WORLD SPORT GROUP (MAURITIUS) LTD.versusMSM SATELLITE (SINGAPORE) PTE. LTD.
- Citation
- 2014 INSC 50
- Decided
- 24 January 2014
- Disposal
- Appeal(s) allowed
- Bench
- A K PATNAIK
Holding
A court must refer the parties to arbitration under Section 45 unless the arbitration agreement itself is null and void, inoperative or incapable of being performed; fraud in the main contract does not affect the separable arbitration clause, so the injunction restraining the foreign arbitration was unlawful.
Summary
The dispute arose from a Facilitation Deed containing an arbitration clause (Clause 9) that required disputes to be referred to ICC arbitration in Singapore. The respondent rescinded the deed alleging fraud and sought a temporary injunction restraining the arbitration. The Bombay High Court granted the injunction, holding the arbitration clause void as contrary to public policy under Sections 23 and 28 of the Indian Contract Act and as inoperative due to fraud. The Supreme Court held that under Section 45 of the Arbitration and Conciliation Act, 1996 a court must refer parties to arbitration unless the arbitration agreement itself is null and void, inoperative or incapable of being performed; allegations of fraud in the main contract do not render the arbitration clause inoperative. Applying the principle of separability, the arbitration agreement was deemed independent of the main contract and not void. Consequently, the High Court’s injunction was erroneous, the appeal was allowed, and the order of the Single Judge restoring arbitration was reinstated.
Issues considered
- The Bombay High Court's jurisdiction to restrain a foreign‑seated arbitration under the principle of comity of courts
- Whether Section 45 of the Arbitration and Conciliation Act, 1996 obliges a court to refer parties to arbitration unless the arbitration agreement is null and void, inoperative or incapable of being performed
- Whether allegations of fraud or misrepresentation in the main contract make the arbitration agreement inoperative or incapable of being performed
- The validity of Clause 9 of the Facilitation Deed under Sections 23 and 28 of the Indian Contract Act, 1872 (public policy and restraint of legal proceedings)
- The applicability of the principle of separability to the arbitration clause
- Whether the existence of a parallel suit bars the court from referring the matter to arbitration
Legislation cited
- Arbitration and Conciliation Act, 1996s. 44, s. 45
- Code of Civil Procedure, 1908s. 20, s. 9
- Indian Contract Act, 1872s. 23, s. 28
Subjects
Judgment
[2014) 1 S.C.R. 796
A WORLD SPORT GROUP (MAURITIUS) LTD.
v.
MSM SATELLITE (SINGAPORE) PTE. LTD.
(Civil Appeal No. 895 of 2014)
JANUARY 24, 2014
8
[A.K. PATNAIK AND FAKKIR MOHAMED
IBRAHIM KALIFULLA, JJ.]
Arbitration and Conciliation Act, 1996:
c ss.44 and 45 - Foreign seated arbitration - Jurisdiction
of High Court to pass an order of injunction restraining a
foreign seated international arbitration at Singapore between
the parties - Plea of respondent that the main agreement
D which contains the arbitration agreement is void because of
fraud and misrepresentation by the appellant and therefore
court cannot refer the parties to arbitration - Held: s.45 of the
Act postulates that even where request of arbitration is made
by a party, it will not refer the parties to arbitration, if it finds
that the agreement is null and void, inoperative or incapable
E of being performed - The words "inoperative or incapable of
being performed" in s.45 have been taken from Article II (3)
of the New York Convention - Jn the case of such arbitrations
covered by the New York Convention, the Court can decline
to make a reference of a dispute covered by the arbitration
F agreement only if it comes to conclusion that the arbitration
agreement is null and void, inoperative or incapable of being
performed, and not on the ground that allegations of fraud or
misrepresentation have to be inquired into while deciding the
disputes between the parties - In the instant case, the
G allegation of fraudulent misrepresentation in the main
agreement did not impact the validity of the arbitration
agreement which was separable from the rest of the contract
- Therefore, applying principle of separability parties were
wrongly refused to refer arbitration on the ground that
H 796
WORLD SPORT GROUP (MAURITIUS) LTD. v. MSM 797
SATELLITE (SINGAPORE) PTE. LTD.
arbitration agreement was also void along with main A
agreement - Principle of separability.
Arbitration restricting the right of the parties to move the
courts for appropriate relief and also barring the right to trial
by a jury - Whether void for being opposed to public policy 8
as provided in s.23 of the Indian Contract Act, 1872 and void
for being an agreement in restraint of the legal proceedings
in view of s.28 of the said Act - Held: Parliament has made
the Arbitration and Conciliation Act, 1996 providing domestic
arbitration and international arbitration as a mode of resolution C
of disputes between the parties and Exception 1 to s. 28 of the
Contract Act, 1872 clearly states that s.28 shall not render
illegal a contract, by which two or more persons agree that any
dispute which may arise between them in respect of any
subject or class of subjects shall be referred to arbitration and
that only the amount awarded in such arbitration shall be D
recoverable in respect of the dispute so referred - The right
to jury trial is not available Under Indian laws - In the instant
case, the finding of the Division Bench of the High Court that
arbitration clause of the Facilitation Deed is opposed to public
policy and is void u/ss.23 and 28 of the Contract Act, 1872 is E
clearly erroneous - Contract Act, 1872 - ss.23, 28.
Doctrines/Principles: Principle of Comity of Courts -
Applicability of - Plea of appellant that. on principle of comity
of courts, the Bombay High Court should have refused to F
interfere in the matter and should have allowed the parties to
resolve their dispute through ICC arbitration subject to the
jurisdiction of the Singapore Courts in accordance with the
arbitration clause of the Facilitation Deed - Held: Not
applicable in the instant case, no decision of a court of foreign G
country or no law of a foreign country was cited on behalf of
the appellant to contend that the courts in India out of
deference to such decision of the foreign court or foreign Jaw
mu'st not assume jurisdiction to restrain arbitration
proceedings at Singapore - On the other hand, uls. 9 of the H
798 SUPREME COURT REPORTS [2014] 1 S.C.R.
A CPC, the courts in India have jurisdiction to try all suits of a
civil nature excepting suits of which cognizance is either
expressly or impliedly barred - Thus, the appropriate civil
court in India has jurisdiction to entertain the suit and pass
appropriate orders in the suit by virtue of s.9 of the CPC -
B Code of Civil Procedure, 1908 - s. 9.
The BCCI invited tenders for IPL Media Rights on a
worldwide basis. Amongst the tenders submitted, the bid
of WSG (India) was accepted by BCCI. By a pre-bid
arrangement, however, the respondent was to get the
C media rights for the sub-continent for the period from
2008 to 2010. On 21.01.2008, the BCCI and the
respondent entered into a Media rights Licence
Agreement for the period from 2008 to 2010. After the first
IPL season, the BCCI terminated the agreement dated
D 21.01.2008 and entered into a new agreement with the
WSG (India).
Pursuant to the negotiations between BCCI and WSG
(India), the BCCI entered into an agreement with the
E appellant whereunder the media rights for the Indian sub-
continent was awarded to the appellant. To operate the
media r~hts in India, the appellant was required to get a
sub-licensee which it could not get within stipulated time.
Thereafter, the appellant claimed to have allowed media
F rights in India to have lapsed and then facilitated on
25.03.2009, a new Media Rights License Agreement
between the BCCI and the respondent for the Indian sub-
continent for the same contract value of Rs.4, 791.08
crores. BCCI and WSG India, however, continued with
G the Rest of the World media rights.
Thereafter the appellant entered into an agreement
with the respondent called the Facilitation Deed
whereunder the respondent was to pay a sum of Rs.425
crores to the appellant as Facilitation fees. The
H respondent made three payments totaling Rs.125 crores
WORLD SPORT GROUP (MAURITIUS) LTD. v. MSM 799
SATELLITE (SINGAPORE) PTE. LTD.
to the appellant under the Facilitation Deed during 2009 A
but did not make the balance payment. Instead, on
25.06.2010, the respondent wrote to the appellant
rescinding the Facilitation Deed on the ground that it was
voidable on account of misrepresentation and fraud. The
respondent also filed suit for a declaration that the B
Facilitation Deed was void and for recovery of Rs.125
crores already paid to the appellant.
On 28.6.2010, the appellant acting under Clause 9 of
the Facilitation Deed sent a request for arbitration to ICC C
Singapore and ICC issued a notice to the respondent to
file its answer for arbitration.
On 30.06.2010, the respondent filed a second suit
before the High Court against the appellant for a
declaration that as the Facilitation Deed stood rescinded, D
the appellant was not entitled to invoke the arbitration
clause in the Facilitation Deed. The respondent also filed
an application for temporary injunction against the
appellant from continuing with the arbitration
proceedings commenced by the appellant under the E
aegis of ICC.
The Single Judge of the High Court dismissed the
application for temporary injunction of the respondent
saying that it would be for the arbitrator to consider F
whether the Facilitation Deed was void on account of
fraud and misrepresentation and that the arbitration
must, there'fore, proceed and the Court could not
intervene in matters governed by the arbitration clause.
The Division Bench of the High Court allowed the appeal
and passed an order of temporary injunction restraining G
the arbitration by ICC. Aggrieved, the appellant filed the
instant appeal.
Allowing the appeal, the Court
H
800 SUPREME COURT REPORTS [2014] 1 S.C.R.
A HELD: 1. The first plea of the appellant is not
. accepted that as Clause 9 of the Facilitation Deed
provides that any party may seek equitable relief in a
court of competent jurisdiction in Singapore, or such
other court that may have jurisdiction over the parties and
B that the Bombay High Court had no jurisdiction to
entertain the suit and restrain the arbitration proceedings
at Singapore because of the principle of Comity of
Courts. What is meant by the principle of "comity" is that
courts of one state or jurisdiction will give effect to the
c laws and judicial decisions of another state or
jurisdiction, not as a matter of obligation but out of
deference and mutual respect. In the instant case no
decision of a court of foreign country or no law of a
foreign country has been cited on behalf of the appellant
to contend that the courts in India out of deference to
0
such decision of the foreign court or foreign law must not
assume jurisdiction to restrain arbitration proceedings.at
Singapore. On the other hand, it was rightly submitted by
the respondent that under Section 9 of the CPC, the
courts in India have jurisdiction to try all suits of a civil
E nature excepting suits of which cognizance is either
expressly or impliedly barred. Thus, the appropriate civil
court in India has jurisdiction to entertain the suit and
pass appropriate orders in the suit by virtue of Section 9
of the CPC and Clause 9 of the Facilitation Deed providing
F that courts in Singapore or any other court having
jurisdiction over the parties can be approached for
equitable relief could not oust the jurisdiction of the
appropriate civil court conferred by Section 9 of the CPC.
In the plaint In second suit, it was stated that the
G Facilitation Deed in which the arbitration clause is
incorporated came to be executed by the defendant at
Mumbai and the fraudulent inducement on the part of the
defendant resulting in the plaintiff entering into the
Facilitation Deed took place in Mumbai and the
H rescission of the Facilitation Deed on the ground that it
WORLD SPORT GROUP (MAURITIUS) LTD. v. MSM 801
SATELLITE (SINGAPORE) PTE. LTD.
was induced by fraud of defendant has also been issued A
from Mumbai. Thus, the cause of action for filing the suit
arose within the jurisdiction of the Bombay High Court
and the Bombay High Court had territorial jurisdiction to
entertain the suit under Section 20 of the CPC. [Para 20]
[820-B-H; 821-A-D] B
Black's Law Dictionary, 5th Edition - referred to.
1.2. Any civil court in India which entertains a suit,
however, has to follow the mandate of the legislature in
Sections 44 and 45 in Chapter I of Part II of the Arbitration C
and Conciliation Act. As per Section 45 of the Act,
notwithstanding anything contained in Part I or in the
Code of Civil Procedure, a judicial authority, when seized
of an. action in a matter in respect of which the parties
have made an agreement referred to in Section 44, shall, D
at the request of one of the parties or any person claiming
through or under him, refer the parties to arbitration,
unless it finds that the said agreement is null and void,
inoperative or incapable of being performed. Thus, even
if, under Section 9 read with Section 20 of the CPC, the E
Bombay High Court had the jurisdiction to entertain the
suit, once a request is made by one of the parties or any
· person claiming through or under him to refer the parties
to arbitration, the Bombay High Court was obliged to
refer the parties to arbitration unless it found that the F
agreement referred to in Section 44 of the Act was null
and void, inoperative or incapable of being performed. In
the instant case, the appellant may not have made an
application to refer the parties to arbit~tion, but Section
45 of the Act does not refer to any application as such. G
Instead, it refers to the request of one of the parties or
any person claiming through or under him to refer the
parties to arbitration. In this case, the appellant has filed
an affidavit in reply to the notice of motion and has stated
therein that the defendant had already invoked the H
802 SUPREME COURT REPORTS [2014) 1 S.C.R.
A arbitration agreement in the Facilitation Deed and the
arbitration proceedings have commenced and that the
suit was an abuse of the process of court. The appellant
had thus made a request to refer the parties to arbitration
at Singapore which had already commenced. [para 21]
8 [821-E; 822-D-H; 823-A-B]
2. Section 45 of the Act also makes it clear that even
where such request is made by a party, it will not refer
the parties to arbitration, if it finds that the agreement is
null and void, inoperative or incapable of being
C performed. As per Section 45 of the Act the word
"agreement" would mean the agreement referred to in
Section 44 of the Act. Clause (a) of Section 44 of the Act
refers to "an agreement in writing for arbitration to \Vhich
the Convention set forth in the First Schedule applies."
D The First Schedule of the Act sets out the different Articles
of the New York Convention on the Recognition and
Enforcement of Foreign Arbitral Awards, 1958. It will be
clear from clauses 1, 2 and 3 of the New York Convention
as set out in the First Schedule of the Act that the
E agreement referred to in Section 44 of the Act is an
agreement in writing under which the parties undertake
to submit to arbitration all or any differences which have
arisen or which may arise between them. Thus, the court
will decline to refer the parties to arbitration only if it finds
F that the arbitration agreement is null and void, inoperative
or incapable of being performed. [para 22] [823-B-E; 824-
B-C]
3. Applying the principle of separability to the facts
of this case, the respondent rescinded the Facilitation
G Deed on the grounds that the appellant did not have any
right to relinquish and/or to facilitate the procurement of
Indian subcontinent media rights for the IPL from BCCI
and no facilitation services could have been provided by
the appellant and therefore the representation by the
H appellant that the appellant relinquished its Indian
WORLD SPORT GROUP (MAURITIUS) LTD. v. MSM 803
SATELLITE (SINGAPORE) PTE. LTD.
subcontinent media rights for the IPL in favour of the A
respondent for which the appellant had to be paid the
facilitation fee under the deed was false and accordingly
the Facilitation Deed was voidable at the option of the
respondent on account of false representation and fraud.
This ground of challenge to the Facilitation Deed does B
not in any manner affect the arbitration agreement
contained in Clause 9 of the Facilitation Deed, which is
independent of and separate from the main Facilitation
Deed and does not get rescinded as void by the letter
dated 25.06.2010 of the respondent. The Division Bench c
of the Bombay High Court, therefore, could not have
refused to refer the parties to arbitration on the ground
that the arbitration agreement was also void along with
the main agreement. [Para 25] [826-H; 827-A; 828-E-H;
829-A] D
4. The plea of the respondent was that the arbitration
agreement was inoperative or incapable of being
performed as allegations of fraud could be enquired into
by the court and not by the arbitrator. However, the
authorities on the meaning of the words "inoperative or E
incapable of being performed" do not support such plea.
The words "inoperative or incapable of being performed"
in Section 45 of the Act have been taken from Article II
(3) of the New York Convention. Thus, the arbitration
agreement does not become "inoperative or incapable of F
being performed" where allegations of fraud have to be
inquired into and the court cannot refuse to refer the
parties to arbitration as provided in Section 45 of the Act
on the ground that allegations of fraud have been made
by the party which can only be inquired into by the court G
.and not by the arbitrator. In the case of such arbitrations
· covered by the New York Convention, the Court can
decline to make a reference of a dispute covered by the
arbitration agreement only if it comes to the conclusion
that the arbitration agreement is null and void, inoperative H
804 SUPREME COURT REPORTS [2014) 1 S.C.R.
A or incapable of being performed, and not on the ground
that allegations of fraud or misrepresentation have to be
inquired into while deciding the disputes between the
parties. [paras 26, 29) [829-A-C; 831-D-G]
N. Radhakrishnan v. Maestro Engineers & Ors. (2010)
B 1 SCC 72: 2009 (15) SCR 371; Abdul Kadir Shamsuddin
Bubere v. Madhav Prabhakar Oak AIR 1962 SC 406:1962
Suppl. SCR 702 - Distinguished.
Redfern and Hunter on International Arbitration (Fifth
C Edition); Albert Jan Van Den Berg in an article titled "The
New York Convention, 1958 -An Overview" published in
the website of ICCA [www.arbitration-icca.org/medla/O/
12125884227980/new york convention of 1958 overview
.pdf]; 'Recognition and Conferment of Foreign Arbitral
D Awards: A Global Commentary on the New York
Convention' by Kronke, Nacimiento, et al.(ed.) (2010) -
referred to.
5.1. The Division Bench of the High Court has held
E that the Facilitation Deed was part of several agreements
entered into amongst different parties commencing from
25.03.2009 and, therefore, cannot be considered as stand
apart agreement between the appellant ·and the
respondent and so considered the Facilitation Deed as
contrary to public policy of India because it is linked with
F the finances, funds and rights of the BCCI, which is a
public body. This approach of the Division Bench of the
High Court is not in consonance with the provisions of
Section 45 of the Act, which mandates that in the case
of arbitration agreements covered by the New York
G Convention, the Court which is seized of the matter will
refer the parties to arbitration unless the arbitration
agreement is null and void, inoperative or incapable of
being performed. In view of the provisions of Section 45
of the Act, the Division Bench of the High Court was
H required to only consider in this case whether Clause 9
WORLD SPORT GROUP (MAURITIUS) LTD. v. MSM 805
SATELLITE (SINGAPORE) PTE. LTD.
of the Facilitation Deed which contained the arbitration A
agreement was null and void, inoperative or incapable of
being performed. The Division Bench of the High Court
has further held that Clause 9 of the Facilitation Deed
insofar as it restricted the right of the parties to move the
courts for appropriate relief and also barred the right to B
trial by a jury was void for being opposed to public policy
as provided in Section 23 of the Indian Contract Act, 1872
and was also void for being an agreement in restraint of
the legal proceedings in view of Section 28 of the said
Act. Parliament has made the Arbitration and Conciliation c
Act, 1996 providing domestic arbitration and international
arbitration as a mode of resolution of disputes between
the parties and Exception 1 to Section 28 of the Indian
Contract Act, 1872 clearly states that Section 28 shall not
render illegal a contract, by which two or more persons 0
agree that any dispute which may arise between them in
respect of any subject or class of subjects shall be
referred to arbitration and that only the amount awarded
in such arbitration shall be recoverable in respect of the
dispute so referred. Clause 9 of the Facilitation Deed is
consistent with this policy of the legislature as reflected E
in the Arbitration and Conciliation Act, 1996 and is saved
by Exception 1 to Section 28 of the Indian Contract Act,
1872. The right to jury trial is not available under Indian
laws. The finding of the Division Bench of the High Court,
therefore, that Clause 9 of the Facilitation Deed is F
opposed to public policy and is void under Sections 23
and 28 of the Indian Contract Act, 1872 is clearly
erroneous. [Paras 30, 31] [831-H; 832-A-H; 833-A-B]
5.2. The Division Bench of the High Court has also G
held that as allegations of fraud and serious malpractices
on the part of the appellant are in issue, it is only the court
which can decide these issues through furtherance of
judicial evidence by either party and these issues cannot
be properly gone into by the arbitrator. Section 45 of the H
806 SUPREME COURT REPORTS [2014] 1 S.C.R.
A Act does not provide that the court will not refer the
parties to arbitration if the allegations of fraud have to be
inquired into. Section 45 provides that only if the court
finds that the arbitration agreement is null and void,
inoperative or incapable of being performed, it will
B decline to refer the parties to arbitration. The Division
Bench of the High court has further held that since the
earlier suit was pending in court since 25.06.2010 and
that suit was inter-connected and inter-related with the
second suit, the court could not allow splitting of the
C matters and disputes to be decided by the court in India
in the first suit and by arbitration abroad in regard to the
second suit and invite conflicting verdicts on the issues
which are inter-related. This reasoning adopted by the
Division Bench of the Bombay High Court in the
impugned judgment is alien to the provisions of Section
0 45 of the Act which does not empower the court to
decline a reference to arbitration on the ground that
another suit on the same issue is pending in the Indian
court. Hence, it has been rightly held by the Single Judge
of the Bombay High Court that it is for the arbitrator to
E decide this dispute in accordance with the arbitration
agreement. [Paras 32, 33, 34] [833-B-G; 834-D]
Chloro Controls India Private Limited v. Seven Trent
Water Purification Inc. & Ors. (2013) 1 SCC 641; National
F Insurance Co. Ltd. v. Boghara Polyfab Pvt. Ltd. (2009) 1 SCC
267: 2008 (13) SCR 638; Reva Electric Car Company Private
Ltd. v. Green Mobil (2012) 2 SCC 9: 2011 (13) SCR 359;
Branch Manager, Magma Leasing and Finance Ltd. & Anr.
v. Potluri Madhavilata & Anr. (2009) 10 SCC 103: 2009 (14)
G SCR 815; V. 0. Tractoroexport, Moscow v. Tarapore &
Company and Anr. (1969) 3 SCC 562:1970 (3) SCR 53; Oil
and Natural Gas Commission v. Western Company of North
America (1987) 1 SCC 496: 1987 (1) SCR 1024; SMS Tea
Estates (P) Ltd. v. Chandmari Tea Co. (P) Ltd. (2011) 14 SCC
H 66: 2011 (9) SCR 382; Haryana Telecom Ltd. v. Sterlite
WORLD SPORT GROUP (MAURITIUS) LTD. v. MSM 807.
SATELLITE (SINGAPORE) PTE. l TD.
Industries (India) Ltd. (1999) 5 SCC 688: 1999 (3) SCR 861; A
Mis Zee Tele Films Ltd. & Anr. v. Union of India & Ors. AIR
2005 SC 2677:2005 (1) SCR 913; Booz Allen·& Hamilton v.
SB/ Home Finance (2011) 5 SCC 532: 2011 (7) SCR 310;
India Household and Healthcare Ltd. v. LG Household and
Healthcare Ltd. (2007) 5 SCC 510: 2007 (3) SCR 726 - B
referred to.
Premium Nafta Products Ltd. v. Fili Shipping Company
Ltd. & Ors. 2007 UKHL 40; United States in Buckeye Check
Cashing, Inc. v. John Cardegna et al 546 US 440 (2006); C
Russel on Arbitration, para 7 -056, 7 -058, and Claxton
Engineering v. Txm olaj - es gaz Kutao Ktf [2011] EWHC 345
(COMM.) - referred to.
Redfern An<:J Hunter On International Arbitration (Fifth
Edition page 134 para 2.141) - referred to. D
Case Law Reference:
(2013) 1 sec 641 Referred to Para 8
2008 (13) SCR 638 Referred to Para 9
E
2011 (13) SCR 359 Referred to Para 9
2007 UKHL 40 Referred to Para 9
546 us 440 (2006) Referred to Para 9
F
2009 (15) SCR 371 Distinguished Para 10
1962 Suppl. SCR 702 Distinguished Para 10
1970 (3) SCR 53 Referred to Para 15
1987 (1) SCR 1024 Referred to Para 15 G
2011 (9) SCR 382 Referred to Para 16
1999 (3) SCR 861 Referred to Para 17
H
808 SUPREME COURT REPORTS [2014] 1 S.C.R.
A 2005 (1) SCR 913 Referred to Para 18
2011 (7) SCR 310 Referred to Para 18
2007 (3) SCR 726 Referred to Para 18
B CIVIL APPELLATE JURISDICTION: Civil Appeal No. 895
of 2014.
From the Judgment and Order dated 17.09.2010 of the
High Court of Judicature at Bombay in Appeal (L) No. 534 of
2010 in Notice of Motion No. 1809 of 2010 in Suit No. 1828 of
c 2010.
K.K. Venugopal, V.K. Misra, Pojat T., line A., Swapnil
Jain, Madhav Misra, Devendra Singh for the Appellant.
Gopal Subramonium, Devansh Mohta, Vijay K. Sondhi,
D Sanjay Kumar, Ashish Prasad, Soham Kumar, Samir Ali Khan,
Mayank Grover for the Respondent.
The Judgment of the Court was delivered by
E A.K. PATNAIK, J. 1. Leave granted.
2. This is an appeal against the order dated 17.09.2010
of the Division Bench of the Bombay High Court in Appeal
(Lodging) No.534 of 2010.
F Facts:
3. The facts very briefly are that on 30.11.2007 the Board
of Control for Cricket in India (for short 'BCCI') invited tenders
for IPL (Indian Premier League) Media Rights for a period of
G ten years from 2008 to 2017 on a worldwide basis. Amongst
the tenders submitted, the bid of World Sports Group India (for
short 'WSG India') was accepted by BCCI. By a pre-bid
arrangement, however, the respondent was to get the media
rights for the sub-continent for the period from 2008 to 2010.
H Accordingly, on 21.01.2008 BCCI and the respondent entered
WORLD SPORT GROUP (MAURITIUS) LTD. v. MSM 809
SATELLITE (SINGAPORE) PTE. LTD. [A.K. PATNAIK, J.]
into a Media Rights License Agreement for the period from A
2008 to 2012 for a sum of US$274.50 million. After the first
IPL season, the BCCI terminated the agreement dated
21.01.2008 between BCCI and the respondent for the Indian
sub-continent and commenced negotiations with WSG India.
On 14.03.2009, the respondent filed a petition under Section B
9 of the Arbitration and Conciliation Act, 1996 (for short 'the
Act') against the BCCI before the Bombay High Court praying
for injunction against the BCCI from acting on the termination
letter dated 14.03.2009 and for preventing BCCI from granting
the rights under the agreement dated 21.01.2008 to any third c
party. Pursuant to the negotiations between BCCI and WSG
India, BCCI entered into an agreement with the appellant
whereunder the media rights for the Indian sub-continent for the
period 2009 to 2017 was awarded to the appellant for a value
of Rs.4, 791.08 crores. To operate the media rights in India, the D
appellant was required to seek a sub-licensee within seventy
two hours. Though, this time period was extended twice, the
appellant was not able to get a sub-licensee. Thereafter, the
appellant claimed to have allowed media rights in India to have
lapsed and then facilitated on 25.03.2009, a new Media Rights E
License Agreement between the BCCI and the respondent for
the Indian sub-continent for the same contract value of
Rs.4,791.08 crores. BCCI and WSG India, however, were to
continue with the Rest of the World media rights.
4. On 25.03.2009, the appellant and the respondent also F
executed the Deed for Provision of Facilitation Services
(hereinafter referred to as 'the Facilitation Deed') whereunder
the respondent was to pay a sum of Rs.425 crores to the
appellant as facilitation fees. Clause 9 of the Facilitation Deed
dated 25.03.2009 between the appellant and the respondent G
was titled 'Governing Law' and read as follows:
"9. GOVERNING LAW
This Deed shall be governed by and construed in
accordance with the laws of England and Wales, without H
810 SUPREME COURT REPORTS 120141 1 s.c.R.
A regard to choice of law principles. All actions or
proceedings arising in connection with, touching upon or
relating to this Deed, the breach thereof and/or the scope
of the provisions of this Section shall be submitted to the
International Chamber of Commerce (the "Chamber") for
B final and binding arbitration under its Rules of Arbitration,
to be held in Singapore, in the English language before a
single arbitrator who shall be a retired judge with at least
ten years of commercial experience. The arbitrator shall
be selected by mutual agreement of the Parties, or, if the
c Parties cannot agree, -then by striking from a list of
arbitrators supplied by the Chamber. If the Parties are
unable to agree on the arbitrator, the Chamber shall
choose one for them. The arbitration shall be a confidential
proceeding, closed to the general public. The arbitrator
shall assess the cost of the arbitration against the losing
D
party. In addition, the prevailing party in any arbitration or
legal proceeding relating to this Deed shall be entitled to
all reasonable expenses (including, without limitation,
reasonable attorney's fees). Notwithstanding the foregoing,
the arbitrator may require that such fees be borne in such
E other manner as the arbitrator determines is required in
order for this arbitration provision to be enforceable under
applicable law. The arbitrator shall issue a written opinion
stating the essential findings and conclusions upon which
the arbitrator's award is based. The arbitrator shall have
F the power to entsr temporary restraining orders and
preliminary and permanent injunctions. No party shall be
entitled or permitted to commence or maintain any action
in a court of law with respect to any matter in dispute until
such matter shall have been submitted to arbitration as
G herein provided and then only for the enforcement of the
arbitrator's award; provided, however, that prior to the
appointment of the arbitrator or for remedies beyond the
jurisdiction of an arbitrator, at any time, any party may seek
equitable relief in a court of competent jurisdiction in
H Singapore, or such other court that may have jurisdiction
WORLD SPORT GROUP (MAURITIUS) LTD. v. MSM 811
SATELLITE (SINGAPORE) PTE. LTD. [A.K. PATNAIK, J.]
over the Parties, without thereby waiving its right to A
arbitration of the dispute or controversy under this section.
THE PARTIES HEREBY WAIVE THEIR RIGHT TO JURY
TRIAL WITH RESPECT TO ALL CLAIMS AND ISSUES
ARISING UNDER, IN CONNECTION WITH, TOUCHING
UPON OR RELATING TO THIS DEED, THE BREACH B
THEREOF AND/OR THE SCOPE OF THE PROVISIONS
OF THIS SECTION, WHETHER SOUNDING IN
CONTRACT OR TORT, AND INCLUDING ANY CLAIM
FOR FRAUDULENT INDUCEMENT THEREOF."
5. The respondent made three payments totaling Rs.125 C
crores to the appellant under the Facilitation Deed during 2009
and did not make the balance payment. Instead, on 25.06.2010,
the respondent wrote to the appellant rescinding the Facilitation
Deed on the ground that it was voidable on account of
misrepresentation and fraud. On 25.06.2010, the respondent D
also filed Suit No.1869 of 2010 for inter alia a declaration that
the Facilitation Deed was void and for recovery of Rs.125
crores already paid to the appellant. On 28.06.2010, the
appellant acting under Clause 9 of the Facilitation Deed sent
'ii request for arbitration to ICC Singapore and the ICC issued E
a riotice to the respondent to file its answer to the requestfor
arbitration. In the meanwhile, on 30.06.2010, the respondent
filed a second suit, Suit No.1828 of 2010, before the Bombay
High Court against the appellant for inter alia a declaration that
as the Facilitation Deed stood rescinded, the appellant was not F
entitled to invoke the arbitration clause in tbe Facilitation Deed.
The respondent also filed an application for temporary injunction
against the appellant from continuing with the arbitration
proceedings commenced by the appellant under the aegis of
ICC. G
6. On 09.08.2010, the learned Single Judge of the
Bombay High Court dismissed the application for temporary
injunction of the respondent saying that it would be for the
arbitrator to consider whether the Facilitation Deed was void
H
812 SUPREME COURT REPORTS [2014) 1 S.C.R.
A on account of fraud and misrepresentation and that the
arbitration must, therefore, proceed and the Court could not
intervene in matters governed by the arbitration clause. The
respondent challenged the order of the learned Single Judge
before the Division Bench of the Bombay High Court and by
B the impugned order, the Division Bench of the Bombay High
Court allowed the appeal, set aside the order of the learned
Single Judge and passed an order of temporary injunction
restraining the arbitration by ICC. Aggrieved, the appellant has
filed this appeal.
C Contentions on behalf of the appellant:
7. Mr. K.K. Venugopal, learned senior counsel for the
appellant, submitted that the Division Bench of the High Court
failed to appreciate that the Bombay High Court had no
D jurisdiction to pass an order of injunction restraining a foreign
seated international arbitration at Singapore between the
parties, who were not residents of India. In this context, he
referred to Clause 9 of the Facilitation Deed which stipulated
that any party may seek equitable relief in a court of competent
E jurisdiction in Singapore, or such other court that may have
jurisdiction over the parties. He submitted that on the principle
of Comity of Courts, the Bombay High Court should have
refused to interfere in the matter and should have allowed the
parties to resolve their dispute through ICC arbitration, subject
F to the jurisdiction of the Singapore courts in accordance with
Clause 9 of the Facilitation Deed.
8. Mr. Venugopal next submitted that the Division Bench
of the High Court failed to appreciate that under Section 45 of
the Act, the Court seized of an action in a matter in respect of
G which the parties have made an agreement referred to in
Section 44 has to refer the parties to arbitration, unless it finds
that the agreement referred to in Section 44 is null and void,
inoperative or incapable of being performed. He submitted that
the agreement referred to in Section 44 of the Act is 'an
H agreement in writing for arbitration' and, therefore, unless the
WORLD SPORT GROUP (MAURITIUS) LTD. v. MSM 813
SATELLITE (SINGAPORE) PTE. LTD. [A.K. PATNAIK, J.)
Court finds that the agreement in writing for arbitration is null A
and void, inoperative or incapable of being performed, the Court
will not entertain a dispute covered by the arbitration agreement
and refer the parties to the arbitration. In support of this
submission, he relied on the decision of this Court in Chloro
Controls India Private Limited v. Seven Trent Water B
Purification Inc. & Ors. [(2013) 1 SCC 641].
9. Mr. Venugopal submitted that the Division Bench of the
High Court, instead of examining whether the agreement in
writing for arbitration was null and void, inoperative or C
incapable of being performed, has held that the entire
Facilitation Deed was vitiated by fraud and misrepresentation
and was, therefore, void. He vehemently submitted that it was
for the arbitrator to decide whether the Facilitation Deed was
void on account of fraud and misrepresentation as has been
rightly held by the learned Single Judge and it was not for the D
Court to pronounce on whether the Facilitation Deed was void
. on account of fraud and misrepresentation. He referred to
Article 6(4) of the ICC Rules of Arbitration which permits the
Arbitral Tribunal to continue to exercise jurisdiction and
adjudicate the claims even if the main contract is alleged to be E
null and void or non-existent because the arbitration clause is
an independent and distinct agreement. He submitted that this
principle of Kompetenz Kompetenz has been recognized in
Section 16 of the Act under which the Arbitral Tribunal has the
competence to rule on its own jurisdiction and on this point F
relied on National Insurance Co. Ltd. v. Boghara Polyfab Pvt.
Ltd. [(2009) 1 SCC 267] and Reva Electric Car Company
Private Ltd. v. Green Mobil [(2012) 2 SCC 93]. He submitted
that as a corollary to this principle, Courts have also held that
unless the arbitration clause itself, apart from the underlying G
contract, is assailed as vitiated by fraud or misrepresentation,
the Arbitral Tribunal will have jurisdiction to decide all issues
including the validity and scope of the arbitration agreement.
He submitted that in the present case, the arbitration clause
itself was not ass.ailed as vitiated by fraud or misrepresentation. H
814 SUPREME COURT REPORTS [2014] 1 S.C.R.
A In support of this argument, he relied on the decision of the
House of Lords in Premium Nafta Products Ltd. v. Fili
Shipping Company Ltd. & Ors. [2007] UKHL 40], the decision
of the Supreme Court of United States in Buckeye Check
Cashing, Inc. v. John Cardegna et al [546 US 440 (2006)] and
B the decision of this Court in Branch Manager, Magma Leasing
and Finance Ltd. & Anr. v. Potluri Madhavilata & Anr. [(2009)
10 sec 103].
10. Mr. Venugopal submitted that the Division Bench of the
C High Court relied on the decision in N. Radhakrishnan v.
Maestro Engineers & Ors. [(2010) 1 SCC 72] to hold that
serious allegations of fraud can only be enquired by a Court
and not by an arbitrator, but the Division Bench failed to
appreciate that in N. Radhakrishnan v. Maestro Engineers &
Ors. (supra) this Court relied on Abdul Kadir Shamsuddin
D Bubere v. Madhav Prabhakar Oak [AIR 1962 SC 406] in which
it was observed that it is only a party against whom a fraud is
alleged who can request the Court to inquire into the allegations
of fraud instead of allowing the arbitrator to decide on the
allegations of fraud. In the present case, the respondent has
E alleged fraud against the appellant and thus it was for the
appellant to make a request to the Court to decide on the
allegations of fraud instead of referring the same to the
arbitrator, and no such request has been made by the appellant.
He further submitted that in any case the judgment of this Court
F in N. Radhakrishnan v. Maestro Engineers & Ors. (supra) was
rendered in the context of domestic arbitration in reference to
the provisions of Section 8 of the Act. He submitted that the
language of Section 45 of the Act, which applies to an
international arbitration, is substantially different from the
G language of Section 8 of the Act and it will be clear from the
language of Section 45 of the Act that unless the arbitration
agreement is null and void, inoperative or incapable of being
performed, the parties will have to be referred to arbitration by
the Court. In the present case, the respondent has not made
H
WORLD SPORT GROUP (MAURITIUS) LTD. v. MSM 815
SATELLITE (SINGAPORE) PTE. LTD. [A.K. PATNAIK, J.J_
out that the arbitration agreement is null and void, inoperative A
or incapable of being performed.
11. Mr. Venugopal submitted that the High Court has
taken a view that Clause 9 forecloses an open trial in a court
of law except to the extent permitted therein and the parties
8
have to necessarily submit themselves to a confidential
proceeding which is closed to the general public. He submitted
that the Bombay High Court thus appears to have held that
Clause 9 is opposed to public policy and, in particular, Sections
23 and 28 of the Indian Contract Act, 1872. He submitted that
in any case the arbitration agreement contained in Clause 9 C
of the Facilitation Deed cannot be held to be opposed to public
policy and void under Sections 23 and 28 of the Indian Contract
Act, 1872. This will be clear from Exception 1 of Section 28 of
the Indian Contract Act, 1872, which says that the section shall
not render illegal a contract, by which two or more persons D
agree that any dispute which may arise between them in
respect of any subject or class of subjects shall be referred to
arbitration and that only the amount awarded in such arbitration
shall be recoverable in respect of the dispute so referred. He
explained that under the American Law, in a suit for common E
law where the value of claim is more than US$20, the right to
jury trial is preserved and this applies even in relation to claims
for breach of contract and for this reason, the parties made a
provision in Clause 9 of the Facilitation Deed waiving their right
to jury trial with respect to all claims and issues arising under, F
in connection with, touching upon or relating to the Facilitation
Deed. He submitted that this provision in Clause 9 of the
Facilitation Deed cannot, therefore, be held to be opposed to
public policy.
G
12. Mr. Venugopal next submitted that the crux of the case
of the respondent is set out in its letter dated 25.06.2010 to
the appellant in which it was alleged that 'in view of the false
misrepresentations and fraud played by WSGM the deed is
~oidable at the option of our client and thus our client rescinds
H
816 SUPREME COURT REPORTS [2014] 1 S.C.R.
A the deed with immediate effect'. In other words, the
respondent's case is that it was induced to enter into the
Facilitation Deed on account of the misrepresentation by the
appellant and was led to believe that it was paying the
facilitation fees to the appellant to allow the rights of the
B appellant under an alleged agreement dated 23.03.2009 to
lapse, but the respondent subsequently discovered that there
was no agreement dated 23.03.2009 and the rights of the
appellant had come to an end on 24.03.2009. He submitted
that the appellant has denied these allegations of the
c respondent in its affidavit-in-reply filed before the Bombay High
Court and that there was no false representation and fraud as
alleged by the respondent. He submitted that the Facilitation
Deed was executed by the senior executives of the parties and
in the case of respondent, it was signed by Michael Grindon,
D President, International, Sony Picture Television, and the
appellant and the respondent had entered into the Facilitation
Deed after consulting their sports media experts and after a
lot of negotiations. He submitted that in fact a Press Release
was issued by the respondent on 23.04.2010, which will go to
show that there was no misrepresentation and fraud by the
E appellant before the Facilitation Deed was signed by the
parties, and thus the entire case of the respondent that the
Facilitation Deed was vitiated by misrepresentation and fraud
is false.
F 13. Mr. Venugopal finally submitted that it will be clear from
the language of the letter dated 25.06.2010 of the respondent
to the appellant that according to the respondent the Facilitation
Deed was voidable at the option of the respondent. He
submitted that under Section 45 of the Act, the Court will have
G to refer the parties to the arbitration unless it finds that the
arbitration agreement is 'null and void'. He argued that an
agreement which is voidable at the option of one of the parties
is not the same as the agreement which is void and, therefore,
the Division Bench of the High Court should have referred the
H parties to arbitration instead of restraining the arbitration.
WORLD SPORT GROUP (MAURITIUS) LTD. v. MSM 817
SATELLITE (SINGAPORE) PTE. LTD. [A.K. PATNAIK, J.]
According to Mr. Venugopal, this is a fit case in which this A
Court should set aside the impugned order of the Division
bench of the High Court and restore the order of the learned
Single Judge of the High Court.
Contentions on behalf of the respondent: B
14. In reply, Mr. Gopal Subramanium, learned senior
counsel appearing for the respondent, submitted that the
Division Bench of the Bombay High Court has rightly restrained
the arbitration proceedings under the aegis of ICC as the
Facilitation Deed, which also contains the arbitration agreement C
in Clause 9, is void because of fraud and misrepresentation
by the appellant. He submitted that Section 45 of the Act makes
it clear that the Court will not refer the parties to arbitration if
the arbitration agreement is null and void, inoperative or
incapable of being performed and as the respondent has taken D
the plea that the Facilitation Deed, which contained the
arbitration agreement, is null and void on account of
misrepresentation and fraud, the Court will have to decide
whether the Facilitation Deed including the arbitration
agreement in Clause 9 was void on account of fraud and E
misrepresentation by the appellant. He submitted that the
respondent filed the first suit in the Bombay High Court (Suit
No.1869 of 2010) for declaring the Facilitation Deed as null
and void but in the said suit, the appellant did not file a written
statement and instead issued the notice for arbitration only to . F
frustrate the first suit and in the circumstances the respondent
was compelled to file the second suit (Suit No.1828 .of 2010)
for an injunction restraining the arbitration.
15. Mr. Subramanium submitted that Section 9 of the
Code of Civil Procedure, 1908 (for short 'the CPC') confers G
upon the court jurisdiction to try all civil suits except suits which
are either expressly or impliedly barred. He submitted that the
Bombay High Court, therefore, had the jurisdiction to try both
the first suit and the second suit and there was no express or
implied bar in Section 45 of the Act restraining the Bombay H
818 SUPREME COURT REPORTS [2014] 1 S.C.R.
A High Court to try the first suit and the second suit. He submitted
that in India as well as in England, Courts have power to issue
injunctions to restrain parties from proceeding with arbitration
proceedings in foreign countries. In support of this submission,
he relied on V. 0. Tractoroexport, Moscow v. Tarapore &
B Company and Anr. [(1969) 3 SCC 562] and Oil and Natural
Gas Commission v. Western Company of North America
!(1987) 1 SCC 496]. He also relied on Russel on Arbitration,
para 7-056, 7-058, and Claxton Engineering v. Txm olaj- es
gaz Kutao Ktf [2011] EWHC 345 (COMM.).
c 16. Mr. Subramanium relying on the decision of this Court
in Chloro Controls India Private Limited v. Seven Trent Water
Purification Inc. & Ors. (supra) submitted that Section 45 of the
Act casts an obligation on the court to determine the validity of
the agreement at the threshold itself because this is an issue
D which goes to the root of the matter and a decision on this issue
will prevent a futile exercise of proceedings before the
arbitrator. He submitted that under Section 45 of the Act the
Court is required to consider not only a challenge to the
arbitration agreement but also a serious challenge to the
E substantive contract containing the arbitration agreement. He ·
cited the decision of this Court in SMS Tea Estates (P) Ltd. v.
Chandmari Tea Co. (P) Ltd. [(2011) 14 SCC 66] in support of
this argument. He submitted that the contention on behalf of the
appellant that the Court has to determine only whether the
F arbitration agreement contained in the main agreement is void
is, therefore, not correct.
17. Mr. Subramanium next submitted that in cases where
allegations of fraud are prima facie made out, the judicial trend
G in India has been to have them adjudicated by the Court. In this
context, he referred to the decisions of this Court in Abdul Kadir
Shamsuddin Bubere v. Madhav Prabhakar Oak (supra),
Haryana Telecom Ltd. v. Sterlite Industries (India) Ltd. [(1999)
5 SCC 688] and N. Radhakrishnan v. Maestro Engineers &
H Ors. (supra). In reply to the submission of Mr. Venugopal that it
WORLD SPORT GROUP (MAURITIUS) LTD. v. MSM 819
SATELLITE (SINGAPORE) PTE. LTD. [A.K. PATNAIK, J.]
was only the parties against whom the allegations are made A
who can insist on the allegations being decided by the Court,
Mr. Subramanium 'submitted that in the decision of the Madras
High Court in H.G. Oomor Sait v. 0 Aslam Sait [(2001) 3 CTC
. 269 (Mad)] referred to in N. Radhakrishnan v. Maestro
Engineers & Ors. (supra) the situation was reverse. B
18. Mr. Subramanium next submitted that the facts in this
case prima facie establish that a grave fraud was played by
the appellant not only upon the respondent but also on the
BCCI. He argued that the Facilitation Deed ultimately deals with C
media rights belonging to the BCCI and it has been held by
this Court in Mis Zee Tele Films Ltd. & Anr. v. Union of India
& Ors. [AIR 2005 SC 2677] that BCCI is a public body. He
submitted that the Division Bench of the Bombay High Court
has, therefore, rightly taken the view that the disputes in this
case cannot be kept outside the purview of the Indian Courts D
and if arbitration is allowed to go on without BCCI, the interest
of BCCI will be adversely affected. He submitted that having
regard to the magnitude of fraud alleged in the present case,
the disputes were incapable of being arbitrated. Relying on
Booz ~lien & Hamilton v. SB/ Home Finance [(2011) 5 SCC E
532], Haryana Telecom Ltd. v. Sterlite Industries (India) Ltd.
(Supra), India Household and Healthcare Ltd. v. LG
Household and Healthcare Ltd. [(2007) 5 SCC 510] and N.
Radhakrishnan v. Maestro Engineers & Ors. (supra), he ·
submitted that such allegations of fraud can only be inquired F
into by the court and not by the arbitrator.
Findings of the Court:
19. The question that we have to decide is whether the
Division Bench of the Bombay High Court could have passed ·G
the order of injunction restraining the arbitration at Singapore
between the parties. As various contentions have been raised
by Mr. Venugopal, learned counsel for the appellant, in support
of the case of the appellant that the Division Bench of the
Bombay High Court could not have passed the order of · H
820 SUPREME COURT REPORTS [2014] 1 S.C.R.
A injunction restraining the arbitration at Singapore, we may deal
with each of these contentions separately and record our
findings. While recording our findings, we will also deal with the
submissions made by Mr. Gopal Subramanium on behalf of
respondent in reply to the contentions of Mr. Venugopal. We
B will also consider the correctness of the findings of the Division
Bench of the Bombay High Court separately.
20. We are unable to accept the first contention of Mr.
Venugopal that as Clause 9 of the Facilitation Deed provides
that any party may seek equitable relief in a court of competent
C jurisdiction in Singapore, or such other court that may have
jurisdiction over the parties, the Bombay High Court had no
jurisdiction to entertain the suit and restrain the arbitration
proceedings at Singapore because of the principle of Comity
of Courts. In Black's Law Dictionary, 5th Edition, Judicial
D Comity, has been explained in the following words:
•Judicial comity. The principle in accordance with which the
courts of one state or jurisdiction will give effect to the laws
and judicial decisions of another, not as a matter of ,
E obligation, but out of deference and respect.·
Thus, what is meant by the principle of "comity" is that courts
of one state or jurisdiction will give effect to the laws and judicial
decisions of another state or jurisdiction, not as a matter of
obligation but out of deference and mutual respect. In the
F present case no decision of a court of foreign country or no law
of a foreign country has been cited on behalf of the appellant
to contend that the courts in lndi·a out of deference to such
decision of the foreign court or foreign law must not assume
jurisdiction to restrain arbitration proceedings at Singapore. On
G the other hand, as has been rightly submitted by Mr.
Subramanium, under Section 9 of the CPC, the courts in India
have jurisdiction to try all suits of a civil nature excepting suits
of which cognizance is either expressly or impliedly barred.
Thus, the appropriate civil court in India has jurisdiction to
H entertain the suit and pass appropriate orders in the suit by
WORLD SPORT GROUP (MAURITIUS) LTD. v. MSM 821
SATELLITE (SINGAPORE) PTE. LTD. [A.K. PATNAIK, J.]
virtue of Section 9 of the CPC and Clause 9 of the Facilitation A
Deed providing that courts in Singapore or any other court
having jurisdiction over the parties can be approached for
equitable relief could not oust the jurisdiction of the appropriate
civil court conferred by Section 9 of the CPC. We find that·in
para 64 of the plaint in Suit No.1828 of 2010 filed before the B
Bombay High Court by the respondent, it is stated that the
Facilitation Deed in which the arbitration clause is incorporated
came to be executed by the defendant at Mumbai and the
fraudulent inducement on the part of the defendant resulting in
the plaintiff entering into the Facilitation Deed took place in c
Mumbai and the rescission of the Facilitation Deed on the
ground that it was induced by fraud of defendant has also been
issued from Mumbai. Thus, the cause of action for filing the suit
arose within the jurisdiction of the Bombay High Court and the
Bombay High Court had territorial jurisdiction to entertain the D
suit under Section 20 of the CPC.
21. Any civil court in India which entertains a suit, however,
. has to follow the mandate of the legislature in Sections 44 and
45 in Chapter I of Part II of the Act, which are quoted
hereinbelow: E
"CHAPTER I
NEW YORK CONVENTION AWARDS
44. Definition. In this Chapter, unless the context F
otherwise requires, "foreign award" means an arbitral
award on differences between persons arising out of legal
relationships, whether contractual or not, considered as
commercial 'under the law in force in India, made on or after
the 11th day of October, 1960 - G
,{fil in pursuance of an agreement in writing for
arbitration to which the Convention set forth in the
First Schedule applies, and
H
822 SUPREME COURT REPORTS [2014] 1 S.C.R.
A ill in one of such territories as the Central Government,
being satisfied that reciprocal provisions have
been made may, by notification in the Official
Gazette, declare to be territories to which the said
Convention applies.
B
45. Power of judicial authority to refer parties to
arbitration.- Notwithstanding anything contained in Part I
or in the Code of Civil Procedure, a judicial authority, when
seized of an action in a matter in respect of which the
c parties have made an agreement referred to in section 44,
shall, at the request of one of the parties or any person
claiming through or under him, refer the parties to
arbitration, unless it finds that the said agreement is null
and void, inoperative or incapable of being performed."
D The language of Section 45 of the Act quoted above makes it
clear that notwithstanding anything contained in Part I or in the
Code of Civil Procedure, a judicial authority, when seized of
an action in a matter in respect of which the parties have made
an agreement referred to in Section 44,'Shall, at the request of
E one of the parties or any person claiming through or under him,
refer the parties to arbitration, unless it finds that the said
agreement is null and void, inoperative or incapable of being
performed. Thus, even if, under Section 9 read with Section 20
of the CPC, the Bombay High Court had the jurisdiction to
F entertain the suit, once a request is made by one of the parties
or any person claiming through or under him to refer the parties
to arbitration, the Bombay High Court was obliged to refer the
parties to arbitration unless it found that the agreement referred
to in Section 44 of the Act was null and void, inoperative or
G incapable of being performed. In the present case, the appellant
may not have made an application to refer the parties to
arbitration, but Section 45 of the Act does not refer to any
application as such. Instead, it refers to the request of one of
the parties or any person claiming through or under him to refer
H the parties to arbitration. In this case, the appellant may not have
WORLD SPORT GROUP (MAURITIUS) LTD. v. MSM 823
SATELLITE (SINGAPORE) PTE. LTD. [A.K. PATNAIK, J.]
made an application to refer the parties to arbitration at A
Singapore but has filed an affidavit in reply to the notice of
motion and has stated in paragraphs 3, 4 and 5 of this affidavit
that the defendant had already invoked the arbitration
agreement in the Facilitation Deed and the arbitration
proceedings have commenced and that the suit was an abuse B
of the process of court. The appellant had thus made a request
to refer the parties to arbitration at Singapore which had already
commenced.
22. Section 45 of the Act quoted above also makes it clear
that even where such request is made by a party, it will not refer C
the parties to arbitration, if it finds that the agreement is null and
void, inoperative or incapable of being performed. As the very
language of Section 45 of the Act clarifies the word "agreemenf'
would mean the agreement referred to in Section 44 of the Act.
Clause (a) of Section 44 of the Act refers to "an agreement in D
writing for·arbitration to which the Convention set forth in the
, First Schedule applies.· The First Schedule of the Act sets out
the different Articles of the New York Convention on the
Recognition and Enforcement of Foreign Arbitral Awards,
1958. Article II of the New York Convention is extracted E
herein below:
"1. Each Contracting State shall recognize an agreement
in writing under which the parties undertake to submit to
arbitration all or any differences which have arisen or which F
may arise between them in respect of defined legal
relationship, whether contractual or not, concerning a
subject-matter capable of settlement by arbitration.
2. The term "agreement in writing" shall include an arbitral
clause in a contract or an arbitration agreement, signed G
by the parties or contained in an exchange of letters or
telegrams.
3. The court of a Contracting State, when seized of an
action in. a matter in respect of which the parties have H
824 SUPREME COURT REPORTS [2014] 1 S.C.R.
A made an agreement within the meaning of this article, shall,
at the request of one of the parties, refer the parties to
arbitration, unless it finds that the said agreement is null
and void, inoperative or incapable of being performed."
It will be clear from clauses 1, 2 and 3 of the New York
8
Convention as set out in the First Schedule of the Act that the
agreement referred to in Section 44 of the Act is an agreement
in writing under which the parties undertake to submit to
arbitration all or any differences which have arisen or which may
arise between them. Thus, the court will decline to refer the
C parties to arbitration only if it finds that the arbitration agreement
is null and void, inoperative or incapable of being performed.
23. According to Mr. Subramanium, however, as the main
agreement is voidable on account of fraud and
D misrepresentation by the appellant, clause 9 of the main
agreement which contains the arbitration agreement in writing
is also null and void. In support of his submission, he cited the
decision of this Court in SMS Tea Estates (P) Ltd. v.
Chandmari Tea Co. (P) Ltd. (supra). Paragraphs 12 and 13
E of the judgment of this Court in SMS Tea Estates (P) Ltd. v.
Chandmari Tea Co. (P) Ltd. (supra) are quoted hereinbelow:
"12. When a contract contains an arbitration agreement,
it is a collateral term relating to the resolution of disputes,
unrelated to the performance of the contract. It is as if two
F contracts-one in regard to the substantive terms of the
main contract and the other relating to resolution of
disputes-had been rolled into one, for purposes of
convenience. An arbitration clause is therefore an
agreement independent of the other terms of the contract
G or the instrument. Resultantly, even if the contract or its
performance is terminated or comes to an end on account
of repudiation, frustration or breach of contract, the
arbitration agreement would survive for the purpose of
resolution of disputes arising under or in connection with
H the contract.
WORLD SPORT GROUP (MAURITIUS) LTD. v. MSM 825
SATELLITE (SINGAPORE) PTE. LTD. [A.K. PATNAIK, J.]
13. Similarly, when an instrument or deed of transfer (or a A
document affecting immovable property) contains an
arbitration agreement, it is a collateral term relating to
resolution of disputes, unrelated to the transfer or
transaction affecting the immovable property. It is as if two
documents-one affecting the immovable property B
requiring registration and the other relating to resolution of
disputes which is not compulsorily registerable-are rolled
into a single instrument. Therefore, even if a deed of
transfer of immovable property is challenged as not valid
or enforceable, the arbitration agreement would remain c
unaffected for the purpose of resolution of disputes arising
with reference to the deed of transfer."
In the aforesaid case, this Court has held that if the document
containing the main agreement is not found to be duly stamped,
even if it contains arbitration clause, it cannot be acted upon D
because Section 35 of the Stamp Act bars the said document
from being acted upon, but if the document is found to be duly
stamped but not registered though required to be compulsorily
registered, the court can act upon the arbitration agreement
which is a collateral term of the main agreement and is saved E
by the proviso to Section 49 of the Registration Act. Thus, as
per the aforesaid decision of this Court in SMS Tea Estates
(P) Ltd. v. Chandmari Tea Co. (P) Ltd. (supra), the court will
have to see in each case whether the arbitration agreement is
also void, unenforceable or inoperative along with the main F
agreement or whether the arbitration agreement stands apart
from the main agreement and is not null and void.
24. The House of Lords has explained this principle of
separability in Premium Nafta Products Ltd. v. Fili Shipping G
Company Ltd. & Ors. (supra) thus:
"17. The principle of separability enacted in section 7
means that the invalidity or rescission of the main contract
does not necessarily entail the invalidity or rescission of
the arbitration agreement. The arbitration agreement must H
826 SUPREME COURT REPORTS [2014] 1 S.C.R.
A be treated as a "distinct agreemenr and can be void or
voidable only on grounds which relate directly to the
arbitration agreement. Of course there may be cases in
which the ground upon which the main agreement is invalid
is identical with the ground upon which the arbitration
B agreement is invalid. For example, if the main agreement
and the arbitration agreement are contained in the same
document and one of the parties claims that he never
agreed to anything in the document and that his signature
was forged, that will be an attack on the validity of the
c arbitration agreement. But the ground of attack is not that
the main agreement was invalid. It is that the signature to
the arbitration agreement, as a "distinct agreement•, was
forged. Similarly, if a party alleges that someone who
purported to sign as agent on his behalf had no authority
whatever to conclude any agreement on his behalf, that is
D
an attack on both the main agreement and the arbitration
agreement.
18. On the other hand, if (as in this case) the allegation is
that the agent exceeded his authority by entering into a
E main agreement in terms which were not authorized or for
improper reasons, that is not necessarily an attack on the
arbitration agreement. It would have to be shown that
whatever the terms of the main agreement or the reasons
for which the agent concluded it, he would have had no
F authority to enter into an arbitration agreement. Even if the
allegation is that there was no concluded agreement (for
example, that terms of the main agreement remained to
be agreed) that is not necessarily an attack on the
arbitration agreement. If the arbitration clause has been
G agreed, the patties will be presumed to have intended the
question of whether there was a concluded main
agreement to be decided by arbitration."
25. Applying the principle of separability to the facts of this
H case, the respondent rescinded the Facilitation Deed by notice
WORLD SPORT GROUP (MAURITIUS) LTD. v. MSM 827
SATELLITE (SINGAPORE) PTE. LTD. [A.K. PATNAIK, J.]
dated 25.06.2010 to the appellant on the following grounds A
stated in the said notice by its lawyers:
"1. Reference is made to the Deed for the Provison of
Facilitation Services dated March 25, 2009 (the "Deed")
between World Sport Group (Mauritius) Limited ("WSGM")
8
and our client. Under the Deed, which is styled as a
facilitation agreement, our client agreed to pay WSGM
"facilitation" fees for the "facilitation" services stated
thereunder to have been provided by WSGM. The
underlying consideration for the payments by our client to C
WSGM, in fact were the representation made by WSGM
that : (a) WSGM, had executed in India ("BCCI")
whereunder WSGM had been unfettered Global Media
Rights ("the said rights"), including the Indian Subcontinent
(implying thereby as natural corollary that the earlier Media
Rights agreement dated March 15, 2009 between WSGM D
and BCCI along with its restrictive conditions had been
mutually terminated); (b) WSGM could thereafter relinquish
the Media Rights for the Indian Subcontinent in favour of
our client for said valuable consideration to enable our
client to enter into a direct agreement with BCCI; (c) the E
said rights were subsisting with WSGM at the time of
execution of the Deed, i.e, March 25, 2009; and (d)
WSGM had relinquished those rights in favour of BCCI to
enable BCCI and our client to execute a direct Media
Rights License Agreement for the Indian Subcontinent. F
2. BCCI has recently brought to the attention of our client
that the Global Media Rights agreement between WSGM
and BCCI dated March 23, 2009 does not exist and in
terms of Clause 13.5 of the agreement dated March 15, G
2009, after expiry of the 2nd extension the media rights
had automatically reverted to BCCI at 3 a.m. on March 24,
2009 and thus at the time of execution of the Deed, WSGM
did not have any rights to relinquish and/or to facilitate the
procurement of India Subcontinent media rights for the IPL H
828 SUPREME COURT REPORTS [2014] 1 S.C.R.
A from BCCI and thus no facilitation services could have been
provided by WSGM.
3. In view of the above, it is evident that the representation
by WSGM that WSGM relinquished its Indian
Subcontinent media rights for the IPL in favour of our client
B
to pay the "facilitation" fees under the Deed.
4. Taking cognizance of the same, BCCl's Governing
council at its meeting held at Mumbai, India on June 25,
201 O appropriately executed an amendment to Media
c Rights License Agreement dated March 25, 2009 between
BCCI and our client by deleting, inter alia, clause 10.4
thereof.
5. On its part, and in view of the false representations and
D fraud played by WSGM, the Deed is voidable at the option
of our client and thus our client rescinds the Deed with
immediate effect.·
The ground taken by respondent to rescind the Facilitation Deed
thus is that the appellant did not have any right to relinquish and/
E or to facilitate the procurement of Indian subcontinent media
rights for the IPL from BCCI and no facilitation services could
have been provided by the appellant and therefore the
representation by the appellant that the appellant relinquished
its Indian subcontinent media rights for the IPL in favour of the
F respondent for which the appellant had to be paid the facilitation
fee under the deed was false and accordingly the Facilitation
Deed was voidable at the option of the respondent on account
of false representation and fraud. This ground of challenge to
the Facilitation Deed does not in any manner affect the
G arbitration agreement contained in Clause 9 of the Facilitation
Deed, which is independent of and separate from the main
Facilitation Deed and does not get rescinded as void by the
letter dated 25.06.2010 of the respondent. The Division Bench
of the Bombay High Court, therefore, could not have refused
H to refer the parties to arbitration on the ground that the
WORLD SPORT GROUP (MAURITIUS) LTD. v. MSM 829
SATELLITE (SINGAPORE) PTE. LTD. [A.K. PATNAIK, J.]
arbitration agreement was also void along with the main A
agreement.
26. Mr. Gopal Subramanium's contention, however, is also
that the arbitration agreement was inoperative or incapable of
being performed as allegations of fraud could be enquired into B
by the court and not by the arbitrator. The authorities on the
meaning of the words "inoperative or incapable of being
performed" do not support this contention of Mr. Subramanium.
The words "inoperative or incapable of being performed" in
Section 45 of the Act have been taken from Article II (3) of the C
New York Convention as set out in para 22 of this judgment.
Redfern and Hunter on International Arbitration (Fifth Edition)
published by the Oxford University Press has explained the
meaning of these words "inoperative or incapable of being
performed" used in the New York Convention at page 148, thus:
D
"At first sight it is difficult to see a distinction between the
terms 'inoperative' and 'incapable of being performed'.
However, an arbitration clause is inoperative where it has
ceased to have effect as a result, for example, of a failure
by the parties to comply with a time limit, or where the E
parties have by their conduct impliedly revoked the
arbitration agreement. By contrast, the expression
'incapable of being performed' appears to refer to more
practical aspects of the prospective arbitration
proceedings. It applies, for example, if for some reason it F
is impossible to establish the arbitral tribunal."
27. Albert Jan Van Den Berg in an article titled "The New
York Convention, 1958 -An Overview" published in the website
of ICCA [www.arbitration-icca.org/media/0/12125884227980/
new_york_convention_of-1958_overview.pdf], referring to G
Article 11(3) of the New York Convention, states:
"The words "null and void' may be interpreted as referring
to those cases where the arbitration agreement is affected
by some invalidity right from the beginning, such as lack H
830 SUPREME COURT REPORTS [2014] 1 S.C.R.
A of consent due to misrepresentation, duress, fraud or
undue influence.
The word "inoperative" can be said to cover those cases
where the arbitration agreement has ceased to have
effect, such as revocation by the parties.
B
The words "incapable of being performec!' would seem
to apply to those cases where the arbitration cannot be
effectively set into motion. This may happen ·where the
arbitration clause is too vaguely worded, or other terms of
c the contract contradict the parties' intention to arbitrate, as
in the case of the so-called co-equal forum selection
clauses. Even in these cases, the courts interpret the
contract provisions in favour of arbitration."
D 28. The book 'Recognition and Conferment of Foreign
Arbitral Awards: A Global Commentary on the New York
Convention' by Kronke, Nacimiento, et al.(ed.) (2010) at page
82 says:
"Most authorities hold that the same schools of thought
E and approaches regarding the term null and void also
apply to the terms inoperative and incapable of being
performed. Consequently, the majority of authorities do not
interpret these terms uniformly, resulting in an unfortunate
lack of uniformity. With that caveat, we shall give an
F overview of typical examples where arbitration agreements
were held to be (or not to be) inoperative or incapable of
being performed.
The terms inoperative refers to cases where the arbitration
G agreement has ceased to have effect by the time the court
is asked to refer the parties to arbitration. For example,
the arbitration agreement ceases to have effect if there has
already been an arbitral award or a court decision with res
judicata effect concerning the same subject matter and
parties. However, the mere existence of multiple
H
WORLD SPORT GROUP (MAURITIUS) LTD. v. MSM 831
SATELLITE (SINGAPORE) PTE. LTD. [A.K. PATNAIK, J.]
proceedings is not sufficient to render the arbitration A
agreement inoperative. Additionally, the arbitration
agreement can cease to have effect if the time limit for
initiating the arbitration or rendering the award has expired,
provided that it was the parties' intent no longer to be bound
by the arbitration agreement due to the expiration of this B
time limit.
Finally, several authorities have held that the arbitration
agreement ceases to have effect if the parties waive
arbitration. There are many possible ways of waiving a C
right to arbitrate. Most commonly, a party will waive the
right to arbitrate if, in a court proceeding, it fails to properly
invoke the arbitration agreement or if it actively pursues
claims covered by the arbitration agreement."
29. Thus, the arbitration agreement does not become D
"inoperative or incapable of being performed" where allegations
of fraud have to be inquired into and the court cannot refuse to
refer the parties to arbitration as provided in Section 45 of the
Act on the ground that allegations of fraud have been made by
the party which can only be inquired into by the court and not E
by the arbitrator. N. Radhakrishnan v. Maestro Engineers &
Ors. (supra) and Abdul Kadir Shamsuddin Bubere v. Madhav
Prabhakar Oak (supra) were decisions rendered in the context
of domestic arbitration and not in the context of arbitrations
under the New York Convention to which Section 45 of the Act F
applies. In the case of such arbitrations covered by the New
York Convention, the Court can decline to make a reference
of a dispute covered by the arbitration agreement only if it
comes to the conclusion that the arbitration agreement is null
and void, inoperative or incapable of being performed, and not G
on the ground that allegations of fraud or misrepresentation
have to be inquired into while deciding the disputes between
the parties.
30. We may now consider the correctness of the findings
of the Division Bench of the High Court in the impugned H
832 SUPREME COURT REPORTS [2014] 1 S.C.R.
A judgment. The Division Bench of the High Court has held that
the Facilitation Deed was part of several agreements entered
into amongst different parties commencing from 25.03.2009
and, therefore, cannot be considered as stand apart agreement
between the appellant and the respondent and so considered
B the Facilitation Deed as contrary to public policy of India
because it is linked with the finances, funds and rights of the
BCCI, which is a public body. This approach of the Division
Bench of the High Court is not in consonance with the provisions
of Section 45 of the Act, which mandates that in the case of
c arbitration agreements covered by the New York Convention,
the Court which is seized of the matter will refer the parties to
arbitration unless the arbitration agreement is null and void,
inoperative or incapable of being performed. In view of the
provisions of Section 45 of the Act, the Division Bench of the
High Court was required to only consider in this case whether
D Clause 9 of the Facilitation Deed which contained the arbitration
agreement was null and void, inoperative or incapable of being
performed.
31. The Division Bench of the High Court has further held
E that Clause 9 of the Facilitation Deed insofar as it restricted
the right of the parties to move the courts for appropriate relief
and also barred the right to trial by a jury was void for being
opposed to public policy as provided in Section 23 of the
Indian Contract Act, 1872 and was also void for being an
F agreement in restraint of the legal proceedings in view of
Section 28 of the said Act. Parliament has made the
Arbitration and Conciliation Act, 1996 providing domestic
arbitration and international arbitration as a mode of resolution
of disputes between the parties and Exception 1 to Section 28
G of the Indian Contract Act, 1872 clearly states that Section 28
shall not render illegal a contract, by which two or more persons
agree that any dispute which may arise between them in
respect of any subject or class of subjects shall be referred to
arbitration and that only the amount awarded in such arbitration
H shall be recoverable in respect of the dispute so referred.
WORLD SPORT GROUP (MAURITIUS) LTD. v. MSM 833
SATELLITE (SINGAPORE) PTE. LTD. [A.K. PATNAIK, J.]
Clause 9 of the Facilitation Deed is consistent with this policy A
of the legislature as reflected in the Arbitration and Conciliation
Act, 1996 and is saved by Exception 1 to Section 28 of the
Indian Contract Act, 1872. The right to jury trial is not available
under Indian laws. The finding of the Division Bench of the High
Court, therefore, that Clause 9 of the Facilitation Deed is B
opposed to public policy and is void under Sections 23 and
28 of the Indian Contract Act, 1872 is clearly erroneous.
32. The Division Bench of the High Court has also held
that as allegations of fraud and serious malpractices on the part
of the appellant are in issue, it is only the court which can decide C
these issues through furtherance of judicial evidence by either
party and these issues cannot be properly gone into by the
arbitrator. As we have already held, Section 45 of the Act does
not provide that the court will not refer the parties to arbitration
if the allegations of fraud have to be inquired into. Section 45 D
provides that only if the court finds that the arbitration agreement
is null and void, inoperative or incapable of being performed,
it will decline to refer the parties to arbitration.
33. The Division Bench of the High court has further held E
that since the earlier suit (Suit No.1869 of 2010) was pending
in court since 25.06.2010 and that suit was inter-connected and
inter-related with the second suit (Suit No.1828 of 2010), the
, court could not allow splitting of the matters and disputes to be
decided by the court in India in the first suit and by arbitration F
abroad in regard to the second suit and invite conflicting verdicts
on the issues which are inter-related. This reasoning adopted
by the Division Bench of the Bombay High· Court in the
impugned judgment is alien to the provisions of Section 45 of
the Act which does not empower the court to decline a reference G
to arbitration on the ground that another suit on the same issue
is pending in the Indian court.
34. We make it clear that we have not expressed any
opinion on the dispute between the appellant and the
respondent as to whether the Facilitation Deed was voidable H
834 SUPREME COURT REPORTS [2014) 1 S.C.R.
A or not on account of fraud and misrepresentation. Clause 9 of
the Facilitation Deed states inter alia that all actions or
proceedings arising in connection with, touching upon or relating
to the Facilitation Deed, the breach thereof and/or the scope
of the provisions of the Section shall be submitted to the ICC
B for final and binding arbitration under its Rules of Arbitration.
This arbitration agreement in Clause 9 is wide enough to bring
this dispute within the scope of arbitration. To quote Redfern
And Hunter On International Arbitration (Fifth Edition page 134
para 2.141)
c "Where allegations of fraud in the procurement or
performance of a contract are alleged, there appears to
be no reason for the arbitral tribunal to decline jurisdiction."
Hence, it has been rightly held by the learned Single Judge
D of the Bombay High Court that it is for the arbitrator to decide
this dispute in accordance with the arbitration agreement.
35. For the aforesaid reasons, we allow the appeal, set
aside the impugned judgment of the Division Bench of the High
E Court and restore the order of the learned Single Judge. The
parties shall bear their own costs.
D.G. Appeal allowed.
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.