Bombay High Court
SHRI MEWALAL HIRALAL SHAHversusKALYAN-DOMBIVALI MUNICIPAL CORPORATION, THR. COMMISSIONER AND ORS.
- Decided
- Disposal
- Disposed Off
Holding
The Court held that no case was made out for contempt and therefore dismissed the contempt petition.
Summary
The petitioner, Mewalal Hiralal Shah, filed a contempt petition alleging that Kalyan Dombivali Municipal Corporation (KDMC) failed to reconstruct his shop according to the dimensions ordered by this Court in Writ Petition No. 6592 of 2013. The Court had directed KDMC to rebuild the shop within two months after demolition, matching the specifications set out in the writ petition. The petitioner claimed the newly built shop was smaller than the original and complained that KDMC officials did not act on his requests for improvements. The Court examined the petitioner's pleadings and found no specific details showing how the reconstruction deviated from the court‑ordered dimensions. It also noted that the petitioner had already received the court‑ordered compensation and had not filed a separate civil suit for additional damages. Consequently, the Court held that there was no basis to initiate contempt proceedings and dismissed the contempt petition.
Issues considered
- Did the respondents violate the court’s direction to reconstruct the shop as per the specified dimensions?
- Is there sufficient pleading to constitute contempt of court under the Contempt of Courts Act?
Legislation cited
Subjects
- contempt of court
- municipal corporation
- reconstruction order
- civil procedure
- compensation
Judgment
Digitally
signed by
RUSHIKESH
RUSHIKESH VISHNU
VISHNU PATIL
PATIL Date:
2026.08.07
18:33:28 1/3 5 CP.350.2018.odt
+0530
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION
CONTEMPT PETITION NO. 350 OF 2018
Mewalal Hiralal Shah .. Petitioner
Versus
Kalyan Dombivali Municipal Corporation
Through Its Commissioner and Ors. .. Respondents
…
Mr. Gauresh Khandalekar a/w Ms Mansi Mhatre, for the
Petitioner.
Mr. Ketan Joshi, ‘B’ Panel Counsel, for the State.
…
CORAM: BHARATI DANGRE &
MANJUSHA DESHPANDE, JJ.
DATED : 06th AUGUST, 2026
P.C:-
1. The Contempt Petition is >led alleging disobedience of the
directions issued by this Court in Writ Petition No. 6592 of
2013, when the Petition was disposed of with a direction to
reconstruct the structure of the shop of the Petitioner, which
was damaged while demolishing the structure erected by
Respondent No. 10 on the site, which was illegal. The direction
issued speci>cally was to the following effect:
“within a period of two months from the date of
demolition of the said structure, the >rst Respondent
shall reconstruct the structure of the shop of the
Petitioner as per the dimension set out in clause (d) of
paragraph 3 of the Petition.”
Rushikesh
2/3 5 CP.350.2018.odt
2. The Contempt Petition is >led based on the following
pleadings:
In the Petition, in paragraph (d), the Petitioner has given
the description of the shop as “Shop No. 4- area 35 X 10 (350
Sq. Ft.) including varhandas, front and back, being situated in
CTS No. 4122 of Kalyan, District-Thane. The shop had an A.C.
sheet roof with a height in front and back 8.5 ft. and a height
12 ft. in the middle, with a brick masonry structure with a
wooden door in front.
3. This Contempt Petition is >led alleging that the shop
which is constructed do not match the said speci>cations.
Therefore, we speci>cally asked the learned counsel for the
Petitioner to point out about his pleadings in the Contempt
Petition which would demonstrate that the Respondents have
violated the directions issued by this Court so as to construe
as contempt of the order of the Court, and our attention is
invited to the following pleading:
“aa) The Petitioner states that in the meanwhile when
reconstruction of the above said shop was in progress,
he visited the site and it was revealed to the Petitioner
that current area of the newly constructed shop was
less than of the shop before demolition. Therefore the
Petitioner continuously tried to contact one Mr. Dhute,
of>cer of KDMC for making improvements in said Shop
as it was before demolition but no steps were taken by
the respondents, other concerned Of>cers and
Contractor who is doing reconstruction of the said
shop.”
We persistently inquired with the learned counsel as to
what are the speci>cations of the newly constructed structure,
Rushikesh
3/3 5 CP.350.2018.odt
and the learned counsel is not able to provide any details
except stating that it is less than the shop which was earlier
standing. If this is the accusation on the basis of which the
Petitioner expect that we should initiate contempt action
against the Respondents, we refuse to do so, as for initiating an
action under the Contempt of Court Act, there ought to have
been a speci>c pleading by the Petitioner to the effect that
what is constructed is less than what was described by him in
clause (d) of the Writ Petition.
The learned counsel also make a grievance about his
machinery being damaged, and we note that the order passed
by the Court had directed payment of compensation of
Rs.2,00,000/- to the Petitioner, which amount the Petitioner
has already received. Apart from this, liberty was granted to
the Petitioner to >le a civil suit to recover compensation over
and above the amount granted under the Judgment and Order,
but we are informed that the Petitioner has not >led any such
proceedings.
4. On hearing the learned counsel for the Petitioner and
upon perusal of the pleadings, we are of the view that no case
is made out for initiating action against the Respondent-
Authorities for the alleged disobedience of the order passed by
this Court. Hence, we drop the Contempt proceedings.
(MANJUSHA DESHPANDE, J.) (BHARATI DANGRE, J.)