Created by Fuzzy Cloud

Bombay High Court

SHAILESH MANILAL SHETH AND ANR.versusNANASAHEB SHANKARDAS MUKADAM

Decided
Disposal
Allowed

Holding

The court allowed the interim application to record the legal heirs and ordered the civil revision to be heard on 24 August 2026, permitting reconstruction subject to conditions.

Summary

Nanasaheb Shankardas Mukadam filed a civil revision against Shailesh Manilal Sheth and others. An interim application was filed to record the legal heirs of a deceased respondent, which faced no objection and was allowed. The respondents also filed a civil application seeking permission to reconstruct a 134 sq.ft. structure as directed by the trial and appellate courts, subject to an undertaking and at their own cost. The court, by consent, fixed the final hearing of the civil revision for 24 August 2026 and directed the parties to file short synopses by 17 August 2026. The interim application was granted and the matter was scheduled for further hearing.

Issues considered

  • Whether the interim application to record the legal heirs of the deceased respondent can be allowed.
  • Whether the respondents may be permitted to reconstruct the structure as per trial and appellate court directions.
  • Whether the civil revision application should be fixed for a final hearing.

Subjects

  • civil revision
  • interim application
  • legal heirs
  • reconstruction of structure
  • court procedure

Judgment

                       KVM
                                                          1/3
                                                                              18 - CRA 39 OF 2009.doc



          Digitally
          signed by
          KANCHAN
                                  IN THE HIGH COURT OF JUDICATURE AT BOMBAY
KANCHAN   VINOD
VINOD     MAYEKAR
MAYEKAR   Date:
          2026.07.30
          15:04:08
          +0530
                                          CIVIL APPELLATE JURISDICTION

                                    CIVIL REVISION APPLICATION NO. 39/2009
                                                  ALONGWITH
                                       INTERIM APPLICATION NO. 522/2019
                                                      IN
                                    CIVIL REVISION APPLICATION NO.39/2009

                       NANASAHEB SHANKARDAS MUKADAM                       ….. APPLICANT

                             VS

                       SHAILESH MANILAL SHETH & ORS.                      ….. RESPONDENTS

                                                   ALONGWITH
                                         CIVIL APPLICATION NO. 123/2019
                                                       IN
                                     CIVIL REVISION APPLICATION NO.39/2009

                       SHAILESH MANILAL SHETH & ANR.                      ….. APPLICANT

                       IN THE MATTER BETWEEN

                       NANASAHEB SHANKARDAS MUKADAM                       ….. APPLICANT

                             VS

                       SHAILESH MANILAL SHETH & ORS.                      ….. RESPONDENTS

                       Adv. Vishwali V. Botle h/f. Adv. A. R. Gole for the Applicant in
                       IA/522/2019 and CRA/39/2009.

                       Adv. R. D. Soni i/b. Adv. V. R. Kasle for the Respondents.

                                                       CORAM : RAJESH S. PATIL, J.

                                                       DATE     : 27 JULY, 2026
KVM
                                   2/3
                                                           18 - CRA 39 OF 2009.doc


P.C. :-

INTERIM APPLICATION NO. 522/2019

1)           This interim application has been filed to bring on record

the legal heirs of the deceased respondent no.1.

2)           Mr.Soni, learned counsel appearing for the respondents

has no objection if this interim application is allowed.

3)           In view of the statement made by Mr.Soni, this interim

application is allowed in terms of prayer clauses (a) and (b).

4)           Amendment to be carried out within a period of two

weeks.

CIVIL APPLICATION NO. 123/2019 ALONGWITH CIVIL REVISION
APPLICATION NO. 39/2009


5)           This civil application is filed by the respondents seeking

prayer to permit them to reconstruct the structure of 134 sq.ft. in

accordance with the directions given by the Trial Court and as

confirmed by the Appellate court, at his cost, subject to filing an usual

undertaking.

6)           In the alternate, a prayer is made that the civil revision

application be fixed for final hearing.

7)           By consent, let civil revision application to come up for

final hearing on 24 August, 2026 at 3:00 p.m.
KVM
                               3/3
                                                  18 - CRA 39 OF 2009.doc


8)         The parties are free to file short synopsis alongwith

proposition of law   and the judgments relied upon by them by 17

August, 2026 and exchange copies amongst themselves.



                                        [RAJESH S. PATIL, J.]


Continue reading with your account

Sign in to read the full judgment. It’s free.

Sign in to read

Checking your session…

For a signed copy suitable for filing, refer to the court's website.