Patna High Court

Ramjee Singh and CompanyversusThe State of Bihar

Decided
Disposal
ALLOWED

Holding

The court set aside both the black‑listing order and the appeal dismissal order, remitting the matter to the authorities to act afresh in accordance with Clause 16 and Clause 17 of the contract.

Summary

The petitioner, a Class‑I contractor, completed a water‑resource project and was under a maintenance contract until 2026. The Water Resources Department issued a show‑cause notice and subsequently black‑listed the petitioner for five years under Memo No. 3441/2025, and dismissed its appeal under Memo No. 6281/2025, without invoking the contractual clauses governing defect rectification and maintenance. The petitioner contended that the black‑listing violated natural‑justice principles, Article 14 of the Constitution, and the Bihar Contractor Registration Rules, 2007, as no prior notice under Clause 16 or 17 of the agreement was given. The respondents argued that the rules permitted black‑listing for failure to perform maintenance work. The court held that the department must first invoke the specific contract clauses before imposing any penalty and that the orders were procedurally defective. Consequently, both memoranda were set aside and the matter remitted to the department to proceed afresh in compliance with the contract.

Issues considered

  • Whether the black‑listing order under Memo No. 3441/2025 violates principles of natural justice and Article 14 of the Constitution.
  • Whether the dismissal of the petitioner's appeal under Memo No. 6281/2025 is jurisdictionally valid.
  • Whether the department was required to issue notice and invoke Clause 16 and Clause 17 of the contract before imposing a black‑listing penalty.
  • Whether the Bihar Contractor Registration Rules, 2007 empower the department to blacklist a contractor without complying with contractual procedural requirements.

Legislation cited

Subjects

  • blacklisting
  • contractor registration
  • natural justice
  • Article 14
  • certiorari
  • maintenance contract
  • breach of contract
  • writ petition
  • civil writ jurisdiction

Judgment

          IN THE HIGH COURT OF JUDICATURE AT PATNA
                      Civil Writ Jurisdiction Case No.651 of 2026
     ======================================================
     Ramjee Singh and Company a registered partnership, having its registered
     office at Village Rampur, P.O and P.S. -Barahra, Ara, District-Bhojpur, Bihar-
     802311 through its authorized partner namely Ashok Kumar Singh (Male),
     aged about 50 years, son of Late Janardan Prasad Singh, resident of Village-
     Rampur, P.O and P.S.-Barahra, District- Bhojpur, Bihar-802311


                                                                 ... ... Petitioner/s
                                        Versus


1.   The State of Bihar through Principal Secretary, Water Resource Department,
     Government of Bihar, Patna
2.   The Principal Secretary, Water Resource Department, Government of Bihar,
     Patna.
3.   The Additional Principal        Secretary,   Water   Resource    Department,
     Government of Bihar, Patna.
4.   The Engineer-in-Chief (Head Office), Water Resource Department,
     Government of Bihar, Patna.
5.   The Chief Engineer, Irrigation Creation, Water Resource Department,
     Siwan.
6.   The Superintending Engineer, Flying Squad Circle-01, Water Resource
     Department, Government of Bihar, Patna.
7.   The Flying Squad, Circle-01, Water Resource Department, Government of
     Bihar through the Assistant Engineer, Flying Squad, Circle-01, Water
     Resource Department, Government of Bihar, Patna.
8.   The Assistant Engineer, Flying Squad Circle 1, Water Resource Department,
     Government of Bihar, Patna.
9.   The Executive Engineer, Flying Squad Division 4, Water Resource
     Department, Government of Bihar, Patna.
10. The Executive Engineer, Water Resource Department, Saran Canal Division,
    Mairwa (Siwan).

                                               ... ... Respondent/s
     ======================================================
     Appearance :
     For the Petitioner/s   :      Mr. Ashish Giri, Sr. Advocate
                            :      Ms. Riya Giri, Advocate
                            :      Mr. Sumit Kumar Jha, Advocate
     For the Respondent/s   :      Mr. P.K. Shahi, Advocate General
                            :      Mr. Amish Kumar, Advocate
     ======================================================
     CORAM: HONOURABLE MR. JUSTICE SUDHIR SINGH
             and
             HONOURABLE MR. JUSTICE RAJESH KUMAR VERMA
Patna High Court CWJC No.651 of 2026 dt.25-02-2026
                                           2/10




       ORAL JUDGMENT
       (Per: HONOURABLE MR. JUSTICE RAJESH KUMAR VERMA)

         Date : 25-02-2026


                    Heard Mr. Ashish Giri, learned counsel for the petitioner

       and Mr. P.K. Shahi, learned Advocate General assisted by Mr.

       Amish Jha, learned counsel for the Respondents.

                    2. Following are the reliefs sought for in the present writ

       application:-

                    “(i) To issue a writ/order/ direction in the
                    nature of certiorari to set aside order contained
                    in Memo No.3441 dated 24.07.2025 issued
                    under the signature of the Engineer-in-Chief
                    (Head Office), Water Resource Department,
                    Government of Bihar. Patna by which the
                    petitioner has been blacklisted for a period of 5
                    years. (Annexure-P 9. Page No328).
                    (ii) To issue a writ/order/ direction in the nature
                    of certiorari to set aside order contained in
                    Memo No. 6281 dated 14. 11.2025 issued under
                    the signature of the Principal Secretary, Water
                    Resource Department Government of Bihar,
                    Patna by which the appeal of petitioner has
                    been dismissed mechanically (Annexure-P-14
                    Page No.369).
                    (iii) To produce the entire enquiry report
                    submitted by the Flying Squad, Circle-01, Water
                    Resource Department, Government of Bihar,
                    Patna and quash the same as it is arbitrary,
                    malafide, perverse and violative of principles of
                    natural justice and Article 14 of the
                    Constitution of India.
                    (iv) To produce the order of the competent
                    authority by which decision has been taken to
Patna High Court CWJC No.651 of 2026 dt.25-02-2026
                                           3/10




                    blacklist the petitioner as mentioned in the
                    Memo No. 3441 dated 24.07.2025 issued under
                    the signature of the Engineer-in-Chief (Head
                    Office),    Water     Resource      Department,
                    Government of Bihar, Patna, and quash the
                    same being violative of principles of natural
                    justice and Article 14 of the Constitution of
                    India.
                    (v) To pass interim /ex-parte interim order
                    staying Memo No. 3441 dated 24.07.2025
                    issued under the signature of the Engineer-in-
                    Chief (Head Office), Water Resource
                    Department, Government of Bihar, Patna by
                    which the petitioner has been blacklisted for a
                    period of 5 years and/or staying the order
                    contained in Memo No.6281 dated 14.11.2025
                    issued under the signature of the Principal
                    Secretary, Water Resource Department,
                    Government of Bihar, Patna by which the
                    appeal of the petitioner has been dismissed
                    mechanically and/or the petitioner be allowed
                    to participate in other tenders, during the
                    pendency of the present writ application.”

                    3. Learned counsel for the petitioner submits that the

       petitioner is a registered Class-I contractor under the Water

       Resource Department, Government of Bihar, Patna. The genesis of

       the present case is that a notice inviting tender was issued by the

       office of the Executive Engineer, Water Resource Department,

       Saran Canal Division, Mairwa, Siwan (respondent no.10) bearing

       Short NIT No.01 SBD/2017-18 dated 21.12.2017. The petitioner

       possessing the required qualification had participated successfully

       in the tender process and later on the petitioner was issued letter of
Patna High Court CWJC No.651 of 2026 dt.25-02-2026
                                           4/10




       acceptance dated 25.01.2018. Thereafter an agreement dated

       01.02.2018 was executed between the parties, wherein date of

       completion of project was 20.03.2019, the defect liability period

       was from 21.03.2019 to 20.03.2021 and the maintenance period

       was 21.03.2021 to 20.03.2026. The petitioner duly completed the

       work in question on 20.03.2019. Thereafter the petitioner also

       completed the work of defect liability period on 20.03.2021 and

       currently, the petitioner is engaged in maintenance work which in

       terms of the agreement is from 21.03.2021 to 20.03.2026.

                    4. Learned counsel for the petitioner submits that the

       petitioner has received a show-cause notice dated 06.06.2025

       (Annexure-7) issued under the signature of the Engineer-in-Chief

       (Head Office), Water Resource Department, Government of Bihar,

       Patna (Respondent no.4). In the said notice it was requested to the

       petitioner to reply to the show cause notice within 15 days as to

       why petitioner’s registration number should not be blacklisted for

       the reported allegations as mentioned in inspection report of the

       department of flying squad.

                    5. Learned counsel for the petitioner submits that before

       the conduction of investigation by the Flying Squad, Zone-01, the

       petitioner was not issued any notice. Thereafter, the petitioner has

       submitted its reply vide letter dated 20.06.2025 but the Respondent
Patna High Court CWJC No.651 of 2026 dt.25-02-2026
                                           5/10




       no.4 without properly considering the reply of the petitioner,

       blacklisted the petitioner for a period of five years vide Memo No.

       3441 dated 24.07.2025 (Annexure P/9).

                    6. Learned counsel for the petitioner submits that the

       petitioner has been blacklisted under the special rule namely Bihar

       Contractor Registration rules, 2007, under Rule 11(d)(ii) and as

       per rules the petitioner also preferred an appeal under Rule 11 (ङ)

       which was also rejected by the respondent authorities.

                    7. Learned counsel for the petitioner submits that the

       respondent authorities without issuing any notice under Clause-16

       of the agreement, blacklisted the petitioner. The said clause is

       reproduced hereinbelow:-

                    CLAUSE 16 Action in case, work not done as
                    per specifications
                    All works under or in course of execution or
                    executed in pursuance of the contract shall at all
                    times be open and accessible to the inspection
                    and supervision of the Engineer-in- Charge, his
                    authorized subordinates in charge of the work
                    and all the superior officers, officer of the Quality
                    Control Organisation of the Department and of
                    the Cabinet (Technical) Vigilance, and the
                    contractor shall, at all times, during the usual
                    working hours and at all other times at which
                    reasonable notice of the visit of such officers has
                    been given to the contractor, either himself be
                    present to receive orders and instructions or have
                    a responsible agent duly accredited in writing,
                    present for that purpose. Orders given to the
                    Contractor's agent shall be considered to have the
Patna High Court CWJC No.651 of 2026 dt.25-02-2026
                                           6/10




                    same force as if they had been given to the
                    contractor himself.
                    If it shall appear to the Engineer-in-Charge or his
                    higher authority or his authorised subordinates in
                    charge of the work or to the Cabinet (Technical)
                    Vigilance or his subordinate officers, that any
                    work has been executed with unsound, imperfect,
                    or unskillful workmanship, or with materials or
                    article provides by him for the execution of the
                    work which are unsound or of a quality inferior to
                    that contracted or otherwise not in accordance
                    with the contract the contractor shall, on demand
                    in writing which shall be made within the period
                    specified in schedule - F of contract data from the
                    Engineer-in-Charge         specifying   the    work,
                    materials       or     articles     complained    of
                    notwithstanding that the same may have been
                    passed, certified and paid for forthwith rectify, or
                    remove and reconstruct the work so specified in
                    whole or part, as the case may require or as the
                    case may be, remove the materials or articles so
                    specified and provide other proper and suitable
                    materials or articles at his own charge and cost.
                    In the event of the contractor failing do so within
                    a period specified by the Engineer-in-Charge in
                    his demand aforesaid, then the contractor shall be
                    liable to pay compensation at the same rate as
                    under clause 2 of the contract (for non-
                    completion of the work in time) for this default.
                    In such case the Engineer-in-Charge may not
                    accept the item of work at the rates applicable
                    under the contract but may accept such items at
                    reduced rates as the competent authority may
                    consider reasonable during the preparation of on
                    account bills or final bill if the item is so
                    acceptable without detriment to the safety and
                    utility of the item and the structure and incidental
                    items rectified, or removed and re-executed at the
                    risk and cost or contractor. Decision of the
Patna High Court CWJC No.651 of 2026 dt.25-02-2026
                                           7/10




                    Engineer-in-Charge to be conveyed in writing in
                    respect of the same will be final and binding on
                    the contractor.”

                    8. Learned counsel for the petitioner further refers to

       Clause 17 of the agreement which is reproduced hereinbelow:-

                       “CLAUSE 17 Contractor liable for Damages
                       defects during Maintenance period
                       If the contractor or his working people or
                       servants shall break, deface, injure or destroy
                       any part of building in which they may be
                       working, or any building, road, road curb,
                       fence, enclosure, water pipe, cables, drains,
                       electric or telephone post or wired, trees, grass
                       or grassland, or cultivated ground contiguous
                       to the premises on which the work or any part is
                       being executed, or if any damage shall happen
                       to the work while in progress, from any cause
                       whatever or if any defect, shrinkage or other
                       faults appear in the work within defect liability
                       period after a certificate final or otherwise of
                       its completion shall have been given by the
                       Engineer-in-Charge as aforesaid arising out of
                       defect or improper materials or workmanship
                       the contractor shall upon receipt of a notice in
                       writing on that behalf make the same good at
                       his own expense or in default the Engineer-in-
                       Charge cause the same to be made good by
                       other workmen and deduct the expense from
                       any sums that may be due or at any time
                       thereafter may become due to the contractor, or
                       from his security deposit except for the portion
                       pertaining to asphalted work which is governed
                       by sub-para (iii) of clause 35 or the proceeds of
                       sale thereof or sufficient option thereof. The
                       security deposit of the contractor shall not be
                       refunded before the expiry of defected liability
Patna High Court CWJC No.651 of 2026 dt.25-02-2026
                                           8/10




                       period after the issue of the certificate final or
                       otherwise, of completion of work, or till the
                       final bill has been prepared and passed
                       whichever is later.
                       In case of Maintenance and Operation works of
                       Electrical & Mechanical services, the security
                       deposit deducted from contractors shall be
                       refunded within one month from the date of
                       final payment or within one month from the date
                       of completion of the maintenance contract
                       which ever is earlier.”
                    9. Learned counsel for the petitioner submits that as per

       terms of agreement dated 01.02.2018, the clause 16 of the

       agreement provides for “Action in case, work not done as per

       specification” and as per clause 17 of the agreement provides for

       “Contractor liable for damages defects during maintenance

       period”.

                    10. Learned counsel for the petitioner submits that in the

       present case no such notice for any defect in the work of the

       petitioner was given and without evoking the aforesaid clause the

       present case will not fall under the category of Bihar Contractor

       Registration rules, 2007, under Rule 11(d)(ii) and the action of the

       respondents of blacklisting the petitioner is without jurisdiction.

                    11. Learned counsel for the respondents submits that the

       Bihar Contractors Registration Rules, 2007 empowers the

       department to blacklist the contractor if he does not fulfill the

       terms and condition of the agreement and in the present case,
Patna High Court CWJC No.651 of 2026 dt.25-02-2026
                                           9/10




       while entering into the agreement, the petitioner had agreed to

       carry out the maintenance of the road in question for a period of

       five years (2011-2006). Despite repeated request/reminders made

       to the petitioner from 2021 to 2025 to complete the maintenance

       work otherwise penal action will be taken against the petitioner,

       the petitioner chooses not to respond to the said notices and also

       did not start the maintenance work. The department had no other

       option than to take steps of blacklisting of the petitioner for the

       negligence and not fulfilling the terms and condition which he had

       agreed to while entering into agreement.

                    12. We have heard the counsel for the parties. It

       transpires that the respondent authorities before passing the

       impugned order must evoke clause 16 and 17 of the agreement and

       if the petitioner does not fulfill the term and condition of clause 16

       and 17 of the agreement then the respondent authorities have to

       take curative action against the petitioner.

                    13. In view of the aforesaid, the order dated 24.07.2025

       (Annexure-P/9) and order dated 14.11.2025(Annexure-P/14) are

       set aside. The matter is remitted back to the respondent authorities

       who shall proceed afresh in accordance with law as well clause 16

       and 17 of the agreement.

                    14. Accordingly, the present writ petition is allowed.
             Patna High Court CWJC No.651 of 2026 dt.25-02-2026
                                                       10/10




                                 15. Pending Application(s), if any shall also stand

                    disposed of.



                                                  (Sudhir Singh, J)


                                              (Rajesh Kumar Verma, J)
Suruchi/-
AFR/NAFR                NAFR
CAV DATE                NA
Uploading Date          16.03.2026
Transmission Date       NA


Continue reading with your account

Sign in to read the full judgment. It’s free.

Sign in to read

Checking your session…

Lawyer court records for this case

Associated through the court’s case reference.

For a signed copy suitable for filing, refer to the court's website.