Bombay High Court
THE EXECUTIVE ENGINEER, LOWER DUDHANA PROJECT DIVISIONversusMANORAMABAI MAHAVEERPRASAD KALA AND ORS
- Disposal
- DISPOSED OFF
- Bench
- SANJAY A DESHMUKH
Holding
The application for stay was dismissed as infructuous because of the lapse of time.
Summary
The Executive Engineer, Lower Dudhana Project Division filed a first appeal against Manorambai Mahaveer Prasad Kala and others. An application for a stay of the proceedings was also filed, relating to events that occurred in 2011. The court noted that more than fifteen years had elapsed since the year in question. It held that the passage of such a long period rendered the application infructuous. Consequently, the application for a stay was disposed of. The matter was adjourned for final hearing on 16 June 2026.
Issues considered
- Whether the application for stay of proceedings filed in 2011 can be entertained after more than fifteen years
Subjects
- stay of proceedings
- limitation period
- procedural delay
- civil procedure
Judgment
(1) 949 2064.12
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD
949 FIRST APPEAL NO. 2064 OF 2012
WITH CIVIL APPLICATION NO. 15828 OF 2011
THE EXECUTIVE ENGINEER, LOWER DUDHANA PROJECT DIVISION
VERSUS
MANORAMABAI MAHAVEER PRASAD KALA AND ORS
…..
Advocate for Appellant : Mr. Chawre Anand
AGP for Respondents/State : Mrs. Chaitali Choudhari Kutti
…..
CORAM : SANJAY A. DESHMUKH, J.
DATE : 12.06.2026
P.C.:-
1. Filing of the paper book is dispensed with. Learned advocate for
the appellant is absent.
2. Stand over to 16.06.2026 for final hearing.
Application for Stay:
3. The application has become infructuous, as it pertains to the year
2011 and more than 15 years have passed since then. There is no point in
keeping this application pending. Therefore, the application for grant of stay
is therefore disposed of.
[SANJAY A. DESHMUKH, J.]