Holding
The Court allowed the interim applications, granting withdrawal of the Rs. 25 lakh deposit and return of the bank guarantees, and corrected the typographical error.
Summary
The petitioners, Garlick Engineering Ltd (formerly a division of Empire Industries Ltd), filed interim applications seeking the withdrawal of Rs. 25 lakh deposited pursuant to an order dated 22 April 2019 and the return of bank guarantees issued under that order. The respondents indicated an intention to challenge the original order before the Supreme Court, arguing that the interim relief should not be granted. The Court examined the reasons set out in the original judgment and found that the petitioners had established a sufficient case for the relief sought in prayer clause “a”. It also noted that prayer clause “b” pertained merely to a typographical error and therefore warranted correction. Consequently, the Court allowed both the withdrawal of the deposited amount and the return of the bank guarantees, including the correction of the typographical mistake.
Issues considered
- Whether the petitioners are entitled to interim relief for withdrawal of the Rs. 25 lakh deposit despite pending Supreme Court challenge
- Whether a typographical error in the original order can be corrected through the interim application
Subjects
- interim relief
- bank guarantee
- withdrawal of deposit
- typographical error
- high court
- appeal
Judgment
22-IA-3054-26+.doc
Sayali
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION
INTERIM APPLICATION NO.3054 OF 2026
IN
SAYALI WRIT PETITION NO. 3805 OF 2019
DEEPAK WITH
UPASANI INTEIRM APPLICATION NO.3058 OF 2026
Digitally signed
by SAYALI IN
DEEPAK
UPASANI WRIT PETITION NO. 3836 OF 2019
Date: 2026.04.23
16:51:42 +0530
Garlick Engineering Ltd (Erstwhile Applicant/
closed division of Empire Industries Ltd) Org. Respondent
…
In the matter Between
s
Garlick Engineering Ltd Division of
Empire Industries Ltd Petitioner
V/s.
Suresh Karale and Others … Respondents
Mr. Sudhir Talsania, Senior Advocate i/b Mr. Sujeet P.
Salkar, for Applicant.
Mr. C. M. K. Lokes i/b Mr. Ravindra Nair, for
Respondent.
CORAM : AMIT BORKAR, J.
DATED : APRIL 23, 2026
P.C.:
1. The applications are filed seeking relief of withdrawal of an
amount of Rs. 25 lakhs deposited in furtherance of the order
dated 22 April 2019 and for return of the Bank guarantees
furnished as per the said order.
1
22-IA-3054-26+.doc
2. The learned Advocate for the respondent states that the
respondent intends to challenge the order before the Supreme
Court and, therefore, the applications may not be allowed.
3. Having considered the reasons assigned in the judgment, in
my opinion, the applicants have made out a case for grant of
relief in terms of prayer clause “a”.
4. Hence, the applications are allowed in terms of prayer
clause “a” and, insofar as prayer clause “b” relates to a
typographical error, the same is also allowed.
(AMIT BORKAR, J.)