The ad‑interim relief stands confirmed.
Summary
The Executive Engineer, Majalgaon Canal Division, filed a civil application seeking relief against Govind Baburao Katare and others. The dispute arose from a land acquisition proceeding where an award amount was payable by the acquiring body. The acquiring body deposited the entire award amount, prompting the court to consider whether the ad‑interim relief previously granted should continue. The court held that, since the award has been fully paid, the ad‑interim relief remains in force. Consequently, the civil application was disposed of.
Issues considered
- Whether the ad‑interim relief granted earlier should stand confirmed after the acquiring body has deposited the entire award amount.
Subjects
- land acquisition
- award deposit
- interim relief
- civil application
- high court
Judgment
2026:BHC-AUG:839
1 942 ca 7772.23
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD
CIVIL APPLICATION NO. 7772 OF 2023
IN
FIRST APPEAL NO. 4223 OF 2023
The Executive Engineer, Majalgaon
Canal Division No. 10 Parbhani
Jayakwadi Vasahat Parbhani .. Applicant
Versus
Govind Baburao Katare and others .. Respondents
Shri Vinayak P. Narwade, Advocate for the Applicant.
Shri Ramchandra J. Nirmal, Advocate for the Respondent No. 1.
Shri S. V. Hange, A.G.P. for the Respondents/State.
CORAM : SHAILESH P. BRAHME, J.
DATE : 08TH JANUARY, 2026.
FINAL ORDER :
. As the entire amount under the award has been deposited
by the acquiring body, ad-interim relief granted earlier shall
stand confirmed. The civil application is disposed of.
[ SHAILESH P. BRAHME J. ]