Patna High Court

M/s Khushee ConstructionversusThe State of Bihar

Work with this judgment

Open a tool with this judgment prefilled as editable reference text. Add your question or case details. You choose when to generate.

Use this judgment as a legal authority. Your own parties and facts stay for you to enter.

Decided
Disposal
DISPOSED

Holding

The petitioner must avail the dispute‑resolution mechanism under Clause 25 of the contract and the court will not interfere with the termination orders.

Summary

The petitioner, Khushee Construction, challenged several office orders dated 28‑08‑2025 that terminated seven water‑supply contracts, forfeited its security deposit and recommended its blacklisting without any show‑cause notice. The petitioner sought quashing of those orders and permission to complete the work, claiming it had already finished over 90% of the project. The court examined the contractual dispute‑resolution clause (Clause 25) which mandates a step‑wise internal grievance mechanism culminating in arbitration under the Arbitration and Conciliation Act, 1996. It held that the petitioner must first exhaust the remedies provided in Clause 25 before approaching the court. Consequently, the writ petition was dismissed and the application was disposed, with the petitioner directed to pursue arbitration as per the contract.

Issues considered

  • Whether the termination orders and forfeiture of security can be quashed without a show‑cause notice.
  • Whether the petitioner is entitled to complete the contracts despite the termination.
  • Whether the petitioner must first invoke the contractual arbitration clause before seeking judicial relief.

Legislation cited

Subjects

  • contract termination
  • arbitration clause
  • show‑cause notice
  • public procurement
  • writ petition
  • procedural fairness

Judgment

                      IN THE HIGH COURT OF JUDICATURE AT PATNA
                                 Civil Writ Jurisdiction Case No.18551 of 2025
                 ======================================================
                 M/s Khushee Construction through its Partner, namely Rajeev Kumar @
                 Rajeev Ranjan Kumar, aged about 37 years (Male), son of Virendra Singh,
                 resident of village- Rampur, Dumra, P.S.-Maranchi, District- Patna.

                                                                     ... ... Petitioner
                                                Versus
           1.    The State of Bihar through the Principal Secretary, Public Health
                 Engineering Department, Government of Bihar, Patna.
           2.    The Principal Secretary, Public          Health   Engineering    Department,
                 Government of Bihar, Patna.
           3.    The Engineer-in-Chief-cum- Special Secretary, Public Health Engineering
                 Department, Government of Bihar, Patna.
           4.    The Chief Engineer, Design, Public Health Engineering Department,
                 Government of Bihar, Patna.
           5.    The Chief Engineer (Zonal), Public Health Engineering Department, Purnea
                 Zone, Purnea.
           6.    The Superintendent Engineer, Public Health Engineering Department,
                 Purnea Circle, Madhepura.
           7.    The Executive Engineer, Public Health Engineering Division Purnea, Bihar.
           8.    The Executive Engineer, Public Health Engineering Division Dhamdaha,
                 Bihar

                                                           ... ... Respondents
                 ======================================================
                 Appearance :
                 For the Petitioner    :         Mr. Vikas Kumar, Advocate
                                                 Mrs. Aradhana Kumari, Advocate
                                                 Mr. Akash Deep, Advocate
                 For the Respondents   :         Mr. Addl.Advocate General-3
                 ======================================================
                 CORAM: HONOURABLE MR. JUSTICE SUDHIR SINGH
                                          and
                         HONOURABLE MR. JUSTICE RAJESH KUMAR VERMA
                                       ORAL ORDER

                          (Per: HONOURABLE MR. JUSTICE SUDHIR SINGH)

5   23-02-2026                  In the present writ petition, the petitioner has prayed

                   for the following relief(s):-

                                           “(i) For quashing of office order no. 176, 178 to
                                           183   all   dated   28.08.2025     contained   in
                                           respective memo no. 2788, 2800 to 05 all dated
Patna High Court CWJC No.18551 of 2025(5) dt.23-02-2026
                                           2/7




                                  28.08.2025 issued by the Executive Engineer,
                                  Public Health Division, Purnea, whereby and
                                  where-under altogether 7 agreements i.e SBD
                                  No. 149, 147, 146, 143, 142, 140 and 148 of
                                  2019-20 for "Design, Construction, Supply,
                                  Testing, commissioning of Water supply Scheme
                                  with Electric Driven Pumps and Iron Removal
                                  Treatment        Plant       having   Technology
                                  (Adsorption/ Nano Technology) of CSIR or
                                  certified by CSIR or any other Technology
                                  endorsed/ approved by GOI in the Iron effected
                                  Habitations under different wards/ Panchayat
                                  under different Blocks in the Purnea division,
                                  District-Purnea of Bihar on turnkey basis with 3
                                  month Trial Run after Commissioning and
                                  comprehensive operation and maintenance of 60
                                  months after successful completion of Trial Run
                                  Period under Mukhyamantri Nishchay (Quality
                                  Affected)" (herein after to be referred as 'the
                                  work in question'), has been terminated and
                                  security money has also been forfeited along
                                  with decision has been taken to recommend the
                                  higher officials to blacklist the registration of
                                  the petitioner without issuance of any show-
                                  cause notice and affording any opportunity of
                                  hearing to the petitioner.
                                  (ii) For direction to the respondent authorities
                                  to allow the petitioner to complete the work
                                  pursuant to aforesaid agreements as mentioned
                                  in sub-para- (i) as petitioner has completed
                                  almost more than 90% of work in the
                                  ward/panchayat of the work in question.
Patna High Court CWJC No.18551 of 2025(5) dt.23-02-2026
                                           3/7




                                  (iii) For any other appropriate relief/reliefs on
                                  the facts and circumstances of the present case
                                  for which the petitioner is found entitle too.”



                      2. From perusal of the record and the General

          Conditions of contract forming part of the agreement executed

          between the employer and the contractor, it appears that Clause

          25 of the agreement provides as under:-

                                  “CLAUSE-25
                                  Settlement of Disputes & Arbitration
                                  Except where otherwise provided in the contract
                                  all questions and disputes relating to the
                                  meaning of the specifications, design, drawings
                                  and instructions here-in-before mentioned and
                                  as to the quality of workmanship or materials
                                  used on the work or as to any other question,
                                  claim right matter or thing whatsoever in any
                                  way arising out of or relating to contract,
                                  designs, drawings, specifications, estimates,
                                  instructions, orders or these conditions or
                                  otherwise concerning the works or execution or
                                  failure to execute the same whether arising
                                  during the progress of the work or after the
                                  cancellation,      termination,   completion      or
                                  abandonment thereof shall be dealt with as
                                  mentioned hereinafter.
                                  (i) If the contractor considered any work
                                  demanded of him to be outside of the
                                  requirements of the contract, or dispute any
                                  drawings, record or decision given in the
Patna High Court CWJC No.18551 of 2025(5) dt.23-02-2026
                                             4/7




                                  writing by the Engineer-in-Charge on any
                                  matter in connection with or arising out of the
                                  contract or carrying out of the contract or
                                  carrying out of the work, to be unacceptable, he
                                  shall promptly within 7 days request the
                                  Superintending Engineer in writing for the
                                  written instruction of decision. Thereupon, the
                                  Superintending Engineer shall give his written
                                  instructions of decision within a period of fifteen
                                  days from the receipt of the contractor's letter. If
                                  the Superintending Engineer fails to give his
                                  instructions or decision in writing within the
                                  aforesaid period or if the contractor is
                                  dissatisfied with the instructions or decision of
                                  the Superintending Engineer, the contractor
                                  may, within 15 days of the receipt of
                                  Superintending Engineer's decision, appeal to
                                  the Chief Engineer who shall afford an
                                  opportunity to the contractor to be heard, if the
                                  later so desires, and to offer evidence in support
                                  of his appeal. The Chief Engineer shall give his
                                  decision     within     30   days   of   receipt   of
                                  contractor's appeal. If the contractor is
                                  dissatisfied with this decision, the contractor
                                  shall within a period of 30 days from receipt of
                                  the decision, give notice to the Chief Engineer
                                  for appointment of arbitrator failing which the
                                  said decision shall be final binding and
                                  conclusive and not referable to adjudication by
                                  the arbitrator.
                                  (ii) Except where the decision has become final,
                                  binding and conclusive in terms of Sub Para (i)
Patna High Court CWJC No.18551 of 2025(5) dt.23-02-2026
                                           5/7




                                  above disputes or difference shall be referred
                                  for adjudication through arbitrator appointed
                                  by Engineer-in-Chief or the administrative head
                                  of the said PHED. If the arbitrator so appointed
                                  is unable or unwilling to act or resign his
                                  appointment or vacates his office due to any
                                  reason whatsoever another sole arbitrator shall
                                  be appointed in the manner aforesaid. Such
                                  person shall be entitled to proceed with the
                                  reference from the stage at which it was left by
                                  his predecessor.
                                  It is a term of this contract that the party
                                  invoking arbitration shall give a list of disputes
                                  with amounts claimed in respect of each such
                                  dispute along with the notice for appointment of
                                  arbitrator and giving reference to the rejection
                                  by the Chief Engineer of the appeal.
                                  It is also a term of this contract that no person
                                  other than a person appointed by such
                                  Engineer-in-Chief or the administrative head of
                                  the department as aforesaid should act as
                                  arbitrator and if for any reason that is not
                                  possible, the matter shall not be referred to
                                  arbitrator at all. It is also a term of this contract
                                  that if the contractor does not make any demand
                                  for appointment of arbitrator in respect of any
                                  claims in writing as aforesaid within 45 days of
                                  receiving the intimation from the Engineer-in-
                                  Charge that the final bill is ready for payment,
                                  the claim of the contractor shall be deemed to
                                  have been waived and absolutely barred and the
                                  Government shall be discharged and released of
Patna High Court CWJC No.18551 of 2025(5) dt.23-02-2026
                                           6/7




                                  all liabilities under the contract in respect of
                                  these claims.
                                  The    arbitration      shall   be   conducted     in
                                  accordance       with     the   provisions   of   the
                                  Arbitration and Conciliation Act, 1996 (26 of
                                  1996) or any statutory modifications or re-
                                  enactment thereof and the rules made there
                                  under and for the time being in force shall apply
                                  to the arbitration proceeding under this clause.
                                  It is also a term of the contract that if any fees
                                  are payable to the arbitrator these shall be paid
                                  equally by both the parties.
                                  It is also a term of the contract that the
                                  arbitrator shall be deemed to have entered on
                                  the reference on the date the issues notice to
                                  both the parties calling them to submit their
                                  statement of claims and counter statement of
                                  claims. The venue of the arbitration shall be
                                  such place as may be fixed by the arbitrator in
                                  his sole discretion. The fees, if any, of the
                                  arbitrator shall, if required to be paid before the
                                  award is made and published, be paid half and
                                  half by each of the parties. The cost of the
                                  reference and of the award (including the fees, if
                                  any, of the arbitrator) shall be in the discretion
                                  of the arbitrator who may direct to any by whom
                                  and in what manner such costs or any part
                                  thereof shall be paid and fix or settle the amount
                                  of costs to be so paid.
                                  All arbitration shall be held at PATNA and at no
                                  other place.”
            Patna High Court CWJC No.18551 of 2025(5) dt.23-02-2026
                                                       7/7




                                  3. In view of the aforesaid, the petitioner shall be at

                      liberty to avail the remedy available under Clause 25 of the

                      Agreement. While invoking the remedy under Clause 25, the

                      petitioner shall be at liberty to raise all permissible grounds in

                      accordance with law.

                                  4. Accordingly, with the aforesaid liberty, the present

                      application stands disposed of.

                                  5. Pending application(s), if any, shall also stand

                      disposed of.


                                                             (Sudhir Singh, J.)


                                                        (Rajesh Kumar Verma, J.)

Gaurav Kumar,
Ibrar/-

U


Continue reading with your account

Sign in to read the full judgment. It’s free.

Sign in to read

Checking your session…

Lawyer court records for this case

Associated through the court’s case reference.

To request removal of this judgment, sign in and send a removal request. We review requests within 10 working days.

For a signed copy suitable for filing, refer to the court's website.