Bombay High Court
MUNICIPAL CORPORATION OF GREATER MUMBAIversusBUCON ENGINEERS AND INFRASTRUCTURE PVT.LTD.
- Decided
- Disposal
- DISPOSED OFF
Holding
The arbitral awards are not set aside as they fall within the limited scope of Section 34 and are not patently illegal or contrary to public policy.
Summary
The Municipal Corporation of Greater Mumbai (MCGM) entered into a contract with Bucon Engineers for the design and construction of community toilet blocks in slums, but the work was delayed and extended beyond the original 21‑month period due to site hand‑over issues. Bucon filed multiple claims for additional costs, rate revisions, idle labour, interest, and other expenses, which the arbitral tribunal partially awarded, totaling Rs 37,69,666.07 with interest. MCGM challenged the arbitral awards under Section 34 of the Arbitration and Conciliation Act, 1996, arguing patent illegality and violation of contract terms. The High Court examined the limited scope of judicial interference under Section 34, citing Supreme Court precedents that courts cannot re‑appraise factual findings or contract interpretation absent public‑policy violations. The Court held that the tribunal’s findings were within its expertise, not patently illegal, and therefore not liable to be set aside. Consequently, the court dismissed the arbitration petitions and the related notice of motion.
Issues considered
- The scope of judicial interference under Section 34 of the Arbitration and Conciliation Act, 1996
- Whether the arbitral awards are violative of public policy or contain patent illegality
- Whether the contract breaches by MCGM justify the claimant’s claims for rate revision, idle charges, interest, and other compensation
- Whether the tribunal erred in interpreting contractual clauses relating to site possession, variations, and retention money
Legislation cited
- Arbitration and Conciliation Act, 1996 — s. 18, 34, 34(2)(a)(iii)
Subjects
- Arbitration
- Section 34
- Public policy
- Contract breach
- Rate revision
- Idle labour charges
- Interest on delayed payment
- Retention money
- Cost of arbitration
- Technical arbitrator
Judgment
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION
ARBITRATION PETITION NO.1158 OF 2014
WITH
NOTICE OF MOTION NO. 1148 OF 2018
IN
ARBITRATION PETITION NO.1158 OF 2014
The Municipal Corporation of Greater .... Petitioner
Mumbai.
Vs.
Bucon Engineers & Infrastructure Pvt.
Limited .... Respondent
WITH
ARBITRATION PETITION NO.256 OF 2015
The Municipal Corporation of Greater .... Petitioner
Mumbai.
Vs.
Bucon Engineers & Infrastructure Pvt.
Limited .... Respondent
Mr. P.G. Lad, Senior Advocate a/w Mr. Paras Pawar, Ms. Pooja
Yadav i/by Ms. Komal Punjabi for Petitioner- MCGM in both
Petitions.
Mr. Faran Khan i/b Ms. Pranjali Bhandari, Advocate for Respondent
in both Petitions.
CORAM : ARUN R. PEDNEKER, J.
RESERVED ON : 28th AUGUST 2026
PRONOUNCED ON : 11th SEPTEMBER 2026
1/34
901 ARBPs 1158.14,256.15.doc Dusane
JUDGMENT :
1. Heard the learned Counsel for the parties.
2. By the present Petitions, the Petitioners challenge the arbitral awards
dated 24th April 2014 and 10th October 2014 under Section 34 of the
Arbitration and Conciliation Act, 1996.
3. Learned counsel appearing for the Petitioners–MCGM submits that
both the Awards are identical and that he has advanced his arguments in
Arbitration Petition No. 1158 of 2014, and the facts are set out from
Arbitration Petition No. 1158 of 2014.
4. The Municipal Corporation invited a tender for the planning,
designing, and construction of community toilet blocks in slums in R-
Central Ward, Lot-7, Mumbai. The tender had two phases, one of which
related to the publicity for slum sanitation, community participation, and
health and hygiene education by creating awareness and understanding
through Community Based Organisations (CBOs), while the Second Phase
related to Construction. The slums in Mumbai are situated on Government
land, MHADA land, Municipal Corporation land, and private land.
5. After the CBO was registered and the required upfront contribution
had been paid, the Bidder was required to prepare an architectural layout of
the proposed community toilet in consultation with the concerned CBO and
2/34
901 ARBPs 1158.14,256.15.doc Dusane
QAC and submit the said layout to the Petitioner-MCGM. Once the layout
and RCC drawings were approved, the Bidder could commence
construction.
6. The contract period was for 21 months, commencing on 25 th January
2001 and ending on 31st October 2002. The tendered work could not be
completed within the stipulated contractual period, and multiple extensions
were consequently granted. The contract ultimately remained operative until
31st December 2005, with the final extension being granted without levy of
liquidated damages. Thereafter, no further sites were available for
construction, and the work could not be proceeded with.
7. The proposed construction comprised a total of 20 toilet blocks, each
having a maximum capacity of 20 seats. These toilet blocks were proposed
to be constructed in the slum areas and involved different types of disposal
systems.
8. All the sites could not be handed over to the Respondent-Claimant at
one time. The sites that were made available to the Claimant were allotted at
different points in time and, consequently, the work was required to be
completed over an extended period. Accordingly, the Respondent-Claimant
raised various claims before the learned Arbitrator on different dates. The
Arbitrator has awarded certain amounts in respect of the said claims, against
3/34
901 ARBPs 1158.14,256.15.doc Dusane
which the present Petitions have been filed.
9. The learned Arbitral Tribunal rejected Claim No. 1 relating to
excavation of hard rock, disallowed the claim for idle establishment in its
entirety, and rejected Claim Nos. 9 and 12 in full. It further directed that the
costs of the Reference and the Arbitrator’s fees be borne equally by the
parties. The learned Tribunal rejected four heads of claim, substantially
reduced the claim of Rs.77 lakhs to Rs.14.69 lakhs, reduced the rate of
interest from 24% to 12%, and corrected the Respondent’s/Claimant’s own
computation against it. The total amount awarded against the Claims is set
out in the table below:
Claim Claim Particulars Claim Awarded
No. (Rs.)
1(i) Excavation of hard rock at Kulupwadi Rejected
site, Rs.94,597.20.
1(ii) Construction of UCR masonry wall at 45,883.00.
Shantidoot Site
1(iii) Providing and fixing individual tap to 1,78,500.00.
each W.C. of toilet block
2 Compensation towards revision of 13,92,853.47
rates.
3 Loss of interest due to delay in 3,49,998/-
payment
4 Compensation 14,69,388/-
5 Infructuous expenditure 1,82,500/-
6 Delay in returning the Retention money 41,252.80
4/34
901 ARBPs 1158.14,256.15.doc Dusane
7 Extra cost incurred 56,111/-
8 Loss of profits and overheads 3,180/-
9 Compensation towards miscellaneous Rejected
expenses
10 Appointment of sole Arbitrator 50,000/-
11 Compensation towards loss of interest Rejected
on due amounts as per above claims
12 Cost of Arbitration Rejected
Total : 37,69,666.07
12% interest on above amounts from 28.2.2008 to 24.4.2014
10. Before considering the claims and the findings thereon, it is necessary
to examine the relevant clauses of the contract and the alleged breaches
thereof, if any. The General Conditions of Contract and the relevant clauses,
including the provisions defining the site and area under the contract, are set
out below.
14 : Site Investigation Reports :
14.1 The Contractor, in preparing the Bid, shall rely on any
Site, Investigation Reports referred to in the Contract Data,
supplemented by any information available to the Bidder.
17. The Works to be completed by the Intended Completion
Date :
17.1 The Contractor may commence execution of the Works
on the Start date and shall carry out the Works in accordance
5/34
901 ARBPs 1158.14,256.15.doc Dusane
with the Programme submitted by the Contractor, as updated
with the approval of the Engineer, and complete them by the
Intended Completion Date.
18. Approval by the Engineer :
18.5 All Drawings prepared by the Contractor for the
execution of the Temporary or Permanent Works, are subject to
prior approval by the Engineer before their use.
21. Possession of the Site :
21.1 The Employer shall give possession of all parts of the Site
to the Contractor. If possession of a part is not given by the date
stated in the Contract Data, the Employer is deemed to have
delayed the start of the relevant activities, and this will be a
compensation event.
39. Variations :
39.1 All Variations shall be included in updated programmes
and Activity Schedule produced by the Contractor.
40. Payments for Variations :
40.1 The contractor shall provide the Engineer with a quotation
(with breakdown of unit rates) for carrying out the Variations
when requested to do so by the Engineer. The Engineer shall
assess the quotation, which shall be given within 7 days of the
request or within any longer period stated by the Engineer and
before the Variations is ordered.
40.4 If the Engineer decides that the urgency of varying the
work would prevent a quotation being given and considered
without delaying the work, no quotation shall be given and the
Variation shall be treated as a Compensation Event.
48. Retention :
6/34
901 ARBPs 1158.14,256.15.doc Dusane
48.1 The Employer shall retain from each payment due to the
Contractor, the proportion stated in the Contract Data until
completion of the whole of the Works.
48.2 On completion of the whole of the Works, half the total
amount retained is repaid to the Contractor and half when the
Defects Liability Period has passed and the Engineer has
certified that all Defects notified by the Engineer to the
Contractor before the end of this period have been corrected.
11. Before deciding each claim, the law governing interference under
Section 34 with an arbitral award passed by a technical expert may be noted
from the judgment of Hindustan Construction Company Limited v. National
Highways Authority of India1,wherein the Supreme Court observed as under:
“25. This Court in Voestalpine Schienen GmbH v. DMRC2
commenting on the value of having expert personnel as
arbitrators, emphasised that "technical aspects of the dispute
are suitably resolved by utilising their expertise when they act
as arbitrators". Such an approach was commended also in
Delhi Airport Metro Express (P) Ltd. v. DMRC3 wherein this
Court held that: (Delhi Airport Metro Express case4, SCC p.
155, para 41)
"41. The members of the Arbitral Tribunal, nominated
in accordance with the agreed procedure between the
parties, are engineers and their award is not meant to
be scrutinised in the same manner as one prepared by
legally trained minds. In any event, it cannot be said
that the view of the Tribunal is perverse. Therefore,
we do not concur with the High Court's opinion21 that
the award of the Tribunal on the legality of the
termination notice is vitiated due to the vice of
perversity."
1 (2024) 2 SCC 613
7/34
901 ARBPs 1158.14,256.15.doc Dusane
26. The prevailing view about the standard of scrutiny
review, of an award, by persons of the disputants' choice being
that of their not judicial decisions to stand and not interfered
with, (save a small area where it is established that such a view
is premised on patent illegality or their interpretation of the
facts or terms, perverse, as to qualify for interference, courts
have to necessarily choose the path of least interference, except
when absolutely necessary). By training, inclination and
experience, Judges tend to adopt a corrective lens; usually,
commended for appellate review. However, that lens is
unavailable when exercising jurisdiction under Section 34 of
the Act. Courts cannot, through process of primary contract
interpretation, thus, create pathways to the kind of review
which is forbidden under Section 34.”
(ii) In the case of PSA Sical Terminals Private Limited v. Board of
Trustees of V.O. Chidambaranar Port Trust, Tuticorin & Ors.2, the Supreme
Court considered the scope of judicial interference with an arbitral award
under Section 34 of the Arbitration and Conciliation Act, 1996, and observed
as under:
40. It will thus appear to be a more than settled legal position,
that in an application under Section 34, the court is not
expected to act as an appellate court and reappreciate the
evidence. The scope of interference would be limited to
grounds provided under Section 34 of the Arbitration Act. The
interference would be so warranted when the award is in
violation of "public policy of India", which has been held to
mean "the fundamental policy of Indian law". A judicial
intervention on account of interfering on the merits of the
award would not be permissible. However, the principles of
natural justice as contained in Sections 18 and 34(2)(a)(iii) of
the Arbitration Act would continue to be the grounds of
challenge of an award. The ground for interference on the basis
that the award is in conflict with justice or morality is now to
2 (2023) 15 SCC 781
8/34
901 ARBPs 1158.14,256.15.doc Dusane
be understood as a conflict with the "most basic notions of
morality or justice". It is only such arbitral awards that shock
the conscience of the court, that can be set aside on the said
ground. An award would be set aside on the ground of patent
illegality appearing on the face of the award and as such,
which goes to the roots of the matter. However, an illegality
with regard to a mere erroneous application of law would not
be a ground for interference. Equally, reappreciation of
evidence would not be permissible on the ground of patent
illegality appearing on the face of the award.”
12. Claim No.1-
(i) Excavation of hard rock at Kulupwadi site, Rs.94,597.20.
This Claim is rejected.
Claim No.1-
(ii) Construction of UCR masonry wall at Shantidoot Site and is of
Rs.45,883.00.
. This Claim relates to the construction of UCR masonry wall at the
Shantidoot Site and is of Rs.45,883.00. The Petitioner objected to this Claim
on the ground that the same could not be claimed as an extra item. Claimant
had not shown the work to the Petitioner during the site visit nor demanded
any of the interim payment certificate or in final certificate, and that the
work was not certified by the Engineer.
. The learned Tribunal, however allowed the claim on the ground that
the existing compound wall collapsed due to heavy rains at site and the
Petitioner had directed the Respondent to construct the wall at the site again.
The item was not included in the tender and as such it is an extra amount of
9/34
901 ARBPs 1158.14,256.15.doc Dusane
Rs.45,883.00.
13. The learned Arbitrator has observed that the UCR masonry wall at the
Shantidoot Site, which was constructed in place of existing compound wall
had collapsed due to heavy rains at the site and that the Claimant had
thereafter completed the work. The Claimant submitted that, contrary to the
contention of the Petitioners, said work was not done as a variation, as there
was no description of the compound wall in the contract. The Arbitrator
observed that the construction of wall was an existing fact and the Employer
did not object for the construction of the wall, which was required to make
good the collapsed wall and though the Claimant did not have the written
approval of the Employer, since the work had been completed, as admitted
by the Respondent, and physically existing at the site, the claim merits
considerations and hence the claim amounting to Rs.45,883.00 is allowed.
14. Considering that the actual work had in fact been completed, and that
the same constitutes a measure ordinarily required to be undertaken and was
existing at the site, the claim allowed by the learned Arbitrator for Rs.
45,883.00 is a reasonable allowance towards the construction. Merely
because there appears to be a violation of Clause 44.04, and there is no
dispute regarding the necessity of the work, the award cannot be interfered
with. Since the entire work has been executed and the Tribunal has granted
10/34
901 ARBPs 1158.14,256.15.doc Dusane
the claim, it would not be permissible for this Court, in exercise of its
jurisdiction under Section 34 of the Arbitration and Conciliation Act, to
interfere with the same on any of the grounds available under Section 34.
. The Claim has been correctly decided and no case is made out to
interfere with.
15. Claim No.1- (iii) Providing and fixing individual tap to each W.C. of
the toilet block for Rs.1,78,500.00.
. The learned Tribunal observed that the drawing did not provide for
taps, nor were such taps mentioned in the specifications forming part of the
contract. Accordingly, the Respondents/Claimants placed an order for the
supply of taps at the negotiated rate of Rs. 1,050/- per tap. The learned
Tribunal further held that the contract did not obligate the
Respondents/Claimants to provide individual taps for each W.C. However,
since it subsequently became necessary to provide such taps, and the
Claimants accordingly supplied them, the Tribunal found the claim to be
reasonable and justified.
16. It is the submission of the learned counsel for the Petitioner-MCGM
that the provision of taps formed part of the contract. However, the Tribunal
has recorded a finding that the provision of taps was not included in the
original contract. The learned counsel for the Respondent/Claimant, in the
course of arguments, has also submitted that one of the reasons for the same
11/34
901 ARBPs 1158.14,256.15.doc Dusane
was that the tap was initially intended to be provided only outside the
common toilet block, as the provision of individual taps in each W.C. would
result in the taps being left open and thereby cause wastage of water.
Initially, it was contemplated that the persons using the toilets would carry
water collected in the tank situated outside the toilet block. Subsequently,
however, it was decided that each W.C. should have an individual tap.
Accordingly, taps were fixed in each of the toilets. In view of the aforesaid
facts and circumstances, the finding recorded by the Tribunal cannot be
interfered with in the exercise of appellate jurisdiction under Section 34 of
the Arbitration Act.
17. The finding of the Tribunal are that the original contract did not
provide for taps, and that taps were subsequently provided, thereby
justifying the claim, and the same cannot be interfered with in the Petition
under Section 34.
. The Claim has been correctly decided and no case is made out to
interfere with.
18. Claim No. 2 : Compensation towards revision of rates.
The compensation towards revision of rates for execution during the
extended period i.e. from 1st November 2002 to 31st December 2005 of
Rs.13,92,853.47. The said claim is allowed by the learned Tribunal.
12/34
901 ARBPs 1158.14,256.15.doc Dusane
. Learned counsel appearing for the Petitioner submits that the learned
Tribunal has erred in allowing the claim. It is contended that the Respondent,
by letter dated 7th February 2003, had sought an extension of time and
expressly stated that it would carry out the work at the same rates and on the
same terms and conditions as stipulated in the contract, without claiming any
compensation under the contract. It is further submitted that, relying upon
the said terms, the Petitioner granted an extension of time to the Respondent
on three occasions. In these circumstances, learned counsel contends that the
Arbitrator erred in allowing the said claim.
. The learned Tribunal has analysed the Petitioner’s contention that they
were required to hand over all the sites to enable the Claimant to commence
and proceed with the work. However, the Petitioner-MCGM were able to
hand over only five sites pursuant to their letter dated 12 th February 2001.
Even these sites were subsequently cancelled on 31st January 2002.
. Thereafter, the Petitioner-MCGM, vide letter dated 15 February 2001,
issued work orders in respect of five additional sites. Out of these, four sites
were subsequently cancelled on 28th June 2001 and 9th January 2002,
respectively. Further, two sites were handed over on 9 th May 2001 and 13th
July 2001. The Petitioner thus failed to hand over all the sites to the
13/34
901 ARBPs 1158.14,256.15.doc Dusane
Respondent-Claimant within the time contemplated, thereby preventing the
Claimant from proceeding with and completing the work as stipulated.
19. It is significant to note that the last site was handed over only on 15
September 2001 and, even thereafter, the said site was cancelled on 31 st
January 2002 for various reasons. Consequently, the Respondent-Claimant
was left with substantially reduced time to complete the work within the
stipulated period of 21 months, which was due to expire on 24th October
2002.
20. Clause 21.1 of the Contract provides that the Employer shall give
possession of all parts of the sites to the Contractors. It further provides that
if possession of any part is not given by the date stated in the Contract Data,
the Employer shall be deemed to have delayed the commencement of the
relevant activities, and such delay shall constitute a compensation event.
21. Further, by letter dated 23rd September 2002, the Respondent-Claimant
had informed the Petitioner as to how the delay was being caused in giving
possession of the sites in accordance with the Contract. The Respondent-
Claimant also stated therein that the undertaking given by them, to the effect
that the work on the alternative sites would be carried out at the rates
specified in the original contract, was withdrawn.
22. It is further noted that the method adopted for computing the excess
14/34
901 ARBPs 1158.14,256.15.doc Dusane
amount claimed is set out by the Tribunal in paragraph 10.79. It cannot be
said that the valuations have not been worked out appropriately by the
learned Arbitrator. The contention is that the higher rates could not have
been granted in view of the undertaking given. However, the Tribunal has
noticed the breach of contract as well as the withdrawal of the undertaking
during the subsistence of the contract. The increase granted is also marginal,
as the same is based on the prevailing SSR rates and determined on the basis
of the increase in costs for work executed in 2003, 2004 and 2005.
23. The challenge is essentially with regard to the consideration of the
escalation in the cost of raw materials and the natural increase in costs. The
Arbitrator has merely granted the amount towards such increase in cost.
. The Claim has been correctly decided and no case is made out to
interfere with.
24. Claim No. 3 : Compensation towards loss of interest due to delay in
payment of Rs.7,88,406/- - granted Rs.3,49,998/-
The Respondent-Claimant has submitted that its claim for interest is
based on Clause 43.1 of the Conditions of Contract, which provides that
payments shall be adjusted for deductions towards advance payments,
retention, other recoveries under the Contract, and taxes at source applicable
under law. Clause 43.1 further provides that the Employer shall pay the
Contractor the amount certified by the Engineer within 28 days from the
15/34
901 ARBPs 1158.14,256.15.doc Dusane
date of each certificate. In the event of delayed payment by the Employer,
the Contractor shall be paid interest on the delayed payment in the next
payment, calculated from the date on which the payment became due until
the date on which the delayed payment is actually made, at the rate of 12%
per annum.
25. The Respondent-Claimant has accordingly claimed interest on the
ground that the R.A. Bills were not cleared within 28 days from the date of
their submission. The Petitioner-MCGM, however, has contended that, in
terms of Clause 43.1, the period of 28 days is to be reckoned from the date
of certification of each R.A. Bill by the Engineer and not from the date of
submission of the bill by the Claimant.
26. The Petitioner-MCGM denied that the Claimant was entitled to make
any claim for compensation and submitted that, as per Clause 43.1 of the
Conditions of Contract, read with Clause 6 of the Special Conditions of
Contract, the Employer was under an obligation to pay the amount certified
by the Engineer within 28 days from the date of each certificate, and not
within 28 days from the submission of the bill, as contended by the
Respondent-Claimant. Learned counsel for the Petitioner-MCGM submitted
that, despite having received the advance payment, the Claimants
considerably delayed the commencement of the work. It was further
16/34
901 ARBPs 1158.14,256.15.doc Dusane
submitted that the Petitioner-MCGM had taken a liberal view of the matter
and had refrained from imposing any penalty for the breach committed by
the Claimants. It was also submitted that the Claimants had never made any
request for payment of interest, nor had they raised or included any such
demand in any of the Interim Payment Certificates or the Final Certificate.
Accordingly, the Petitoner-MCGM contended that it was not liable to make
any payment towards interest.
27. The learned Tribunal allowed the claim, observing that neither the
Respondents-Claimants nor the Petitioner-MCGM had furnished the dates
on which the R.A. Bills were certified by the Engineer. The learned Tribunal
further noted that Annexure-III to the Statement of Claim (“S.O.C.”)
contained complete particulars of the bills, including the bill numbers, bill
amounts, etc. It was also held that the Petitioner-MCGM had merely denied
the contents of the claim without furnishing any particulars or supporting
details to substantiate such denial. In the absence of any contrary material,
the learned Tribunal accepted the dates of submission of the bills as
furnished by the Respondents-Claimants for the purpose of determining the
period of delay and consequential interest. Accordingly, the learned Tribunal
awarded a sum of Rs. 3,49,998/- towards compensation for loss of interest
arising out of the delay in payment of the R.A. Bills. This Court finds no
17/34
901 ARBPs 1158.14,256.15.doc Dusane
error in the same.
. The Claim has been correctly decided and no case is made out to
interfere with.
28. Claim No. 4 : Compensation due to idle labour, staff, machineries etc.
Rs.77,07,468.00.
It is the contention of the Petitioner-MCGM that they have brought to
the notice of the Respondent-Claimant, on several occasions, the slow
progress of the work and asked the Respondent-Claimant to expedite the
work or face action under the provisions of the Contract. The claim also does
not fall under any of the conditions of Clause 44.1 and is not covered under
any Compensation Event. It is also submitted that the Contract is an item-
rate contract, and the grievance of the Respondent-Claimant that, due to non-
provision of sufficient sites, a claim for idle resources is being made.
29. It is further submitted that the Tribunal has failed to consider that, in
terms of the contract between the Respondent-Claimant and the Petitioner-
MCGM , the Respondent-Claimant will execute the said work at the same
work site and will not ask for compensation, and that the work would not
commence at the site on account of the failure of the N.G.Os. to convince
the slum dwellers. The Tribunal has noted that the Petitioner has not initiated
any action against the Claimants for not adhering to the programme
submitted by them, in spite of the provisions available in the contract for
18/34
901 ARBPs 1158.14,256.15.doc Dusane
levying liquidated damages. The Claimants were granted three extensions of
time after expiry of the original period without liquidated damages, which
would indicate that there was no fault on the part of the
Respondents/Claimants for not maintaining the progress of the work as per
the programme.
30. In terms of Clause 44.1(a), if the Employer does not give access to
any part of the Site as per the stated date in the Contract, it shall be a
Compensation Event. So also, Clause 44.2 provides that if a Compensation
Event would cause additional cost or would prevent the work from being
completed before the Intended Completion Date, the Contract Price shall be
increased and/or the Intended Completion Date shall be extended. The
Engineer shall decide whether, and by how much, the Contract Price shall be
increased and whether, and by how much, the Intended Completion Date
shall be extended.
31. Since the Petitioner-MCGM had granted an extension of time, it was
required to take into consideration the increased cost incurred in executing
the contract works. Accordingly, the additional expenditure incurred by the
Claimants towards idle labour, machinery, establishment, etc., was found to
be tenable by the learned Arbitrator. The Arbitrator, therefore, assessed the
charges towards labour, staff, machinery and establishment, setting out the
19/34
901 ARBPs 1158.14,256.15.doc Dusane
details of each component, which aggregated to Rs. 77,07,408.00, with the
following break-up:
a) Idle labour : Rs.19,78,250/-
b) Idle Staff : Rs. 9,60,350/-
c) Idle Machinery : Rs.27,25,700/-
d) Idle establishment : Rs.20,43,108/-
The grant is made in terms of the Chart given below :
Sr. Period Value of Compensation % of idle
No. W.D. (Rs.) towards idle charges on
labour the value of
claimed work done
1 Agreement period 12,69,894/- 7,50,100/- 59%
1.3.2001 to 1.10.2002
2 1st extension 69,13,000/- 2,94,310/- 4.25%
1.11.2002 to
31.12.2003
3 2nd extension 28,37,000/- 2,20,230/- 7.8%
1.1.2004 to
31.12.2004
4 3rd extension 11,54,000/- 7,13,610/- 61.8%
1.1.2005 to
31.12.2005
19,78,250.00
32. It has been held that the Petitioner-MCGM committed breaches of the
contract by failing to hand over proper sites for execution of the works
entrusted to the Claimants. To the extent that the sites were handed over, the
works were carried out in different spells over a period of 59 months, as
20/34
901 ARBPs 1158.14,256.15.doc Dusane
against the 21 months stipulated under the agreement. Consequently, the
Claimants were required to deploy labour for the execution of the works
over an extended period. Accordingly, the Tribunal proceeded to award the
claim after undertaking a detailed and voluminous examination of the matter.
. This Court finds no error in the same. The Claim has been correctly
decided and no case is made out to interfere with.
33. Claim No.5. : Compensation due to infructuous expenditure
incurred on appointment of N.G.O. due to certain sites becoming
infeasible later Rs.1,82,500/-:
. Learned counsel for the Petitioner-MCGM submits that the claim
arises out of the additional expenditure incurred in appointing an N.G.O. for
various sites, as contemplated under the contract. However, the sites made
available by the Petitioner-MCGM subsequently turned out to be infeasible,
thereby rendering the expenditure incurred by the Claimants infructuous.
Accordingly, the Claimants are entitled to recover the infructuous
expenditure so incurred, the consequences of which could not have been
reasonably foreseen at the time of incurring such expenditure.
. Learned Counsel for the Petitioner–MCGM submits that the
expenditure incurred by the Respondent–Claimant towards NGO/CBO
activities was not infructuous. Guideline A-2, sub-clauses (e) to (h), required
registration of the CBO, payment of the upfront contribution, and approval
21/34
901 ARBPs 1158.14,256.15.doc Dusane
of the layouts and drawings before construction could commence. The
Contract, therefore, compelled the Respondent-Claimant to incur such
expenditure before the feasibility of the sites could be ascertained. The
Petitioner subsequently cancelled the sites on the basis of the very reports
for which the Respondent-Claimant had incurred the expenditure and which
it had duly submitted. Accordingly, the Petitioner/MCGM submits that the
Respondent-Claimant is not entitled to claim the said expenditure as
infructuous.
. The learned Tribunal has rendered a finding that the Bidder was
expected to engage a non-governmental organisation for the purpose of
programme publicity, to create awareness about the programme and an
understanding among the community about the conditions to be satisfied to
qualify for participation in the programme, and to assess the interested slum
communities' willingness to pay an upfront contribution towards the
operation and maintenance of improved sanitation facilities. Twenty-two
sites were found to be infeasible for various reasons, such as the community
being interested in 10 seats, but the land being unsuitable; the toilet having
recently been repaired by the Corporation and, the people not being
interested; as well as political misunderstandings. The same was
communicated by the Respondent-Claimant to the Petitioner-MCGM.
22/34
901 ARBPs 1158.14,256.15.doc Dusane
. After carrying out the activities expected to be performed by the
NGO, the sites were thereafter not made available for the work. As such, the
cost incurred by the Respondents-Claimants towards expenditure on
engaging NGOs and undertaking the groundwork was allowed to the extent
of ₹1,82,000/-. There is no material to interfere with the finding that the
computation is ex facie erroneous. There is no error in the Tribunal granting
the claim.
. The Claim has been correctly decided and no case is made out to
interfere with.
34. Claim no. 6 : Interest due to delayed payment of Retention money :
. Learned counsel for the Petitioner-MCGM submits that the claim
arises out of the delay in returning the retention money, both in the form of
cash and bank guarantee. Learned counsel further submits that the Petitioner
had quoted its tender on the premise that the entire retention money would
be returned upon completion of the Defect Liability Period of 12 months,
following completion of the stipulated contract period of 21 months.
However, owing to the extension of the completion period from 21 months
to 60 months, the release and return of the retention money, both in the form
of cash and bank guarantee, were abnormally delayed, thereby necessitating
23/34
901 ARBPs 1158.14,256.15.doc Dusane
the payment of heavy interest charges.
. Learned counsel for the Petitioner-MCGM submits that the Claimants
had not submitted the MOU in respect of certain works and, consequently,
the bank guarantee was required to be extended. It is therefore contended
that the works could not be treated as completed and that the claim is wholly
misconceived.
. The Tribunal has observed that Clause 48.2 provides that, upon
completion of the whole of the work, half of the total amount retained is to
be repaid to the Contractor, while the remaining half is to be repaid after the
expiry of the Defect Liability Period and upon certification by the Engineer
that all defects notified by the Engineer to the Contractor before the expiry
of the said period have been duly rectified.
. Clause 48.3 further provides that, upon completion of the whole of the
works, the Contractor may substitute the retention money with an on-
demand Bank Guarantee (BG).
. The value of the work executed by the Claimant as on 31.12.2005 was
accordingly taken into consideration. Thus, half of the amount retained was
required to be paid to the Contractor upon completion of the whole of the
work, while the remaining half became payable after the expiry of the Defect
Liability Period, i.e., on 31.12.2006. There was a delay in making payment
24/34
901 ARBPs 1158.14,256.15.doc Dusane
of the said amounts. Accordingly, interest at the rate of 12% per annum was
awarded on the delayed payments, which worked out to Rs. 41,252.80. I find
no error in the aforesaid reasoning or in the award of interest.
. The Claim has been correctly decided and no case is made out to
interfere with.
35. Claim no.7 : Compensation towards extra cost incured towards
supplies made by B.S.E.S. Ltd. (Electricity Supply
Company Rs.56,111.00)
. Learned counsel for the Respondent-Claimant submits that the claim
arises out of the Petitioners’/MCGM’s failure to pay certain charges levied
by the Electric Supply Company towards the supply of service cables, GT
land, earthing charges, connection fees, etc. The Petitioner-MCGM was
required to make payment of the said charges pursuant to the demand notice;
however, they failed and neglected to do so, thereby compelling the
Claimants to make payment of the same, contrary to Condition No. 1 under
the General Specifications for Electrical Installation Works forming part of
the contract. It is further submitted that, although the Petitioner-MCGM had
initially paid the said charges, they subsequently recovered the amounts
from the Respondents-Claimants through deductions from their R.A. bills.
. Learned counsel for the Petitioner-MCGM submits that the
Petitioners-MCGM were liable to pay only the security deposit required for
25/34
901 ARBPs 1158.14,256.15.doc Dusane
obtaining the electricity connection from the electricity supply company,
whereas all other incidental charges were to be borne by the Claimants
themselves. The Petitioner-MCGM further submitted that, during the pre-bid
meeting, it was expressly clarified that the cost of the cables, meter, and the
connection from the meter room to the cabin would be borne by the
Contractor. The minutes of the said meeting form part of the contract and are
binding upon the parties.
. The learned Tribunal held that, as per the contract, the electrical
installation work, including the arrangement for supplying a connection to
the meter room, was the responsibility of the Petitioner/MCGM. Thereafter,
other electrical connections, such as providing the main switch, fuses,
MCBs, etc., were to be carried out as approved by the Engineer.
. It was further observed that the Claimant had made a provision of Rs.
30,000/- in respect of electrical works in each block, for each type of work,
towards other expenditure to be incurred as described in the General
Specifications for Electrical Installation Works. The said amount was
accordingly allowed by the Tribunal.
. The demand raised by the electricity supply company against the
Petitioner-MCGM was initially paid by the Claimants. Although the
Petitioner-MCGM had paid the charges, the same were subsequently
26/34
901 ARBPs 1158.14,256.15.doc Dusane
recovered from the running account (R.A.) bill. The Tribunal found that the
liability to pay the said charges was that of the Petitioner-MCGM and,
accordingly, awarded an amount of Rs. 37,000/-. No case is made out for
interference with the said findings under Section 34 of the Arbitration and
Conciliation Act, 1996.
. The Claim has been correctly decided and no case is made out to
interfere with.
36. Claim No. 8 : Compensation towards loss of profits and overheads
Rs.1,27,33,000/- :
. Learned counsel for the Respondents-Claimants submitted that the
present claim arises out of the loss suffered by the Claimants on account of
the Petitioners’-MCGM failure to permit the Respondent-Claimants to
execute the entire contracted work. It was further submitted that
approximately 40% of the work that was permitted to be executed was not
carried out within the original stipulated contract period, but during the
extended contract period, which ultimately extended to 59 months. The
Claimants, therefore, contend that the Respondents are liable to compensate
them for the losses suffered on this account.
. Learned counsel for the Petitioner-MCGM denied the submissions,
contending that the contract was admittedly based on a demand-based
programme and, therefore, the quantum of work could not be ascertained in
27/34
901 ARBPs 1158.14,256.15.doc Dusane
advance. It was further submitted that it was the obligation of the NGO
appointed by the Respondent-Claimants to create awareness among the
public regarding S.S.P., generate demand, and facilitate the formation of
C.B.Os. The Petitioner-MCGM permitted the Respondents-Claimants to
utilise the funds in the P/North Ward during the extended period, subject to
the same terms and conditions as stipulated in the contract.
. The learned Tribunal considered 15% of the value of the work that
could not be executed, amounting to Rs.212 lakhs, as a reasonable measure
of loss of profit. Accordingly, the claim towards loss of profit, quantified at
Rs. 31.80 lakhs, was allowed.
. The Claim has been correctly decided and no case is made out to
interfere with.
37. Claim No.9 : Compensation towards miscellaneous expenses,
Rs.7,82,050/- :
. Learned counsel for the Respondent-Claimants submits that the
various expenses like (a) Consultation charges, (b) Diesel and Petrol charges
for inspection vehicles, (c) Telephone, Fax, Mobile etc. charges, (d)
Emergency Repairs required to be carried out to machineries, (e) Medical
expenses, (f) Insurance Charges, (g) Electric & Water charges and (h) Other
Miscellaneous Charges.
. Learned Counsel for the Petitioner-MCGM submitted that any such
28/34
901 ARBPs 1158.14,256.15.doc Dusane
expenses alleged to have been incurred by the Respondents-Claimants are
part of the rates quoted by the Respondents-Claimants and are not separately
payable.
. Learned Tribunal held that the Respondents-Claimants are not
justified to claiming this amount and rejected the claim.
. The Claim has been correctly decided and no case is made out to
interfere with.
38. Claim No.10 – Compensation towards expenses incurred towards
appointment of Sole Arbitrator Rs.75,000.00 :
. The learned Tribunal granted Rs.50,000.00 on the ground that
Petitioner-MCGM failed to follow the contractual obligation and neglected
to settle the genuine claim, disputes and differences of the Respondents-
Claimants as per Clause 3.1(d) of Special Condition of Contract which states
that the expenses incurred by each party in connection with preparation,
presentation, etc. shall be borne by each party itself. However, the fees and
expenses paid to the Arbitrator appointed shall be shared equally by both the
parties.
. The Claim has been correctly decided and no case is made out to
interfere with.
39. Claim No. 11 – Compensation towards loss of interest on due amounts
as per above claims :
29/34
901 ARBPs 1158.14,256.15.doc Dusane
. Learned counsel for the Claimant/Respondent submits that this claim
is arising out of interest on amounts claimed and not paid by the Petitioners-
MCGM and that is claimed from the due dates considered for each of the
claims from 1 to 9 till the actual date of payment for the ante-lite, pendent-
lite and post-pendent-lite.
. Learned counsel for the Petitioner-MCGM submitted that since no
amount is due to be paid to the Claimants, question of payment of interest
does not arise and that the claims for interest made are prior to 3 years of
invoking the Arbitration clause and are hopelessly barred by law of
limitation.
. The learned Tribunal held that the Respondent-Claimant submitted the
claim towards loss of interest on due amount. The submission of the
Petitioner-MCGM that no payment is due to be paid to the Respondent-
Claimant is considered untenable in as much as analysis made earlier with
reference to each claim. The learned Tribunal considers it appropriate to
allow the interest @ 12% and accordingly awards interest @ 12% on the
amounts awarded on all the claims, from the date of final bill i.e. 28 th
February 2008 till the date of the Award.
. The Claim has been correctly decided and no case is made out to
30/34
901 ARBPs 1158.14,256.15.doc Dusane
interfere with.
40. Claim No. 12 : Cost of Arbitration Rs.10,00.000/- :
. Learned counsel for the Respondent-Claimant submits that this claim
is arising out of the extra expenses required to be incurred on account of
arbitration process, which was thrust upon them and that this at present
tentative, on the probable expenditure which is likely to be incurred by them
and they crave leave to amend this claim amount at the end of arbitration
proceedings, on the basis of actual expenditure incurred by them.
. Learned counsel for the Petitioner-MCGM submitted that since the
proceedings filed by the Respondents-Claimants are totally false and
frivolous, they are not liable to pay any amount towards the alleged cost of
Arbitration and that in Clause 3.1(d) of the Special Conditions of Contract, it
is clearly provided that the expenses incurred by each party in connection
with preparation, presentation etc. of its proceedings, shall be borne by each
party itself and that is further provided that the fees and expenses paid to the
Arbitrator shall be shared equally by both the parties and submitted that the
claim is liable to be rejected.
. The learned Tribunal held that as per Sub-Clause 4 (c) of Clause 7 of
Arbitration and Conciliation Act, the Arbitration Agreement deem to have
been made when an exchange of statements and defence in which the
31/34
901 ARBPs 1158.14,256.15.doc Dusane
existence of the agreement allegedly by one party and not denied by the
other. In as much as the Arbitration clause is invoked by the Respondent-
Claimant which has been agreed to by the Petitioner-MCGM in the present
case, no question of considering that the Arbitration has been thrust upon the
Respondent-Claimant and as such he cannot claim any amount so claimed.
Hence, the claim is rejected. Accordingly, the learned Tribunal has not
awarded cost to either party, the cost of Arbitration proceedings and the fee
of the Arbitrator is borne by both the parties on 50:50 basis. No case is made
out for interference.
41. The arguments regarding the alleged overlapping of claims,
particularly in respect of idle charges and revision of rates, are
misconceived. The revision of rates pertains to the cost of executing the
work and constitutes a price claim in respect of the work actually executed.
In contrast, idle charges relate to the costs incurred towards labour, staff,
machinery and other resources that remained available at the site but could
not be utilised, or were under-utilised, due to circumstances beyond the
Respondent/claimant’s control. Thus, the two claims arise from distinct
heads of loss and compensate for different consequences. The revision of
rates compensates for the increased cost of executing the work, whereas idle
charges compensate for the resources that remained idle or under-utilised
32/34
901 ARBPs 1158.14,256.15.doc Dusane
during the relevant period. Accordingly, there is no overlap between the two
claims, and both are independently recoverable.
42. The Tribunal has awarded compensation under different heads and at
different rates. In particular, the Tribunal has awarded compensation towards
idling charges for the extended period required to complete the works at the
sites. Separately, it has awarded compensation towards loss of profits. Thus,
there is no overlap between the respective claims, as they pertain to distinct
heads of compensation, and the Tribunal has correctly treated them as such.
43. As held by the Supreme Court in the judgment of Associate Builders
V. Delhi Development Authority3, the limited scope of Judicial interference
under Section 34, at paragraph 33 is noted below :-
“33. It must clearly be understood that when a court is
applying the "public policy" test to an arbitration award, it
does not act as a court of appeal and consequently errors of
fact cannot be corrected. A possible view by the arbitrator on
facts has necessarily to pass muster as the arbitrator is the
ultimate master of the quantity and quality of evidence to be
relied upon when he delivers his arbitral award. Thus an award
based on little evidence or on evidence which does not
measure up in quality to a trained legal mind would not be
held to be invalid on this score 17. Once it is found that the
arbitrators approach is not arbitrary or capricious, then he is
the last word on facts. In P.R. Shah, Shares & Stock Brokers
(P) Ltd. v. B.H.H. Securities (P) Ltd. 18, this Court held: (SCC
pp. 601-02, para 21).”
. Thus, once the quantum of compensation awarded by the Tribunal is
3 (2015) 3 SCC 49
33/34
901 ARBPs 1158.14,256.15.doc Dusane
found to be reasonable, free from patent illegality, and within the terms of
the contract, the same cannot be interfered with in a petition under Section
34 of the Arbitration and Conciliation Act, 1996. Accordingly, no case for
interference with the impugned order is made out.
44. Learned counsel submitted that the claims in both petitions, i.e.
Arbitration Petition No. 1158 of 2014 and Arbitration Petition No. 256 of
2015, are identical, and that the contracts and claims therein are also
identical. The difference in the amounts awarded is attributable to the
respective allotment of the sites. Since the principal issues involved are
similar, no separate arguments were advanced in respect of the second
petition. In view of the same, no case is made out for interference in the
second petition also.
45. The Arbitration Petitions stand dismissed.
46. In view of dismissal of the Arbitration Petitions, Notice of Motion
does not survive, the same is also disposed of.
47. Learned counsel appearing for the Petitioner prays for a stay of the
order passed today. However, as the Award is in favour of the Claimant and
the challenge thereto has also been dismissed, the prayer for stay of the order
is rejected.
(ARUN R. PEDNEKER, J.)
BHALCHANDRA
GOPAL DUSANE
34/34
901 ARBPs 1158.14,256.15.doc Dusane