Decided
Disposal
ALLOWED

Holding

The Court held that insisting on a succession certificate where legal heirship is undisputed is without legal basis and directed the Railway to release the pending dues without such certificate.

Summary

The petitioners, legal heirs of the deceased contractor Late Rabindra Kumar, sought payment of pending contractual dues from Eastern Railway, which had refused to release the amounts pending a succession certificate. The Railway argued that a court‑issued succession certificate was necessary to safeguard government interests. The Court observed that where heirship is undisputed, insisting on a succession certificate has no legal basis and can be replaced by an indemnity affidavit. It held that the Railway’s refusal violated the petitioners’ constitutional rights under Articles 14 and 300‑A. Consequently, the Court directed the Railway to release the dues within eight weeks without demanding a succession certificate, subject to an indemnity affidavit if required, and allowed the petition to obtain interest on the amounts.

Issues considered

  • Can the Railway authorities insist on a succession certificate when the legal heirship of the claimants is undisputed?
  • Does the refusal to release contractual dues without a succession certificate violate Articles 14 and 300‑A of the Constitution?
  • Are the petitioners entitled to a writ of mandamus directing the release of the pending dues and interest?
  • May the Railway be satisfied with an indemnity affidavit in lieu of a succession certificate?

Legislation cited

Subjects

  • succession certificate
  • legal heirship
  • contractual dues
  • mandamus
  • Article 14
  • Article 300-A
  • Eastern Railway
  • indemnity affidavit
  • constitutional rights

Judgment

                     IN THE HIGH COURT OF JUDICATURE AT PATNA
                                Civil Writ Jurisdiction Case No.5643 of 2026
                 ======================================================
           1.     Pushpa Devi, W/o Late Rabindra Kumar, Resident of Rabindra Niwas,
                  Mohalla- Station Road, Jamalpur, District- Munger.
           2.    Ritesh Kumar, S/o Late Rabindra Kumar, Resident of Rabindra Niwas,
                 Mohalla- Station Road, Jamalpur, District- Munger.
           3.    Radhika, D/o Late Rabindra Kumar, Resident of Rabindra Niwas, Mohalla-
                 Station Road, Jamalpur, District- Munger.

                                                                        ... ... Petitioner/s
                                                Versus
           1.    The Union of India through the Secretary, Ministry of Railway, Govt. of
                 India, New Delhi.
           2.    The General Manager, Eastern Railway, 1st Floor, Netaji Subhas Road,
                 Fairlie Place, BBD bagh, Kolkata, West Bengal-700001.
           3.    The Divisional Railway Manager, Eastern Railway, Malda Town, West
                 Bengal-732102.
           4.    The Senior Divisional Electrical Engineer (G), Eastern Railway, Malda
                 Town, West Bengal-732102.
           5.    The Senior Divisional Engineer-II, Eastern Railway, Malda Town, West
                 Bengal-732102.

                                                           ... ... Respondent/s
                 ======================================================
                 Appearance :
                 For the Petitioner/s   :     Mr.Shivendra Kumar Roy, Adv.
                 For the Respondent/s   :     Mr.Additional Solicitor General
                 ======================================================
                 CORAM: HONOURABLE MR. JUSTICE A. ABHISHEK REDDY
                                       ORAL ORDER

3   24-06-2026                  Heard learned counsel for the parties.

                               2. The present writ petition has been filed for the

                   following relief(s):-

                                    “a) To hold and declare that the actions of the
                                    Respondents concerned in not considering the
                                    representation dated 31.1.2026 which was
                                    submitted to the Respondent Authorities by the
                                    petitioners as the class-I legal heirs of the
                                    deceased contractor- Late Rabindra Kumar for
Patna High Court CWJC No.5643 of 2026(3) dt.24-06-2026
                                            2/9




                            releasing the contractual dues in connection
                            with LOA bearing No.EL/MLDT/25/22/37 of
                            2017-18       dated     17.1.2018   issued   by   the
                            Electrical Department, Eastern Railway, Malda
                            Division and also in connection with LOA
                            bearing No.OAM/2/38/19-20/SBG/Z-32 dated
                            1.8.2019 issued by the Engineering Department,
                            Eastern Railway, Malda Division is arbitrary,
                            illegal and in violation of the fundamental and
                            constitutional        rights   guaranteed    to   the
                            petitioners under Article-14 & Article-300-A of
                            the Constitution of India and further, is also
                            violative of certain other legal rights of the
                            petitioners.
                             (b) For issuance of writ/order in the nature of
                            Mandamus directing the Respondents concerned
                            and more specifically, the Respondent No. 4 to
                            consider the representation dated 31.1.2026
                            submitted by the petitioners and accordingly,
                            release the remaining contractual dues of
                            Rs.4.58 lacs in connection with letter of
                            acceptance bearing No.EL/MLDT/25/22/37 of
                            2017-18 dated 17.1.2018 in favour of the
                            petitioners as being the class-I legal heirs of the
                            deceased contractor-Late Rabindra Kumar.
                             (c) For issuance of writ/order in the nature of
                            Mandamus directing the Respondents concerned
                            and more specifically, the Respondent No. 5 to
                            consider the representation dated 31.1.2026
                            submitted by the petitioners and accordingly,
Patna High Court CWJC No.5643 of 2026(3) dt.24-06-2026
                                            3/9




                            release the remaining contractual dues of
                            Rs.5.21 lacs and further, also return the
                            Performance guarantee amount of Rs.1.25 lacs
                            deposited in the form of FDR along with interest
                            in connection with letter of acceptance bearing
                            No.OAM/2/38/19-20/SBG/Z-32 dated 1.8.2019
                            in favour of the petitioners as being the class-I
                            legal heirs of the deceased contractor- Late
                            Rabindra Kumar.
                             (d) Consequently, for issuance of a writ in the
                            nature of Certiorari quashing the letter bearing
                            No. W-7/Misc. dated 14.1.2026 issued by the
                            Senior       Divisional         Engineer-II,     Eastern
                            Railways, Malda i.e. Respondent No.5 herein
                            along      with       the    enclosed   letter   bearing
                            No.E.59/Legal Vetting/Electrical /2026 dated
                            13.1.2026 issued by the Law Officer, Eastern
                            Railways, Malda whereby and wherein, the
                            petitioner no.1 has been asked to submit the
                            Succession Certificate issued by a Competent
                            Court of law to claim the release of the pending
                            bills of the awarded contracts to the deceased
                            contractor- Late Rabindra Kumar.
                             (e) For issuance of writ in the nature of
                            Mandamus directing the Respondents concerned
                            to make payment of interest to the petitioners at
                            the rate of term deposit on the remaining
                            contractual dues in connection with letter of
                            acceptance bearing No. EL/MLDT/25/22/37 of
                            2017-18 dated 17.1.2018 and in connection with
Patna High Court CWJC No.5643 of 2026(3) dt.24-06-2026
                                            4/9




                             letter of acceptance bearing No.OAM/2/38/19-
                             20/SBG/Z-32 dated 1.8.2019 w.e.f. June'2020
                             i.e. the date on which the remaining contractual
                             dues became due and payable till the date of
                             payment.
                             (f) For any other relief / reliefs as your
                             Lordships may deem fit and proper in the facts
                             and circumstances of the case.”


                        3.    Learned counsel appearing on behalf of the

          petitioners submits that the petitioners are the legal heirs of

          Late Rabindra Kumar, who was a contractor engaged by the

          Respondent-Railways. It is submitted that during the lifetime

          of Late Rabindra Kumar, he was awarded and the contract for

          the work he executed the works. The amounts claimed under

          the bills submitted in respect of the works executed remain

          unpaid till date and are payable to the petitioners, being the

          legal heirs of Late Rabindra Kumar. That the authorities are

          not paying the due amounts to Petitioner No. 1, who is the

          wife of Late Rabindra Kumar, even though Respondent Nos. 2

          and 3, being the son and daughter of Late Rabindra Kumar,

          have submitted that they have no objection if the amount is

          paid to their mother, Smt. Puspa Devi. Learned counsel

          submits that, out of the three works executed by Late Rabindra

          Kumar, the authorities have already paid the amount due under
Patna High Court CWJC No.5643 of 2026(3) dt.24-06-2026
                                            5/9




          one contract to the wife of the deceased, i.e., petitioner no. 1

          herein. However, insofar as the other two contracts are

          concerned, the authorities are insisting for the production of a

          succession certificate. Learned counsel submits that there is no

          dispute among the petitioners herein either with regard to the

          disbursement of the amount or with respect to the legal heirs

          of the deceased, as there are no legal heirs other than the three

          petitioners. That the petitioners have submitted a Legal Heir

          Certificate issued by the concerned Circle Officer, however the

          Respondent-Railways are not accepting the same. Learned

          counsel submits that the present writ petition may be allowed

          and the Respondent-Railways may be directed to pay the

          amounts due to the petitioners herein in respect of the works

          executed by Late Rabindra Kumar.

                        4. In the counter affidavit filed by the Respondent-

          Railways, the factum of completion of the work by Late

          Rabindra Kumar has not been disputed. However, the

          authorities have taken the stand that unless and until a

          succession certificate issued by the competent Civil Court is

          produced by the petitioners, they are not in a position to

          release the amounts due. Further a specific stand has been

          taken in the counter affidavit stating that the succession
Patna High Court CWJC No.5643 of 2026(3) dt.24-06-2026
                                            6/9




          certificate from a competent court of law will conclusively

          establish the entitlement of the claimants and safeguard the

          interest of the Government against any future disputes, claims

          or liabilities.

                         5. This Court is of the opinion that the insistence on

          a succession certificate from the competent Civil Court is

          without any legal basis, particularly when there is no dispute

          among       the    legal    heirs       regarding   succession   or   the

          disbursement of the amounts payable. When there is no inter

          se dispute between the legal heirs of Late Rabindra Kumar.

          The authority cannot force the parties to approach the Civil

          Court for succession certificate. The stand of the Respondent-

          Railways in insisting upon the production of a succession

          certificate is without any legal basis and deserves to be

          deprecated, particularly when there is no dispute among the

          legal heirs.

                         6. Further, it is to be noted that in the counter

          affidavit, the authorities have stated that, in order to safeguard

          against any future disputes, they are insisting upon the

          production of a succession certificate by the claimants is also

          misplaced. The said concern can be adequately addressed by

          requiring the legal heirs to furnish an indemnity affidavit
Patna High Court CWJC No.5643 of 2026(3) dt.24-06-2026
                                            7/9




          indemnifying the Railways against any future claims or

          liabilities that may arise in the event any other person asserts

          entitlement to the due amounts. A Single Judge Bench of the

          Delhi High Court, in W.P.(C) No. 10594 of 2022 dated

          10.02.2026, in similar circumstances, held in paragraphs 10,

          11 and 12 as under::-

                                “10. The Karnataka High Court in Union of
                                India Department of Postal and Telegraph
                                and Another vs. Smt. Seethamma has held
                                as under:
                                                  5.     Insofar   as   the   second
                                                  condition of Sri Prakash Shetty
                                                  is concerned, admittedly, the
                                                  respondent has produced the
                                                  legal heirship certificate issued
                                                  by the Tahsildar, which is a valid
                                                  document. To draw the family
                                                  pension, no sucession certificate
                                                  is required. In addition to that
                                                  her name would be found in the
                                                  service records of late P.N.
                                                  Rama Iyengar. Unfortunately,
                                                  the service records have not
                                                  been looked into before filing
                                                  this appeal.
                                  11. It is well settled that a succession
                                  certificate ought not to be insisted upon as
                                  a matter of course where the legal heirship
Patna High Court CWJC No.5643 of 2026(3) dt.24-06-2026
                                            8/9




                                  is undisputed and stands duly established.
                                  In the absence of any rival or competing
                                  claims,     and        where     the    identity     and
                                  entitlement of the legal heirs are clearly
                                  verified, the competent authority may
                                  release retiral benefits, pensionary dues,
                                  compensation. Nothing contrary has been
                                  submitted by learned counsel for the
                                  respondent.
                                  12.     Having         considered       the    overall
                                  prospectus of the facts and situation and in
                                  absence         of   their     being    any    specific
                                  requirement           under     both     the       Office
                                  Memorandums,             the    Court     finds      that
                                  insistence for production of the succession
                                  certificate is not called for. The respondents
                                  are accordingly directed to act upon the
                                  petitioner’s         request    on     production      of
                                  survivorship certificate.



                        7. Having regard to the above and also the reasons

          given in the above prargraphs, the present writ petition is

          allowed. The Respondent-Railways is directed to release the

          amounts due to the petitioners as expeditiously as possible

          preferable within a period of eight weeks from the date of

          receipt of a copy of this order without insisting for production

          of the succession certificate. In case the authorities require any
             Patna High Court CWJC No.5643 of 2026(3) dt.24-06-2026
                                                         9/9




                       indemnity       affidavit,     the      petitioners   shall   be   notified

                       accordingly, and on such notice, the petitioners shall furnish an

                       affidavit indemnifying and absolving the Railways of any

                       future liability in respect of any claims relating to the amounts

                       paid.

                                     8. In case the petitioners make any representation

                       seeking payment of interest on the outstanding amounts due,

                       they shall be at liberty to do so. The competent authority shall

                       consider the said representation and dispose of the same in

                       accordance with law.

                                     9. With the above directions, the present writ

                       petition stands allowed to the extent indicated.



                                                                 (A. Abhishek Reddy , J)
Bhardwaj/-

U


Continue reading with your account

Sign in to read the full judgment. It’s free.

Sign in to read

Checking your session…

Lawyer court records for this case

Associated through the court’s case reference.

To request removal of this judgment, sign in and send a removal request. We review requests within 10 working days.

For a signed copy suitable for filing, refer to the court's website.