Bombay High Court
VATCHALABAI SHIVAJI MOREversusTHE STATE OF MAHARASHTRA AND OTHERS
- Disposal
- DISMISSED
Holding
The appeal is dismissed; no separate compensation for trees, well, bore‑well, pipeline or structure is awarded.
Summary
The appellant, Vatchalabai Shivaji More, challenged the award of a land acquisition proceeding where 2.82 hectares of irrigated land were taken for a storage tank. While accepting the market‑value rate fixed by the Reference Court (Rs 1,78,400 per acre), she sought separate compensation for fruit‑bearing trees, a well, bore‑well, pipeline and other structures, relying on private valuation reports. The respondents contested the reliability of those reports, pointing to discrepancies with revenue mutation records and the lack of detailed particulars. The High Court examined the material, noting the material discrepancy in the number of trees and the insufficiency of evidence for the claimed structures, and held that the Reference Court was justified in rejecting the separate compensation claims. Consequently, the appeal was dismissed, leaving the original award unchanged.
Issues considered
- Whether the private valuation reports establishing the existence and value of fruit‑bearing trees are reliable for awarding separate compensation.
- Whether separate compensation is payable for a well, bore‑well, pipeline and other structures when the land has already been treated as irrigated in determining market value.
- Whether the Reference Court erred in rejecting the appellant’s claims for additional compensation under Section 18 of the Land Acquisition Act.
Legislation cited
- Land Acquisition Act, 1894 — s. 11, 18, 4
Subjects
- land acquisition
- compensation
- valuation report
- fruit‑bearing trees
- irrigation facilities
- Section 4
- Section 11
- Section 18
- reference court
Judgment
2026:BHC-AUG:40821
31-FA-2133-2013.odt
1
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD
FIRST APPEAL NO. 2133 OF 2013
Vatchalabai Shivaji More
VERSUS
The State Of Maharashtra And Others
……
Mr. Manish P. Tripathi, Advocate for Appellant
Mr. A.D. Wange, AGP for Respondents No.1 and 2
Mr. S.S. Dande, Advocate for Respondent No.3
……
CORAM : SIDDHESHWAR S. THOMBRE, J.
DATE : 29 AUGUST, 2026
PER COURT :
1. Heard learned counsel Mr. Manish P. Tripathi for the appellant,
learned AGP Mr. A.D. Wange for respondent Nos.1 and 2-State and learned
counsel Mr. S.S. Dande for respondent No.3-Acquiring Body.
2. This appeal is preferred by the original claimant against the
Judgment and Award dated 02.02.2013 passed by the learned 2nd Joint
Civil Judge, Senior Division, Osmanabad in Land Acquisition Reference
No.446 of 2007. By the said Judgment and Award, the learned Reference
Court partly allowed the Reference and determined the market value of the
acquired irrigated land at the rate of Rs.1,78,400/- per Acre.
3. The land of the appellant admeasuring 2 Hectare 82 R from Survey
No.110, situated at village Lohagaon, Taluka Tuljapur, District Osmanabad,
was acquired for the purpose of construction of Lohagaon Storage Tank. The
31-FA-2133-2013.odt
2
notification under Section 4 of the Land Acquisition Act, 1894 was published
on 04.05.2000. The Special Land Acquisition Officer passed the award under
Section 11 of the Act on 17.03.2003 and awarded compensation at the rate
of Rs.46,000/- per Hectare, apart from compensation towards trees. The
appellant, being dissatisfied with the compensation awarded, accepted the
amount under protest and sought a reference under Section 18 of the Act.
4. Before the learned Reference Court, the appellant relied upon sale
instances and valuation reports and claimed enhanced compensation
towards the acquired land, fruit-bearing trees, well, pipeline and other
structures. The learned Reference Court, after considering the material
placed on record, determined the market value of the acquired irrigated
land at the rate of Rs.1,78,400/- per Acre. However, the claim for separate
compensation towards trees and structures was not accepted. Hence, the
present appeal.
5. Learned counsel Mr. Tripathi for the claimant submits that, insofar as
the compensation for the acquired land is concerned, the claimant is
accepting the rate determined by the learned Reference Court. He submits
that, in some other LARs, i.e., LAR No.447 of 2007 and connected LARs, the
rate of Rs.1,78,000/- per Acre determined by the learned Reference Court
has been confirmed by this Court vide its order dated 23.07.2026 passed in
First Appeal No.1904 of 2017 and connected matters. However, insofar as
the present appeal is concerned, the claimant is assailing the impugned
31-FA-2133-2013.odt
3
Judgment and Award to the extent that no compensation has been granted
towards the trees, structure and well.
6. As regards the trees, learned counsel for the appellant submits that
the existence of fruit-bearing trees is supported by the revenue record as
well as the valuation report. He submits that the valuer had inspected the
acquired land and had prepared the valuation report. The valuer was also
examined before the learned Reference Court. According to him, once the
valuation report was proved through the examination of the valuer, the
learned Reference Court ought not to have discarded it merely on the
ground that it was prepared by a private valuer. He submits that the
appellant was, therefore, entitled to compensation for the fruit-bearing
trees.
7. As regards the well, bore-well, pipeline and structure, learned
counsel submits that the appellant had placed on record the valuation report
of Mr. Ramchandra S. Baraskar. According to him, the said valuer had
inspected the acquired property and had valued the well, pipeline, bund and
bore-well on the basis of the D.S. rates applicable for the year 2000-2001.
He submits that the learned Reference Court has rejected the said claim
without assigning sufficient reasons. He further submits that the fact that
the acquired land was treated as irrigated land would not, by itself,
disentitle the appellant from claiming separate compensation for the well
and other irrigation facilities. In support of this submission, reliance is
31-FA-2133-2013.odt
4
placed upon the judgments of the Hon'ble Supreme Court in Ambya Kalya
Mahtra (D) by L.Rs. and Others v. State of Maharashtra, 2011 AIR SCW
5749 and Mahesh Dattatray Thirthkar v. State of Maharashtra, AIR 2009
Supreme Court 2238.
8. Learned counsel for the Acquiring Body and learned AGP oppose the
appeal. They submit that the valuation reports relied upon by the appellant
are not reliable and, therefore, cannot be accepted. As regards the trees,
they invite attention to the mutation entry and submit that the entry relied
upon by the appellant does not support the large number of trees
subsequently shown in the valuation report. According to them, mutation
entry No.1033 dated 15.01.1997 records only two mango trees, whereas the
valuation report subsequently records 101 mango trees, 5 tamarind trees
and 6 coconut trees. They, therefore, submit that there is a substantial
discrepancy between the contemporaneous revenue record and the
valuation report.
9. Learned counsel further submits that the valuation report of Mr. N.G.
Patil cannot be safely relied upon. According to him, the report is in a
prescribed format, with the particulars filled in the blank spaces, and the
valuer was not a Government registered valuer. It is further submitted that
the report records that the valuer inspected the land on 27.09.2000 and
submitted the report on 30.09.2000, whereas the other circumstances
appearing on record do not support the existence of the number of trees
31-FA-2133-2013.odt
5
claimed by the appellant. The Acquiring Body, therefore, submits that the
learned Reference Court was justified in rejecting the claim based upon the
said report.
10. As regards the claim towards well, bore-well, pipeline and structure,
learned counsel for the Acquiring Body submits that the learned Reference
Court has already treated the acquired land as irrigated land while
determining its market value. The existence of irrigation facilities was thus
taken into consideration while determining the value of the land. According
to him, the valuation report relied upon by the appellant is not sufficient to
establish the separate value claimed for the alleged structures. He, therefore,
supports the Judgment and Award.
11. I have considered the submissions advanced by the learned counsel
for the parties and the learned AGP. With their able assistance, I have gone
through the impugned Judgment and Award and the record and
proceedings.
12. At the outset, it is necessary to note that the appellant is not seeking
any further enhancement in the market value of the acquired land.
Therefore, the controversy in the present appeal is confined to the
appellant's claim for additional compensation towards trees, well, bore-well,
pipeline and structure.
13. As regards the claim for fruit-bearing trees, the principal material
31-FA-2133-2013.odt
6
relied upon by the appellant is the valuation report prepared by Mr. N.G.
Patil. The said report records that the valuer inspected the acquired land on
27.09.2000 and mentions 101 mango trees, 5 tamarind trees and 6 coconut
trees.
14. However, the said valuation report has to be considered in the light
of the other material on record. The respondents have relied upon mutation
entry No.1033 dated 15.01.1997. According to the respondents, the said
entry does not support the existence of 101 mango trees as subsequently
stated in the valuation report. Therefore, there is a material discrepancy
between the revenue entry relied upon by the respondents and the number
of trees mentioned in the valuation report.
15. There is another circumstance which affects the reliability of the
valuation report. The report itself states that the inspection was carried out
on 27.09.2000. The report does not furnish particulars such as the age of the
trees or other material particulars which would enable the Court to
independently assess the valuation of the alleged fruit-bearing trees. The
mere fact that the valuer was examined would not, by itself, make the
contents of the report conclusive. The Court is required to assess the report
along with the other evidence on record.
16. In the present case, considering the material discrepancy regarding
the number of trees and the absence of sufficient particulars in the valuation
31-FA-2133-2013.odt
7
report to establish their age, nature and value, the learned Reference Court
was justified in not placing reliance upon the said report for awarding
additional compensation towards trees. I, therefore, find no reason to take a
different view.
17. The claim towards well, bore-well, pipeline and structure also rests
principally upon the valuation report of Mr. Ramchandra S. Baraskar. The
said report is stated to have been prepared after inspection of the acquired
property and on the basis of the D.S. rates for the year 2000-2001.
18. In the present case, the learned Reference Court has considered the
material placed before it and has not accepted the valuation report as
sufficient proof for awarding separate compensation towards the well, bore-
well, pipeline and structure. Apart from the valuation report, no sufficient
material has been demonstrated before this Court which would justify
interference with that finding. The report itself, without satisfactory
supporting evidence regarding the existence and value of the individual
structures, cannot be treated as conclusive.
19. As regards the judgments relied by the learned counsel for the
appellant are concerned, it is also relevant that while determining the
market value of the acquired land, the learned Reference Court has treated
the land as irrigated. Thus, the irrigated nature of the land was taken into
consideration while determining its market value. In the facts of the present
31-FA-2133-2013.odt
8
case, the appellant has not demonstrated any error in the assessment made
by the learned Reference Court so as to warrant grant of further
compensation on the basis of the valuation report.
20. The authorities relied upon by learned counsel for the appellant,
therefore, do not assist the appellant in the facts and circumstances of the
present case. The entitlement to separate compensation would depend upon
the evidence establishing the existence and value of the particular assets. In
the present case, such evidence has not been found sufficient by the learned
Reference Court, and I see no perversity or error in that conclusion.
21. In view of the above discussion, I find that the appellant has failed to
demonstrate any error in the findings recorded by the learned Reference
Court in rejecting the claim for separate compensation towards the trees,
well, bore-well, pipeline and structure. The impugned Judgment and Award
does not warrant interference in the present appeal. Hence, the present
appeal deserves to be dismissed.
22. The First Appeal is, accordingly, dismissed.
23. Pending Civil Applications, if any, also stand disposed of.
[ SIDDHESHWAR S. THOMBRE ]
JUDGE
S P Rane
Checking your session…