Bombay High Court

NAVNEETDAS GULABDAS SHAH, L.RS. KUSUMBEN AND OTHERSversusTHE STATE OF MAHARASHTRA AND ANOTHER

Disposal
DISPOSED OFF

Holding

The Court held that the enhanced compensation rate of Rs 23,000 per acre applies to all portions of the land, with CIDCO liable for its acquisition and the State Government liable for the earlier acquisition, and the claimants are entitled to the statutory solatium and additional component.

Summary

The High Court of Bombay heard two first appeals and two cross‑objections arising from the same land‑acquisition proceedings for 4 acres and 8 acres in Garkheda, Aurangabad, originally awarded at Rs 7,500 per acre in 1980. The claimants sought a higher compensation and the acquiring body (CIDCO) challenged the enhancement granted by the reference court, which had fixed the market value at Rs 23,000 per acre. The Court noted that a portion of the land had earlier been acquired by the State Government for the Buildings & Communication Department, for which compensation remained unpaid. Relying on its earlier decision in First Appeal No. 332 of 2005, the Court held that the same enhanced rate applies to both acquisition proceedings and that the State Government, not CIDCO, must pay compensation for the land it had previously acquired. Consequently, the appeals were partly allowed, the award was modified to grant Rs 23,000 per acre plus statutory solatium and additional components, and the State was directed to pay the pending amounts.

Issues considered

  • Whether the enhanced market value of Rs 23,000 per acre determined in the reference court applies to the portions of land previously acquired by the State Government.
  • Whether CIDCO is liable to pay compensation for the land it acquired and the State Government liable for the land acquired earlier for the B & C Department.
  • Whether the claimants are entitled to statutory solatium and additional compensation under the 1984 amendment to the Land Acquisition Act.

Legislation cited

Subjects

  • land acquisition
  • compensation enhancement
  • solatium
  • additional component
  • statutory benefits
  • cross objection
  • CIDCO
  • B & C Department
  • 1984 amendment

Judgment

2026:BHC-AUG:42064
                                                                       908-FA-2674-2013.odt
                                                1


                       IN THE HIGH COURT OF JUDICATURE AT BOMBAY
                                  BENCH AT AURANGABAD
                              908 FIRST APPEAL NO. 2674 OF 2013
                         Navneetdas Gulabdas Shah (Since Deceased)
                     Through L.Rs. Kusumben Navneetdash Shah And Others
                                          VERSUS
                            The State Of Maharashtra And Another
                                            AND
                         X-OBJECTION NO. 136 OF 2023 IN FA/2674/2013

                            The State Of Maharashtra And Another
                                          VERSUS
                         Navneetdas Gulabdas Shah (Since Deceased)
                     Through L.Rs. Kusumben Navneetdash Shah And Others

                                            AND
                                FIRST APPEAL NO. 1287 OF 2014

                           Purushottamdas S/o. Gulabdas Shah (Died)
                     Through L.Rs. Hiraben Purushottamdas Shah And Others
                                            VERSUS
                             The State Of Maharashtra And Another

                                            AND
                         X-OBJECTION NO. 234 OF 2025 IN FA/1287/2014

                             The State Of Maharashtra And Another
                                            VERSUS
                           Purushottamdas S/o. Gulabdas Shah (Died)
                     Through L.Rs. Hiraben Purushottamdas Shah And Others

                                              ……
          Mr. Anand P. Bhandari, Advocate for Appellants-Claimants in FA/2674/2013
          and for Respondents in X-Obj/136/2023
          Mr. J.R. Shah, Advocate for Appellants-Claimants in FA/1287/2014 and for
          Respondents in X-Obj/234/2025
          Mr. A.M. Phule, AGP for Respondent No.1-State in Both FAs
          Mr. Shambhuraje V. Deshmukh, Advocate for Respondent No.2 in both FAs
                                              ……

                                         CORAM : SIDDHESHWAR S. THOMBRE, J.
                                         DATE       : 04 SEPTEMBER, 2026
                                                              908-FA-2674-2013.odt
                                     2

PER COURT :

1.    Heard learned counsel appearing for the respective parties.


2.    These First Appeals and Cross Objections arise out of the judgments

and awards passed by the learned Civil Judge, Senior Division, Aurangabad

in Land Acquisition Reference Nos. 172 of 1997 and 173 of 1997. Since the

appeals and cross objections arise out of the same acquisition, they are

heard together and are being disposed of by this common judgment and

order. The Cross Objections are filed by the Acquiring Body challenging the

enhancement granted by the learned Reference Court, whereas the First

Appeals are preferred by the claimants seeking further enhancement of

compensation.


3.    The lands belonging to the respective claimants, admeasuring 4 Acres

and 8 Acres out of Survey Nos. 11/1 and 11/3-1, situated at Garkheda,

Aurangabad, were acquired for the purpose of development of New

Aurangabad. The notification under Section 126 of the Maharashtra

Regional and Town Planning Act, 1966, read with Section 6 of the Land

Acquisition Act, 1894, was published on 16.10.1975. The Special Land

Acquisition Officer (SLAO) passed the award under Section 11 of the Land

Acquisition Act on 21.03.1980 and awarded compensation at the rate of

Rs.7,500/- per acre for the acquired lands. When the award was declared, 4

Acres of land belonging to the claimant in LAR No. 172 of 1997 (First

Appeal No. 2674 of 2013) were acquired. The claimants received the said
                                                                 908-FA-2674-2013.odt
                                        3

amount under protest by reserving their right to claim an enhanced amount

of compensation. Dissatisfied with the award, the claimants sought

references under Section 18 of the Land Acquisition Act.


4.    The learned Reference Court enhanced the market value to

Rs.23,000/- per acre. Being dissatisfied with the quantum of compensation

so awarded, the claimants as well as the Acquiring Body have preferred the

present appeals and cross-objections.


5.    Mr.   Shambhuraje    Deshmukh,        learned   counsel   appearing       for

Respondent No. 2–Acquiring Body tendered across the Bar a copy of the

order dated 17.08.2026 passed by this Court in First Appeal No. 332 of 2005

and connected matters. Under the same notification and award, lands from

different survey numbers were acquired, and this Court determined the

market value of the acquired lands therein at the rate of Rs. 23,000/- per

acre. Therefore, he submitted that the present appeals and cross-objections

are squarely covered by the order dated 17.08.2026 passed by this Court in

First Appeal No. 332 of 2005. He submitted that when the said order was

passed, it was not brought to the notice of this Court that as per the 1984

Amendment, the claimants are entitled to receive 30% solatium and 12%

additional component.


6.    There is no dispute about the fact that this Court has already

determined the market value of the acquired lands arising out of the same
                                                               908-FA-2674-2013.odt
                                     4

notification and award vide order dated 17.08.2026 in First Appeal No. 332

of 2005 and connected matters, wherein compensation was enhanced. Since

the present First Appeals arise out of the same notification, same award, and

same acquisition scheme, this Court holds that the order passed by this

Court in First Appeal No. 332 of 2005 is squarely applicable to the present

case. The learned Reference Court in the present proceedings has also

determined the market value at exactly the same rate.

7.    After going through the record, I find that CIDCO initiated

proceedings to acquire 4 Acres and 8 Acres lands of the respective claimants.

However, after passing the award, it was noticed that out of the 4 Acres of

land, 1 Acre 36 R of claimant Purushottamdas and land to the extent of 24 R

of claimant Navneetdas had already been acquired by the State Government

for the construction of a V.I.P. Guest House by the Buildings and

Communication (B & C) Department. The possession receipt demonstrates

that possession of the said portion was handed over to the B & C

Department on 09.07.1974, and CIDCO acquired only the remaining land to

the extent of 2 Acres 04 Gunthas and 3 Acres 16 Gunthas of the respective

claimants. In fact, it has also come in the evidence of the claimants that

prior to the acquisition by CIDCO, the land was acquired by the State

Government for B & C Department under award dated 02.02.1970.


8.    It is an admitted position on record that a portion of the claimants’

land was acquired by the B & C Department; however, the compensation
                                                               908-FA-2674-2013.odt
                                     5

payable towards such acquisition is yet to be disbursed and continues to

remain pending in the T-Account of the B & C Department.


9.    Once the land forming part of the same Survey Number has been

acquired, albeit under a different acquisition proceeding, the factors

warranting enhancement of compensation ought to have been considered by

the learned Reference Court, so as to grant the same rate of compensation in

both the acquisition proceedings. Consequently, the learned reference Court

ought to have granted enhancement for both the acquisition proceedings.


10.   Therefore, as regards the amount of compensation at the rate

determined by this Court, CIDCO is liable to pay for the land acquired by it.

However, simultaneously, it cannot be ignored that the claimants' lands were

acquired by the B & C Department as well, and therefore, the claimants

cannot be deprived of compensation in respect of those portions. Since the

State Government had already acquired those portions of land and no

compensation was paid, the mere fact that CIDCO is not liable to pay for

that portion would not mean that the claimants are not entitled to receive

compensation for the land acquired by the B & C Department. Once it is

brought to the notice of this Court that the land was acquired by the State

Government for the B & C Department, the State Government is liable to

pay the amount.
                                                                908-FA-2674-2013.odt
                                      6

11.   In the interest of justice, this Court is of the opinion that while CIDCO

is liable to pay compensation for the lands acquired by it at the rate

determined by this Court, the State Government is liable to pay

compensation for the lands acquired for the B & C Department, i.e. 1 Acre

36 R and 24 R of the respective claimants.


12.    It was brought to the notice of this Court that, after passing of the

award dated 21.03.1980, it was found that land admeasuring 1 Acre 36 R

belonging to claimant Purushottamdas and land admeasuring 24 R

belonging to claimant Navneetdas had already been acquired under the

award dated 02.02.1970. In view of the said prior acquisition, the award

dated 21.03.1980 was amended, and the amended award dated 19.09.1980

came to be passed, which is placed at Exhibit-32 (corrigendum to the

award). Exhibit-32 reflects that the original claimants had not withdrawn

the amount payable in respect of the lands acquired by the State and that

the said amount has been lying deposited with the Department in the T-

Account maintained by the Assistant Collector since 17.03.1971, without

any claimant coming forward to receive the same. Thus, the record supports

the position that the said portions of land had already been dealt with in the

earlier acquisition proceedings and that the compensation amount

pertaining thereto was separately lying deposited with the concerned

Department.
                                                                 908-FA-2674-2013.odt
                                        7

13.     In view of the aforesaid discussion, the appeals filed by the claimants

deserve to be partly allowed by modifying the impugned judgment and

award. Hence, the following order is passed:


                                   ORD ER


(i)     The First Appeals filed by the claimants are partly allowed.


(ii)    The common impugned Judgment and Award dated 01.01.2013

passed by the learned Civil Judge, Senior Division, Aurangabad in Land

Acquisition Reference Nos. 172 of 1997 and 173 of 1997 is hereby modified.


(iii)   The Claimants in First Appeal No. 2674 of 2013 (LAR No. 173 of

1997) are held entitled to receive compensation at the rate of Rs.23,000/-

per Acre for their acquired land admeasuring 24 R acquired by the State for

the B & C Department.


(iv)    The Claimants in First Appeal No. 1287 of 2013 (LAR No. 172 of

1997) are held entitled to receive compensation at the rate of Rs.23,000/-

per Acre for their acquired land admeasuring 1 Acre 36 R acquired by the

State for the B & C Department.


(v)     The State Government shall be liable to pay the compensation for the

aforesaid remaining lands admeasuring 24 R and 1 Acre 36 R respectively.


(vi)    The claimants shall be entitled to all consequential statutory benefits

including interest as per the law laid down by Full Bench decision in State

of Maharashtra vs. Kailas Shiva Rangari, 2016 (3) Mh.L.J. 457.
                                                                     908-FA-2674-2013.odt
                                            8


(vii) The claimants are entitled to receive 30% solatium and 12%

additional component in respect of land acquired by the State Government

for construction of B & C Department as well as the land acquired by CIDCO,

subject to the claimants’ entitlement under the Land Acquisition Act, 1894.


(viii) The remaining part of the common impugned Judgment and Award

dated 01.01.2013 passed by the learned Civil Judge, Senior Division,

Aurangabad in Land Acquisition Reference Nos. 172 of 1997 and 173 of

1997 shall remain unaltered.


(ix)       The claimants shall pay deficit court fees, if any.


(x)        Modified award be drawn accordingly.


(xi)       In view of the disposal of the appeals filed by the original claimants,

the Cross Objections filed by the Respondent-State stand disposed of.


(xii)       Pending Civil Applications, if any, stand disposed of.



                                                  [ SIDDHESHWAR S. THOMBRE ]
                                                            JUDGE
S P Rane
