Bombay High Court
RAMDAS AMBADAS DHATBALE AND ANOTHERversusTHE STATE OF MAHARASHTRA THROUGH, LAND ACQUISITION OFFICER, SDO OFFICE, KANNAD, AURANGABAD AND ANR
- Disposal
- Admitted/Allowed/Granted/Rule Absolute
- Bench
- SHAILESH P BRAHME
Holding
The delay is condoned on the condition that the appellants shall not be entitled to interest or statutory benefits for the delayed period and lapses.
Summary
The appellants, Ramdas Ambadas Dhatbale and another, filed a civil application seeking condonation of a 1,706‑day delay in preferring their first appeal against orders of the Land Acquisition Officer, State of Maharashtra. The court noted that the delay was largely attributable to the appellants and that there was no malafide intent. It was held that the delay could be condoned provided the appellants would forfeit any interest and statutory benefits accruing during the delayed period and the period of lapses. The State’s Advocate General and the counsel for the second respondent both waived service of notice. The court ordered that the record and proceedings be called from the concerned court and dispensed with printing the order. Consequently, the civil application for condonation was allowed subject to the stipulated conditions.
Issues considered
- Whether the court should condone a delay of 1,706 days in filing the first appeal.
- Whether the appellants should be entitled to interest and statutory benefits for the period of delay and lapses.
Subjects
- condonation of delay
- first appeal
- interest
- statutory benefits
- service of notice waiver
- land acquisition
- civil procedure
Judgment
1 22-CA.407-23.odt
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD
22 CIVIL APPLICATION NO. 407 OF 2023
IN FAST/18234/2022
RAMDAS AMBADAS DHATBALE AND ANOTHER
VERSUS
THE STATE OF MAHARASHTRA THROUGH, LAND
ACQUISITION OFFICER, SDO OFFICE, KANNAD,
AURANGABAD AND ANR
...
Advocate for Applicants : Mr. Pahune Patil Nandkishor J.
AGP for Respondent/s-State : Mr. S. V. Hange.
Advocate for Respondent No.2 : Ms. Vaishali S. Swami h/f Mr.
Swami Mahesh C.
...
CORAM : SHAILESH P. BRAHME, J.
DATE : 13.01.2026
PER COURT :-
1. Heard both sides.
2. Applicants seek condonation of delay of 1706 days in
preferring first appeal. The averments of the application have
not been controverted. The applicants are ready to give up
interest and statutory benefits. I find no malafides on part of
the applicants. It is desirable to condone the delay. It also
reveals that application for condonation of delay was not
circulated in time. The first order was solicited on 27.01.2023
The lapses from 11.07.2022 to 27.01.2023 are attributable to
the applicants. The delay stands condoned on condition that
2 22-CA.407-23.odt
applicants shall not be entitled to interest and statutory
benefits for the delayed period as well as for the period of
lapses.
3. Civil application is allowed.
First Appeal
4. Admit.
5. Learned AGP waives service of notice for the
respondent/State. Learned counsel Mr. Swami waives service
of notice for respondent No.2.
6. Call for Record and Proceedings from the concerned
Court.
7. Print is dispensed with.
8. Appellants shall not be entitled to interest and the
statutory benefits for the delayed period as well as for the
period of lapses.
(SHAILESH P. BRAHME, J.)
...
vmk/-