Bombay High Court
Umesh SarkarversusKEC International Limited
- Decided
- Disposal
- DISPOSED OFF
- Bench
- ARIF S DOCTOR
Holding
The Court held that, under Section 29-A, a time extension may be granted when the petitioner demonstrates progress and there is no opposition, and therefore allowed the extension.
Summary
The petitioner, Umesh Sarkar, filed a Commercial Arbitration Petition under Section 29-A of the Arbitration and Conciliation Act, 1996, seeking an extension of the mandate of the sole arbitrator in the pending arbitration. The petition asserted that this was the first request for an extension and that substantial progress had already been made in the arbitration proceedings. The respondent, Kec International Limited, did not oppose the extension. The Court examined whether the statutory provision allowed a time extension without opposition. Finding no procedural impediment and noting the progress made, the Court granted the extension. The order extended the arbitration timeline from the date the order was uploaded.
Issues considered
- What is the scope of Section 29-A of the Arbitration and Conciliation Act, 1996 regarding the extension of an arbitrator's mandate?
- Is the absence of opposition from the respondent sufficient for the Court to grant an extension?
Legislation cited
- Arbitration and Conciliation Act, 1996 — s. 29-A
Subjects
- Arbitration
- Extension of time
- Section 29-A
- Commercial arbitration
- High Court of Bombay
Judgment
1/1 23-CARBP-736-2026 (OS).DOC
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION
COMMERCIAL ARBITRATION PETITION NO. 736 OF 2026
Umesh Sarkar ...Petitioner
Versus
Kec International Limited ...Respondent
_______
Ms. Gayatri Devendra i/b Lalit Jain, for the Petitioner.
Mr. S. Kalbere a/w Mr. Anuj Athalye i/b Legasis Partners, for the Respondent.
_______
CORAM : ARIF S. DOCTOR, J.
DATE : 25th JUNE, 2026
P.C.
1. The captioned Petition is filed under the provisions of Section 29-A of the
Arbitration and Conciliation Act, 1996 for extension of the mandate of the
Arbitral proceedings pending before the learned Sole Arbitrator. I am informed
that this is the first extension for time and that substantial progress has been
made in the arbitration proceedings. There is no opposition to the time being
extended.
2. Hence, the Petition is allowed in terms of prayer clause (a).
3. Time is extended from the date on which a copy of this order is uploaded.
[ARIF S. DOCTOR, J.]