The appellant, Sonali Power Equipments, supplied transformers to the Maharashtra State Electricity Board between 1993 and 2004 and faced delayed payments. It referred the dispute to the Micro and Small Enterprises Facilitation Council under Section 18 of the MSMED Act, obtaining an award in 2010, …
The appellant, M/s Interstate Construction, executed work orders for a power project for the respondent, NPCC, and later disputed certain recoveries, leading to arbitration. The arbitral tribunal awarded the appellant principal sum plus interest, distinguishing pre‑reference, pendente‑lite and …
The appellant, Gayatri Project Ltd., entered into a works contract with the Madhya Pradesh Road Development Corporation and invoked arbitration under Clause 67.4 of the contract, resulting in a 2011 award in its favour. The respondent challenged the award under Section 34 of the Arbitration and …
The Union of India filed a money suit of over Rs 8.73 crore in a Commercial Court in August 2019 without first complying with the pre‑institution mediation requirement of Section 12A of the Commercial Courts Act, 2015. The defendant, Dhanbad Fuels Pvt. Ltd., raised a preliminary objection and sought …
The appellant, a MSME supplier based in Delhi, entered into a contract with ISRO for construction of staff quarters, which contained a clause fixing Bengaluru as the seat of arbitration. Disputes arose and the supplier invoked the Micro, Small and Medium Enterprises (Development) Act, 2006, …
The appellant, Office for Alternative Architecture, challenged a Delhi High Court order that, while appointing an arbitral tribunal under Section 11 of the Arbitration and Conciliation Act, 1996, excluded certain claims as non‑arbitrable. The appellant argued that the court should only examine …
The petitioners filed a suit seeking a permanent injunction and damages for alleged infringement of the trademark ‘SRI ANGANNAN BIRIYANI HOTEL’. The respondents filed a Section 8 application invoking arbitration clauses in two assignment deeds of the trademark, alleging that the deeds were …
The appellants Jindal Steel issued a work order to Bansal Infra and obtained an unconditional bank guarantee to secure an advance payment. After alleged delays, quality deficiencies and termination of the contract, the appellants threatened to encash the guarantee unless a debit balance was paid. …
Arabian Exports Private Limited (the appellant) claimed insurance proceeds for flood damage amounting to Rs 5,71,69,554 against National Insurance Company Ltd. (the respondent). After a long delay, the respondent offered a much lower sum of Rs 1,88,14,146, which the appellant accepted by signing an …
The respondent, Shapoorji Pallonji and Company Private Limited (SPCPL), filed counter-claims in an arbitration initiated by Black Canyon SEZ Pvt. Ltd. (BCSPL) against BCSPL and two non-signatory entities, ASF Buildtech Private Limited (ABPL) and ASF Insignia SEZ Pvt. Ltd. (AISPL), invoking the group …
The Supreme Court was asked to resolve a long‑standing controversy over whether courts exercising jurisdiction under Sections 34 and 37 of the Arbitration and Conciliation Act, 1996 can modify an arbitral award. The issue arose from the earlier decision in Project Director, NHAI v. M. Hakeem, where …
The appellant, Consolidated Construction Consortium Ltd., was contracted by the respondent, Software Technology Parks of India, to construct a building. The contract stipulated liquidated damages for delay, but the respondent granted several extensions of time before finally deducting Rs. 82,43,499 …
The petitioner, a welfare association, owned a resort property that the respondent was licensed to occupy for ten years on payment of monthly fees. The respondent repeatedly defaulted on those fees, leading to arbitration, a settlement reducing the fees, and subsequent execution proceedings ordering …
The appellants, shareholders of RBT Private Ltd., filed a contempt petition alleging that the respondent, a fellow shareholder, willfully violated court and arbitral orders by removing assets and failing to pay loan EMIs. A Single Judge of the Delhi High Court on 5 December 2023 held the respondent …
Electrosteel Steel Ltd. (now ESL Steel Ltd.) filed a petition under Article 227 challenging an order that directed it to comply with an arbitral award dated 06.07.2018 passed by the West Bengal MSME Facilitation Council in favour of Ispat Carrier Pvt. Ltd. The award was rendered after the corporate …
Larsen & Toubro (L&T) and Puri Construction Ltd (PCL) entered into a Development Agreement for land development, later supplemented by a Supplementary Agreement and a Tripartite Agreement involving a bank. Disputes arose over alleged economic duress, non‑fulfilment of conditions precedent, and L&T's …
The appellant and respondent No.1 formed an LLP governed by an agreement containing an arbitration clause (Clause 40). Disputes arose over the ITF project, and the appellant issued a Section 21 notice of arbitration only to respondent No.1 and filed a Section 11 application appointing an arbitrator, …
The parties entered into a contract for bauxite mining, and an arbitral award dated 9 April 2022 was issued in favour of the appellant. The respondent filed an application under Section 34 of the Arbitration and Conciliation Act, 1996 on 11 July 2022 to set aside the award. The issue before the …
M/s Ferro Concrete Construction (India) Pvt. Ltd. entered into a works contract with the State of Rajasthan that contained Clause 22 prohibiting the contractor from claiming any interest on payments, arrears or balances. Disputes led to arbitration under the Arbitration Act, 1940, where the …
The Madhya Pradesh Road Development Corporation sought to acquire land for a highway project and determined compensation using the circle rate fixed under the Indian Stamp Act, as prescribed by the Collector’s Guidelines. The landowners challenged the award, arguing that the compensation was …
The respondent, Snehasis Nanda, bought a flat and entered into a sale agreement with a borrower, while Citicorp Finance (the appellant) granted a home loan to the borrower and transferred part of the loan amount to the bank to foreclose the borrower's existing loan. Nanda claimed that under a …
Disortho S.A.S., a Colombian company, and Meril Life Sciences, an Indian company, entered an International Exclusive Distributor Agreement for medical products in Colombia. Clause 16.5 of the agreement states that Indian law governs the contract and Gujarat courts have jurisdiction, while Clause 18 …
The dispute involved a partnership firm where two of the three partners had died, and the legal heirs of one deceased partner sought to enforce an arbitration clause in the partnership deed to resolve a claim for rendition of accounts. The respondents argued that the heirs, being non‑signatories to …
The stock broker AC Chokshi Share Broker invoked arbitration under BSE Bye‑law 248(a) to recover a large debit balance that accrued in the wife’s trading account after the 2001 market crash, alleging that the husband had orally agreed to be jointly and severally liable. The arbitral tribunal held …
The appellant, C & C Constructions Ltd., contracted with IRCON International Ltd. to construct five road over bridges, but delays attributable to the respondent led the appellant to seek extensions of time under clause 49 of the General Conditions of Contract (GCC). The appellant gave a solemn …
The Supreme Court heard an appeal by Somdatt Builders‑NCC‑NEC (JV) against a Delhi High Court Division Bench order that set aside an arbitral award under Section 37 of the Arbitration and Conciliation Act, 1996. The dispute concerned whether the excess quantity of geogrid required for a reinforced …
The appeal concerned whether a writ petition under Article 226 of the Constitution can be filed against an order of the Micro and Small Enterprises Facilitation Council (MSEFC) made under Section 18 of the MSMED Act, 2006, and if so, under what circumstances. The Supreme Court examined earlier …
The appellants received an arbitral award on 14 February 2022 and were required to file a Section 34 application within three months, extended by a COVID‑19 order to 29 May 2022, with a further 30‑day condonable period ending on 28 June 2022. The 30‑day period fell during the Delhi High Court's …
NBCC (India) Ltd., a micro‑small enterprise, entered into several construction contracts with the State of West Bengal and later filed a memorandum under Section 8 of the MSMED Act, 2006 after the contracts were executed. The enterprise then referred a payment dispute to the Micro and Small …
R.K. Pandey, a former lab assistant of a state‑run medical college, claimed that his superannuation age should be 60 years and sought relief through arbitration, relying on an alleged 1957 arbitration agreement between the municipal board and the Governor of Uttar Pradesh. He unilaterally appointed …
Serosoft Solutions and Dexter Capital Advisors were in arbitration over unpaid fees. During the arbitration, the respondent sought additional time to cross‑examine the appellant's witness RW‑1, which the arbitral tribunal rejected, holding that sufficient opportunity had already been given. The …
The North Delhi Municipal Corporation (appellant) contracted with M/s S.A. Builders Ltd. (respondent) for construction work, which was not completed and led to a dispute. An arbitrator awarded Rs. 1,70,70,720.80 with simple interest and later issued a clarification on 15 March 2005 regarding …
The appellant, an assistant manager, was terminated by the respondent employer alleging absenteeism, after a show‑cause notice and disciplinary inquiry. The appellant filed a petition under Section 15(2) of the Payment of Wages Act for unpaid wages and later approached the Industrial Tribunal under …
The appellant, as legal representative of a deceased partner, invoked an arbitration clause in a partnership deed under Section 11(6) of the Arbitration and Conciliation Act, 1996, after the High Court dismissed his petition. The central issue was whether the clause was merely optional or required …
The appellant, a construction contractor, entered into a works contract with the respondent and later referred their dispute to arbitration, resulting in the appointment of a sole arbitrator. The arbitral tribunal was required to render its award within 12 months of the completion of pleadings, …
The appellant's land was acquired under the National Highways Act, leading to an arbitral award on 25 July 2011. A regular first appeal was filed on 20 October 2011, but the High Court registry notified defects on 9 November 2011, which the appellant's counsel received only on 20 January 2012. …
The Supreme Court examined whether arbitration clauses that allow one party, especially a government entity, to unilaterally appoint a sole arbitrator or control the composition of a three‑member tribunal are valid. It held that such unilateral appointment provisions create a real risk of bias, …
M/s Arif Azim Co. Ltd., an Afghan distributor, entered into a 2010 distributorship agreement with M/s Micromax Informatics FZE (UAE) that contained an arbitration clause designating Dubai as the venue and subjecting the arbitration to UAE Arbitration and Conciliation rules. After a credit dispute, …
Goqii Technologies (appellant) entered a Master Services Agreement with Sokrati Technologies (respondent) containing an arbitration clause (Clause 18.12). After paying over Rs 5.5 crore, Goqii raised concerns based on an independent audit reporting alleged overcharges and fraudulent practices, and …
The appellant, HPCL Bio‑Fuels Ltd., entered into turnkey contracts with the respondent, Shahaji Bhanudas Bhad, for equipment supply. After a dispute over unpaid dues arose in 2014, the respondent invoked the arbitration clause and filed a Section 11(6) application in the Bombay High Court in …
International Seaport Dredging Pvt Ltd entered into a dredging contract with Kamarajar Port Limited, a statutory undertaking, which later gave rise to disputes and arbitration. The arbitral tribunal awarded the appellant approximately Rs 21.07 crore with interest and costs, and the respondent sought …
The Central Warehousing Corporation (CWC), a statutory body, entered into a three‑year lease with M/s Sidhartha Tiles for storage space, which contained an arbitration clause (Clause 16). Disputes later arose over the renewal of the lease and the legality of revised storage charges, prompting CWC to …
OPG Power Generation (the appellant) and its holding company Gita Power were sued by Enexio Power Cooling Solutions for unpaid amounts under supply and erection orders for an air‑cooled condenser unit. The arbitral tribunal held that Gita Power, as the holding company, was bound by the arbitration …
The AMP Group and the JRS Group entered into a Family Arrangement Agreement (FAA) containing an arbitration clause, and later sought to appoint a sole arbitrator under Section 11(6) of the Arbitration and Conciliation Act, 1996. The petition raised two questions: the scope of the referral court’s …
Rohan Builders sought an extension of time under Section 29A of the Arbitration and Conciliation Act, 1996 after the statutory twelve‑month period (or the six‑month consent‑based extension) for making an arbitral award had expired. The Calcutta High Court had held that such an application was not …
The appellant, a contractor, entered into a 1997 contract with the Telecom Department of Haryana for laying underground cables. Disputes over unpaid bills were referred to arbitration, and the arbitrator awarded the claim but denied interest, citing a contractual clause that prohibited it. The …
Cox & Kings Ltd. sought appointment of an arbitrator under Clause 15.7 of its Services General Terms and Conditions Agreement with SAP India Pvt. Ltd., alleging breach of a software implementation project. The petition raised questions on whether a prima facie arbitration agreement existed under …
The appellant, a former managing director of Sri Lakshmi Hotel Private Ltd., challenged the e‑auction of the company's property, alleging that the reserve price was under‑valued, that the liquidator failed to form a Stakeholders’ Consultation Committee, and that the liquidator violated Regulation 33 …
Pam Developments Private Ltd entered into a work contract with the State of West Bengal for road widening, which was completed after a five‑month delay. The contractor claimed several sums, including labour charges for uneconomical stoppage, interest on delayed payment of running‑account bills, and …
The Supreme Court considered an appeal by DLF Ltd. and another Indian company against a Croatian generator firm concerning the enforcement of a foreign arbitral award expressed in euros. The key issues were the appropriate date for fixing the foreign exchange rate to convert the award into rupees …
SBI General Insurance issued a fire insurance policy to Krish Spinning, which settled the first fire claim by a discharge voucher and payment of Rs 84,19,579. Krish Spinning later disputed the quantum of the settlement, alleging coercion, and invoked the arbitration clause in the policy by filing a …
The petitioners, a UAE entity, claimed that the respondents defaulted on payments under a 2004 MoU and invoked arbitration in 2022, eleven years after the alleged breach in 2011. The petition sought appointment of an arbitrator under Section 11(6) of the Arbitration and Conciliation Act, 1996, while …
The dispute arose from a slum redevelopment project where the respondent, Samir Narain Bhojwani, alleged default by the appellant, Bombay Slum Redevelopment Corporation Private Limited, leading to arbitration and an award in favour of the respondent. The appellant challenged the award under Section …
The State of West Bengal appointed Rajpath Contractors to construct a bridge, and an arbitral award dated 30 June 2022 directed the State to pay Rs.2.11 crore. The State received the award on the same day and filed a petition under Section 34 of the Arbitration and Conciliation Act on 31 October …
The dispute involved Dani Wooltex Corporation (appellant) and Sheil Properties (respondent) arising from parallel arbitrations concerning a development agreement and a memorandum of understanding. While the arbitration concerning Marico Industries concluded with an award in 2017, the arbitration …
The Supreme Court examined an appeal challenging a Bombay High Court order that disposed of a writ petition by adopting a "Minutes of Order" signed by counsel, without impleading parties who would be affected by the construction of a compound wall. The writ petition sought police protection for the …
The Delhi Metro Rail Corporation (DMRC) and Delhi Airport Metro Express Private Ltd (DAMEPL) entered into a 2008 concession agreement for the Delhi Airport Metro project. DAMEPL alleged safety defects, issued a cure notice, and later terminated the agreement; an arbitral tribunal awarded substantial …
Snehadeep Structures Pvt. Ltd. (SSPL) entered into a supply/purchase order with Maharashtra Small Scale Industries Development Corporation Ltd. (MSSIDCL) on 30 March 1995 for the delivery of goods to the Maharashtra State Electricity Board. The contract stipulated that MSSIDCL would pay SSPL only …
The dispute arose from a US$60 million investment by HSBC PI Holdings in Avitel Post Studioz, governed by an arbitration clause designating Singapore as the seat. After alleged fraud, SIAC rendered a final award in 2014 ordering the appellants to pay the amount. The appellants challenged enforcement …
The petitioners, an Afghan franchisee, sought appointment of a sole arbitrator under Section 11(6) of the Arbitration and Conciliation Act, 1996 to resolve disputes over royalty payments and renewal of franchise agreements with the respondent. The key issues were whether the Limitation Act, 1963 …
The appellant, a civil engineering contractor, entered into a contract with the Karnataka State Public Works Department and later sought arbitration for alleged delays and non‑payment, obtaining an award of Rs.14,68,239 with 18% interest. The Civil Judge, invoking Section 34 of the Arbitration and …
The appellants, heirs of the late Shivkumar Daga, filed a civil suit seeking declaration that a conveyance deed of 17‑12‑2019 and several development agreements were void. The respondents moved a Section 8 application under the Arbitration and Conciliation Act, 1996, relying on arbitration clauses …
The Supreme Court examined whether an arbitration agreement embedded in an unstamped or insufficiently stamped contract is void, unenforceable, or merely inadmissible under the Indian Stamp Act. It held that such agreements are only inadmissible as evidence under Section 35 of the Stamp Act and that …
The Supreme Court examined whether the "group of companies" doctrine, which allows an arbitration agreement signed by one member of a corporate group to bind non‑signatory affiliates, is valid under Indian law and how it should be applied. The Court considered the interpretation of the phrase …
Lombardi Engineering, a Swiss design consultancy, entered into a contract with Uttarakhand Vidyut Nigam Ltd for a hydro‑electric project, which was later transferred from UPDCC to the respondent. After the respondent terminated the contract, Lombardi invoked the arbitration clause in the General …
M/s Unibros was awarded a construction contract by All India Radio, but the project was delayed by about 42.5 months due to the employer's failure to provide site and drawings. The arbitrator awarded the contractor Rs. 1.44 crore as loss of profit based on Hudson's formula, despite the contractor …
The appellant, Ruchir Rastogi, filed an FIR alleging that his brother Pankaj Rastogi, a co‑partner in a family HUF, illegally removed gold, silver, diamonds and other assets from a jointly‑run shop in violation of an interim injunction ordered under the Arbitration and Conciliation Act. The High …
Chennai Metro Rail Ltd. entered into a Rs 1566‑crore contract with Afcons, which later gave rise to arbitration. The three‑member tribunal initially fixed the arbitrators' hearing fee at Rs 1,00,000 per session, but later unilaterally raised it to Rs 2,00,000. Chennai Metro challenged the fee …
The dispute arose from a 1982 contract between National Projects Construction Corporation Ltd (NPCCL) and Royal Construction Company Private Ltd (RCCPL) for earth‑work in Iraq, which stipulated payments in Iraqi Dinars and US Dollars. An arbitrator awarded a sum in Iraqi Dinars and a separate rupee …
Solaris Chem Tech Industries Ltd, a water consumer, challenged notices demanding payment of arrears on revised water tariffs, arguing that the notices violated the contractual rate provisions and statutory procedures. The High Court dismissed the writ petition and the subsequent writ appeal, relying …
The appellants, a group of builders, entered into a sale agreement to construct a villa for the respondent, a home‑buyer, but failed to deliver possession and subsequently terminated the agreement. The buyer filed a complaint under the Consumer Protection Act, 2019 before the District Consumer …
The appellants, nine defendants in a commercial suit filed by IL and FS Financial Services Ltd, failed to file written statements within the 30‑day period (ending 8 March 2020) and the 120‑day outer limit (ending 6 June 2020). They sought an extension on 20 January 2021, invoking the Supreme Court's …
Batliboi Environmental Engineers Ltd (BEEL) entered into a turnkey contract with Hindustan Petroleum Corporation Ltd (HPCL) to construct a sewage water reclamation plant. The project was delayed, work was 80% complete and BEEL abandoned it, later claiming damages for overheads, profit, idle …
RPS Infrastructure Ltd entered into a development agreement with KST Infrastructure Pvt Ltd, which later led to an arbitral award in favour of RPS in 2016. While the award was under challenge under Section 34 of the Arbitration Act, a corporate insolvency resolution process (CIRP) was initiated …
Hindustan Construction Company Ltd (the contractor) executed embankment work for the National Highways Authority of India (NHAI) under the Allahabad bypass project and disputed how quantities should be measured for payment—whether soil and pond‑ash embankments should be measured as a single …
Konkan Railway Corporation Limited (the appellant) entered into a lump‑sum contract with Chenab Bridge Project Undertaking (the respondent) for constructing a high‑altitude railway bridge. Disputes arose over increased entry tax and toll tax during execution, leading to a standing arbitral tribunal …
The dispute arose from a government contract where the arbitrator, in 1999, awarded 18% compound interest on the sum due. The Union of India challenged the award under Section 34 of the Arbitration and Conciliation Act, 1996, and the Allahabad High Court reduced the interest to 9% simple interest, …
The appellant and his brother, the first respondent, entered into a Memorandum of Understanding (MoU) in 2010 that included an arbitration clause. The appellant later filed two suits involving additional parties, including a private company and Canara Bank, seeking injunctions over family property. …
The Central Government acquired parcels of land in Mau district for a highway widening project under the National Highways Authority Act, 1956. The Special Land Acquisition Officer (SLAO) determined the total compensation and apportioned shares among the landowners, a determination accepted by the …
The dispute arose from a representation agreement between D.M.C. Management Consultants Ltd. and Integrated Sales Service Ltd., which contained an arbitration clause. After the arbitrator awarded US $6.9 million against DMC, the award was sought to be enforced against non‑signatory parties, …
The Ministry of Home Affairs floated a tender for the supply of Glock pistols, which was awarded to Glock Asia‑Pacific Ltd. The tender’s conditions stipulated that any dispute be referred to a sole arbitrator appointed by the Secretary of the Ministry of Home Affairs, specifically an officer of the …
The parties entered into a 2012 contract for the supply of sub‑machine guns, after which the Ministry of Defence encashed a bank guarantee and deducted liquidated damages in September 2016. The petitioner claimed the dispute should be resolved by arbitration and, after a series of bilateral …
Reliance Infrastructure Ltd. built a power plant for the State of Goa under a Power Purchase Agreement, but the State failed to pay for the electricity generated. The parties referred their dispute to a sole arbitrator, who awarded Rs. 278.29 crore with interest at 15% per annum. The High Court …
The appellant, a construction firm, entered into a contract with the Engineer-in-Chief, received full payment, and issued a notice invoking the arbitration clause on 26‑12‑2013. It later filed an application under Section 11(6) of the Arbitration and Conciliation Act, 1996 on 27‑04‑2016, after the …
The Indian Oil Corporation (IOC) entered into a 15‑year petrol pump dealer agreement with Sathyanarayana Service Station, which contained a clause allowing either party to terminate the agreement by giving three months' notice. The dealer gave a notarised notice to withdraw, which IOC accepted; the …
Gujarat Composite Ltd. entered into a licence agreement with A Infrastructure Ltd. in 2005 that contained an arbitration clause, and later entered into a tripartite loan agreement with the same party and Bank of Baroda that lacked any arbitration provision. Disputes arose over possession, loan …
Ganesh Benzoplast Ltd. (complainant) entered into Inter‑Corporate Deposit agreements with Morgan Securities & Credits Ltd., pledging shares as security. When the value of the pledged shares fell, the lender invoked the pledge and sold the shares to itself and its group companies in 2001. The …
The case concerns a sub-contract (Work Order) containing an arbitration clause, which was unstamped. The appellant argued that the arbitration agreement was unenforceable due to non-payment of stamp duty under the Indian Stamp Act, 1899. The Supreme Court, by a 3:2 majority, held that an arbitration …
NTPC Ltd. and SPML Infra Ltd. entered into a contract for installation services. After SPML completed the work, NTPC released the final payment but retained SPML's bank guarantees, linking their release to disputes in other projects. The parties settled the matter through a Settlement Agreement that …
The appellant, a cooperative society, sought to set aside an arbitral award under Section 34 of the Arbitration and Conciliation Act, 1996, but filed the application after the 90‑day statutory period and the additional 30‑day discretionary period had expired because the court was on winter vacation. …
The Union of India and others entered into a contract with M/s. Bharat Enterprise for repair work, which required the contractor to submit a final bill and a No Claims Certificate. The contractor submitted the final bill on 13‑02‑2002, but payment was delayed for over a year, after which the …
IRCON entered into a construction contract with NBCC for a railway station‑cum‑commercial complex. NBCC failed to complete the work and the work was abandoned, prompting IRCON to terminate the contract under clause 60.1. NBCC invoked the arbitration clause; the Arbitral Tribunal held the termination …
Shinhan Bank entered a Leave and Licence agreement and a contemporaneous Amenities agreement with Carol Info Services for office premises. After termination, the parties disputed the refund of security deposits and alleged fees, and the bank invoked an arbitration clause contained in the Amenities …
The dispute concerned partnership accounts where the surviving partner of Super Diamond Tools alleged that K. Mohan Rao falsified accounts and siphoned funds. An arbitrator, appointed after a court reference, found Rao guilty of fraud and awarded a sum with interest. Rao sought to set aside the …
Tata Sons Pvt. Ltd. initiated arbitration against Siva Industries and its promoter under an inter‑se agreement, invoking the London Court of International Arbitration. The sole arbitrator was appointed by the Supreme Court under Section 11(6) of the Arbitration and Conciliation Act, 1996. The …
The arbitral award dated 14‑04‑2000 directed Nepa Ltd to pay Rs 14,49,300 to Manoj Kumar Agrawal with 18% interest from the award date. The High Court, on a stay order, required Nepa to deposit 50% of the amount (Rs 7,78,280) which the respondent withdrew on 08‑11‑2001 after giving a personal …
M/s Meenakshi Solar Power Pvt. Ltd. entered into a Share Purchase Agreement (SPA) with M/s Abhyudaya Green Economic Zones Pvt. Ltd. and its promoters to acquire a solar power project, later executing a Tripartite Agreement and an addendum involving a financier. Disputes arose and the appellant …
The appellant bank granted a loan to a partnership firm which defaulted, leading to a Lavad suit under the Gujarat Co-operative Societies Act, 1961. An award was passed in 1988 and a certificate under Section 103 was issued in 1995, creating a deemed decree. The bank filed an execution petition in …
The appellant, Texco Marketing Pvt. Ltd., bought a fire insurance policy from Tata AIG that excluded coverage for basement premises, yet the insured shop was located in a basement. After a fire, the insurer denied the claim relying on the exclusion clause. The State Consumer Commission held the …
The Supreme Court examined a series of appeals arising from disputes between buyers and micro‑small suppliers under the Micro, Small and Medium Enterprises Development Act, 2006 (MSMED Act) and the Arbitration and Conciliation Act, 1996. The core issue was whether Chapter V of the MSMED Act, which …
Weatherford Oil Tool Middle East Ltd entered into three oil‑field service agreements with Baker Hughes Singapore Pte. The respondent terminated the agreements and, when the petitioner invoked the arbitration clauses, raised a contention that the contracts were unstamped under the Maharashtra Stamp …
Jaycee Housing Pvt. Ltd. and others appealed against a notification by the Odisha Government that designated the Court of Civil Judge (Senior Division) as a Commercial Court to hear arbitration applications under the Arbitration and Conciliation Act, 1996. The appellants argued that Section 2(1)(e) …
M/s Emaar India Ltd entered into a Collaboration Agreement and a 2011 Addendum with Tarun Aggarwal Projects LLP. A dispute arose concerning performance under clauses 3, 6 and 9 of the Addendum, and the parties invoked Clause 36, which permits specific performance in a court, while Clause 37 provides …
Sanghi Industries Ltd invoked performance bank guarantees issued by Ravin Cables Ltd in respect of three purchase orders and subsequently commenced arbitration. Ravin Cables filed two applications under Section 9 of the Arbitration and Conciliation Act, 1996 before Commercial Courts seeking to …
The appellants, contractors, obtained an arbitral award that granted them a sum of money plus interest at 18% per annum for the pre‑reference, pendente lite and post‑award periods. The arbitrator did not provide any reasons for fixing the rate of interest. The respondents had remained silent for …
The case involved an Admiralty suit filed by Banque Cantonale de Geneve against the owners of the vessel M.V. Polaris Galaxy for alleged mis‑delivery of cargo. The Commercial Division of the Madras High Court, exercising its power under Order 1 Rule 10(2) of the CPC, added Gulf Petroleum FZC as a …
Daiichi Sankyo Co. Ltd sought enforcement of a Singapore arbitral award of about INR 2,562 crore against 20 respondents, including Oscar Investments Ltd and the Singh brothers. The Supreme Court examined whether the Singh brothers (contemnors 9 and 10) had willfully violated multiple orders and …
The corporate debtor, Seya Industries Ltd., and its investors, including Beacon Trusteeship Ltd., entered into a debenture arrangement which later gave rise to arbitration and a claim for payment. While arbitration was pending, the investors filed a petition under Section 7 of the Insolvency and …
The appellant SEPCO Electric Power Construction Corp. obtained an arbitral award of Rs 142 crore in favour of the respondent Power Mech Projects Ltd. The appellant filed a Section 34 challenge and, on the same day, a Section 36(2) application for a stay of the award. The respondent subsequently …
Essar Steel deposited roughly Rs 35 crore and Rs 47 crore as refundable security deposits with Essar House Private and Essar Services respectively. After Essar Steel entered corporate insolvency resolution, the resolution applicant Arcelor Mittal Nippon Steel (Arcellor) sought repayment of those …
The appellant, a landowner, entered into a Development Agreement with the respondent developer to construct an apartment complex, also granting a General Power of Attorney. The developer failed to complete the work within the stipulated 15‑month period, prompting the appellant to serve a legal …
The appellant, Morgan Securities, obtained an arbitral award granting post‑award interest of 18% only on the principal sum, while the appellant argued that interest should apply to the total award including pre‑award interest. The dispute centered on the interpretation of Section 31(7)(b) of the …
The Supreme Court considered several petitions concerning the determination of arbitrators' fees under the Arbitration and Conciliation Act, 1996. The Court held that arbitrators cannot unilaterally issue binding orders determining their own fees, as this violates party autonomy and the principle …
The National Highways Authority of India (NHAI) acquired land from private owners and an arbitrator awarded enhanced compensation, which NHAI challenged under Section 34 of the Arbitration and Conciliation Act, 1996. The land owners, instead of filing an execution proceeding, approached the High …
Brij Raj Oberoi leased the Norkhill Hotel from the State of Sikkim for 24 years under a deed that contained a renewal clause (clause 4(xiii)) requiring the lessee to give notice and, if the parties could not agree on the rent or period, to refer the dispute to arbitration. Oberoi offered renewal on …
The plaintiff, RAKHEJA ENGINEERS, filed a commercial suit for recovery of money without seeking urgent interim relief. The defendant, M/S. PATIL AUTOMATION, moved to reject the plaint under Order VII Rule 11 of the CPC, arguing that the suit violated Section 12A of the Commercial Courts Act, 2015, …
Mahanadi Coalfields Ltd., a subsidiary of Coal India Ltd., entered into a contract with IVRCL AMR Joint Venture for road works. The contract contained Clause 15 titled “Settlement of Disputes/Arbitration”, which the respondent invoked to issue a notice of arbitration and later sought appointment of …
The dispute arose between General Manager, East Coast Railway (appellant) and Hindustan Construction Co. Ltd. (respondent) over a contract dated 29 November 2018. The respondent filed a Section 9 application before the Additional District Judge, Visakhapatnam, seeking an injunction against the …
The Supreme Court clarified the scope of the term "transfer" under the Land Acquisition Act, 1894, holding that it includes development and collaboration agreements and licences issued during the suspect period (27‑08‑2004 to 29‑01‑2010). It examined numerous applications concerning projects such as …
The dispute arose from a contract between Indian Oil Corporation Limited (IOCL) and NCC Limited (NCCL) for civil and structural works at Paradip Refinery, where NCCL submitted a final bill including "Notified Claims" and sought an extension of time. IOCL released a payment of Rs.4,53,04,021/- and …
Asian Hotels (North) Ltd., the licensor, granted individual shop licenses to various shopkeepers, including the respondents, and later revoked those licenses. The respondents filed suits seeking a declaration that their licenses were irrevocable and perpetual. While the suits were pending, they …
HSBC PI Holdings (Mauritius) Ltd. invested USD 60 million in Avitel, a company owned by the respondents. The Supreme Court, affirming a 2014 order, directed the respondents to maintain a USD 60 million balance in a Corporation Bank account. The respondents failed to comply, repeatedly sought …
The National Highway Authority of India (NHAI) entered into an EPC contract with Transstroy (India) Limited, which was later terminated by NHAI for alleged breaches. The contractor invoked the arbitration clause, filing a claim, while NHAI reserved its right to claim damages and filed a …
The National Highways Authority of India (NHAI) challenged arbitral awards that enhanced compensation for land acquired under the National Highways Act, arguing that the arbitrator improperly relied on post‑acquisition guideline values and failed to give sufficient reasons, violating Sections 28(2) …
BBR (India) Private Limited and S.P. Singla Constructions entered into a contract containing an arbitration clause that did not specify a seat. The first arbitrator fixed the place of proceedings at Panchkula, Haryana, which the Court treated as the jurisdictional seat under Section 20(2) of the …
The petition sought to join the parent company, a non‑signatory, to arbitration proceedings arising from a software licence and services agreement between the petitioner and a subsidiary of the parent. The Court examined the scope of the "group of companies" doctrine, particularly its reliance on …
The dispute arose from a concession agreement between Delhi Airport Metro Express Private Limited (DAMEPL) and Delhi Metro Rail Corporation (DMRC) concerning a termination payment and the interest payable thereon. The arbitral tribunal awarded the termination sum and interest at SBI PLR plus 2% as …
The parties, who were family members, referred their property dispute to a sole arbitrator appointed by mutual consent without any written arbitration agreement. The arbitrator was later alleged to have delayed the proceedings, leading respondents to file applications under section 14(1)(a) of the …
The Kerala government enacted the Kerala Revocation of Arbitration Clauses and Reopening of Awards Act, 1998 to cancel arbitration clauses in agreements for the Kallada Irrigation Project, revoke arbitrators' authority and permit appeals against awards that had become "Rule of Court". The High Court …
NDMC entered into a purchase order with Minosha India Ltd, terminated it for alleged non‑performance and the latter invoked the arbitration clause on 7 June 2016. Before the arbitration could commence, the corporate debtor was admitted to corporate insolvency resolution on 14 May 2018, a moratorium …
Oil and Natural Gas Corporation Ltd. (ONGC) entered into a contract with Discovery Enterprises Pvt. Ltd. (DEPL), a member of the DP Jindal Group, which contained an arbitration clause. ONGC sought to bind Jindal Drilling and Industries Ltd. (JDIL), a non‑signatory affiliate, invoking the …
The dispute concerned a partnership and ownership of a hotel property, where the respondents sought interim relief under Section 9 of the Arbitration and Conciliation Act, 1996, which was rejected by the Commercial Court. The respondents appealed that decision under Section 37 of the same Act. While …
The appellant, a micro‑enterprise, obtained an arbitral award of Rs.2.72 crore against the respondent. The respondent filed a petition under Section 34 of the Arbitration and Conciliation Act, 1996 to set aside the award. The appellant invoked Section 19 of the Micro, Small and Medium Enterprise …
Evergreen Land Mark Pvt. Ltd. (appellant) leased premises from John Tinson & Co. and ran a restaurant/bar. The lease was terminated and a dispute over rental payments for March 2020‑December 2021 arose, leading the parties to arbitration. The owners filed applications under Section 17 of the …
The parties entered into a development agreement for a property in Muzaffarpur, Bihar, which contained an arbitration clause stating that the arbitrators' sittings would be in Kolkata. After a dispute arose, the respondent filed an arbitration petition under Section 11(6) of the Arbitration and …
The Urban Infrastructure Real Estate Fund (U.I.R.E.F) obtained an arbitral award of Rs 78.33 crore against Dharmesh S. Jain and others, which the Bombay High Court stayed on the condition that the respondents deposit 50% of the amount. The High Court’s order dated 08‑08‑2019 was later extended twice …
Vodafone Idea Cellular Ltd. filed a consumer complaint alleging over‑charging for mobile services, which the consumer, Ajay Kumar Agarwal, pursued before the District Consumer Disputes Redressal Forum. The appellant argued that Section 7B of the Telegraph Act, 1885, which mandates arbitration for …
Prakash Corporates filed a money suit against Dee Vee Projects Limited on 21‑12‑2020. The defendant failed to file a written statement within the 30‑day period and sought extensions, which were granted up to 15‑04‑2021, but the 120‑day deadline fell on 06‑05‑2021. The trial court and the High Court …
Future Coupons Private Ltd (FCPL) and Future Retail Ltd (FRL) challenged orders of the Delhi High Court Single Judge that enforced an emergency arbitrator’s interim award in a dispute over FRL’s sale of retail assets to Reliance. The appellants alleged that the judge denied them a fair opportunity …
Indian Oil Corporation Ltd. (IOCL) terminated its dealership agreement with Shree Ganesh Petroleum and the dispute over the lease of the land was referred to arbitration under the dealership agreement. The arbitrator, appointed by the Director (Marketing) of IOCL, increased the lease rent from …
The Intercontinental Hotels Group (India) and its associate entered into a Hotel Management Agreement (HMA) with Waterline Hotels, which required the latter to pay incentive fees for renovations. Waterline Hotels failed to pay and later terminated the HMA, prompting the petitioners to invoke the …
Haryana Tourism Ltd invited tenders for supplying aerated drinks and accepted a bid from M/s Kandhari Beverages Ltd, which was to pay Rs.20 lakh for brand promotion. A dispute arose over the amount spent on promotional activities, leading to termination of the contract and referral to a sole …
UHL Power Company Ltd. and the State of Himachal Pradesh appealed a High Court judgment that had set aside a 2005 arbitral award. The Supreme Court examined whether an arbitrator may award post‑award interest (interest on interest/compound interest) and held that, following Hyder Consulting (UK) …
Ellora Paper Mills Ltd entered into a supply contract with the State of Madhya Pradesh and, after a dispute, the parties were referred to an arbitral tribunal called the Stationery Purchase Committee, which was composed entirely of state officers. The appellant sought termination of that tribunal …
I-Pay Clearing Services Pvt. Ltd. entered into a service agreement with ICICI Bank which the bank allegedly terminated abruptly, leading I‑Pay to claim Rs 95 crore. The dispute was referred to arbitration under Section 8 of the Arbitration and Conciliation Act, 1996, and a sole arbitrator awarded Rs …
Mahindra & Mahindra Financial Services Ltd obtained an arbitral award on 28‑Feb‑2011 in its favour, which was dispatched by registered post on 15‑Mar‑2011 but was refused by the respondent, who finally received it on 23‑Mar‑2011. The appellant filed an execution petition on 27‑Jun‑2011; the …
Jharkhand Urja Vikas Nigam Ltd, the successor to Jharkhand State Electricity Board, entered into a contract with M/s Anamika Conductors Ltd for supply of conductors. The supplier, claiming payment, approached the Rajasthan Micro and Small Enterprises Facilitation Council under Section 18 of the …
The State of Haryana awarded a road‑maintenance contract to M/s. Shiv Shankar Construction Co. for Rs 5.26 crore at a rate of Rs 1,000 per km per month, assuming traffic of 3,364 PCU/day. After the closure of a nearby road, traffic on the contract road surged to 24,418 PCU/day, causing additional …
The Madhya Pradesh Housing and Infrastructure Development Board entered into a construction contract with K.P. Dwivedi, which was later rescinded by the Board. The contractor invoked the arbitration clause, and the High Court, by consent of both parties, appointed the Housing Commissioner as …
Saluja Construction Company entered into a contract with Northern Coalfields Limited for the Bina Project and invoked arbitration under Clause 9, filing an application under Sections 8 and 20 of the Arbitration and Conciliation Act, 1996 limited to that project. The arbitrator, however, issued an …
Tata Consultancy Services Ltd (TCS) terminated a Facilities Agreement with SK Wheels Private Limited, the corporate debtor, alleging service deficiencies. The corporate debtor, represented by the Resolution Professional, sought relief under the Insolvency and Bankruptcy Code (IBC) invoking the …
The parties entered into an agreement in 2003 and a dispute arose over the return of 3,648.80 grams of pure gold. The arbitrator awarded the claimant the gold or its value at Rs.740 per gram with interest, and also awarded costs and a loss amount. The claimant later filed an application under …
Welspun Specialty Solutions Ltd. (formerly Remi Metals Gujarat Ltd.) supplied steel casing pipes to ONGC under four purchase orders that contained a liquidated damages clause for delayed delivery. During performance, ONGC granted several extensions and later deducted US$807,804.03 and Rs.1,05,367 as …
The dispute arose from a contract for the supply of wooden batons. The arbitrator rejected the respondents' claim for payment and the security deposit. The respondents filed a petition under Section 34 of the Arbitration and Conciliation Act, 1996, which the District Judge dismissed. The appellants …
The dispute arose from a settlement deed between Ratnam Sudesh Iyer (appellant) and Jackie Kakubhai Shroff (respondent) concerning the sale of shares in Atlas Equifin Private Limited. The deed required the respondent to withdraw criminal complaints and, in return, receive US$1.5 million in escrow …
The State of Chhattisgarh entered into agreements with M/s Sal Udyog for the supply of Sal seeds, which included a clause for "supervision charges" and were governed by a 1987 government circular imposing a 10% charge. After the State terminated the agreement, Sal Udyog claimed a refund of excess …
The appellant-builder company entered into a Joint Development Agreement and a subsequent MoU with Respondent No.2 to develop a property and sell flats, but a dispute arose over the alleged sale of four excess flats beyond the agreed share. Respondent No.2 filed a criminal complaint alleging …
The appellants, Vaishno Devi Construction and others, claimed to be assignees of a decree holder (the late S.N. Kanungo) and sought execution of arbitration awards turned into decrees under Order XXI Rule 16 of the CPC. The dispute turned on whether the Explanation added to Order XXI Rule 16 by the …
The Gujarat State Disaster Management Authority (appellant) was ordered by a Facilitation Council under the MSME Act to pay Rs 105,053,387 to M/s Aska Equipments Ltd (respondent). The appellant sought to set aside the award under Section 34 of the Arbitration & Conciliation Act, 1996 and, pursuant …
Garg Builders entered into a construction contract with Bharat Heavy Electricals Ltd (BHEL) that contained Clause 17 expressly barring any interest on monies due to the contractor. A dispute was referred to arbitration, and the arbitrator awarded pendente lite and future interest despite the clause. …
M/s. Jai Balaji Industries (operational creditor) entered into MOUs with Orissa Minerals Development Company Ltd for iron ore supply, leading to arbitration awards in its favour. The corporate debtor challenged the awards under the Arbitration and Conciliation Act, 1996; the challenges were …
The dispute involved M/s. Vijeta Construction alleging non‑payment of Rs.2,44,92,846 for TMT bars supplied by M/s. Indus Smelters, which had paid only Rs.1,24,50,000. Indus Smelters approached the Micro and Small Enterprises Facilitation Council under the MSMED Act, which dismissed the application …
The Supreme Court, acting suo motu, extended the limitation period for all judicial and quasi‑judicial proceedings due to the COVID‑19 pandemic, initially ordering an exclusion of the period from 15 March 2020 to 14 March 2021. After a decline in cases, the Court on 8 March 2021 limited the …
DLF Home Developers Ltd (DHDL) entered into share purchase agreements (SPAs) with Rajapura Homes Pvt Ltd and Southern Homes Pvt Ltd, and subsequently executed two Construction Management Service Agreements (RCMA and SCMA) to carry out post‑closing construction obligations. DHDL claimed that the …
Arcelor Mittel Nippon Steel India Ltd. and Essar Bulk Terminal Ltd. entered into a cargo‑handling agreement containing an arbitration clause. The appellant invoked the clause, the respondent claimed the dispute was non‑arbitrable and filed Section 9 applications for interim relief in the Commercial …
The Delhi Airport Metro Express Pvt. Ltd. (DAMEPL) and Delhi Metro Rail Corporation Ltd. (DMRC) entered into a concession agreement for the Airport Metro Express Line. DMRC was served a termination notice for alleged defects in the civil structure, which DAMEPL claimed were not cured within the …
The petitioners, Jaipur Zila Dugdh Utpadak Sahkari Sangh Ltd. and others, entered into a distributorship agreement with the respondent, M/s Ajay Sales & Suppliers, which contained an arbitration clause appointing the Sangh's Chairman as sole arbitrator. The respondent later approached the High Court …
The appellant SEPCO, a Chinese corporation, was awarded a large arbitration award in favour of the Indian respondent Power Mech Projects. The High Court, under Section 9 of the Arbitration Act, directed SEPCO to furnish a Rs 30 crore bank guarantee from a "scheduled bank located in India". SEPCO …
The Supreme Court examined whether a foreign arbitral award could be enforced against entities that were not signatories to the underlying arbitration agreement in a dispute between a Hong Kong representative (ISS) and an Indian company (DMC) over commission payments. The Court held that Section …
Amazon invested in FCPL and, through it, in Future Retail Ltd (FRL). When FRL and its promoters attempted to sell FRL's retail assets to a rival, Amazon sought emergency interim relief under the SIAC Rules, and an Emergency Arbitrator issued an award restraining the transaction. The Delhi High Court …
The dispute arose from a BOT concession for the seventh berth at V.O. Chidambaranar Port, where PSA SICAL Terminals (SICAL) sought to replace a royalty payment model with a revenue‑sharing model, alleging a change in law under Article 14 of its licence agreement. The arbitral tribunal awarded SICAL …
The appeal concerned awards of compensation under the National Highways Act, where the amount was fixed by an arbitrator appointed by the Central Government. The petitioners argued that Section 34 of the Arbitration and Conciliation Act, 1996 should allow the court to modify such awards, especially …
The case concerned disputes arising under the Micro, Small and Medium Enterprises Development Act, 2006 (MSMED Act) where a supplier (Silpi Industries) claimed unpaid amounts from Kerala State Road Transport Corporation (KSRTC) and the corporation raised counter‑claims. The issues before the Supreme …
The appellant, M/s Oriental Structural Engineers Pvt. Ltd., was contracted by the State of Kerala to upgrade two highway stretches. The contract contained a clause (60.8) providing for interest on delayed payments, but the rate for local‑currency interest was left blank in the bid appendix. The …
PASL Wind Solutions and GE Power Conversion India, both Indian companies, entered a settlement agreement that provided for arbitration under ICC rules with the seat in Zurich and the substantive law of India. A dispute over warranty claims was arbitrated, the arbitrator held the seat to be Zurich …
Inox Renewables Ltd entered into a purchase order with Jayesh Electricals Ltd containing an arbitration clause that designated Jaipur as the venue of arbitration. The parties later mutually agreed to shift the arbitration venue to Ahmedabad, which the arbitrator recorded in the award. A Section 34 …
The appellant, Sanjiv Prakash, invoked an arbitration clause in a 1996 Memorandum of Understanding (MoU) among family members after a dispute over share transfers with his sister and mother. The respondents argued that the MoU was superseded and novated by a later Shareholders' Agreement (SHA) dated …
The Haryana government awarded concession agreements to Rapid Metrorail Gurgaon Ltd (RMGL) and Rapid Metrorail Gurgaon South Ltd (RMGSL) for two metro projects, which were later terminated by both parties amid allegations of fraud against the IL&FS group. The State agencies HSVP and HMRTC approached …
Indus Biotech Private Ltd sought arbitration against Kotak India Venture Fund and related entities over the formula for converting optionally convertible redeemable preference shares into equity shares, claiming no default existed. Kotak filed a petition under Section 7 of the Insolvency and …
The Madhya Pradesh Electricity Board entered into a Power Purchase Agreement (PPA) with Narmada Equipments in 1999, which was terminated in 2001. The PPA contained an arbitration clause. In 2011 Narmada invoked the clause and, after receiving no response, filed an application under Section 11(6) of …
The petitioners, Sesh Nath Singh and others, challenged the National Company Law Tribunal's (NCLT) order admitting a Section 7 application by Baidyabati Sheoraphuli Co‑operative Bank to initiate corporate insolvency resolution against the corporate debtor. The issue was whether the three‑year …
The Supreme Court examined whether Section 5 of the Limitation Act, 1963 applies to appeals filed under Section 37 of the Arbitration and Conciliation Act, 1996, especially when those appeals are governed by Articles 116, 117 of the Limitation Act or by Section 13(1A) of the Commercial Courts Act, …
The Secunderabad Cantonment Board entered three contracts with M/s B. Ramachandraiah & Sons that contained arbitration clauses. After final payments were made in early 2003, the contractor sought reimbursement for price variations and, in November 2006, demanded the appointment of an arbitrator, …
The appellants filed a criminal complaint alleging that the second respondent, a property owner, cheated them in a commercial transaction involving the sale of a mortgaged plot, breaching the agreement and misappropriating funds, leading to FIRs under Sections 420, 406 and 34 IPC. The Delhi High …
The dispute arose when BSNL (appellant) withheld Rs.99.70 crore from Nortel (respondent) after completing a telecom tender. Nortel claimed the amount in May 2014, which BSNL rejected on 4 August 2014. After more than five years, Nortel invoked the arbitration clause on 29 April 2020 and sought …
The corporate debtor Ricoh India Ltd. initiated a corporate insolvency resolution process under the IBC, inviting resolution plans. Kotak Investment Advisors Ltd. (KIAL) submitted its plan on time, while Kalpraj submitted a belated plan which was later accepted by the Committee of Creditors (CoC) …
Pravin Electricals alleged that no consultancy agreement dated 7 July 2014 existed with Galaxy Infra, while Galaxy claimed such an agreement, containing an arbitration clause, was executed and sought appointment of a sole arbitrator under Section 11(6) of the Arbitration and Conciliation Act, 1996. …
In a suo motu writ petition, the Supreme Court examined the extension of limitation periods granted due to the COVID-19 pandemic. Earlier orders had excluded the period from 15 March 2020 to a date to be fixed, allowing litigants extra time to file suits, appeals and other proceedings. Observing …
Amway India Enterprises Pvt. Ltd. appointed Ravindranath Rao Sindhia and Indumathi Sindhia, U.S. nationals, as distributors under a sole proprietorship agreement. The respondents filed a petition under Section 11(6) of the Arbitration and Conciliation Act, 1996 seeking appointment of a sole …
The appellant, Dakshin Haryana Bijli Vitran Nigam Ltd., terminated a service level agreement with the respondent, Navigant Technologies Pvt. Ltd., leading to arbitration. The three‑member tribunal orally pronounced a majority award on 27‑04‑2018, but the dissenting arbitrator issued a separate …
The appellant company failed to honour multiple cheques, leading the respondent to issue statutory notices under Sections 138 and 141 of the Negotiable Instruments Act and file criminal complaints. While the corporate debtor was placed under a moratorium under Section 14 of the Insolvency and …
The dispute concerned a 5,082‑square‑yard land in Mulund, where the original suit (No. 1335/1988) was settled by two consent decrees dated 16‑Feb‑2005 and 03‑Oct‑2005 between the Vaity family, the housing society and other parties. M/S Chitralekha Builders and its partners were impleaded only later …
The appellant contractor and respondent entered a development agreement for a wind‑farm project that contained an arbitration clause providing for a three‑member tribunal, each party appointing one arbitrator who would then select a presiding arbitrator. A dispute arose over payments; the respondent …
The Punatsangchhu‑I Hydro‑electric Project contract between the Bhutan Hydro‑electric Authority and Larsen & Toubro contained an arbitration clause (Clause 67) that referred to the Indian Arbitration and Conciliation Act, 1996 in the absence of a Bhutanese arbitration law. After Bhutan enacted its …
Chintels India Ltd. filed an application under section 34 of the Arbitration and Conciliation Act, 1996 to set aside an arbitral award, but the single judge of the Delhi High Court refused to condone the delay in filing the application and dismissed it. The appellant challenged that order by …
The Haryana Space Application Centre (HARSAC), a nodal agency of the Haryana government, awarded a GIS modernisation contract to Pan India Consultants and incorporated an arbitration clause in the service level agreement. HARSAC appointed the Principal Secretary to the Government of Haryana as its …
The appellant, Global Mercantile, entered into a sub‑contract with Indo Unique containing an arbitration clause, but the work order was unstamped under the Maharashtra Stamp Act. A dispute arose when Indo Unique invoked a bank guarantee, which Global Mercantile alleged was fraudulent, leading to a …
The appellant, Bhaven Construction, entered into a contract to manufacture and supply bricks that contained an arbitration clause. It unilaterally appointed a sole arbitrator, who dismissed Respondent No.1's Section 16 challenge to his jurisdiction. Instead of using the statutory remedy under …
Srei Equipment Finance Ltd. entered into a hire‑purchase agreement for a JCB machine with Amarnath Yadav, the original owner, and the vehicle was registered with a hypothecation entry in favour of the financier. After the owner defaulted, an arbitrator awarded the loan amount to the financier, but …
Suresh Shah, the landlord, sub‑leased a property to Hipad Technology India Private Limited. A dispute arose under the sub‑lease dated 14‑11‑2018, and the lease contained an arbitration clause. Shah issued a notice invoking the clause, nominated retired Justice Mukul Mudgal as sole arbitrator, and …
We use cookies for analytics to improve your experience. Essential cookies are always on. Privacy Policy.