of the development indent, developing the source
· and registration with DGQA. In the present writ petition, policy
                                                                        D
  itself was not under challenge. (Para 10] (582-D, G-H; 583-B-C]
       3. The Government cannot put the life of, its defence
personnel and submarine worth crores of rupees to risk simply
because the respondent claims to have the capability and can
supply submarine batteries. For such defence critical spare parts
like submarine batteries, there cannot be any open advertisement        E
inviting tenders. Advertisements are issued calling for tenders
only for common use items which are normally available in the
open market with a wide range of sources. Submarine batteries
do not fall under this category of common use items. The
respondent cannot claim any vested right to be issued a                 F
development indent or RFP or a supply order simply because it
has made investments to manufacture submarine batteries.
Straightway RFP caunot be issued to the respondent by ignoring
the procedure for issuing a development indent and testing the
batteries. [Para 11] [583-F-G]
                                                                        G
      4. The High Court did not keep in view the policy of the
Government in purchasing the critical spare parts for the defence
and in particular, in developing submarine batteries under the
aegis of the Defence Ministry and the High Court erred in
directing the appellants to issue an advertisement giving details
                                                                        H
578            SUPREME COURT REPORTS                            [2016] 1 S.C.R.


A     about the technical specifications for submarine batteries and in
      selecting the product submitted in response to the advertisement.
      [Pl!r.a 13] f.585-Dl
            CIVIL APPELLATE JURISDICTION : Civil Appeal No. 3193
      of 2006
B           From the Judgment and Order dated 27.10.2005 of the High Court
      of Delhi at New Delhi in LPA No. 2448 of2005.
             Pinky Anand, ASG, W. A. Qadri, R. Balasubramanian, Rishabh
      Jain, Karan Seth, Santosh Kumar, Anil Katiyar for the Appellants.

 c          Anitha Shenoy for the Respondent.
            The Judgment of the Court was delivered by
             R. BANUMATID, J. 1. This appeal assails the order dated
      27.10.2005 passed by the High Court of Delhi allowing the appeal in
      LPA No.2448 of2005 thereby directing the Union of India to issue an.
 D    advertisement in leading newspapers having wide circulation inviting
      tenders for the submarine batteries mentioning the detailed technical
      specificationsand the appellants to consider all the products which meet
      the technical specifications and thereby proceed to select the best product
      in accordance with law.
 E           2. The subject-matter involved in the present case is submarine
      batteries required for the Indian Navy. Indian Navy has three types of
      submarines for which three different types of batteries are used. Type-
      ! battery for EKM submarines, Type-II battery for SSK class submarines
      and Type-Ill battery for Foxtrot class submarines. Initially, these batteries
      were imported from the Original Equipment Manufacturer. In view of
 F
      the recurring requirement of the batteries, subsequently a decision was
      taken to progress their indigenisation. Director General Quality Assurance
      (DGQA) working under the Ministry of Defence has a detailed procedure
      to 'develop/indigenise' critical items/spares. As per the said procedure,
      the Government identifies the possible vendors and assesses their
 G    capacity/teclmical qualifications and thereafter a development order is
      placed on the proposed supplier. During this period of development of
      the spares, the Government carries out regular inspection and the product
      is developed under the aegis of officials of the Defence Ministry and
      officers of the DGQA are associated throughout the development process
      right from the time of sourcing of raw materials to ensure that the product
 H
   UNION OF INDIA v. HBL NJFE POWER SYSTEMS LTD.                              579
                 [R. BANUMATHI, J.]

not only meets the technical qualifications but is fully reliable and free    A
from any errors in actual performance.
       3. By following the above rigorous procedure, Mis. Standard
Batteries Ltd. was developed as an indigenous manufacturer for supplying
Type-III submarine batteries. Mis. Standard Batteries Ltd. was
subsequently developed as a manufacturer of Type-I submarine batteries        B
in the year 1988. Mis. Exide Industries Ltd. was developed as an
indigenous manufacturer ofType-11 submarine batteries in 1989. In the
year 1998, Mis. Standard Batteries Ltd. sold its business to Mis. Exide
Industries Ltd. Since then, Mis. Exide Industries Ltd. has become a
single vendor in supplying batteries for all three classes of submarines to
the Indian Navy. Officers of DGQA are constantly associated with the
                                                                              c
manufacturing of the submarine batteries in Exide Industries Ltd. as and
when they are required by the Indian Navy. As Mis. Exide Industries
Ltd. has become the single vendor, in 2004, Government started exploring
the possibility of developing another supplier as second source for
submarine batteries. But as per the policy, the Government cannot register    D
anyone for supply of submarine batteries without following the procedure
or putting the vendor through the process of the development. In any
event, the requirement of the supervision of DGQA in development of
the product and thirteen quality tests intended to test submarine batteries
could never be dispensed with.
                                                                              E
       4. The respondent made its representation in October 2004 to the
Ministry of Defence claiming that it had developed submarine batteries
and that they are under internal evaluation. On 31.03 .2005, the respondent
requested the Ministry of Defence for a development order so that the
respondent can be developed as the second source of submarine batteries
and the respondent agreed to undergo stringent tests before it could be        F
registered for supplying the product. As the residual life of the existing
batteries was coming to an end, in July 2005, the Government has been
processing the request by the Navy to purchase submarine batteries.
Since only Mis. Exide Industries Ltd. was then the only approved supplier
of all types of submarine batteries, it was proposed to issue 'Request        G
For Proposal' (RFP) to Mis. Exide Industries Ltd. alone and the Defence
Minister gave approval to issue RFP to Mis. Exide Industries Ltd. for
supplying eleven sets of submarine batteries.
      5. Respondent filed writ petition before the Delhi High Court on
17.09.2005 claiming that it should be issued a request for proposal as         H
580             SUPREME COURT REPORTS                           [2016] 1 S.C.R.


A     well, as it was registered for some other products namely torpedo
      batteries. Be it noted that the submarine batteries claimed to have been
      developed by the respondent were neither developed under the aegis of
      the DGQA nor the Government paid for development of the prototype
      cells. The learned Single Judge vide order dated 05. l 0.2005 dismissed
      the writ petition observing that ifthe extant policy envisages selection or
B
      shortlisting of a party for purposes of raising a development indent for
      an alternative indigenous source of equipment, this stage must be
      successfully crossed before venturing further into the issuance ofrequest
      for proposal and thereafter issuance of a PAC. The learned Single Judge
      further held that procurement method was a policy matter and the policy
c     did not suffer from any illegality and in any event, the policy has not
      been challenged by the respondent in the writ petition. Aggrieved by
      dismissal of the writ petition, the respondent filed LPA No.2448/2005
      which was allowed vide the impugned judgment dated 27.10.2005 and
      the High Court issued directions to the Ministry of Defence to procure
      even the critical spare parts like submarine batteries only after issuing
D
      advertisement and calling for open tender. Assailing the impugned
      judgment, the appellant-Union oflndia has preferred this appeal.
             6. Ms. Pinky Anand, learned Additional Solicitor General oflndia
      alongwith Mr. Qadri appearing for the appellants contended that while
      tender is issued for common use items, purchase of specialized and
 E    critical spare parts for the Defence Ministry cannot be done by an open
      tender and in the instant case, there were justifiable reasons for the
      Government to classify submarine batteries as critical and specialized
      defence product and to procure the same only from those suppliers who
      have developed the submarine batteries under the aegis of DGQA and
 F    are duly approved/registered with DGQA. It was submitted that in relation
      to essential defence supplies/critical spare parts, the Government must
      ensure that the supplier has the necessary technical qualifications,
      infrastructure and capacity to develop the product and in critical spare
      parts like submarine batteries, the Government cannot put the life of its
      defence personnel and submarine worth several crores of rupees to risk
 G    simply because the respondent claims to have the capability. It was
      submitted that the High Court was not right in directing the Government
      for issuing tenders for critical spare parts like submarine batteries without
      knowing whether the said product can withstand all the thirteen quality
      tests and render reliable performance on board.
 H
   UNION OF INDIA v. HBL NIFE POWER SYSTEMS LTD.                               581
                 [R. BANUMATHI, J.]

       7. Per contra, learned counsel for the respondent submitted that        A
the respondent for the first time vide its letter dated 06.10.1999 had
shown its intention to develop the submarine batteries and requested the
appellant to provide the specifications of the same and in response to the
same, appellants vide letter dated 22.11.1999 duly provided the technical
specifications and on the basis of the same, respondent had developed
                                                                               B
prototype cells of the said batteries for testirig which were offered to the
appellants for evaluation way back in March 2004 and despite such
offering, the appellants did not carry out any test. Contention of the
respondent is that they continued to invest huge sums for developing
prototype cells of submarine batteries under legitimate expectation that
the respondent would be considered as an alternative source for supplying      c
submarine batteries. Further contention of the respondent is that the
goods purchased without any tender on proprietary basis only from one
source is a flagrant violation of the constitutional mandate of Article 14
and by directing to issue an advertisement, the High Court rightly held
against the monopoly of single source for supply of submarine batteries.
                                                                               D
       8. We have carefully considered the rival contentions advanced
by the parties and perused the details of the procedure for development
of submarine batteries and various tests required to be conducted on the
submarine batteries and other material on record.
      9. The defence procurement can be classified into two broad               E
heads:-
       (i) First category are common use items of generic or commercial
       specifications and these are available in open market. For example
       car batteries, spare of various vehicles etc. These items are
       procured by the Ministry of Defence by Open Tender Enquiry               F
       (OTE) i.e. by advertisements in the press and website.
       (ii) Second category are those materials which do not fall within
       the above 'common use' category. These spares are 'mission
       critical' strategic defence products, which are procured only from
       those firms which are registered with Director General of Quality· G
       Assurance (DGQA) whiql"\ functions under, the Ministry of
       Defence. The supplier has to be registered with DGQA for the
       supply of that specific product.
Defence Ministry/DGQA has a very stringent procedure before any
vendor is registered with DGQA for supplying the product. In the second
                                                                               H
582             SUPREME COURT REPORTS                           [2016] l S.C.R.


A     category, though the product is manufactured by a private supplier, it is
      not as if the Government is totally disassociated from the production
      process of the product. As is seen from the Standing Orders of the
      DGQA ( Annexure P-1 ), prior to grant ofregistration, the Government
      pays the vendor to 'develop' the product under its supervision for over a
      period of time. Officials of the DGQA are posted at the factory of the
B
      supplier to ensure that the goods so produced are absolutely in order.
      The inspectors of DGQA inspect every stage of production right from
      the sourcing of the raw materials by the vendor as it is quite possible that
      the vendor may purchase inferior quality material which may be difficult
      to detect in the final product. Development of the second source would
c     require upto a maximum of three years, as the development process
      involves drawing up of detailed technical specifications and performance
      criteria based on which the firm has to prepare a detailed design for
      each and every component to meet the stringent military standards.
              I 0. The subject-matter of the present case is submarine batteries.
D     The importance of submarine batteries to a submarine cannot be
      underestimated as it is strategically a vital equipment for submarines.
      Submarines or diesel electrical vessels run on battery power. Power to
      the submarine is provided by about 240 to 528 batteries, weighing about
      800 kgs each, depending on the nature of submarine. The only source
      of power to a submarine when it dives beyond nine metres into sea/
 E    ocean is submarine batteries. Improvement in battery technology and
      capacity is always an important goal in submarine design. Batteries are
      unique source of electric energy in underwater navigation. When a
      submarine is under surface, all its equipments are powered from the
      batteries, electric machines, lights, internal communication etc. \Vhich
 F    means that right from the first stage, the submarine batteries are vital
      for operating submarine. Survival of submarine depends on its radio
      noise levels which are directly related to the efficient functioning of
      on board equipment and machinery especially when the batteries which
      is the only source of power and energy. If the batteries fail, submarine
      will be without power and it can have catastrophic consequences on
 G    men as also submarine would be lost. DGQA therefore ensures that it is
       associated during the production of the batteries by the arpro\ed vendor
       a11d u11:: tlwsc batteries which pass the thirteen tests are purchased by
      the l\3,\ Ill c"sc of submarine batteries, before a particular \ender is
       :tppr"' J ··''supply of submarine batteries, as per the policy, first the
 H    ~·" crnmcnt issues development indent to the lowest bidder and the
   UNION OF !NOIA v. HBL NIFE POWER SYSTEMS LTD.                                 583
                 [R. BANUMATHI, J.]

Government pays the proposed vendor to develop the product and the               A
product is developed by the vendor under the supervision of the DGQA
officials. Product so developed under the supervision of DGQA has to
undergo thirteen tests as stipulated in Annexure P-2. Ministry of Defence/
Navy authorities cannot accept the final product without being fully
associated with the development of the product right from the stage of
                                                                                 B
procurement of raw material to the stage of final product. As per the
policy, RFP could be issued only to a firm which is duly registered with
DGQA for supply of the product after development of the product under
the aegis of DGQA. Having regard to the requirements of a highly
critical spare part like submarine batteries, the Government has framed
the policy for issuance of the development indent, developing the source         c
and registration with DGQA. lt is pertinent to note that in the writ petition,
policy itself was not under challenge. In fact, in the writ petition,
respondent-company itself prayed only for issuance' of request for
proposal under the policy. The High Court did not keep in view the
policy of the Government and the mandatory requirement of DGQA
                                                                                 D
being associated with the development of submarine batteries which is a
critical defence spare part.
       11. Ifthe country wishes to play a substantial role in the Indian
Ocean and Arabian Sea, India must ensure high standards of defence
power comparing. with the neighbouring countries and it should have
modernized submarines. Modernized submarines require submarine                    E
batteries with high sophisticated standard under the aegis of DGQA.
The Government cannot put the life of its defence personnel and
submarine worth crores of rupees to risk simply because the respondent
claims to have the capability and can supply submarine batteries. For
such defence critical spare parts like submarine batteries, there cannot          F
be any open advertisement inviting tenders. Advertisements are issued
calling for tenders only for common use items which are normally available
in the open market with a wide range of sources. Submarine batteries
do not fall under this category of common use items. The respondent
cannot claim any vested right to be issued a development indent or RFP
or a supply order simply because it has made investments to manufacture           G
submarine batteries. Straightway RFP cannot be issued to the respondent
by ignoring the procedure for issuing a development indent and testing
the batteries.
      12. As the matter was pending for over a decade, we have asked
the appellant-Union of India about the subsequent development of the              H
584             SUPREME COURT REPORTS                           (2016] l S.C.R.


A     second source for supply of submarine batteries and for the status of the
      respondent. In response, on instruction Mr. S.W.A. Qadri, onbehalf of
      the appellant has filed elaborate written submission. It is stated that
      after grant of stay order dated 16.12.2005 by this Court against the
      impugned order, the appellant initiated a case for development of an
      alternate vendor for submarine batteries seeking development indents
B
      from !HQ (N)/DEE as per directives of Ministry of Defence vide ID
      No.3536/04/D(N-I) dated 08.02.2005. Accordingly, open tender was
      issued in newspapers on 29.05.2006 wherein several firms including the
      respondent responded. For development of a second source of Type-I
      batteries, development order was placed on the respondent HBL Ltd.
c     on 22.03.2007, as per which the firm was to develop four Type-I cells at
      a cost ofRs.11.16 lakhs with a delivery schedule of eighteen months.
      The prototype batteries manufactured by respondent-HBL failed to meet
      DGQA's stipulated standard for relevant discharge (C2) test. Thereafter,
      on 12.07.2011, a meeting was held with the participants of DEE and M/
      s. HBL representatives. Post detailed deliberation, the respondent was
D
      asked to manufacture four cells afresh and present them for type testing.
      Test of batteries was completed at the factory premises in June 2012
      and batteries were transferred to BCF, Sewri in January 2013. However,
      on receipt at BCF, Sewri, visible bulging was observed in all batteries
      and lead tape discontinuity in one battery during first maintenance charge.
 E    During analysis in February 2013, bulging was found to exceed permissible
      limit of 12 mm on all batteries post first full charge. However, respondent
      opined that the bulging was due to improper packaging whilst transporting
      batteries from the premises (Hyderabad) to Mumbai. Thereafter,
      respondent firm-HBL agreed on certain conditions for manufacturing
      of four new prototype cells with a lead time of three-six months and
 F
      agreed to complete manufacturing of test cells by February 2014.
      However, there was delay on the part of the respondent and finally the
      trial oftest cells was completed on 14.11.2014 and the trials were validated
      by CQAE, Secunderabad. Test cells were received at BCF, Sewri in
      January 2015. Charging/discharging trials commenced wherein charging
 G    parameters were examined and found to be satisfactory. In this regard,
       in the written submission filed by UOI, it is stated as under:-
             "8 .... The performance report forwarded by ASD (Mbi)/BCF
             wherein all parameters of the cells were examined, indicates
             satisfactory test results. In view of the satisfactory completion of
H            indigenization efforts by respondent herein (M/s. HBL, Hyderabad)
        UNION OF INDIA v. HBL NIFE POWER SYSTEMS LTD.                             585
                      [R. BANUMATHI, J.]

           the firm was nominated as IHQ MOD (N) approved vendor for              A
           supply of Type-I submarine batteries for EKM submarines on
           28.05.20I5
           9 ... the next procurement case shall have an additional qualified
           vendor for Type-I submarine batteries to increase the market
           competence for both technical and financial aspects."                  B
    Though the subsequent developments may not be relevant to determine
    the issue, we have referred to the written submission in extenso for the
    sake of ~ompletion.                                               ·
           13. The aforesaid discussion and also the written submission as
    to how the respondent developed the batteries over a period of time           c
    reiterate that the development of second source could only be as per the
    guidelines of DGQA and under the supervision and inspection of the
    officials of the DGQA and not independently. The High Court did not
    keep in view the policy of the Government in purchasing the critical
    spare parts for the defence and in particular, in developing submarine        D
    batteries under the aegis of the Defence Ministry and the High Court
    erred in directing the appellants to issue an advertisement giving details
    about the technical specifications for submarine batteries and in selecting
    the product.submitted in response to the advertisement and the impugned
    order is not sustainable.
                                                                                  E
           14. The impugned order of the High Court is set aside and this
    appeal is allowed. In the facts and circumstances of the case, we make
    no .order as to costs .
    .Kalpana K. Tripathy                                        Appeal allowed.

                                                                                  F
(




                                                                     •


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "defence procurement"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.