Bombay High Court
THE STATE OF MAHARASTHRAversusV.S. PAWAR
- Decided
- Disposal
- Disposed Off
Holding
The High Court did not interfere with the lower court’s award and ordered the State to comply with the judgment within twelve weeks.
Summary
The State of Maharashtra appealed a land acquisition award to the High Court, contending that the award of Rs. 1,877 by the acquisition officer was insufficient compared to the Rs. 8,030 awarded by the Joint District Judge, Nashik. The learned Additional Government Pleader expressed willingness to accept the Court’s orders, noting the small amounts involved and the protracted delay. The Court, after considering these submissions, chose not to interfere with the lower court’s judgment, emphasizing the meagre sums and the lengthy pendency. It directed the State to implement the impugned judgment within twelve weeks. The order expressly states it does not set a precedent on any legal issues, and the appeal along with any related civil applications were finally disposed of.
Issues considered
- Whether the High Court should interfere with the award granted by the Joint District Judge in a land acquisition matter given the small monetary differences and delay.
Subjects
- land acquisition
- award
- civil appeal
- judgment enforcement
- court discretion
- delay
Judgment
917-FA-712-2000.docs
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION
FIRST APPEAL NO. 712 OF 2000
State of Maharashtra ….Appellant
Versus
V.S. Pawar . ....Respondent
Mr. A.R. Patil, Addl. G.P., for the Appellant.
Mr. P.N. Joshi, for the Respondent.
CORAM : SOMASEKHAR SUNDARESAN, J.
DATE : APRIL 8, 2026
ORDER :
1. Learned AGP is willing to submit to orders of this Court
considering the meagre size of the amounts involved in this Appeal.
First Appeal No. 712 of 2000 relates to Land Acquisition Reference No.
477 of 1990.
2. It is stated that the amount awarded by the land acquisition
officer is a sum of Rs. 1,877/- while the amount awarded by Joint
District Judge, Nashik, the jurisdictional reference court by the
impugned judgement dated January 6, 1998, is a sum of Rs. 8,030/-.
Page 1 of 2
April 8, 2026
Rutuja
917-FA-712-2000.docs
3. Taking on board the submissions by the Learned AGP, and
considering the meagre sums involved and the sheer length of time for
which the matter has remained pending, no interference is made with
the impugned judgment. The State is directed to adhere to the
impugned judgement at the earliest in any event within a period of 12
weeks from today.
4. Nothing contained in this Order would constitute a declaration on
the merits of any legal issues involved in the Appeal to constitute a
precedent for other matters.
5. In these circumstances, the Appeal is finally disposed of. Any Civil
Applications therein are also hereby finally disposed of.
6. All actions required to be taken pursuant to this order shall be
taken upon receipt of a downloaded copy as available on this Court’s
website.
[ SOMASEKHAR SUNDARESAN, J.]
Page 2 of 2
April 8, 2026
Rutuja