The court condoned the 202‑day delay and permitted the amendment of the application.
Summary
The applicant sought to bring the legal representative of the deceased Vivek Gurushantappa Lature into a cross objection and filed a related civil application. The court noted a delay of 202 days in filing the application. It considered whether such delay could be condoned under procedural law. The court held that the delay was condonable and allowed the amendment of the application, directing that it be effected within a week. The matter was also ordered to be listed with related applications on 14 July 2026.
Issues considered
- Whether a delay of 202 days in filing a civil application for cross objection can be condoned
- Whether the amendment of the application is permissible after condoning the delay
Subjects
- civil procedure
- condonation of delay
- amendment of application
- cross objection
- legal representative
Judgment
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD
8 CIVIL APPLICATION NO. 6921 OF 2026 IN FA/33/2012
WITH
X-OBJECTION (STAMP) NO. 4478 OF 2013 IN FA/33/2012
WITH
CIVIL APPLICATION NO. 5826 OF 2017 IN FA/33/2012
VIVEK GURUSHANTAPPA LATURE DEAD THR HIS LEGAL REPR. SAMPADA
AND ORS.
VERSUS
UNION OF INDIA THR DY CHIEF ENGINEER (CONSTRUCTION) CENTRAL
RAILWAY PUNE AND ANR.
...
Advocate for Applicant : Mr. C.V. Borse h/f. Mr. V.B. Patil
AGP for Respondent/State : Mr. S.S. Dande
Advocate for Respondent 1 : Mr. A.D. Soman
...
CORAM : SIDDHESHWAR S. THOMBRE, J.
Dated : July 07, 2026
PER COURT :-
1. In civil application filed for bringing the legal representative of
deceased Vivek Gurushantappa Lature in cross objection and the civil
application therein, for the reasons stated in the application, the
application is allowed by condoning delay of 202 days caused in filing the
application. Amendment be carried out within a period of one week from
today.
2. List the matter along with FA Nos. 33, 34 and 35 of 2012 on
14.7.2026.