The court condoned the 42‑day delay and granted an ad‑interim stay subject to deposit of the award amount.
Summary
The Oriental Insurance Company filed an application seeking condonation of a 42‑day delay in filing its first appeal, alleging administrative exigency. The court examined the application and found the delay was neither deliberate nor intentional, granting condonation in the interest of justice. The same application also sought an ad‑interim stay of the execution of the impugned judgment and award, conditioned upon the appellant depositing the full award amount with the registry within twelve weeks. The court ordered the delay to be condoned and granted the stay, subject to the deposit condition, with a warning that the stay would be vacated if the deposit is not made. Notices were issued to the respondents, and the applications were disposed of accordingly.
Issues considered
- Whether a delay of 42 days in filing the first appeal can be condoned.
- Whether an ad‑interim stay of execution should be granted pending deposit of the award amount.
Subjects
- condonation of delay
- first appeal
- stay of execution
- civil procedure
- insurance
Judgment
19 CA NO. 2454 OF 2026.odt
IN THE HIGH COURT OF JUDICATURE OF BOMBAY
BENCH AT AURANGABAD
19 CIVIL APPLICATION NO. 2454 OF 2026
IN FAST/4571/2026
The Oriental Insurance Company Ltd., T/h Divisional Manager,
Nanded
VERSUS
Rajani Bhagwan Athwale And Others
...
Mr. Malte Uday Shrikant, Advocate for Applicant
WITH
CIVIL APPLICATION NO. 2455 OF 2026
IN FAST/4571/2026
….
CORAM : SANJAY A. DESHMUKH, J.
DATE : 04.03.2026
PER COURT :-
APPLICATION FOR DELAY
1. Heard.
2. This is an application for condonation of delay of 42
days caused in filing the first appeal.
3. Perused the application. For the reasons stated
therein, it appears that the delay is occasioned on account of
administrative exigency. Hence, sufficient cause is made out to
condone the delay. The application deserves to be allowed in the
interest of justice as the delay is neither deliberate nor intentional.
1 of 3
(( 2 )) 19 CA NO. 2454 OF 2026
Hence, the following order:
::ORDER::
a. Civil Application is allowed.
b. The delay of 42 days caused in filing the first appeal is
condoned.
c. The application is disposed of.
FIRST APPEAL
1. Issue notice to the respondents, returnable on
24.06.2026.
2. Call Record and Proceedings.
APPLICATION FOR STAY
1. This is an application seeking stay to the execution and
operation of the impugned judgment and award.
2. Issue notice to the respondents, returnable on 24.06.2026.
3. Till then, there shall be ad-interim-stay to the execution and
operation of the impugned judgment and award on condition that
appellant shall deposit the entire amount under impugned judgment
and award with the Registry of this Court within twelve weeks from
today.
2 of 3
(( 3 )) 19 CA NO. 2454 OF 2026
4. If the award amount is not deposited within the stipulated
period, ad-interim-stay granted by this Court shall be vacated without
further reference to this Court.
[ SANJAY A. DESHMUKH, J. ]