Bombay High Court
BABANRAO SAKHARAM DHERANGEversusTHE MUNICIPAL CORPORATION OF GREATER BOMBAY AND ANR
- Decided
- Disposal
- Disposed Off
- Bench
- SHARMILA U DESHMUKH
Holding
The High Court held that the structure does not fall within the ambit of Section 55 of the MRTP Act as it is not a temporary structure, and therefore the trial court’s denial of injunction was unsustainable.
Summary
The appellant, Babanrao Dherange, challenged a notice issued by the Municipal Corporation of Greater Bombay under Section 55 of the Maharashtra Regional and Town Planning Act, 1966, alleging that the structure in question was a temporary erection and therefore subject to removal. The trial court dismissed the appellant's request for an injunction, relying on the decision in Babar Sher Khan v. MCGM that the planning authority could direct removal of any structure under the section. The appellant argued that the structure, made of MS angles, GI sheet roofing, lightweight partitions and rolling shutters, was not a temporary structure and that the earlier High Court order had protected it. The High Court examined the material and held that the mere label “temporary” in the notice does not bring the structure within Section 55, finding sufficient evidence to dispute the applicability of the provision. Consequently, the court quashed the trial court’s order, directed it to decide the suit on its merits, and allowed the appeal, granting the interim relief sought by the appellant.
Issues considered
- Whether the structure described in the notice qualifies as a ‘temporary structure’ within the meaning of Section 55 of the Maharashtra Regional and Town Planning Act, 1966.
- Whether the decision of the Planning Authority on the nature of the structure is conclusive and binding on the court.
- Whether the appellant is entitled to an interim injunction restraining the municipal corporation from demolishing the structure.
Legislation cited
Subjects
- Section 55
- MRTP Act
- temporary structure
- municipal corporation
- injunction
- demolition
- planning authority
- road widening
Judgment
2026:BHC-AS:17613
8 AO-475-2024.doc
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION
APPEAL FROM ORDER NO. 475 OF 2024
WITH
INTERIM APPLICATION NO. 9728 OF 2024
IN
APPEAL FROM ORDER NO. 475 OF 2024
Babanrao Sakharam Dherange ...Appellant
Versus
The Municipal Corporation of Greater Bombay &
Another ...Respondents
——————
Mr. Uday Warunjikar i/b Mr. Nitesh Bhutekar, Mr. Aaditya Mahamiya for
Appellant.
Mr. Drupad Patil, Ms. Neeta Jadhav i/b Ms. Komal Punjabi for
Respondent-BMC.
——————
CORAM : SHARMILA U. DESHMUKH, J.
DATE : 6th August, 2026
P. C. :
1. The present Appeal is at the instance of original Plaintiff being
aggrieved by the order of 6th May, 2024 passed by the Trial Court in
Notice of Motion No. 1190 of 2023 along with Notice of Motion No.
2171 of 2023 dismissing the Notice of Motions, by which the Plaintiff
sought temporary injunction restraining the Respondent-Corporation
from demolishing the subject property.
Sairaj 1 of 5
8 AO-475-2024.doc
2. L. C. Suit No. 1338 of 2023 was filed seeking to challenge the
notice dated 9/3/2023 issued by the Corporation under Section 55 of
the Maharashtra Regional and Town Planning Act, 1966 [for short,
“MRTP Act”] and subsequent speaking order dated 1st April, 2023.
3. The notice issued under Section 55 of Maharashtra Regional and
Town Planning Act, 1966 was in respect of unauthorized erection of
temporary structures admeasuring the specification mentioned therein
at the junction of M. G. Road and L.B.S. Road Ghatkopar (West). The
Plaintiff’s case was that the notice structure was in existence prior to
datum line and was affected by road widening. Part of structure was
acquired for road widening by the Corporation. In respect of remaining
structure, repair permission was sought, which was granted on
22/10/2022. However, Corporation issued notice for erecting
unauthorised temporary structure. The Trial Court by the impugned
order noted the decision of the High Court in the case of Babar Sher
Khan and Others vs. MCGM1 which had held that under Section 55 of
MRTP Act, the Planning Authority may direct the removal of any
structure or work erected and it must not be necessarily of wooden or
tin sheets or tarpaulin. The Trial Court opined that it is necessary to see
whether the development is of temporary structure and that the
Plaintiff has not brought on record prima facie cogent evidence to
1 2008(2) BomCr 335.
Sairaj 2 of 5
8 AO-475-2024.doc
show that the development is of permanent nature. It further noted
that the allegation of Corporation was that the Plaintiff had carried out
unauthorized construction in violation of the terms and conditions of
the repair permission and Plaintiff has not produced material on record
to show that the dimensions of notice structure and the original
structure are the same and he has not carried out excess unauthorized
construction and dismissed the Notice of Motion.
4. Dr. Warunjikar, learned counsel appearing for Appellant would
assail the very foundation of issuance of notice under Section 55 of
MRTP Act, 1966 on the ground that the structure was not of temporary
nature. He would further point out the order dated 24 th April, 2023
passed by this Court in earlier stage of litigation where the submission
was canvassed as regards the applicability of Section 55 of MRTP Act
and this Court had protected the structure and directed the Trial Court
to decide the motion. He points out that the impugned order is
pursuant to the final decision taken by the Trial court in the Notice of
Motion. He would further point out the provisions of Section 55 of
MRTP Act, which deals with the removal or discontinuance of
unauthorized temporary development summarily. He submits that
considering the notice structure is set out in notice of unauthorized
construction using MS angles, G.I. sheet roof, light weight partition
walls, 7 rolling shutters, etc., the same would not constitute a
Sairaj 3 of 5
8 AO-475-2024.doc
temporary structure for the purpose of Section 55 of MRTP Act.
5. Per contra, Mr. Patil, learned counsel appearing for the
Corporation would submit that the Trial Court has rightly considered
the provisions of Section 55 of MRTP Act and that the decision of
Planning Authority on the question of nature of structure shall be final.
He would submit that the decision in the case of Babar Sher Khan and
Others vs. MCGM (supra) was relied upon rightly by the Trial court in
order to arrive at prima facie findings as regards the applicability of
Section 55 of the MRTP Act. He would submit that the Trial Court has
examined the material on record in order to come to a finding that the
Plaintiff has not brought on record the cogent evidence to show the
development is of permanent nature.
6. I have considered the submissions and perused the record.
7. It is an undisputed fact that part of the structure was acquired
for road widening and for remaining structure, repair permission was
granted. The issue was whether the Plaintiff had carried out
construction in excess of development permission. The notice
structure is described as an unauthorized erection of temporary
structure, which is of the specification mentioned therein using MS
angles, G.I. sheet roof, light weight partition walls and 7 rolling
structures. At the earlier stage of litigation, this Court had noted the
identical contention to hold that the question is as to whether the
Sairaj 4 of 5
8 AO-475-2024.doc
action under Section 55 can be lawfully resorted to and has protected
the structure. Prima facie upon consideration of notice which makes a
reference to GI sheet roof, MS angles, rolling shutters, the mere
mention of the word “temporary” to describe the notice structure
would prima facie not bring it within the ambit of Section 55 of MRTP
Act.
8. The protection has been granted by the order of 2 nd August,
2023, which has been continued till the hearing and final disposal of
the suit. Prima facie, there is material on record to dispute the
applicability of Section 55 of MRTP Act. The structure is therefore
required to be protected.
9. The findings of the Trial Court on the aspect of applicability of
Section 55 of the MRTP Act to deny the interim relief of injunction is
unsustainable and is therefore, quashed and set aside. Needless to
clarify that the Trial Court to decide the suit on its own merits and
uninfluenced by observations of this order.
10. Resultantly, the Appeal is allowed. The Notice of Motion is
allowed in terms of prayer clause (a).
[SHARMILA U. DESHMUKH, J.]
Sairaj 5 of 5